TWRP Industry Briefing 28Nov2018 revFINAL upload version · TUAS WRP DTSS2 Industry Briefing SAFETY...
Transcript of TWRP Industry Briefing 28Nov2018 revFINAL upload version · TUAS WRP DTSS2 Industry Briefing SAFETY...
![Page 1: TWRP Industry Briefing 28Nov2018 revFINAL upload version · TUAS WRP DTSS2 Industry Briefing SAFETY SCHEDULE BUDGET QUALITY 28 November 2018](https://reader033.fdocuments.us/reader033/viewer/2022061617/5c0ced9e09d3f208568cd041/html5/thumbnails/1.jpg)
TUAS WRPDTSS 2
SAFETY ● SCHEDULE ● BUDGET ● QUALITY
Programme Speakers
3.00pm Registration
3.35pm Welcome AddressPart A: Overview of Tuas Water Reclamation Plant (TWRP)
Yong Wei HinDTSS 2 Director, PUB
3.45pm Part B: TWRP Implementation Updates Scott TruslerTWRP Project Director, Jacobs
4.45pm Q&As
5.00pm Networking Session
1
![Page 2: TWRP Industry Briefing 28Nov2018 revFINAL upload version · TUAS WRP DTSS2 Industry Briefing SAFETY SCHEDULE BUDGET QUALITY 28 November 2018](https://reader033.fdocuments.us/reader033/viewer/2022061617/5c0ced9e09d3f208568cd041/html5/thumbnails/2.jpg)
TUAS WRPDTSS 2
Industry BriefingIndustry Briefing
SAFETY ● SCHEDULE ● BUDGET ● QUALITY
28 November 2018
![Page 3: TWRP Industry Briefing 28Nov2018 revFINAL upload version · TUAS WRP DTSS2 Industry Briefing SAFETY SCHEDULE BUDGET QUALITY 28 November 2018](https://reader033.fdocuments.us/reader033/viewer/2022061617/5c0ced9e09d3f208568cd041/html5/thumbnails/3.jpg)
In case of an EmergencyIn case of an Emergency
3SAFETY ● SCHEDULE ● BUDGET ● QUALITY
West Wing(Registration/Security)
East Wing
![Page 4: TWRP Industry Briefing 28Nov2018 revFINAL upload version · TUAS WRP DTSS2 Industry Briefing SAFETY SCHEDULE BUDGET QUALITY 28 November 2018](https://reader033.fdocuments.us/reader033/viewer/2022061617/5c0ced9e09d3f208568cd041/html5/thumbnails/4.jpg)
TUAS WRPDTSS 2
Overview of Tuas Water Reclamation Plant(part of DTSS Phase 2)Overview of Tuas Water Reclamation Plant(part of DTSS Phase 2)
Yong Wei HinDTSS 2 Director, PUB
SAFETY ● SCHEDULE ● BUDGET ● QUALITY
![Page 5: TWRP Industry Briefing 28Nov2018 revFINAL upload version · TUAS WRP DTSS2 Industry Briefing SAFETY SCHEDULE BUDGET QUALITY 28 November 2018](https://reader033.fdocuments.us/reader033/viewer/2022061617/5c0ced9e09d3f208568cd041/html5/thumbnails/5.jpg)
AgendaAgenda
Safety CommitmentOverview of Tuas Water Reclamation Plant (TWRP)Update on Project Progress
5
Tunnel Section of DTSS Phase 1 Concept Rendering of Tuas WRP
SAFETY ● SCHEDULE ● BUDGET ● QUALITY
![Page 6: TWRP Industry Briefing 28Nov2018 revFINAL upload version · TUAS WRP DTSS2 Industry Briefing SAFETY SCHEDULE BUDGET QUALITY 28 November 2018](https://reader033.fdocuments.us/reader033/viewer/2022061617/5c0ced9e09d3f208568cd041/html5/thumbnails/6.jpg)
Safety CommitmentSafety Commitment
6SAFETY ● SCHEDULE ● BUDGET ● QUALITY
![Page 7: TWRP Industry Briefing 28Nov2018 revFINAL upload version · TUAS WRP DTSS2 Industry Briefing SAFETY SCHEDULE BUDGET QUALITY 28 November 2018](https://reader033.fdocuments.us/reader033/viewer/2022061617/5c0ced9e09d3f208568cd041/html5/thumbnails/7.jpg)
DTSS Phase 2 Safety MissionDTSS Phase 2 Safety Mission
SAFETY ● SCHEDULE ● BUDGET ● QUALITY 7
![Page 8: TWRP Industry Briefing 28Nov2018 revFINAL upload version · TUAS WRP DTSS2 Industry Briefing SAFETY SCHEDULE BUDGET QUALITY 28 November 2018](https://reader033.fdocuments.us/reader033/viewer/2022061617/5c0ced9e09d3f208568cd041/html5/thumbnails/8.jpg)
