UArk PROGRAM DOCUMENT

72
Civil Engineering (CVEG) - Research & Education Building University of Arkansas February 20th, 2015 TA# ST14.014.00B Programming Document

Transcript of UArk PROGRAM DOCUMENT

Page 1: UArk PROGRAM DOCUMENT

Civil Engineering (CVEG) - Research & Education Building

University of Arkansas

February 20th, 2015

TA# ST14.014.00B

Programming Document

Page 2: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of ArkansasProgramming Document 2

Acknowledgements

ARCHITECT OF RECORD

DEMX

ASSOCIATE AND PLANNING ARCHITECT

TREANOR ARCHITECTS

STRUCTURAL ENGINEER

WALTER P. MOORE

MECHANICAL / ELECTRICAL / PLUMBING ENGINEER

AFFILIATED ENGINEERS, INC.

CIVIL ENGINEER

MCGOODWIN, WILLIAMS, AND YATES, INC.

COST ESTIMATOR

VERMEULENS

Page 3: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of Arkansas Programming Document 3

Table of Contents

1 Executive Summary

2 Project Description & Vision

3 Site Analysis

4 Program Summary

5 Room Data and Adjacencies

6 Design NarrativesArchitecturalCivilStructuralMechanical ElectricalPipingTechnology ServicesFire Protection

7 Conceptual Design

8 Existing Space Summary

9 Appendix

High-bay Benchmarking Commissioning Format

5

7

9

17

27

55

77

81

85

Page 4: UArk PROGRAM DOCUMENT
Page 5: UArk PROGRAM DOCUMENT

CVEG - Research & Education Building at University of Arkansas Programming Document5

Executive Summary 1

Page 6: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of ArkansasProgramming Document 6

Executive Summary

The Civil Engineering department at the University of Arkansas faces three challenges over the coming decade.

1. Providing a facility that will allow research faculty to aggressively pursue available

funding and grants related to material testing

2. Planning for anticipated growth in the department

3. Consolidate research labs that are currently spread across three facilities on three

separate campuses.

The construction of the new Civil Engineering Research & Education Center will allow all civil engineering research and training disciplines to be located with-in one complex and accommodate departmental growth from 275 to 350 undergraduates and from 30 to 75 researchers. In addition, the new structural high-bay facility will allow for testing of full-scale structural elements, such as beams and girders for buildings and bridges will allow the research faculty to pursue grants that had not been previously possible to pursue.

The Research & Education Center will be located at the Arkansas Research & Technology Park (ARTP). This development will further strengthen the presence of the university at this satellite location and progress the university’s master plan for the ARTP.

Through a series of workshops that included dialog with the various Civil Engineering user groups and Facilities Management Planning Group, the Design Team listened, tested, bench marked, and verifi ed information. This Programming Document summarizes the results of that process and moving forward will serve as a benchmark against which to measure the development of the project throughout its future phases.

Publication of the Programming Document represents the culmination of the Program Phase of the project and lays the groundwork for the Schematic Design Phase. The goal of this phase is to confi rm the programming needs of all concerned parties; to present a detailed, clear, and cogent summary and analysis of those needs; and to illustrate an understanding of the larger project issues and goals. In addition to the traditional programming elements, this document includes a Conceptual Design aid in visualization and bridging to the Schematic Design Phase.

Page 7: UArk PROGRAM DOCUMENT

CVEG - Research & Education Building at University of Arkansas Programming Document7

Project Description & Vision 2

Page 8: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of ArkansasProgramming Document 8

Project Description & Vision

Program Vision

The Civil Engineering Research & Education Center will allow all civil engineering research and training disciplines to be located with-in one complex and accommodate departmental growth from 275 to 350 undergraduates and from 30 to 75 researchers.

The new facility is anticipated to be constructed in three phases. The fi rst phase will include a structural high-bay with a strong fl oor and lay-down yard, concrete and steel materials labs, a fabrication shop, various geotechnical labs, and faculty support spaces. The second phase will include a number of asphalt testing labs and the third phase will include laboratory, classroom and certifi cation spaces for the Center for Training Transportation Professionals (CTTP).

Site and Capacity

The Research & Education Center will be located at the Arkansas Research & Technology Park (ARTP). The ARTP is located on the northwest corner of the W. Cato Springs Road and S. School Ave. intersection in Fayetteville, Arkansas. A series of possible sites in accordance with the university’s master plan for the ARTP were analyzed based on overall building and lay-down yard size requirements and vehicular access. As a result, site (3)three , which lies on the western half of the ARTP as indicated below, was chosen. Additional site analysis and information can be found in chapter 3, Site Analysis.

Approximate Site Area

Required*: 70,000 SF1.6 acres

*Includes: Building Area, Boneyard (lay-down yard), and Delivery Drives

Provided: 99,700 SF 2.3 acres

Approximate Building Size

Phase 1 Net Square Feet: 32,500 SFPhase 2 Net Square Feet: 4,800 SFPhase 3 Net Square Feet: 8,400 SF

Total Gross Square Feet: 45,700 SF

Page 9: UArk PROGRAM DOCUMENT

CVEG - Research & Education Building at University of Arkansas Programming Document17

Program Summary 4

Page 10: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of ArkansasProgramming Document 18

SPACE TYPESPHASE 1 PHASE 2 PHASE 3

NOTESArea (NSF) Qty Total Area (NSF) Area (NSF) Qty Total Area (NSF) Area (NSF) Qty Total Area (NSF)

Building Common 800 0 1,200Lobby 500 1 500Conference Room 300 1 300Computer Classroom 1,200 1 1,200

Offi ce 4,000 0 800Faculty 100 6 600Huddle Room 100 1 100Graduate Student 50 62 3,100Technician 200 1 200CTTP Staff 100 8 800

Structural Labs (Steel and Concrete) 25,200 0 0Strong Floor (High Bay) 5,000 1 5,000 50’x100’Staging Area (High Bay) 2,500 1 2,500Storage Area (High Bay) 3,500 1 3,500Service Chase below Strong Floor (High Bay) 6,500 1 6,500Drive Lane (High Bay) 1,000 1 1,000Material Testing 1,500 1 1,500Concrete Mixing and Testing 2,400 1 2,400Metallurgy 600 1 600Fabrication Shop 1,200 1 1,200Wind Engineering (High Bay) 1,000 1 1,000 small vortex chamber

Geotechnical Labs 2,500 0 0Sample Prep 500 1 500Sample Test 500 1 500Soil Box Room 500 1 500Direct Shear 500 1 500Seismic Lab, common room 300 1 300Seismic Lab, small 100 2 200

Asphalt Labs 0 4,800 0DSR 400 1 400Specifi c Gravity 500 1 500Mixing/Compaction/Testing 2,200 1 2,200Sample Prep 500 1 500Aggregate Lab 1,200 1 1,200

CTTP Labs 0 0 6,400Training Classroom (fl exible classroom) 1,200 1 1,200 50 peopleTraining Conference Room 200 1 200 10 peopleTraining Storage 200 1 200Asphalt 1,600 1 1,600 open labsConcrete 1,600 1 1,600 open labsSupport Lab 400 1 400 shared support, storage and shakersTesting 1,200 1 1,200 (12) 8’x8’ setup stations

Student Projects 2,000 0 0Student Fabrication (High Bay) 2,000 1 2,000 open and fl exible

Subtotal NSF 34,500Subtotal

Building NSF 4,800Subtotal

Building NSF 8,400

Program Summary

Page 11: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of Arkansas Programming Document 19

Program | Building Common

Qty NSF Total NSF Phase

Lobby 1 500 500 1

Conference Room 1 300 300 1

Computer Room 1 1,200 1,200 3

Building Common 2,000

Lobby Conference Room Computer Room

Page 12: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of ArkansasProgramming Document 20

Program | Offi ce

Qty NSF Total NSF Phase

Faculty 6 100 600 1

Huddle Room 1 100 100 1

Graduate Students 62 50 3,100 1

Technician* 1 200 200 1

CTTP Staff 8 100 800 3

Offi ce 4,000

Faculty Offi ces

* Technician Offi ce included with Fabrication Shop diagram

Huddle Room Graduate Students CTTP Staff Offi ces

Page 13: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of Arkansas Programming Document 21

Program | Structural Labs

Qty NSF Total NSF Phase

Strong Floor (High Bay) 1 5,000 5,000 1

Staging Area (High Bay) 1 2,500 2,500 1

Storage Area (High Bay) 1 3,500 3,500 1

Service Chase below Strong Floor 1 6,500 6,500 1

Drive Lane (High Bay) 1 1,000 1,000 1

Material Testing 1 1,500 1,500 1

Concrete Mixing and Testing 1 2,400 2,400 1

Metallurgy 1 600 600 1

Fabrication Shop 1 1,200 1,200 1

Wind Engineering (High Bay) 1 1,000 1,000 1

Structural Labs 25,200

Material Testing

Concrete Mixing and Testing

Metallurgy Fabrication Shop (includes Technician Offi ce)

Page 14: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of ArkansasProgramming Document 22

Program | Structural Labs .... cont.

High-bay: Strong Floor, Staging Area, Storage Area, Wind Engineering, Drive Lane, and Service Chase below Strong Floor

Page 15: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of Arkansas Programming Document 23

Program | Geotechnical Labs

Qty NSF Total NSF Phase

Sample Prep 1 500 500 1

Sample Test 1 500 500 1

Soil Box Room 1 500 500 1

Direct Shear 1 500 500 1

Seismic Lab, common room 1 300 300 1

Seismic Lab, small rooms 2 100 200 1

Geotechnical Labs 2,600

Soil Box Room

Sample Prep Sample Test

Direct Shear Seismic Lab: common room and small rooms

Page 16: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of ArkansasProgramming Document 24

Program | Asphalt LabsQty NSF Total NSF Phase

DSR 1 400 400 2

Specifi c Gravity 1 500 500 2

Mixing / Compaction / Testing 1 2,200 2,200 2

Sample Prep 1 500 500 2

Aggregate Lab 1 1,200 1,200 2

Asphalt Labs 4,800

DSR Specifi c Gravity Mixing / Compaction / Testing Sample Prep Aggregate Lab

Page 17: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of Arkansas Programming Document 25

Program | CTTP LabsQty NSF Total NSF Phase

Training Classroom 1 1,200 1,200 3

Training Conference Room 1 200 200 3

Training Storage 1 200 200 3

Asphalt 1 1,600 1,600 3

Concrete 1 1,600 1,600 3

Support Lab(s) 1 400 400 3

Testing 1 1,200 1,200 3

CTTP Labs 6,400

Asphalt / Concrete / Support Lab(s) / Testing Training Classroom / Conference Room / Storage

Page 18: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of ArkansasProgramming Document 26

Program | Student ProjectsQty NSF Total NSF Phase

Student Fabrication 1 2,000 2,000 1

Student Projects 2,000

Student Fabrication

Page 19: UArk PROGRAM DOCUMENT

CVEG - Research & Education Building at University of Arkansas Programming Document27

Room Data and Adjacencies 5

Page 20: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of ArkansasProgramming Document 28

UP

STU

DEN

T FA

BRIC

ATIO

N

VESTIBULE

HIGH-BAY

FLAT

PAN

EL D

ISPL

AY

Building Common | LobbyGeneral

- Space Type: Lobby- Department: Building Common- Unit Area: 500 SF - 1,000 SF- Occupancy: n/a- Adjacencies: High-Bay, Student Fabrication

Architectural

- Floor Mat.: Concrete- Wall Mat.: Glass Storefront/Gypsum Board- Ceiling Mat.: Acoustic Ceiling Tile (ACT)

Utility Infrastructure

- 120V- Data @ Flat Panel- Wireless Data, TYP.