Tuas WRP OverviewTuas WRP Overview
8SAFETY ● SCHEDULE ● BUDGET ● QUALITY
![Page 9: TWRP Industry Briefing 28Nov2018 revFINAL upload version · TUAS WRP DTSS2 Industry Briefing SAFETY SCHEDULE BUDGET QUALITY 28 November 2018](https://reader033.fdocuments.us/reader033/viewer/2022061617/5c0ced9e09d3f208568cd041/html5/thumbnails/9.jpg)
Today
2016 2017 2018 2019 2020 2021 2022 2023 2024
Consultant Tender
Detailed Design
Construction
D&B Tender
Design & Construction
Consultant Tender
Detailed Design
Construction
DTSS Phase 2 Project Timeline
LINKSEWERS
TUNNELS
TUASWRP
SAFETY ● SCHEDULE ● BUDGET ● QUALITY 9
![Page 10: TWRP Industry Briefing 28Nov2018 revFINAL upload version · TUAS WRP DTSS2 Industry Briefing SAFETY SCHEDULE BUDGET QUALITY 28 November 2018](https://reader033.fdocuments.us/reader033/viewer/2022061617/5c0ced9e09d3f208568cd041/html5/thumbnails/10.jpg)
Overview of Tuas WRPOverview of Tuas WRP
10
Tuas WRP
IWMF
SAFETY ● SCHEDULE ● BUDGET ● QUALITY
![Page 11: TWRP Industry Briefing 28Nov2018 revFINAL upload version · TUAS WRP DTSS2 Industry Briefing SAFETY SCHEDULE BUDGET QUALITY 28 November 2018](https://reader033.fdocuments.us/reader033/viewer/2022061617/5c0ced9e09d3f208568cd041/html5/thumbnails/11.jpg)
Project OverviewProject Overview
11
1. Influent Pumping Stations
2. Liquids (Domestic and Industrial Used Water) Treatment Facilities
3. Biosolids Treatment Facility
4. NW and IW Storage & Pumping
5. Wet Weather Treatment
6. Admin/O&M with Visitor Gallery
Future Expansions
SAFETY ● SCHEDULE ● BUDGET ● QUALITY
![Page 12: TWRP Industry Briefing 28Nov2018 revFINAL upload version · TUAS WRP DTSS2 Industry Briefing SAFETY SCHEDULE BUDGET QUALITY 28 November 2018](https://reader033.fdocuments.us/reader033/viewer/2022061617/5c0ced9e09d3f208568cd041/html5/thumbnails/12.jpg)
Preparation Works StatusPreparation Works Status
Route 2 bridge COMPLETED; Route 3 bridgeTO BE COMPLETEDby year end
Soil investigation COMPLETED
Sitewide instrumentation & monitoring contract AWARDED
12SAFETY ● SCHEDULE ● BUDGET ● QUALITY
![Page 13: TWRP Industry Briefing 28Nov2018 revFINAL upload version · TUAS WRP DTSS2 Industry Briefing SAFETY SCHEDULE BUDGET QUALITY 28 November 2018](https://reader033.fdocuments.us/reader033/viewer/2022061617/5c0ced9e09d3f208568cd041/html5/thumbnails/13.jpg)
TUAS WRPDTSS 2
SAFETY ● SCHEDULE ● BUDGET ● QUALITY
TWRP ImplementationTWRP Implementation
13
Scott TruslerTWRP Project Director, Jacobs
![Page 14: TWRP Industry Briefing 28Nov2018 revFINAL upload version · TUAS WRP DTSS2 Industry Briefing SAFETY SCHEDULE BUDGET QUALITY 28 November 2018](https://reader033.fdocuments.us/reader033/viewer/2022061617/5c0ced9e09d3f208568cd041/html5/thumbnails/14.jpg)
AgendaAgenda
14
Raising the Bar – Safety• Safety UpdateProject Overview
• Major TWRP Components• Key Project Challenges
Project Delivery Updates• Contract Packages (Revised)• Overall Programme Timeline Changes• Scope & Tendering Requirements (Revised)• Pre‐Tender Qualification for Domestic LiquidsKey Takeaways
• Upcoming Tenders• Resources
SAFETY ● SCHEDULE ● BUDGET ● QUALITY
![Page 15: TWRP Industry Briefing 28Nov2018 revFINAL upload version · TUAS WRP DTSS2 Industry Briefing SAFETY SCHEDULE BUDGET QUALITY 28 November 2018](https://reader033.fdocuments.us/reader033/viewer/2022061617/5c0ced9e09d3f208568cd041/html5/thumbnails/15.jpg)
Ground RulesGround Rules
SAFETY ● SCHEDULE ● BUDGET ● QUALITY 15
Second
NO QUESTIONSor information related to ongoing TWRP tenders.
ACTUAL TENDER INFORMATIONfor respective contracts shall be issued by the Board.
INFORMATION SHARED
in this briefing / presentation is only
meant for your guidance and
planning purposes.
![Page 16: TWRP Industry Briefing 28Nov2018 revFINAL upload version · TUAS WRP DTSS2 Industry Briefing SAFETY SCHEDULE BUDGET QUALITY 28 November 2018](https://reader033.fdocuments.us/reader033/viewer/2022061617/5c0ced9e09d3f208568cd041/html5/thumbnails/16.jpg)
Raising the Bar – Safety Raising the Bar – Safety
16SAFETY ● SCHEDULE ● BUDGET ● QUALITY
![Page 17: TWRP Industry Briefing 28Nov2018 revFINAL upload version · TUAS WRP DTSS2 Industry Briefing SAFETY SCHEDULE BUDGET QUALITY 28 November 2018](https://reader033.fdocuments.us/reader033/viewer/2022061617/5c0ced9e09d3f208568cd041/html5/thumbnails/17.jpg)
Workplace Safety and Health Report: Jul to Sep 2018Workplace Safety and Health Report: Jul to Sep 2018
SAFETY ● SCHEDULE ● BUDGET ● QUALITY 17
![Page 18: TWRP Industry Briefing 28Nov2018 revFINAL upload version · TUAS WRP DTSS2 Industry Briefing SAFETY SCHEDULE BUDGET QUALITY 28 November 2018](https://reader033.fdocuments.us/reader033/viewer/2022061617/5c0ced9e09d3f208568cd041/html5/thumbnails/18.jpg)
Workplace Safety and Health Report: Jul to Sep 2018Workplace Safety and Health Report: Jul to Sep 2018
18SAFETY ● SCHEDULE ● BUDGET ● QUALITY
![Page 19: TWRP Industry Briefing 28Nov2018 revFINAL upload version · TUAS WRP DTSS2 Industry Briefing SAFETY SCHEDULE BUDGET QUALITY 28 November 2018](https://reader033.fdocuments.us/reader033/viewer/2022061617/5c0ced9e09d3f208568cd041/html5/thumbnails/19.jpg)
TWRP Safety RequirementsTWRP Safety Requirements
SAFETY ● SCHEDULE ● BUDGET ● QUALITY 19
SAFETY TRAINING FACILITY• Enhanced training• Simulators
04
FALL REDUCTION• Drones and laser scans• Pre fabrication• Machine platform railings
03ELECTRONIC PERMIT TO WORK
• On site• Overlapping / conflicting
• Trends
02
ACCESS CONTROLS• Who• Where• Qualifications
01
SELECTION OF PPE
• Reduced lanyard length
• Cut‐resistant gloves
05
![Page 20: TWRP Industry Briefing 28Nov2018 revFINAL upload version · TUAS WRP DTSS2 Industry Briefing SAFETY SCHEDULE BUDGET QUALITY 28 November 2018](https://reader033.fdocuments.us/reader033/viewer/2022061617/5c0ced9e09d3f208568cd041/html5/thumbnails/20.jpg)
Project OverviewProject Overview
20SAFETY ● SCHEDULE ● BUDGET ● QUALITY
![Page 21: TWRP Industry Briefing 28Nov2018 revFINAL upload version · TUAS WRP DTSS2 Industry Briefing SAFETY SCHEDULE BUDGET QUALITY 28 November 2018](https://reader033.fdocuments.us/reader033/viewer/2022061617/5c0ced9e09d3f208568cd041/html5/thumbnails/21.jpg)
Major TWRP ComponentsMajor TWRP Components
21
An illustration of the process flow
SAFETY ● SCHEDULE ● BUDGET ● QUALITY
Industrial Water Plant
![Page 22: TWRP Industry Briefing 28Nov2018 revFINAL upload version · TUAS WRP DTSS2 Industry Briefing SAFETY SCHEDULE BUDGET QUALITY 28 November 2018](https://reader033.fdocuments.us/reader033/viewer/2022061617/5c0ced9e09d3f208568cd041/html5/thumbnails/22.jpg)