Special Furniture/Equipment

- Flat Panel Display (OFOI)

Page 21: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of Arkansas Programming Document 29

20'-0

"

CONFERENCE

FLAT PANEL DISPLAY

MAR

KER

BOAR

D

MAR

KER

BOAR

D

FLOOR BOX(120V, DATA)

15'-0"

Building Common | Conference RoomGeneral

- Space Type: Conference Room- Department: Building Common- Unit Area: 300 SF- Occupancy: 10-15 People- Adjacencies: Offi ces

Architectural

- Floor Mat.: Carpet- Wall Mat.: Glass Storefront/Gypsum Board- Ceiling Mat.: Acoustic Ceiling Tile (ACT)

Utility Infrastructure

- Floor Box - 120V - Data, Wireless Data, TYP.

Special Furniture/Equipment

- Conference Table (OFOI)- Flat Panel Display (OFOI)- Markerboards (CFCI)

Page 22: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of ArkansasProgramming Document 30

CORRIDOR

MARKERBOARD MARKERBOARDMARKERBOARD

PROJECTOR

MAR

KER

BOAR

D

30'-0

"

CUBBIES

40'-0"

Building Common | Computer ClassroomGeneral

- Space Type: Computer Classroom- Department: Building Common- Unit Area: 1,200 SF- Occupancy: 50 People- Adjacencies: CTTP Training Classroom, Table & Chair Storage

Architectural

- Floor Mat.: Carpet- Wall Mat.: Glass Storefront/Gypsum Board- Ceiling Mat.: Acoustic Ceiling Tile (ACT)

Utility Infrastructure

- Floor Boxes- 120V- Data, Wireless Data, TYP.

Special Furniture/Equipment

- Markerboards (CFCI)- 6 Person Teaching Tables (OFOI)- Backpack Cubbies (CFCI)- Projector (OFOI)- Projection Screen (CFCI)

Page 23: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of Arkansas Programming Document 31

Offi ce | Faculty

10'-0"

10'-0

"

General

- Space Type: Faculty- Department: Offi ce- Unit Area: 100 SF- Occupancy: 5 People- Adjacencies: Conf. Room, Grad. Offi ces

Architectural

- Floor Mat.: Carpet- Wall Mat.: Glass Storefront/Gypsum Board- Ceiling Mat.: Acoustic Ceiling Tile (ACT)

Utility Infrastructure

- 120V- Data, Wireless Data, TYP.

Special Furniture/Equipment

- Desk (OFOI)- Desk Chair (OFOI)- Chairs (OFOI)- Shelving Unit (OFOI)- Filing Cabinet (OFOI)

Page 24: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of ArkansasProgramming Document 32

Offi ce | Huddle Room

10'-0

"

FLAT PANEL DISPLAY

MARKERBOARD

General

- Space Type: Huddle Room- Department: Offi ce- Unit Area: 100 SF- Occupancy: 6 People- Adjacencies: Faculty Offi ces

Architectural

- Floor Mat.: Carpet- Wall Mat.: Glass Storefront/Gypsum Board- Ceiling Mat.: Acoustic Ceiling Tile (ACT)

Utility Infrastructure

- 120V- Data, Wireless Data, TYP.

Special Furniture/Equipment

- Conference Table (OFOI)- Conference Chairs (OFOI)- Flat Panel Display (OFOI)- Markerboard (CFCI)

Page 25: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of Arkansas Programming Document 33

Offi ce | Graduate Student

5'-0

"

10'-0"

General

- Space Type: Graduate Student- Department: Offi ce- Unit Area: 50 SF- Quantity: 62- Total NSF: 3,100SF- Occupancy: 1 Person- Adjacencies: Conf. Room, Faculty Offi ces

Architectural

- Floor Mat.: Carpet- Wall Mat.: Glass Storefront/Gypsum Board- Ceiling Mat.: Acoustic Ceiling Tile (ACT)

Utility Infrastructure

- 120V- Data, Wireless Data, TYP.

Special Furniture/Equipment

- Desk (OFOI)- Desk Chair (OFOI)

Page 26: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of ArkansasProgramming Document 34

Offi ce | CTTP Staff

10'-0"

10'-0

"

General

- Space Type: CTTP Staff - Department: Offi ce- Unit Area: 100 SF- Occupancy: 5 People- Adjacencies: CTTP Training & Lab

Architectural

- Floor Mat.: Unknown- Wall Mat.: Unknown- Ceiling Mat.: Unknown

Utility Infrastructure

- 120V - Data, Wireless Data, TYP.

Special Furniture/Equipment

- Desk (OFOI)- Desk Chair (OFOI)- Chairs (OFOI)- Shelving Unit (OFOI)- Filing Cabinet (OFOI)

Page 27: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of Arkansas Programming Document 35

Structural | Material Testing

MET

ALLU

RG

Y

STO

RAG

E

MTS

MTS

MTS

MTS

COMPUTERTABLE

OVERHEAD DROP, TYP.(120V, CA, DATA)

EQU

IPM

ENT

ZON

E

PAVED APRON

30'-0

"

50'-0"

OVERHEAD DOOR(10'W x 15'H)HIGH-BAY

CA CA

CA

CA

CA CA

PW

PW PW

PWPW

PW

SINK(CS, HW, EW)

General

- Space Type: Material Testing- Department: Structural- Unit Area: 1,500 SF- Occupancy: 30 People- Adjacencies: Metallurgy, High-Bay

Architectural

- Floor Mat.: Polished Concrete- Wall Mat.: Concrete Masonry Unit (CMU)- Ceiling Mat.: None, Exposed Painted Structure

Casework

- Fixed Benches: Yes, against walls- Mobile Benches: n/a- Movable Tables: n/a - Wall Upper Cabinets: Yes, over fi xed benches- Tall Cabinets/Type: n/a- Countertop Mat.: Stainless Steel- Chemical Storage: n/a- Flammables: n/a- Acids/Bases: n/a

Utilities

- Overhead Drop Box- 120V- Data, Wireless Data, TYP.- Stainless Steel Sink (CW, HW, EW)- Compressed Air- Process Water

Special Furniture/Equipment

-Computer Tables (OFOI)-MTS Machine (OFCI)

Page 28: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of ArkansasProgramming Document 36

Structural | Concrete Mixing & Testing

FD

80'-0"

30'-0

"

OPEN TO HIGH-BAY

OVERHEAD DROP, TYP.(120V)

EQUIPMENT ZONE(FREEZE / THAW & CONC. MIX)

(EXISTING)

EQUIPMENT ZONE(END GRINDER)

(EXISTING)ENVIRONMENTALCHAMBER

(NEW)

FLOOR DRAIN, TYP.

OVERHEAD DOOR(10'W x 15'H), ACCESSTO BONEYARD

PAVED & COVERED PATIO

PAVED APRONPAVED APRONHOSE BIB

MET

ALLU

RG

Y

SHAKER & SAW(EXISTING)

CA CA CA

CA

CACA

SINK(CS, HW, EW)

General

- Space Type: Concrete Mixing & Testing- Department: Structural- Unit Area: 2,400 SF- Occupancy: 48 People- Adjacencies: Metallurgy, High-Bay

Architectural

- Floor Mat.: Polished Concrete- Wall Mat.: Concrete Masonry Unit (CMU)- Ceiling Mat.: None, Exposed Painted Structure

Casework

- Fixed Benches: Yes, against wall- Mobile Benches: n/a- Movable Tables: n/a - Wall Upper Cabinets: Yes, over fi xed benches- Tall Cabinets/Type: n/a- Countertop Mat.: Stainless Steel- Chemical Storage: n/a- Flammables: n/a- Acids/Bases: n/a

Utilities

- Overhead Drop Box- 120V- Stainless Steel Sink (CW, HW, EW)- Compressed Air- Floor Drain

Special Furniture/Equipment

- Environmental Chamber (CFCI)- Concrete Mixer (OFCI)- Stock Tanks (OFCI)- Concrete Saw (OFCI)- Freeze/Thaw Concrete Mixer (OFCI)- End Grinder (OFCI)- Shaker (OFCI)

Page 29: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of Arkansas Programming Document 37

Structural | Metallurgy

FD

MAT

ERIA

LS T

ESTI

NG

CO

NC

. MIX

ING

& T

ESTI

NG

EQUIPMENT ZONE

POLISHER,TIE TO SINKDRAIN

TABLES

OVERHEAD DROP, TYP.(120V)

CA

CA

20'-0"

30'-0

"

4' FH(120V, CS)

EWES

W W

SINK(CS, HW)SINK

(CS, HW)

SINK(CS, HW)

SINK(CS, HW)

General

- Space Type: Metallurgy- Department: Structural- Unit Area: 600 SF- Occupancy: 12 People- Adjacencies: Conc. Mixing & Testing, Materials Testing

Architectural

- Floor Mat.: Polished Concrete- Wall Mat.: Concrete Masonry Unit (CMU)- Ceiling Mat.: None, Exposed Painted Structure

Casework

- Fixed Benches: Yes, against walls- Mobile Benches: n/a- Movable Tables: Yes, located center of room - Wall Upper Cabinets: Yes, over fi xed benches- Tall Cabinets/Type: n/a- Countertop Mat.: Stainless Steel- Chemical Storage: n/a- Flammables: n/a- Acids/Bases: n/a

Utilities

- Overhead Drop Box- 120V- Data, Wireless Data, TYP.- Compressed Air- Eyewash Station/Emergency Shower w/ Floor Drain- Stainless Steel Sinks (CW, HW, EW)- Water Outlet

Special Furniture/Equipment

- Fume Hood (CFCI)- Polisher (OFOI)- Microscope (CFCI)

Page 30: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of ArkansasProgramming Document 38

Structural | High-Bay LabGeneral

- Space Type: High-Bay Lab- Department: Structural- Unit Area: 14,000 SF- Occupancy: 30 People- Adjacencies: Boneyard, Concrete Mixing, Material Test

Architectural

- Floor Mat.: Polished Concrete- Wall Mat.: Concrete Masonry Unit (CMU)- Ceiling Mat.: None, Exposed Painted Structure

Casework

- Fixed Benches: n/a- Mobile Benches: n/a- Movable Tables: Yes - Wall Upper Cabinets: n/a- Tall Cabinets/Type: n/a- Countertop Mat.: n/a- Chemical Storage: n/a- Flammables: n/a- Acids/Bases: n/a

Utilities

- 120V- Data, Wireless Data, TYP.

Special Furniture/Equipment

- 50’x100’ Strong Floor w/ Diamond Shape 4-Hole Tie-Downs (CFCI)- (2) 25 Ton Bridge Cranes (CFCI)- Hydraulic System- Hydraulic Actuators- Steel Frame- Control System- Data Acquisition System- Instrumentation- Miscellaneous Start-up Equipment (OFOI)- Fork Lifts (OFOI)- Rigging Equipment (OFOI)- Tables (OFOI)

Page 31: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of Arkansas Programming Document 39

SERVICE CHASE BELOW STRONG FLOORAREA SHOWN IN GRAY

DROP-OFF DRIVE

16'-0

"

STRONG FLOOR

DIAMOND SHAPE, 4-HOLETIE-DOWNS @ 4'-0" O.C.

FLOOR ACCESS DOORS

STORAGE AREA(STRENGTHENED SLAB) STAGING AREA

(STRENGTHENED SLAB)

70'-0

"

200'-0"

100'-0"

50'-0

"

16'-0

"

WIND ENGINEERING

(2) 25 TON BRIDGE CRANES.HOOK HEIGHT = 35'

MEZZANINE ABOVE

WELDING AREA

OVERHEAD DOOR(10'W x 15'H), ACCESSTO BONEYARD

OVERHEAD DOOR(20'W x 25'H), ACCESSTO BONEYARD

Page 32: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of ArkansasProgramming Document 40

Structural | Fabrication Shop & Tech Offi ce

HIGH-BAY

WELDING AREA

TECH OFFICE

CORRIDOR

EQUIPMENT ZONE

EQUIPMENT ZONE

OVERHEAD DOOR(10'W x 15'H)

30'-0

"

40'-0" 10'-0"

OVERHEAD DROP, TYP.(120V, CA, DATA)

SINK(CS, HW, EW)

General

- Space Type: Fabrication Shop & Tech Offi ce- Department: Structural- Unit Area: 1,300 SF- Occupancy: 26 People- Adjacencies: High-Bay Lab

Architectural

- Floor Mat.: Polished Concrete- Wall Mat.: Concrete Masonry Unit (CMU)- Ceiling Mat.: None, Exposed Painted Structure

Casework

- Fixed Benches: Yes, against walls- Mobile Benches: n/a- Movable Tables: Yes, centered in room - Wall Upper Cabinets: Yes, over fi xed benches- Tall Cabinets/Type: n/a- Countertop Mat.: Stainless Steel- Chemical Storage: n/a- Flammables: n/a- Acids/Bases: n/a

Utilities

- Overhead Drop Box- 120V- Data, Wireless Data, TYP.- Compressed Air- Stainless Steel Sink (CW, HW, EW)

Special Furniture/Equipment

-Welding (Arc/Acetylene) (CFCI) -Vented Hood- Drill Press (OFCI)- Lathe (OFCI)- Table Shop (OFCI)- Band Saw (OFCI)

Page 33: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of Arkansas Programming Document 41

Geotechnical | Sample Prep

20'-0

"

25'-0"

CORRIDOR

SAM

PLE

TEST

BONEYARD

OPEN WORKAREA

EQUIPMENT ZONE(SEIVE)

SINK(CS, HW)

SINK(CS, HW, EW)

General

- Space Type: Sample Prep- Department: Geotechnical- Unit Area: 500 SF- Occupancy: 10 People- Adjacencies: Sample Test, Boneyard

Architectural

- Floor Mat.: Polished Concrete- Wall Mat.: Concrete Masonry Unit (CMU)- Ceiling Mat.: None, Exposed Painted Structure

Casework

- Fixed Benches: Yes, against walls- Mobile Benches: n/a- Movable Tables: n/a - Wall Upper Cabinets: Yes, over fi xed benches- Tall Cabinets/Type: n/a- Countertop Mat.: Stainless Steel- Chemical Storage: n/a- Flammables: n/a- Acids/Bases: n/a

Utilities

- Stainless Steel Sink (CW, HW, EW)

Special Furniture/Equipment

- n/a

Page 34: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of ArkansasProgramming Document 42

Geotechnical | Sample Test

20'-0

"

25'-0"

CORRIDOR

SOIL

PR

EP

BONEYARD

OVERHEAD DROP(120V, CA, VAC)

SINK(CS, HW)

SINK(CS, HW, EW)

General

- Space Type: Sample Test- Department: Geotechnical- Unit Area: 500 SF- Occupancy: 10 People- Adjacencies: Soil Prep/Boneyard

Architectural

- Floor Mat.: Polished Concrete- Wall Mat.: Concrete Masonry Unit (CMU)- Ceiling Mat.: None, Exposed Painted Structure

Casework

- Fixed Benches: Yes, against walls- Mobile Benches: n/a- Movable Tables: Yes, centered in room - Wall Upper Cabinets: Yes, over fi xed benches- Tall Cabinets/Type: n/a- Countertop Mat.: Stainless Steel- Chemical Storage: n/a- Flammables: n/a- Acids/Bases: n/a

Utilities

- Overhead Drop Box- 120V- Stainless Steel Sink (CW, HW, EW)- Compressed Air- Vacuum

Special Furniture/Equipment

- Movable Tables (OFOI)

Page 35: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of Arkansas Programming Document 43

Geotechnical | Soil Box Room

20'-0

"

25'-0"

CORRIDOR

BONEYARD

OVERHEAD DROP(120V, CA, VAC)

OVERHEAD DOOR(8'W x 10'H)

SINK(CS, HW, EW)

General

- Space Type: Soil Box Room- Department: Geotechnical- Unit Area: 500 SF- Occupancy: 10 People- Adjacencies: Boneyard, Soil Prep

Architectural

- Floor Mat.: Polished Concrete- Wall Mat.: Concrete Masonry Unit (CMU)- Ceiling Mat.: None, Exposed Painted Structure

Casework

- Fixed Benches: Yes, against walls- Mobile Benches: n/a- Movable Tables: n/a - Wall Upper Cabinets: Yes, over fi xed benches- Tall Cabinets/Type: n/a- Countertop Mat.: Stainless Steel- Chemical Storage: n/a- Flammables: n/a- Acids/Bases: n/a

Utilities

- Overhead Drop Box- 120V- Stainless Steel Sink (CW, HW, EW)- Compressed Air- Vacuum

Special Furniture/Equipment

- n/a

Page 36: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of ArkansasProgramming Document 44

Geotechnical | Direct Shear

20'-0

"

25'-0"

CORRIDOR

OVERHEAD DROP(120V, CA, VAC, DATA)

SINK(CS, HW, EW)

General

- Space Type: Direct Shear- Department: Geotechnical- Unit Area: 500 SF- Occupancy: 10 People-Adjacencies: Soil Prep

Architectural

- Floor Mat.: Polished Concrete- Wall Mat.: Concrete Masonry Unit (CMU)- Ceiling Mat.: None, Exposed Painted Structure

Casework

- Fixed Benches: Yes, against walls- Mobile Benches: n/a- Movable Tables: n/a - Wall Upper Cabinets: Yes, over fi xed benches- Tall Cabinets/Type: n/a- Countertop Mat.: Stainless Steel- Chemical Storage: n/a- Flammables: n/a- Acids/Bases: n/a

Utilities

- Overhead Drop Box- 120V- Data, Wireless Data, TYP.- Stainless Steel Sink (CW, HW, EW)- Compressed Air- Vacuum

Special Furniture/Equipment

- n/a

Page 37: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of Arkansas Programming Document 45

Geotechnical | Seismic Lab

20'-0

"

35'-0"

CORRIDOR

STORAGE

SOLDERING

CA

General

- Space Type: Seismic Lab- Department: Geotechnical- Unit Area: 700 SF- Occupancy: 14 People- Adjacencies: Soil Prep

Architectural

- Floor Mat.: Polished Concrete- Wall Mat.: Concrete Masonry Unit (CMU)- Ceiling Mat.: None, Exposed Painted Structure

Casework

- Fixed Benches: n/a- Mobile Benches: n/a- Movable Tables: Yes, centered in common room - Wall Upper Cabinets: n/a- Tall Cabinets/Type: n/a- Countertop Mat.: n/a- Chemical Storage: n/a- Flammables: n/a- Acids/Bases: n/a

Utilities

- Compressed Air

Special Furniture/Equipment

- Movable Tables (OFOI)- Chairs (OFOI)

Page 38: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of ArkansasProgramming Document 46

Asphalt | DSR

FD

20'-0

"

20'-0"

CORRIDOR

5' FH(120V, CS, CA, VAC)

FLAT PANELDISPLAY

CA, VAC

CA, VAC

EWES

SINK(CS, HW)

General

- Space Type: DSR- Department: Asphalt- Unit Area: 400 SF- Occupancy: 8 People- Adjacencies: Other Asphalt Labs

Architectural

- Floor Mat.: Polished Concrete- Wall Mat.: Concrete Masonry Unit (CMU)- Ceiling Mat.: None, Exposed Painted Structure

Casework

- Fixed Benches: Yes, against walls- Mobile Benches: n/a- Movable Tables: Yes, centered in room - Wall Upper Cabinets: Yes, over fi xed benches- Tall Cabinets/Type: n/a- Countertop Mat.: Stainless Steel- Chemical Storage: n/a- Flammables: n/a- Acids/Bases: n/a

Utilities

- Floor Box- 120V- Data, Wireless Data, TYP.- Stainless Steel Sink (CW, HW, EW)- Compressed Air- Vacuum- Eyewash Station/Emergency Shower w/ Floor Drain

Special Furniture/Equipment

- Fume Hood (CFCI)- Flat Panel Display (OFOI)- Extraction & Recovery (OFOI)

Page 39: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of Arkansas Programming Document 47

Asphalt | Specifi c Gravity

20'-0

"

25'-0"

CORRIDOR

SPECIFICGRAVITYSTATION

CA, VAC

CA, VAC

CA, VAC

SINK(CS, HW)

SINK(CS, HW, EW)

SINK(CS, HW)

SINK(CS, HW)

General

- Space Type: Specifi c Gravity- Department: Asphalt- Unit Area: 500 SF- Occupancy: 10 People- Adjacencies Other Asphalt Labs

Architectural

- Floor Mat.: Polished Concrete- Wall Mat.: Concrete Masonry Unit (CMU)- Ceiling Mat.: None, Exposed Painted Structure

Casework

- Fixed Benches: Yes, against walls- Mobile Benches: n/a- Movable Tables: n/a - Wall Upper Cabinets: Yes, over fi xed benches- Tall Cabinets/Type: n/a- Countertop Mat.: Stainless Steel- Chemical Storage: n/a- Flammables: n/a- Acids/Bases: n/a

Utilities

- Floor Box- 120V- Stainless Steel Sink (CW, HW, EW)- Compressed Air- Vacuum

Special Furniture/Equipment

- Specifi c Gravity Station (CFCI)- Start-up Equipment (CFCI)

Page 40: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of ArkansasProgramming Document 48

Asphalt | Mixing/Compaction/Testing

FD

40'-0

"

55'-0"

CORRIDOR

5' FH(120V, CS, CA,VAC, NG)

OVENS

NG

FLOOR OVENS(208V) ERSA

MACHINE(EXIST.)

EWES

OVERHEAD DROP(120V)

COMPACTORS(EXISTING)

IGNITION OVEN(DIRECT VENT

OUTSIDE)

5' FH(120V, CS, CA,

VAC, NG)

General

- Space Type: Mixing/Compaction/Testing- Department: Asphalt- Unit Area: 2,200 SF- Occupancy: 44 People- Adjacencies: Other Asphalt Labs

Architectural

- Floor Mat.: Polished Concrete- Wall Mat.: Concrete Masonry Unit (CMU)- Ceiling Mat.: None, Exposed Painted Structure

Casework

- Fixed Benches: Yes, against walls- Mobile Benches: n/a- Movable Tables: Yes, centered in room- Wall Upper Cabinets: Yes, over fi xed benches- Tall Cabinets/Type: n/a- Countertop Mat.: Stainless Steel- Chemical Storage: n/a- Flammables: n/a- Acids/Bases: n/a

Utilities

- Overhead Drop Box- 120V- Natural Gas- Compressed Air- Vacuum- Eyewash Station/ Emergency Shower w/ Floor Drain

Special Furniture/Equipment

- Fume Hood (CFCI)- Small Ovens (OFOI)- Compactors (OFCI)- Ignition Oven (OFCI)

- ERSA Machine (OFCI)- AMPT (CFCI)-Large Floor Ovens (OFCI)

Page 41: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of Arkansas Programming Document 49

Asphalt | Sample Prep

FD

20'-0

"

25'-0"

CORRIDOR

SHAKER

SHAKER

AGG

REG

ATEEQUIPMENT ZONE

(SAWS, 220V, DRILL PRESS)(EXISTING)

JANITORSINK

SINK(CS, HW, EW)

General

- Space Type: Sample Prep- Department: Asphalt- Unit Area: 500 SF- Occupancy: 10 People- Adjacencies: Aggregate

Architectural

- Floor Mat.: Polished Concrete- Wall Mat.: Concrete Masonry Unit (CMU)- Ceiling Mat.: None, Exposed Painted Structure