Key Project ChallengesKey Project Challenges
22SAFETY ● SCHEDULE ● BUDGET ● QUALITY
01Manpower / supply chain competition
01Manpower / supply chain competition
03Multiple
overlapping contracts
03Multiple
overlapping contracts
02Safety02Safety
04Constrained
site
04Constrained
site
05Limited access
05Limited access
06Tight
programme
06Tight
programme
07Interfaces07
Interfaces
![Page 23: TWRP Industry Briefing 28Nov2018 revFINAL upload version · TUAS WRP DTSS2 Industry Briefing SAFETY SCHEDULE BUDGET QUALITY 28 November 2018](https://reader033.fdocuments.us/reader033/viewer/2022061617/5c0ced9e09d3f208568cd041/html5/thumbnails/23.jpg)
Project Delivery UpdatesProject Delivery Updates
23SAFETY ● SCHEDULE ● BUDGET ● QUALITY
![Page 24: TWRP Industry Briefing 28Nov2018 revFINAL upload version · TUAS WRP DTSS2 Industry Briefing SAFETY SCHEDULE BUDGET QUALITY 28 November 2018](https://reader033.fdocuments.us/reader033/viewer/2022061617/5c0ced9e09d3f208568cd041/html5/thumbnails/24.jpg)
Overall Programme ChangesOverall Programme Changes
Milestone 1 – September 2023» Industrial used water influent pumping station and only industrial liquids modules commissioned and operational
Milestone 2 – August 2024» Domestic used water influent pumping station and one‐half of liquids treatment stream commissioned and into production
» NEWater plant commissioned and into production
Milestone 3 – December 2025» Completion and commissioning of whole of Tuas WRP (Phase 1)
24SAFETY ● SCHEDULE ● BUDGET ● QUALITY
2017 | 2018
![Page 25: TWRP Industry Briefing 28Nov2018 revFINAL upload version · TUAS WRP DTSS2 Industry Briefing SAFETY SCHEDULE BUDGET QUALITY 28 November 2018](https://reader033.fdocuments.us/reader033/viewer/2022061617/5c0ced9e09d3f208568cd041/html5/thumbnails/25.jpg)
25
Contract Packages (11 nos.)Contract Packages (11 nos.)No. Name Description Remarks
C1A Site Development Works • Temporary site wide support infrastructures and services• Permanent yard piping, utilities, 22 kV, port sewer, near‐shore
outfall
• Award pending
C2A Influent Pumping Stations • Two coarse screen shafts, three pumping stations, rising mains• Two 66 kV substations
• Tendering
C3A Industrial Liquids Modules • Headworks, primary treatment and secondary treatment including MBR
• Scope reduced
C3B Industrial Water Treatment • Tertiary treatment to produce Industrial Water • New contract
C3C Domestic Liquids Modules and NEWater
• Primary and secondary treatment including MBR, and NEWater production
• Prior C3B added to C3C
• Pre‐tender qualification added
• No scope change
C3D Product Water Storage and Pumping
• Storage and pumping of NEWater and Industrial Water • Schedule shifted
C4A Biosolids and Digesters • THP, digestion, thickening, dewatering, solids conveyance • OCFs added
C5A Plant Monitoring and Control System
• SCADA/PLC system with progressive buildout
C6A Administration and Operations Buildings
• Two separate buildings
C6B Site Completion • Scope to be defined, includes roads, CCTV, main entrance and etc.