Casework

- Fixed Benches: Yes, against walls- Mobile Benches: n/a- Movable Tables: n/a- Wall Upper Cabinets: Yes, over fi xed benches- Tall Cabinets/Type: n/a- Countertop Mat.: Stainless Steel- Chemical Storage: n/a- Flammables: n/a- Acids/Bases: n/a

Utilities

- 120V- 220V- Stainless Steel Sink (CW, HW, EW)- Janitor Sink- Floor Drain

Special Furniture/Equipment

- Saws (OFCI)- Shaker (OFCI)

Page 42: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of ArkansasProgramming Document 50

Asphalt | Aggregate Lab

30'-0

"

40'-0"

CORRIDOR

SAM

PLE

PREP

JANITORSINK

OVERHEAD DROP(120V)

EQUIPMENT ZONE

OVEN

440V

CA CA

OVERHEAD DOOR

SINK(CS, HW, EW)

SINK(CS, HW)

General

- Space Type: Aggregate Lab- Department: Asphalt- Unit Area: 1,200 SF- Occupancy: 24 People- Adjacencies: Sample Prep

Architectural

- Floor Mat.: Polished Concrete- Wall Mat.: Concrete Masonry Unit (CMU)- Ceiling Mat.: None, Exposed Painted Structure

Casework

- Fixed Benches: Yes, against walls- Mobile Benches: n/a- Movable Tables: n/a- Wall Upper Cabinets: Yes, over fi xed benches- Tall Cabinets/Type: n/a- Countertop Mat.: Stainless Steel- Chemical Storage: n/a- Flammables: n/a- Acids/Bases: n/a

Utilities

- Overhead Drop Box- 120V- 440V- Compressed Air- Stainless Steel Sink (CW, HW, EW)- Janitor Sink

Special Furniture/Equipment

-Large Floor Ovens (OFCI)

Page 43: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of Arkansas Programming Document 51

CTTP | Training Classroom

30'-0

"

40'-0"

CORRIDOR

10'-0"40'-0" 10'-0"

CONFERENCE

CO

RR

IDO

R

STORAGE

GLASSMARKERBOARD

GLASSMARKERBOARD

GLASSMARKERBOARD

PROJECTOR

GLA

SSM

ARKE

RBO

ARD

COUNTER SPACE

LCD

GLA

SSM

ARKE

RBO

ARD

2'-0

"2'

-6"

5'-0"

FLOOR BOX(120V, DATA)

General

- Space Type: Training Classroom- Department: CTTP- Unit Area: 1,500 SF- Occupancy: 60 People- Adjacencies: CTTP Faculty & Labs

Architectural

- Floor Mat.: Carpet- Wall Mat.: Gypsum Board- Ceiling Mat.: Acoustic Ceiling Tile (ACT)

Utilities

- Floor Box- 120V- Data, Wireless Data, TYP.

Special Furniture/Equipment

- Tables & Chairs (OFOI)- Glass Markerboard (CFCI)- Projector (OFOI)- Projection Screen (CFCI)

Page 44: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of ArkansasProgramming Document 52

CTTP | Asphalt/Concrete LabGeneral

- Space Type: Asphalt/Concrete Lab- Department: CTTP- Unit Area: 5,600 SF- Occupancy: 10 People- Adjacencies: CTTP Training & Faculty

Architectural

- Floor Mat.: Polished Concrete- Wall Mat.: Concrete Masonry Unit (CMU)- Ceiling Mat.: None, Exposed Painted Structure

Casework

- Fixed Benches: Yes, against walls- Mobile Benches: n/a- Movable Tables: Yes, centered in room- Wall Upper Cabinets: Yes, over fi xed benches- Tall Cabinets/Type: n/a- Countertop Mat.: Stainless Steel- Chemical Storage: n/a- Flammables: n/a- Acids/Bases: n/a

Utilities

- Overhead Drop Box- 120V- Data, Wireless Data, TYP.- Stainless Steel Sink (CW, HW, EW)- Natural Gas- Eyewash Station & Floor Drain

Special Furniture/Equipment

- Flat Panel Display (OFOI)- Moveable Lab Benches (CFCI)- Glass Markerboard (CFCI)- Shakers (OFCI)- Environmental Chamber (CFCI)- Sulphur Capping (OFCI)- Large Floor Oven (OFCI)- Specifi c Gravity Stations (OFCI)

Page 45: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of Arkansas Programming Document 53

40'-0

"

CO

RR

IDO

R

80'-0"

15'-0

"15

'-0"

ASPHALT

CONCRETE

LAB CLASSROOM(LAB TABLES AND TEACHING WALL) TRAINING AREA

STORAGE

NUCLEAR STORAGEAND TESTING

SHAKERS

ENV. CHAMBER

SULFURCAPPING(EXIST.)

8'-0"

8'-0

"10'-0

"6'

-0"

10'-0

"

LCD

LCD

GLA

SSM

ARKE

RBO

ARD

GLASSMARKERBOARD

GLASSMARKERBOARD OVEN

OVERHEAD DROP, TYP.(120V, DATA)

CA CA

CA CA

COMPACTOR

OVEN

MOVABLELAB BENCHES

CTTP | Asphalt/Concrete Lab

Page 46: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of ArkansasProgramming Document 54

Student Projects | Student Fabrication

40'-0"

50'-0

"

LOC

KER

S

MOVABLELAB BENCHES

SINK(CS, HW, EW)

General

- Space Type: Student Projects- Department: Student Fabrication- Unit Area: 800 SF- Occupancy: 16 People- Adjacencies: Lobby

Architectural

- Floor Mat.: Polished Concrete- Wall Mat.: Glass Storefront/Concrete Masonry Unit (CMU)- Ceiling Mat.: None, Exposed Painted Structure

Casework

- Fixed Benches: Yes, against walls- Mobile Benches: n/a- Movable Tables: Yes, centered in room- Wall Upper Cabinets: Yes, over fi xed benches- Tall Cabinets/Type: n/a- Countertop Mat.: Stainless Steel- Chemical Storage: n/a- Flammables: n/a- Acids/Bases: n/a

Utilities

- Overhead Drop Box- 120V- Stainless Steel Sink (CW, HW, EW)

Special Furniture/Equipment

- Lockers (CFCI)- Movable Stainless Steel Tables (CFCI)

Page 47: UArk PROGRAM DOCUMENT

CVEG - Research & Education Building at University of Arkansas Programming Document55

Design Narratives 6

Page 48: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of ArkansasProgramming Document 56

Design Narratives | ArchitecturalArchitectural Material Selection Criteria

The application and use of exterior and interior materials will be closely analyzed andevaluated by the design team in consultation with Facilities Management. The appropriatematerials will be selected based on the following criteria:• Durability• Quality• Sustainability• Maintenance• Appropriateness to existing campus• Cost• Aesthetics

Architectural Expression and Materials Considerations

The exterior envelope for the Civil Engineering Research and Education Center will use appropriate materials that not only respond to the existing Arkansas Research and Technology Park (ARTP) campus and region but achieve the desired architectural presence for the facility based on University of Arkansas campus design standards and the ARTP planning study and master plan. The selected materials will complement and enhance the existing campus language of steel, glass, and metal elements. Materials will be in muted tones to reinforce the

look and feel of the ARTP, without being conspicuous. Glass, including storefront and curtain wall systems, and energy effi cient translucent wall panels will be utilized to achieve the desired visibility, day-lighting and transparency, as appropriate for the particular area to highlight the function of the building and emphasize entrances and circulation. Metal louvers will be utilized to provide sun shading. Metal wall panels will be utilized to wrap the building envelope in the classroom and offi ces areas of the building. Precast concrete panels will be utilized for increased durability on the exterior in areas of heavy machinery operation. A human scale and integration of student, faculty, and staff use will be addressed, to forward the goal of a quality University of Arkansas research and education. The interior will include an open steel structure to emphasize the function of the structures laboratory. Interior fi nishes and materials will be commercial quality, durable, cost-eff ective, and easily maintained to respond to the use while conveying an aesthetic sensibility and referencing the building’s exterior and the environment.

Page 49: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of Arkansas Programming Document 57

Design Narratives | Architectural

Page 50: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of ArkansasProgramming Document 58

Design Narratives | CivilUtilities

An existing 8-inch water main is located just north of the site. Approximate static water pressure in the area is calculated to be approximately 150 psi. It is currently anticipated that this main can be accessed for a water line extension and/or loop around the facility for domestic water and fi re protection.

Existing utilities along Cato Springs Road include a 6-inch water main, an 8-inch sanitary sewer main, a gas main, and three-phase electric lines. The existing residential area (to be purchased by the university and demolished) is served by service lines extending from the mains along Cato Springs Road. It is anticipated that these service lines will be abandoned to allow development on the property south of the proposed CVEG site. Based on available records, it is possible to extend a new sewer main north from Cato Springs Road to serve the site (parallel to the future street construction.)

In addition, based on available records, three-phase underground electric and gas is available at the existing Hazardous Materials Site to the east. It is anticipated that fi ber may be run from the existing Engineering Research Center (ENRC) unless connection can be made to the OSP Loop just east of the Hazardous Materials Site.

Page 51: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of Arkansas Programming Document 59

Site Access Roads

As shown in the adjacent fi gure, the University’s current master plan for the technology park illustrates proposed streets on three sides of the site with a plaza (for vehicles and pedestrians) on the south side. At this time, it is unknown whether or not the University will receive assistance from the city of Fayetteville to construct any of the future streets. For the purposes of this study, it is projected that at least one north/south street will be required from Cato Springs Road to serve the new CVEG facility. The facility may receive deliveries from large tractor-trailer trucks, and a loop around the site is ideal. However, for budgetary planning purposes one possible “Phase I” alternative is shown in the fi gure below. This would require approximately 700 linear feet of 30-foot wide (back of curb to back of curb) street construction plus a turnaround area near the truck entrance. This turnaround may need to extend into the area north of the Hazardous Materials facility and could include parking if necessary. An additional/alternative drive could also be constructed by paving/extending the existing gravel drive from the east. Phase I parking may also be constructed in the plaza area, and parallel spaces will be available on the street (spaces are included in the 30-foot width.) It is also pertinent to note that additional fi re lanes may be required by the fi re Marshall, and more discussion with the Fire Marshall will be necessary to determine extent of any fi re lanes.

Although a soil investigation and detailed design will be necessary to provide a pavement design, for budgetary purposes the following section is projected, which is typical for a local street in the area:• Two feet of undercut/replacement of select fi ll for subgrade• 10” Compacted Granular Base Course (AHTD Class 7 ABC)• 3” Asphalt

Design Narratives | Civil

Page 52: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of ArkansasProgramming Document 60

General Grading Discussion

Approximate existing site contours are shown below. As the fi gure illustrates, the site is relatively fl at and earthwork is expected to be minimal. It is anticipated that storm drainage will be conveyed directly to the creek located east of the site via sheet fl ow where possible. No detention is anticipated, but Low Impact Development measures will be implemented where practical to reduce and/or slow stormwater runoff .

Design Narratives | Civil

Page 53: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of Arkansas Programming Document 61

Design Narratives | StructuralIntroduction

The following narrative describes the structural design criterion and proposed structural framing systems for the New Civil Engineering Research Center to be constructed in the Technology Park south of the main campus at the University of Arkansas in Fayetteville, Arkansas. This new facility is anticipated to be a single story High-Bay structure with a below grade basement structure. Adjacent to the High-Bay structure, one and/or two story construction is anticipated.