C6C Wet Weather Treatment Facility • Domestic used water overflow treatment and discharge
SAFETY ● SCHEDULE ● BUDGET ● QUALITY
![Page 26: TWRP Industry Briefing 28Nov2018 revFINAL upload version · TUAS WRP DTSS2 Industry Briefing SAFETY SCHEDULE BUDGET QUALITY 28 November 2018](https://reader033.fdocuments.us/reader033/viewer/2022061617/5c0ced9e09d3f208568cd041/html5/thumbnails/26.jpg)
SAFETY ● SCHEDULE ● BUDGET ● QUALITY 26
Milestone 3Completion of Testing and Commissioning of TWRP
Milestone 2Domestic Used Water & NEWater Commissioned
Milestone 1Industrial Used Water Commissioned
Dec 2018 / Jan 2019
Today
May 2018
Sep / Oct 2018
C1A – Site Development Works
C2A – Influent Pumping Stations
C3A – Industrial Liquids Modules
C3B – Domestic Liquids Module ‐ Primary
C4A – Biosolids and Digesters
C5A – Plant Monitoring and Control System
C6A – Administration and Operations Bldgs
Construct/Operate
Extended Commissioning
Construct/Operate
Construct/Operate
C3C – Domestic Liquids Module ‐ Secondary and NEWater
C3D – Product Water Storage and Pumping
C6B – Site Completion
C6C –Wet Weather Treatment Facility
Construct/Operate
Construct/Operate
Tendering and Construction TimelinesTendering and Construction Timelines
NOTE:The dates are indicative.
![Page 27: TWRP Industry Briefing 28Nov2018 revFINAL upload version · TUAS WRP DTSS2 Industry Briefing SAFETY SCHEDULE BUDGET QUALITY 28 November 2018](https://reader033.fdocuments.us/reader033/viewer/2022061617/5c0ced9e09d3f208568cd041/html5/thumbnails/27.jpg)
27
Milestone 3Completion of Testing and Commissioning of TWRP
Tendering and ConstructionTimelineTendering and ConstructionTimeline
Milestone 2Domestic Used Water & NEWater Commissioned
NOTE:The dates are indicative.
Milestone 1Industrial Used Water Commissioned
Feb 2019
Today
C3A – Industrial Liquids Modules
C4A – Biosolids and Digesters
C5A – Plant Monitoring and Control System
Operate
Construct/Operate
May 2018
Oct 2018
C1A – Site Development Works
Construct/OperateC2A – Influent Pumping Stations
C3C – Domestic Liquids Modules and NEWater
C6A – Administration and Operations Bldgs
C6B – Site Completion
C6C –Wet Weather Treatment Facility
Construct/Operate
C3B – Industrial Water Treatment Operate
Jan 2019 to Apr 2019
2018
SAFETY ● SCHEDULE ● BUDGET ● QUALITY
Construct/OperateC3D – Product Water Storage and Pumping
Pre‐tender qualification
Q4 2019
Apr 2019
Q4 2019
![Page 28: TWRP Industry Briefing 28Nov2018 revFINAL upload version · TUAS WRP DTSS2 Industry Briefing SAFETY SCHEDULE BUDGET QUALITY 28 November 2018](https://reader033.fdocuments.us/reader033/viewer/2022061617/5c0ced9e09d3f208568cd041/html5/thumbnails/28.jpg)
Contract 3A:Industrial Liquids ModulesContract 3A:Industrial Liquids Modules
Scope includes:» Two liquids treatment modules» Headworks, primary treatment tanks, secondary bioreactor and membrane tanks
» Ceramic and polymeric membranes» Industrial water treatment – now tendered separately (C3B)
» Odour control facility
28
Industrial Liquids Modules
SAFETY ● SCHEDULE ● BUDGET ● QUALITY
![Page 29: TWRP Industry Briefing 28Nov2018 revFINAL upload version · TUAS WRP DTSS2 Industry Briefing SAFETY SCHEDULE BUDGET QUALITY 28 November 2018](https://reader033.fdocuments.us/reader033/viewer/2022061617/5c0ced9e09d3f208568cd041/html5/thumbnails/29.jpg)
Contract 4A: Biosolids and DigestersContract 4A: Biosolids and Digesters
29
Biosolids Facilities
Scope includes:» Biosolids building with space for future equipment
» Thermal hydrolysis pre‐digestion, centrifuges for pre‐dewatering and thickening
» 10 silo digesters – potential construction with post‐tensioned precast panels
» Majority of the IWMF interfaces» Food waste and greasy waste receiving and treatment
» Odour control facilities
SAFETY ● SCHEDULE ● BUDGET ● QUALITY
![Page 30: TWRP Industry Briefing 28Nov2018 revFINAL upload version · TUAS WRP DTSS2 Industry Briefing SAFETY SCHEDULE BUDGET QUALITY 28 November 2018](https://reader033.fdocuments.us/reader033/viewer/2022061617/5c0ced9e09d3f208568cd041/html5/thumbnails/30.jpg)
Contract 3C: Entire Domestic Liquids Modules & NEWaterContract 3C: Entire Domestic Liquids Modules & NEWater
Scope includes:» Two liquids treatment modules» Headworks, primary treatment tanks,secondary bioreactor and membrane tanks
» Polymeric MBR membranes» NEWater production» Odour control facilities
30
Domestic Liquids Modules
SAFETY ● SCHEDULE ● BUDGET ● QUALITY
![Page 31: TWRP Industry Briefing 28Nov2018 revFINAL upload version · TUAS WRP DTSS2 Industry Briefing SAFETY SCHEDULE BUDGET QUALITY 28 November 2018](https://reader033.fdocuments.us/reader033/viewer/2022061617/5c0ced9e09d3f208568cd041/html5/thumbnails/31.jpg)
Contract 3A:Tendering Requirements – BCA Contract 3A:Tendering Requirements – BCA
31
C3A
SAFETY ● SCHEDULE ● BUDGET ● QUALITY
![Page 32: TWRP Industry Briefing 28Nov2018 revFINAL upload version · TUAS WRP DTSS2 Industry Briefing SAFETY SCHEDULE BUDGET QUALITY 28 November 2018](https://reader033.fdocuments.us/reader033/viewer/2022061617/5c0ced9e09d3f208568cd041/html5/thumbnails/32.jpg)
Contract 3A, 3C & 4A:Tendering Requirements – BCA Contract 3A, 3C & 4A:Tendering Requirements – BCA
32SAFETY ● SCHEDULE ● BUDGET ● QUALITY
Structure» Prime w/ named ME11‐L5* (or higher) subcontractor » Consortium
○ Lead plus 1 or 2 members (3 parties maximum)○ May require named ME11‐L5* (or higher) subcontractor IF no ME11‐L6*member
Prime or Consortium Lead» CW01‐A1» CW02‐A1
Consortium»Members may be CW01‐A1, CW02‐A1, or ME11‐L6*» Consortium parties must be exclusive» Joint and Several – all parties
ME11‐L5* means ME11‐L5 with min. paid‐up capital and min. net worth of $1.5 million (equivalent to Mechanical Engineering L6 financial grade)ME11‐L6* means ME11‐L6 with min. paid‐up capital and min. net worth of $15 million (equivalent to Civil Engineering A1 financial grade)
![Page 33: TWRP Industry Briefing 28Nov2018 revFINAL upload version · TUAS WRP DTSS2 Industry Briefing SAFETY SCHEDULE BUDGET QUALITY 28 November 2018](https://reader033.fdocuments.us/reader033/viewer/2022061617/5c0ced9e09d3f208568cd041/html5/thumbnails/33.jpg)
ExamplesExamples
SAFETY ● SCHEDULE ● BUDGET ● QUALITY 33
CW02 – A1
ME11 – L6*
CONSORTIUMME11‐L6* LEADNot Allowed
CW01 – A1
CW02 – A1 ME11 – L6*
CONSORTIUM(No Subcon Req’d)
ME11 – L6
CW02 – A1
PRIME WITH SUBCONTRACTOR
ME11 – L5*
![Page 34: TWRP Industry Briefing 28Nov2018 revFINAL upload version · TUAS WRP DTSS2 Industry Briefing SAFETY SCHEDULE BUDGET QUALITY 28 November 2018](https://reader033.fdocuments.us/reader033/viewer/2022061617/5c0ced9e09d3f208568cd041/html5/thumbnails/34.jpg)