Codes and References

The provisions of the following codes and references will be used for both design and construction of the new building. These documents establish the minimum structural strength and serviceability requirements to be met in order to safeguard the public health, safety, and general welfare.a. International Building Code (IBC)b. American Society of Civil Engineers (ASCE) 7, Minimum Design Loads for Buildings and Other Structuresc. American Concrete Institute (ACI) 318, Building Code Requirements for Structural Concreted. American Institute of Steel Construction (AISC) 360, Specifi cation for Structural Steel Buildings

Design Gravity Loads

a. Roof Live 20 PSFb. Strong Floor 250 PSFc. Main Floor Level 100 PSFd. Typical Elevated Floors 100 PSFe. Mechanical Rooms 150 PSF

Materials

Materials for the design and construction of the primary structural frame shall comply with the governing building code, design codes and manuals noted previously, and the following:

Cast-in-Place ConcreteStructural cast-in-place concrete shall be designed and constructed in accordance with the requirements of the governing building code and applicable American Concrete Institute standards. Concrete materials and classes shall conform to the following: a. Reinforcing Steel ASTM A615 Grade 60b. Deformed Bar Anchors ASTM A496c. Headed Stud Anchors ASTM A108d. Smooth Welded Wire Reinforcement ASTM A185e. Grade Beams 4000 psi NWCf. Slabs-on-Grade 4000 psi NWCg. Elevated Floors 4000 psi NWC

Structural SteelStructural steel shall be defi ned as that work prescribed in Section 2.1 of the AISC “Code of Standard Practice for Steel Buildings and Bridges”. All structural steel shapes shall be new steel as defi ned by ASTM A6 unless noted otherwise. Structural steel materials shall conform to the following:a. Wide Flange and WT Shapes ASTM A992 Grade 50b. Channels ASTM A36c. Angles ASTM A36d. Structural Steel Plates and Bars ASTM A36e. Base Plates ASTM A36f. Hollow Structural Sections ASTM A500 Grade Bg. High Strength Bolts ASTM A325 and A490h. Threaded Round Stock ASTM A36i. Anchor Rods ASTM F1554 Grade 55j. Steel Decking ASTM A1008 or A653

Page 54: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of ArkansasProgramming Document 62

Design Narratives | StructuralStructural Systems

Roof FramingThe roof framing system will likely consist of 1½” deep galvanized steel roof decking supported by conventional K- and/or LH-series open web steel joists spaced at a maximum of 6 feet on center. Additional framing will be provided as required for any fans or minor equipment located on the roof. These open web steel joists will be supported by conventional structural steel wide fl ange beams and columns.

High-Bay Structures LaboratoryThe cast-in-place concrete strong fl oor slab shall have a minimum thickness of 3’-0” and shall be heavily reinforced to support 100 kip reaction points located at 3’-0” on center in each direction. This fl oor structure shall span between basement tunnel walls allowing for a clear height of 8’-0” below the strong fl oor. Two 25-ton overhead bridge cranes, with a minimum hook height of 35’-0”, are anticipated to be installed above the structures lab to facilitate the movement of test specimens and loading frames. The building superstructure is anticipated to be comprised of structural steel wide fl ange columns and beams.

Elevated Floor Framing Elevated fl oor framing will likely consist of 4½” of normal weight cast-in-place concrete supported by 2” deep galvanized steel composite fl oor decking, supported by conventional structural steel wide fl ange beams and columns. In mechanical rooms, we anticipate 4” cast-in-place concrete housekeeping pads to be located on top of the structural slab to support mechanical equipment that is to be isolated from the structure for vibrations.

Phase II and Phase III Construction Architectural material selection is still preliminary for these buildings, but we anticipate the lab spaces to utilize CMU wall construction, which may be used as load bearing elements if the plan confi guration allows. Structural steel beam and column framing may also be utilized in concert with the CMU construction or as the primary framing system to allow for future fl exibility if the program needs change and spaces require reconfi guration.

Lateral Load Resisting SystemLateral loads due to wind and seismic will likely be transferred to the foundation level using conventional structural steel concentrically loaded braced frames designed as “Steel Systems Not Specifi cally Detailed for Seismic Resistance” as defi ned by ASCE 7 and the governing building code. Steel bracing systems off er an effi cient and economical solution for resisting lateral loads but also present challenges to the design team locating these frames throughout the building while attempting to accommodate the architectural layout.

Ground Floor LevelThe ground fl oor level is anticipated to be a conventional normal weight cast-in-place concrete slab-on-grade over a vapor retarder on a granular base material over a prepared subgrade of low volume change material. Required subgrade preparation will be determined based on the borings taken on the site and the subsequent recommendations off ered in the geotechnical investigation report. The slab-on-grade will likely be 5-inches thick, reinforced with welded wire reinforcing or synthetic macro fi ber reinforcement such as WR Grace’s Strux 90/40 (or an equivalent product). FoundationsA geotechnical investigation and subsequent foundation recommendations are not currently available for the site.

Page 55: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of Arkansas Programming Document 63

Design Narratives | MechanicalMECHANICAL

Lab Name Space

Temp

(°F)

HVAC

Zone

Exhaust Pressure

Relation

Process

Cooling

Water

Structural Labs

Strong Floor (High-Bay) 60-90 1Staging Area (High-Bay) 60-90 1Storage Area (High-Bay) 60-90 1Drive Lane (High-Bay) 60-90 1

Material Testing Lab 69-76 2 YesConcrete Mixing and Testing 60-90 1 Sieve room (-) to

High-BayMetallurgy 69-76 2 (1) 4’ Fume hood (+)Fabrication Shop and Tech Offi ce

60-90 1 (2) Snorkels (welding alcove, curtain to High-Bay)(1) Welding table (welding alcove, curtain to High-Bay)

(-) to High-Bay

Wind Engineering (High-Bay) 60-90 1Geotechnical Labs

Sample Prep 69-76 3 Sieve room (-) to Sample Test

Sample Test 69-76 3 (+)Soil Box Room 69-76 3 (+)Direct Shear 69-76 3 (+)Seismic Lab, common room 69-76 3 (+)Seismic Lab, small (Soldering Room)

69-76 3 (1) Snorkel in Soldering room (+) to common

Asphalt Labs

DSR 69-76 4 (1) 5’ Fume hood(1) Ventilated chemical storage

(-)

Specifi c Gravity 69-76 4Mixing/Compaction/Testing 69-76 4 (2) 5’ Fume hoods

Oven exhaust hoods(-)

Sample Prep 69-76 4 Sieve Room(s) (-)

Aggregate Lab 69-76 4 (4) SnorkelsOven exhaust hood(s)

(-)

HVAC Zone 1:

Two air rotation units will serve the High-Bay and associated spaces. Units will be externally mounted, vertical type air handing units with DX cooling, gas fi red heat exchanger, fi lters and a propeller type supply fan. The air rotation unit will be constructed of galvanized double wall housing meant for exterior installation. Return and supply air grilles will extend from each unit into the space. No distribution ductwork will be routed through the space. Each unit will have a remote air cooled condensing unit.

Natural ventilation will be used during periods when outdoor conditions permit it. Intake louvers will be located at a low point in the space, and relief louvers will be located at a high point in the space. When the outdoor ambient conditions permit, the air rotation units will shut down and the natural ventilation intake and relief louvers will open. Two exhaust/relief fans will be provided to assist the natural air circulation.

A welding exhaust system will be located in the High-Bay. The system will consist of a welding downdraft table and two snorkels. The ductwork serving this system will be galvanized steel, except the fan stack, which will be constructed of type 304 stainless steel. The welding exhaust fan will be a centrifugal utility type fan. The constant volume system will operate on an on/off switch located in the space.

A sieve/saw room is located in the Concrete Mixing and Testing Lab. This room will have a dedicated exhaust fan that will discharge directly to the exterior. The ductwork serving this system will be galvanized steel. The exhaust fan will be an inline axial fan. The constant volume system will operate on an on/off switch located in the space.

The Fabrication Shop and Tech Offi ce is included in zone 1, but is not open to the High-Bay. Supply air will be transferred from the High-Bay space into the Fabrication Shop and Tech Offi ce though a three transfer grilles, and two wall mounted exhaust fans.

HVAC Zone 2:

A packaged rooftop unit will provide the Materials Testing Lab and Metallurgy Lab with the required heating, cooling and ventilation air. The rooftop unit will be a factory fabricated packaged unit, designed for outdoor installation. The unit casing will be a heavy gauge coated steel with baked enamel fi nish. The unit will consist of a DX cooling coil, gas fi red heat exchanger, 4” throwaway fi lter, plenum supply fan and condenser/compressor section.

Page 56: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of ArkansasProgramming Document 64

Design Narratives | MechanicalLow pressure galvanized steel ductwork will distribute supply and return air to/from the rooftop unit to the spaces. Supply air ductwork will be externally insulated with 2” fi berglass insulation.

A 4’ fume hood will be located in the Metallurgy Lab. The ductwork serving the fume exhaust system will be constructed of type 304 stainless steel. The fume exhaust fan will be a centrifugal utility type fan. The constant volume system will operate 24 hours per day, 365 days a year.

HVAC Zone 3:

A packaged rooftop unit will provide the Geotechnical Lab Suite with the required heating, cooling and ventilation air. The rooftop unit will be a factory fabricated packaged unit, designed for outdoor installation. The unit casing will be a heavy gauge coated steel with baked enamel fi nish. The unit will consist of a DX cooling coil, gas fi red heat exchanger, 4” throwaway fi lter, plenum supply fan and condenser/compressor section.

Low pressure galvanized steel ductwork will distribute supply and return air to/from the rooftop unit to the spaces. Supply air ductwork will be externally insulated with 2” fi berglass insulation.

A sieve/saw room is located in the Sample Prep Room. This room will have a dedicated exhaust fan that will discharge the directly to the exterior. The ductwork serving this system will be galvanized steel. The exhaust fan will be an inline axial fan. The constant volume system will operate on an on/off switch located in the space.

A snorkel exhaust system will be located in the Seismic Lab. The ductwork serving this system will be galvanized steel, except the fan stack, which will be constructed of type 304 stainless steel. The exhaust fan will be a centrifugal utility type fan. The constant volume system will operate on an on/off switch located in the space.

HVAC Zone 4:

A packaged rooftop unit will provide the Asphalt Lab Suite with the required heating, cooling and ventilation air. The rooftop unit will be a factory fabricated packaged unit, designed for outdoor installation. The unit casing will be a heavy gauge coated steel with baked enamel fi nish. The unit will consist of a DX cooling coil, gas fi red heat exchanger, 4” throwaway fi lter, plenum supply fan and condenser/compressor section.

Low pressure galvanized steel ductwork will distribute supply and return air to/from the rooftop unit to the spaces. Supply air ductwork will be externally insulated with 2” fi berglass insulation.

The Asphalt Lab Suite will have a fume exhaust system. The fume exhaust system consists of (1) 5’ fume hood and a ventilated chemical storage cabinet in the DSR Lab, and (2) 5’ fume hoods in the Mixing/Compaction/Testing Lab. The ductwork serving the fume exhaust system will be constructed of type 304 stainless steel. The fume exhaust fan will be a centrifugal utility type fan. The constant volume system will operate 24 hours per day, 365 days a year.

A snorkel exhaust system will be located in the Seismic Lab. The ductwork serving this system will be galvanized steel, except the fan stack, which will be constructed of type 304 stainless steel. The exhaust fan will be a centrifugal utility type fan. The constant volume system will operate on an on/off switch located in the space.

Canopy hoods will be located over the ovens in the Mixing/Compaction/Testing Lab and Aggregate Lab. The ductwork serving this system will be galvanized steel, except the fan stack, which will be constructed on type 304 stainless steel. The exhaust fan will be a centrifugal utility type fan. The constant volume system will be interlocked with the ovens to operate whenever the ovens are turned on.

A sieve/saw room is located in the Sample Prep Room. This room will have a dedicated exhaust fan that will discharge the directly to the exterior. The ductwork serving this system will be galvanized steel. The exhaust fan will be an inline axial fan. The constant volume system will operate on an on/off switch located in the space.

Page 57: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of Arkansas Programming Document 65

Design Narratives | MechanicalProcess Cooling Water:

Process cooling water will be distributed to the hydraulic pumps. Process cooling water will be supplied from a packaged air cooled modular chiller. The system will consist of the air cooled chiller, (2) primary inline circulating pumps, water storage tank, bladder type expansion tank, air separator, side-stream water fi lter and a glycol feed tank.Process cooling water will be distributed through Type L copper piping with wrought copper fi tting and soldered joint for piping 2” and less, and ASTM A53 carbon steel piping and standard weight, seamless, carbon steel welded fi ttings for piping larger than 2-1/2”.

Process cooling water piping will be insulated with 1-1/2” of closed cell elastomeric type insulation.

Classrooms, Offi ces, and Student Spaces:

Packaged rooftop units will provide Classrooms, Offi ces, and Student Spaces with the required heating, cooling and ventilation air. The rooftop unit will be a factory fabricated packaged unit, designed for outdoor installation. The unit casing will be a heavy gauge coated steel with baked enamel fi nish. The unit will consist of a DX cooling coil, gas fi red heat exchanger, 4” throwaway fi lter, plenum supply fan and condenser/compressor section.

Low pressure galvanized steel ductwork will distribute supply and return air to/from the rooftop unit to the spaces. Supply air ductwork will be externally insulated with 2” fi berglass insulation.

The rooftop units will operate during occupied periods, or when there is a call for heating or cooling. Individual space controls will be provided to shut down ventilation supply air and return air to/from each space when not needed.

Toilet/General Exhaust System:

A central toilet/general exhaust system will provide exhaust for toilet rooms, janitor’s closets, storage rooms, etc. The system will consist of roof mounted, downblast exhaust fan. The fan will be constant volume and will operate during occupied periods only. The ductwork serving this system will be galvanized steel.

Electrical/ Telecom/ Mechanical/ Elevator Machine Room Cooling:

Electrical rooms, telecom rooms and elevator machine rooms will be cooled using DX fan coil units. The system will cycle on/off to maintain space temperature.

Control System:

Mechanical systems will be controlled and monitored through a microprocessor-based Direct Digital Control (DDC)/Building Automation System (BAS) with distributed processing at the local level. The overall building controls will be commercial grade and compatible with existing campus standards. The design must be compatible with the existing network in place.

A remote access option that is web based shall be provided for plug in laptop computers to interface with the BAS at the controller level.

DDC controllers, networks, and software will be the vendors standard product off ering.Control dampers will be commercial grade and will be selected for intended use with seals for low leakage. Modulating dampers will be sized for linear control characteristics.

Control valves will be commercial grade such as JCI standard ball or globe valves and will be selected for intended use. Control valves will be sized to provide suffi cient control authority throughout the required range.

Actuators will be selected for intended use and will have suffi cient torque and shutoff off characteristics to match system pressures and criteria. Fail positions will be chosen and specifi ed to minimize risks during failure modes.

Page 58: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of ArkansasProgramming Document 66

Design Narratives | ElectricalELECTRICAL

Site Electrical

The electric utility American Electric Power has 12.47kV available to the East of the proposed site at an existing 15kV switch. New utility power will be brought to the site to a new utility provided exterior pad mounted transformer. Secondary electrical service will be provided into the building.

Normal Power

Provide 480Y/277V, 2000 amp service switchboard with an insulated case main breaker, utility metering cabinet and group mounted feeder breakers. A SPD (Surge Protective Device) will be provided at the main service for transient protection. A digital meter will also be provided at the main breaker at the switchboard with communication port for use by the owner. Additional metering will be provided as part of all feeder breakers in the main switchboard with communication port for remote monitoring. Provide feeder breakers to all distribution panels and fl oor electrical room transformers via conduit and wire. Normal power distribution panels will contain bolt-on feeder circuit breakers. The capacity of the panels will be suffi cient for the addition of 20% future connected load. Provide a 480Y/277V panel at the mechanical room for HVAC and piping equipment. Provide a 150 amp Lighting panel to serve all lighting.

The main electrical room will also house (2) 300kVA transformers and 208Y/120V, 1000 amp distribution panels. The transformers will be 480:208Y/120V dry type. Branch panels will be located either within the electrical room, in the labs or within the corridors adjacent to the labs.

Point-of-use power connection devices will include specifi cation, grade, receptacles (120V, 20A, single-phase), power receptacles (208V and higher amperage), and surface metallic raceway (SMR). The SMR will be divided into two raceway compartments, one for power and one for telecommunications. There will also be empty raceways for the data acquisition system from the users equipment to the head-end equipment.

Lab Name Quantity

Service Chase below Strong Floor Provide Wiremold Raceway with 120V, 20A receptacles at each wall. 10 foot lengths of Wiremold with 20 feet of space between Wiremold.

Strong Floor (High-Bay) No power in middle of room.Staging Area (High-Bay) 1. 120V devices around perimeter at 6 foot spacing

2. 208V & 480V around perimeter. 4 total of each. Storage Area 120V devices around perimeter at 6 foot spacing

Drive Lane N/AMaterial Testing Lab 1. (2) 480V for hydraulic pumps.

2. Wiremold around perimeter with 120V and 208V.3. Computers at center of room require 120V (2 at each worksta-

tion).Concrete Mixing and Testing 1. Environmental Chamber 208/1/80A.

2. Freeze/Thaw Chamber 208/1/60A3. Misc. machines. (6) 208/1/30A4. 120V devices around perimeter at 6 foot spacing.5. (2) 208V for general use.6. 120V and 208/1 power at exterior of building for portable

equipmentMetallurgy 120V Wiremold around perimeterFabrication Shop and Tech Offi ce 1. 208V/1/60A for Welding

2. 120V SO cord drops at center.3. 120V along perimeter every 5 feet for equipment and general

use.Wind Engineering 120V around perimeter every 6 feet.Sample Prep 1. 120V SO cord drops at center.

2. 120V along perimeter every 18” for equipment and general use.

3. (2) 208/1/40A ovensSample Test 1. 120V SO cord drops at center.

2. 120V along perimeter every 18” for equipment and general use.

Soil Box Room 1. 120V SO cord drops at center.2. 120V along perimeter every 18” for equipment and general

use.Direct Shear 1. 120V SO cord drops at center.

2. 120V along perimeter every 18” for equipment and general use.

Seismic Lab, common room 120V around perimeterSeismic Lab, small Minimal 120VDSR 120V around perimeter. Some dedicated circuits. Panel and

receptacles get surge protection.

Page 59: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of Arkansas Programming Document 67

Design Narratives | ElectricalSpecifi c Gravity 120V around perimeter. Some dedicated circuits.Mixing/Compaction/Testing 1. (4) Large ovens 208/1/50A

2. (2) Small countertop ovens 120V. Dedicated circuits.3. 120V along perimeter every 18” for equipment and general

use.4. Power drop at middle of room.

Sample Prep 1. Concrete saw 208/1/30A.2. 120V along perimeter every 18” for equipment and general

use.Aggregate Lab 1. Large oven 480/3/60A.

2. 120V along perimeter every 18” for equipment and general use.

3. (2) 120V drops at middle of room.

Emergency Power

Provide an exterior 250 kW diesel generator with a skid mounted day tank that will have adequate capacity to operate the generator at full load for 8 hours. The generator will be provided with a weatherproof enclosure with a critical silencer. Generator will serve Egress lighting, fi re alarm system, BAS (Building Automation System), Access Control System, some select user equipment, Exhaust fans and make up air units for Fume Hoods.

A separate emergency electrical room will house the generator distribution panels and ATS’s. Provide (1) 70 amp ATS (Automatic Transfer Switch) for emergency loads and (1) 400 amp ATS for optional standby loads. Provide distribution panels to serve the above loads.

The following table lists the emergency power proposed for the user equipment:

Lab Name Quantity

Service Chase Below Strong Floor None

Strong Floor (High-Bay) Hydraulic Pump Control system (not the pumps). A couple of 120V receptacles.

Staging Area (High-Bay) NoneStorage Area NoneDrive Lane NoneMaterial Testing Lab Computer and controls.Concrete Mixing and Testing NoneMetallurgy NoneFabrication Shop and Tech Offi ce NoneWind Engineering NoneSample Prep NoneSample Test NoneSoil Box Room NoneDirect Shear NoneSeismic Lab, common room NoneSeismic Lab, small NoneDSR NoneSpecifi c Gravity NoneMixing/Compaction/Testing NoneSample Prep NoneAggregate Lab None

Grounding A complete low-impedance grounding electrode system will be provided for this building and will connect into the existing Lindley Hall grounding system. The grounding electrode system will include the main water service line, structural steel, Ufer Ground, and ground ring around the perimeter of the building. The equipment grounding system will extend from the building service entrance equipment to the branch circuit. All grounding system connections will be made using irreversible compression connections. Bonding jumpers will be provided as required across pipe connections to water meters, dielectric couplings in a metallic cold water system, and across expansion/defl ection couplings in conduit and piping systems. All feeders and branch circuits will be provided with an equipment ground conductor. Under no circumstances will the raceway system be used as an equipment grounding conductor.

Page 60: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of ArkansasProgramming Document 68

Design Narratives | ElectricalLightning Protection System

Protect all structures and associated appurtenances with a system of conductance designed to safely divert the energy of a lightning strike to the earth while minimizing damage to the facility. The two buildings will be connected together and be a single Master Label.

Lighting

All site lights will be the LED fi xture for parking lots as well as walkways. All interior lighting will be LED’s where possible. Lighting will be designed meet ASHRA 90.1.

Lighting controls will consist of occupancy sensors within the rooms as well as all corridors and stairwells. Daylight control will also be used throughout the building where practical.

Lab Name Quantity Notes

Service Chase Below Strong Floor

4’ Enclosed and gasketed. Wall mount every 20’ along all walls.

20 footcandles

Strong Floor (High-Bay) 4 Lamp 2’x4’ High-Bay T5HO fi xtures. 50 footcandlesStaging Area (High-Bay) 4 Lamp 2’x4’ High-Bay T5HO fi xtures. 50 footcandlesStorage Area 4 Lamp 2’x4’ High-Bay T5HO fi xtures. 50 footcandlesDrive Lane 4 Lamp 2’x4’ High-Bay T5HO fi xtures. 50 footcandlesMaterial Testing Lab 4’ Industrial fi xture 50 footcandlesConcrete Mixing and Testing 4’ Enclosed and gasketed. Pendant mount. 50 footcandlesMetallurgy 4’ Lens fi xture 50 footcandlesFabrication Shop and Tech Offi ce

4’ Industrial fi xture 50 footcandles

Wind Engineering 4 Lamp 2’x4’ High-Bay T5HO fi xtures. 50 footcandlesSample Prep 4’ Enclosed and gasketed. Pendant mount. 50 footcandlesSample Test 4’ Enclosed and gasketed. Pendant mount. 50 footcandlesSoil Box Room 4’ Enclosed and gasketed. Pendant mount. 50 footcandlesDirect Shear 4’ Industrial fi xture 50 footcandlesSeismic Lab, common room 4’ Industrial fi xture 50 footcandlesSeismic Lab, small 4’ lens fi xture 50 footcandlesDSR 4’ Industrial fi xture 50 footcandlesSpecifi c Gravity 4’ Industrial fi xture 50 footcandlesMixing/Compaction/Testing 4’ Industrial fi xture 50 footcandlesSample Prep 4’ Industrial fi xture 50 footcandlesAggregate Lab 4’ Industrial fi xture 50 footcandles

Fire Alarm

Provide an addressable fi re alarm and mass notifi cation system. This system will be a one way voice system with dual fi re alarm strobes and mass notifi cation strobes. Main fi re alarm panel will be located within a separate small closet with a Fire Alarm Annunciator panel located at the main entrance.

Page 61: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of Arkansas Programming Document 69

Design Narratives | Piping

Storm and Clearwater Drainage

A storm drainage system will be provided to convey rainwater from roofs to grade. Secondary roof drainage will be accomplished by using parapet scuppers or a dedicated piped overfl ow drainage system separate from the primary storm drainage system which will discharge through the building wall onto grade. The storm drainage system will be sized to handle a 3.9 in/hr rain event.

Clearwater waste from air handling units, coolers, and other devices and equipment that discharge clearwater will be conveyed by gravity fl ow through a separate piping system and will connect to the building storm system.

Drain points that cannot drain by gravity grade will fl ow into a sump with duplex sump pumps. Each pump will be sized for 100% of the load and can run at the same time. The pumps will be connected to the emergency (standby) power system. The piping for the storm and clearwater drainage system will be cast iron with hub and spigot joints below grade and no-hub joints above grade.

Sub-Soil Drainage

A sub-soil drainage system will convey groundwater from exterior footing, interior footing, underslab to a sump as determined by the Geotechnical Report. The effl uent will be pumped into the building storm drainage system and routed to grade.

Subsoil drainage systems will be drained by gravity to a sump for each building and will be pumped into the building storm drainage system. Each sump will consist of duplex sump pumps sized for 100% of the estimated design fl ow. Sump pumps will be connected to the emergency (standby) power system to permit operation during a loss of normal power.

Subsoil drainage piping, will be PVC perforated piping with solvent cement socket joints with fi lter socks.

Sanitary Waste and Vent

A sanitary waste and vent system will be provided for all plumbing fi xtures and other devices that produce sanitary waste. Plumbing fi xtures will be drained by gravity through conventional soil, waste and vent stacks, building drains and building sewers to the site sanitary sewer. Sanitary wastes which cannot discharge to the sewer by gravity fl ow will be drained by gravity to duplex sewage ejectors and will be pumped into the sanitary drainage system. The sump pump system serving the High-Bay will have its own oil interceptor to prevent any pump hydraulic fl uid from entering the sanitary system.

The piping for the sanitary drainage system will be cast iron with hub and spigot joints below grade and no-hub joints above grade.

Lab Name Quantity Notes

Structural Labs

Strong Floor (High-Bay) 5 Drains One per quadrant (4 drains total) under the strong fl oor located in the basement. 1 Drain in front of overhead door.

Staging Area (High-Bay) 3 Drains Evenly spacedStorage Area N/ADrive Lane 1 Drain Drain in front of overhead

doorMaterial Testing Lab 1 Drain, 1 sink along wall Floor drain for emergen-

cy in case pump water line breaks

Concrete Mixing and Testing 2 Drains, 1 sink with foot pedals Drains evenly spacedMetallurgy 4 Sinks 2 Sinks per wallFabrication Shop and Tech Offi ce 1 Sink Sink along wallWind Engineering 1 Drain Located near overhead

doorGeotechnical Labs

Sample Prep 2 Sinks Sinks along opposite walls

Sample Test 2 SinksSoil Box Room 1 Sink Along wallDirect Shear 1 Sink Along wallSeismic Lab, common room N/ASeismic Lab, small N/A

PIPING

Page 62: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of ArkansasProgramming Document 70

Design Narratives | PipingAsphalt Labs

DSR 1 Sink, 1 cup sink in hood Along wallSpecifi c Gravity 4 SinksMixing/Compaction/Testing N/ASample Prep 1 Sink, 1 janitor mop basinAggregate Lab 2 Sinks, 1 janitor mop basin

Laboratory Waste and Vent

Plumbing fi xtures in laboratories and laboratory support spaces will be provided with point of use waste treatment for sinks in labs using chemicals.

The piping for laboratory waste from sink to treatment device will be Schedule 80 fl ame-retardant polypropylene pipe, ASTM D4101, with socket fusion joints.

Lab Name Quantity Notes

Structural Labs

Strong Floor (High-Bay) N/AStaging Area (High-Bay) N/AStorage Area N/ADrive Lane N/AMaterial Testing Lab N/AConcrete Mixing and Testing N/AMetallurgy N/AFabrication Shop and Tech Offi ce N/AWind Engineering N/AGeotechnical Labs

Sample Prep N/ASample Test N/ASoil Box Room N/ADirect Shear N/ASeismic Lab, common room N/ASeismic Lab, small N/AAsphalt Labs

DSR 1 Treatment device Located under the sinkSpecifi c Gravity N/AMixing/Compaction/Testing N/ASample Prep N/AAggregate Lab N/A

Domestic Water System

Domestic water will be provided to all toilet room fi xtures, laboratory spaces, electric water coolers, sinks, emergency shower/eyewash units, and any other devices that require a domestic water supply. Hot water at 120°F will be provided to all fi xtures and devices that require hot water. The emergency fi xtures (showers and eyewashes) will be supplied with local mixing valve to supply tepid water.

A water meter will be provided on each building service entrance. The water meter will be sized for the building’s maximum design fl ow rate. The High-Bay building is estimated to be 150 gallons per minute. The smaller building is estimated to be 50 gallons per minute. The building’s water system will be isolated from the municipal water system by a duplex reduced pressure backfl ow preventer located downstream of the water meter. A water pressure booster pump is not anticipated at this time. A water fl ow test is needed to validate our assumption. Domestic hot water in the main building will be produced by duplex natural gas-fi red storage water heaters. Each water heater will be sized for 75% of the total load. Domestic hot water for the smaller building will be produced by a simplex natural gas-fi re storage water heater. The hot water system temperature will be maintained by recirculating the hot water through a continuous loop with an in-line circulating pump. Duplex alternating water softeners will be installed ahead of the water heaters.

The piping for the domestic hot and cold water will be type L copper tube with wrought copper fi ttings and soldered joints. Hot and cold water piping will be insulated.

Page 63: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of Arkansas Programming Document 71

Design Narratives | PipingLab Name Quantity Notes

Structural Labs

Strong Floor (High-Bay) N/AStaging Area (High-Bay) 2 Hose bibbs Evenly spaced along back

wallStorage Area N/ADrive Lane 1 Hose bibb Located on adjacent wall

to overhead doorMaterial Testing Lab 1 Sink along wallConcrete Mixing and Testing 1 Sink with foot pedals, 1-1/2” hose

bibb, 1 emergency eyewashHose bibb in center or room fed from ceiling

Metallurgy 4 Sinks 2 sinks per wallFabrication Shop and Tech Offi ce 1 Sink with eyewash Sink along wallWind Engineering N/AGeotechnical Labs

Sample Prep 2 Sinks Sinks along opposite walls

Sample Test 2 SinksSoil Box Room 1 Sink Along wallDirect Shear 1 Sink Along wallSeismic Lab, common room N/ASeismic Lab, small N/AAsphalt Labs

DSR 1 Sink, 1 cup sink in hood, 1 emer-gency shower and eyewash unit

Along wall

Specifi c Gravity 4 SinksMixing/Compaction/Testing 1 Emergency shower and eyewash

unitSample Prep 1 Sink, 1 janitor mop basinAggregate Lab 2 Sinks, 1 janitor mop basin

Non-potable Water System

Non-potable water system will provide make-up water to mechanical (HVAC) systems. A single reduced pressure backfl ow preventer will protect the domestic water supply and will be sized for 100% of the design load.

The piping for the non-potable water will be type L copper tube with wrought copper fi ttings and soldered joints. The non-potable water piping will be insulated.

Compressed Air Systems

Shop compressed air (SA) will be produced by triplex, oil-free rotary screw air compressors. Compressors will be base mounted. Air will be treated with coalescing fi lters, charcoal fi lters and particulate fi lters and dried with duplex refrigerant air dryers. Compressed air will be stored in an ASME rated vertical receiver with outlet pressure regulator. Shop compressed air will be distributed at 100 psi for pneumatic tools. Shop Compressed air piping system will be ASTM A53 carbon steel piping with threaded joints. Shop air will be routed underground to the smaller building from the production equipment located in the main building.

Lab compressed air (LA) will be produced by simplex, oil-less dry type point of use air compressor. Compressor will be base mounted. Air will be treated with coalescing fi lters, charcoal fi lters and particulate fi lters and dried with simplex heatless desiccant air dryer. Lab compressed air will be distributed at 150 psi.

Lab compressed air piping system will be ASTM B-819 type L copper piping with brazed joints, or type 316L stainless steel tubing.

Page 64: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of ArkansasProgramming Document 72

Design Narratives | PipingLab Name Quantity Notes

Structural Labs

Strong Floor (High-Bay) SA outlets located along the perim-eter walls

Evenly spaced every 20-25 ft

Staging Area (High-Bay) SA outlets located along the perim-eter walls

Evenly spaced every 20-25 ft

Storage Area SA outlets On separate wallsDrive Lane N/AMaterial Testing Lab SA outlets Evenly spaced around

roomConcrete Mixing and Testing SA outlets Evenly spaced along wallMetallurgy SA outlets Along 2 opposite wallsFabrication Shop and Tech Offi ce SA outlets Spaced over island benchWind Engineering N/AGeotechnical Labs

Sample Prep N/ASample Test LA outlets Spaced over island benchSoil Box Room SA outlets Spaced in center of roomDirect Shear SA outlets Spaced in center of roomSeismic Lab, common room N/ASeismic Lab, small SA outlet Located in solder roomAsphalt Labs

DSR SA outlets 2 per wall on opposite walls and 3 evenly spaced in center of room

Specifi c Gravity SA outlets Along wallMixing/Compaction/Testing SA outlet In fume hoodSample Prep N/AAggregate Lab SA outlets Along wall

Laboratory Vacuum System

Laboratory vacuum will be produced by duplex rotary vacuum pumps to serve the main building. Each vacuum pump will be sized for 65% of the load. The vacuum will be distributed at 20 in Hg. The piping will be copper type L, ASTM B-88 with wrought copper fi ttings and soldered joints.Laboratory vacuum for the smaller building will be produced by simplex point of use vacuum pump. The vacuum will be distributed at 20 in Hg. The piping will be copper type L, ASTM B-88 with wrought copper fi ttings and soldered joints.

A high vacuum system will be produced by a simplex local dry diaphragm vacuum pump operating at 25-30 mm Hg. Piping will be type 316L with compression joints.

Lab Name Quantity Notes

Structural Labs

Strong Floor (High-Bay) N/AStaging Area (High-Bay) N/AStorage Area N/ADrive Lane N/AMaterial Testing Lab N/AConcrete Mixing and Testing N/AMetallurgy N/AFabrication Shop and Tech Offi ce N/AWind Engineering N/AGeotechnical Labs

Sample Prep N/ASample Test High vacuum outlets Spaced over island bench Soil Box Room Outlets Spaced in center of roomDirect Shear Outlets Spaced in center of roomSeismic Lab, common room N/ASeismic Lab, small N/AAsphalt Labs

DSR 5 Outlets On opposite walls and in fume hood

Specifi c Gravity Outlets Along wallMixing/Compaction/Testing Outlets In fume hoodSample Prep N/AAggregate Lab N/A

Page 65: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of Arkansas Programming Document 73

Design Narratives | PipingNatural Gas System

Natural gas service will be supplied to the buildings from the main near the site. The natural gas will be supplied to the mechanical heating equipment at 2 psi and the rest of the building will be regulated down to 14 inches of water column or lower. The natural gas will also serve the domestic water heating equipment.

The piping will be distributed in ASTM A 53 carbon steel with welded joints in concealed locations or threaded joints in exposed locations.

Lab Name Quantity Notes

Structural Labs

Strong Floor (High-Bay) N/AStaging Area (High-Bay) N/AStorage Area N/ADrive Lane N/AMaterial Testing Lab N/AConcrete Mixing and Testing N/AMetallurgy N/AFabrication Shop and Tech Offi ce N/AWind Engineering N/AGeotechnical Labs

Sample Prep N/ASample Test N/ASoil Box Room N/ADirect Shear N/ASeismic Lab, common room N/ASeismic Lab, small N/AAsphalt Labs

DSR N/ASpecifi c Gravity N/AMixing/Compaction/Testing Outlets In fume hood and for

ovensSample Prep N/AAggregate Lab N/A

Page 66: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of ArkansasProgramming Document 74

Design Narratives | Technology Services

Equipment Spaces

Telecommunications Room (TR) placement must be located to keep individual cabling lengths less than 90 meters in length. There should be at least one TR located on each fl oor of the facility to ensure this cable length requirement is satisfi ed. Each TR requires minimum inside dimensions of 10 feet by 11 feet and should be positioned with direct access from a public corridor. One of the TR’s should also serve as a Building Entrance Facility (BEF) which accommodates incoming Fiber Optic and Copper Communication Cables to the facility. This BEF/TR must be located and operational in Phase 1. If the BEF cannot be located on the side of the building near the existing campus Fiber Optic Hut, a small wall fi eld within the MEP rooms may be required to ground any copper communications cables and to provide service access for this entry point to the facility. Should station cable distance limits be exceeded from TR to any outlets in the corner of the High-Bay, a small wall mounted communication rack may be required (pending University approval) in mezzanine storage or similar space. This would serve as a mii TR.

Each TR requires dedicated power and cooling services, and the associated fan coil units which will provide the room cooling cannot be mounted within the TR itself. It would be helpful to locate the TRs adjacent to a utility room or other space type where the fan coil units will have above ceiling mounting space outside and adjacent to the TRs.

Space for security control panels and building automation control panels must be provided separately from the TRs. Only systems maintained and controlled (or directly related) to University of Arkansas are allowed in the TRs. Exception would be the BEF which would have space for incoming Fiber Optic and Copper Communication cables.

Potential future horizontal expansion should be considered when programming room locations.

Incoming Services

A concrete encased duct bank containing Four (4) 4” conduits will be provided from the existing Fiber Optic Communications Building just East of the Facility to the new BEF.

An additional Four (4) 4” conduits should also be provided in a concrete encased duct bank from the existing Communications Building and stubbed just West of the Facility for campus expansion. This may share the same duct bank as the facility for a portion of the route.

Duct Banks should route around the perimeter of the building and not underneath, except where needed to route to the BEF. The BEF should be located near building’s exterior to minimize under fl oor raceway.

Structured Cabling

Primary distribution within the Facility will use fi ber optic and copper backbone cabling to connect incoming services to each of the TRs from the BEF/TR. Individual voice, data, wireless access points service drops within the Facility will use Category 6A rated copper cabling to support speeds up to 10 Gigabit Ethernet. Ethernet connections will also be provided at MTS head Ends. Assumption is there will be at least four of MTS connections. Active Electronics, wireless set up confi guration will be provided by the University. General convenience wall phones should be anticipated throughout the facility.

Lab Name Quantity Notes

Structural Labs

Strong Floor (High-Bay) Perimeter and center drops 3 Drops along each long side wall. 6 total

Staging Area (High-Bay) Perimeter and center drops 3 Drops along each long side wall. 6 total

Storage Area NoneDrive Lane NoneMaterial Testing Lab Drops in center of room and to MTSConcrete Mixing and Testing NoneMetallurgy NoneFabrication Shop and Tech Offi ce Center drops. Offi ce dropsWind Engineering Perimeter and center dropsGeotechnical Labs

Sample Prep Computer Work StationsSample Test Computer Work StationsSoil Box Room Computer Work Stations, center room

drops.Direct Shear Computer Work Stations, center room

drops.Seismic Lab, common room NoneSeismic Lab, small NoneAsphalt Labs

TECHNOLOGY SERVICES

Page 67: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of Arkansas Programming Document 75

Design Narratives | Technology ServicesDSR Computer Work Stations Large fl at screen.Specifi c Gravity Computer Work StationsMixing/Compaction/Testing Computer Work StationsSample Prep Computer Work StationsAggregate Lab Computer Work StationsCTTP Class rooms and training. Computer Work Stations. Offi ces

Floor Boxes I Data per table (20) for training.

Large fl at screen Distance Learning.

Wireless Networking

The Campus IT department will provide direction for placement of Wireless Access Point (WAP) locations throughout the Facility to accommodate full Wireless Ethernet (i.e. Wi-Fi) coverage in all areas. Additional WAP locations may also be located in public areas surrounding the building to provide outdoor Wi-Fi coverage. WAP enclosures may be required in some areas to protect Access Point electronics from harsh conditions.

Lab Name Quantity Notes

Structural Labs

Strong Floor (High-Bay) Yes, assume one WAP/antenna per 50’ radius.

Staging Area (High-Bay) Yes, assume one WAP/antenna per 50’ radius.

Storage Area Yes, assume one WAP/antenna per 50’ radius

Drive Lane NoMaterial Testing Lab Yes, assume one WAP/antenna per 50’

radiusConcrete Mixing and Testing Yes, assume one WAP/antenna per 50’

radiusMetallurgy Yes, assume one WAP/antenna per 50’

radiusFabrication Shop and Tech Offi ce Yes, assume one WAP/antenna per 50’

radius Yes, assume one WAP/antenna per 50’ radius

Wind Engineering Yes, assume one WAP/antenna per 50’ radius Yes, assume one WAP/antenna per 50’ radius

Geotechnical Labs

Sample Prep Yes, assume one WAP/antenna per 50’ radius

Sample Test Yes, assume one WAP/antenna per 50’ radius

Soil Box Room Yes, assume one WAP/antenna per 50’ radius

Direct Shear Yes, assume one WAP/antenna per 50’ radius

Seismic Lab, common room Yes, assume one WAP/antenna per 50’ radius

Seismic Lab, small Yes, assume one WAP/antenna per 50’ radius

Asphalt Labs

DSR Yes, assume one WAP/antenna per 50’ radius

Specifi c Gravity Yes, assume one WAP/antenna per 50’ radius

Mixing/Compaction/Testing Yes, assume one WAP/antenna per 50’ radius

Sample Prep Yes, assume one WAP/antenna per 50’ radius

Aggregate Lab Yes, assume one WAP/antenna per 50’ radius

Security System

Access control and CCTV systems supporting the building security system will be accommodated with device boxes and pathways provided by the project contractors. Detailed locations and sizes of these boxes and pathways will be as directed by the Campus Security Offi ce as program develops. Project documents will provide pathway only. Head End equipment and devices will be provided by The University.

All exterior doors, including overhead, will be controlled by Card Readers. MEPT rooms will not be controlled by Card readers. CCTV cameras will be required within the High-Bay space.

Page 68: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of ArkansasProgramming Document 76

Design Narratives | Fire Protection

Wet Pipe Sprinkler System

The building will be protected throughout with hydraulically calculated sprinkler systems, which except for special protection needs, will be wet pipe systems. All areas of the building will be protected per NFPA 13, including electrical rooms (i.e. switchgear rooms, transformer rooms, generator rooms, electrical closets, and similar rooms), loading docks, stair towers, exterior canopies, and mechanical rooms. The sprinkler system for the building will be designed and installed in accordance with NFPA 13. All systems will be hydraulically calculated with a computer calculation program using the Hazen-Williams method.

The piping for the wet pipe sprinkler system will be black steel. Piping 2” and smaller in size will be Schedule 40 with threaded joints. Piping larger than 2” will be Schedule 10 or Schedule 40 with welded fi ttings or roll groove couplings. The type of sprinkler heads installed in a particular area will be selected by the Engineer and the Project Architect. Generally, concealed sprinklers will be installed in areas having suspended ceilings. Pendent or upright sprinklers will be installed in areas without ceilings. Sidewall sprinklers will be provided only when other types cannot be utilized. Areas subject to temperatures below 40°F will be protected by dry sprinklers when possible. If dry sprinklers cannot be provided, then a dry pipe sprinkler system will be installed. A glycol antifreeze system will not be an option to dry sprinklers or a dry pipe system.

The Mixing/Compaction/Testing room and general mechanical rooms will be protected using ultra high temperature-rated sprinkler heads.

FIRE PROTECTION

Page 69: UArk PROGRAM DOCUMENT

CVEG - Research & Education Building at University of Arkansas Programming Document77

Conceptual Design 7

Page 70: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of ArkansasProgramming Document 78

Conceptual Design | Exterior Rendering & Site Plan

View from southeast corner

Conceptual design for the building was provided to aid in fundraising support for the construction of Phase 1 and to provide further accuracy of the cost model (located in appendix). The image and plans located here are schematic in nature, but refl ect planning and visual input from all stakeholders.

Phase 1 includes all building portions shown south of the phase line, the entire laydown yard, temporary parking in front of the building, relocation of (3) storage buildings, and limited drive lanes for vehicular access and material drop-off .

Phase 2 includes the addition of (5) asphalt labs to the north end of phase 1.

Phase 3 is a separate building located at the northeast corner of the site. This phase includes all laboratory, instruction, and administrative space to support the CTTP. Parking needed by CTTP is anticipated to be available from the master planned ARTP parking lots located to the east.

Page 71: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of Arkansas Programming Document 79

Conceptual Design | Floor Plans

INSTRUCTIONALAND

TESTINGLAB

MEN'S WOMEN'S

SHAKERS

STORAGE

OFFICE

OFFICE

OFFICE

OFFICE

OFFICE

OFFICE

DIR.OFFICEOFFICE

TELE

CO

M

STORAGE

CONFERENCE

TRAININGCLASSROOM

KITCHEN

LOBBY

CORRIDOR RECEPT

CO

RR

IDO

R

CONCRETE

ASPHALT

VEST.

VEST.

COMPUTERCLASSROOM

STUDENTFABRICATION

HIGHBAY

MEN

'S

WO

MEN

'S

JAN.

ELEV

LOBBY

VEST.

CO

RR

IDO

R

CORRIDOR

DIRECTSHEAR

SEISMIC

CONCRETEMIXING

ANDTESTING M

ETAL

LUR

GY

MATERIALTESTING

MECHANICAL

PUM

P

ELEC

TRIC

AL

SAMPLEPREP

SAMPLETEST

SOIL BOX

T.C.

STOR.

DSR AGGREGATE

SPECIFICGRAVITY

SAMPLEPREP

MIXING /COMPACTION

/ TESTING

VEST.

BONEYARD

FABRICATION

STAI

RS

OFF

ICE

WELDEMR

COOLER &STOR.TANKCONC. WASH AREA

JAN.

SHADED REGION ISSERVICE BASEMENTBELOW

25 TON CRANE

25 TON CRANE

STOR.

DEPARTMENT

ASPHALT

BONEYARD

BUILDING SUPPORT

CIRCULATION

COMMON

CTTP

GEOTECHNICAL

OFFICE

STRUCTURAL

STUDENT PROJECTS

EMERG.ELECT.

FIREALARMPANEL

TLT TLT ELEV.

CORR.

OFFICEOFFICE OFFICE OFFICE OFFICE OFFICE

CO

NFE

REN

CE

HUDDLE

GRADSTUDENTS

CORRIDOR

OPEN TO BELOW

OPEN TO BELOW

ROOF

ROOF

ROOF

MEZZANINESTORAGE

JAN.

T.C.GRADSTUDENTS

STO

R.

DEPARTMENT

ASPHALT

BONEYARD

BUILDING SUPPORT

CIRCULATION

COMMON

CTTP

GEOTECHNICAL

OFFICE

STRUCTURAL

STUDENT PROJECTS

Level 1

Phase 2 Phase 2Phase 1 Phase 1

Phase 3 Phase 3

Level 20 8' 16' 3 0 8' 16' 3

Page 72: UArk PROGRAM DOCUMENT

CVEG - Research & Education Center at University of ArkansasProgramming Document 80

High Bay Interior Perspec ve

Conceptual Design | Interior Rendering