![Page 35: TWRP Industry Briefing 28Nov2018 revFINAL upload version · TUAS WRP DTSS2 Industry Briefing SAFETY SCHEDULE BUDGET QUALITY 28 November 2018](https://reader033.fdocuments.us/reader033/viewer/2022061617/5c0ced9e09d3f208568cd041/html5/thumbnails/35.jpg)
Pre‐Tender Qualification (PTQ) for Domestic LiquidsPre‐Tender Qualification (PTQ) for Domestic Liquids
35SAFETY ● SCHEDULE ● BUDGET ● QUALITY
![Page 36: TWRP Industry Briefing 28Nov2018 revFINAL upload version · TUAS WRP DTSS2 Industry Briefing SAFETY SCHEDULE BUDGET QUALITY 28 November 2018](https://reader033.fdocuments.us/reader033/viewer/2022061617/5c0ced9e09d3f208568cd041/html5/thumbnails/36.jpg)
Contract 3C: PTQ Requirements – BCAContract 3C: PTQ Requirements – BCA
36SAFETY ● SCHEDULE ● BUDGET ● QUALITY
Structure» Prime* » Consortium*
Prime or Consortium Lead» CW01‐A1» CW02‐A1
Consortium Applicants»May be CW01‐A1, CW02‐A1, or ME11‐L6*» Consortium parties must be exclusive
*Note: Subcontractors must be named and only Applicant(s) shall provide detailed information
![Page 37: TWRP Industry Briefing 28Nov2018 revFINAL upload version · TUAS WRP DTSS2 Industry Briefing SAFETY SCHEDULE BUDGET QUALITY 28 November 2018](https://reader033.fdocuments.us/reader033/viewer/2022061617/5c0ced9e09d3f208568cd041/html5/thumbnails/37.jpg)
Contract 3C: PTQ CriteriaContract 3C: PTQ Criteria
37SAFETY ● SCHEDULE ● BUDGET ● QUALITY
Approach & Scope of Appreciation
Understanding of the project and requirements
Response to specific topics
OTHER CRITERIAOTHER CRITERIA
Personnel & Organisation
Staff proposed for the work
Performance of the work
Track Record
Certified HSE policy and track record
Large, complex WRPprojects and processing plants and facilities
OTHER CRITERIA
Necessary resources to support project
BCA Registration
CRITICAL CRITERIA
Safety, Debarment Record
Safety, ISO Certifications
![Page 38: TWRP Industry Briefing 28Nov2018 revFINAL upload version · TUAS WRP DTSS2 Industry Briefing SAFETY SCHEDULE BUDGET QUALITY 28 November 2018](https://reader033.fdocuments.us/reader033/viewer/2022061617/5c0ced9e09d3f208568cd041/html5/thumbnails/38.jpg)
Contract 3C: PTQ and Tendering TimelineContract 3C: PTQ and Tendering Timeline
38
1
2
3
4Industry Briefing
Pre‐Tender Qualification
Calling
Pre‐Tender Qualification Evaluation
Pre‐Tender Qualification Shortlist
Notification
JAN 2019 ‐FEB 2019
MAR ‐APR 2019
APR 201928 NOV
SAFETY ● SCHEDULE ● BUDGET ● QUALITY
![Page 39: TWRP Industry Briefing 28Nov2018 revFINAL upload version · TUAS WRP DTSS2 Industry Briefing SAFETY SCHEDULE BUDGET QUALITY 28 November 2018](https://reader033.fdocuments.us/reader033/viewer/2022061617/5c0ced9e09d3f208568cd041/html5/thumbnails/39.jpg)
Key TakeawaysKey Takeaways
39SAFETY ● SCHEDULE ● BUDGET ● QUALITY
![Page 40: TWRP Industry Briefing 28Nov2018 revFINAL upload version · TUAS WRP DTSS2 Industry Briefing SAFETY SCHEDULE BUDGET QUALITY 28 November 2018](https://reader033.fdocuments.us/reader033/viewer/2022061617/5c0ced9e09d3f208568cd041/html5/thumbnails/40.jpg)
Upcoming Tenders and ResourcesUpcoming Tenders and Resources
40SAFETY ● SCHEDULE ● BUDGET ● QUALITY
UPCOMING TENDERSC3C Pre‐tender qualification – Jan 2019 to Apr 2019C3A Tender – Q1 2019C3C Tender – Q3 2019C4A Tender – Q2 2019 C5A Tender – Q3 2019C3D Tender – Q4 2019
DTSS 2 RESOURCESVisit https://www.pub.gov.sg/dtss/phase2/resources for more information related to DTSS 2 projects
FOR ENQUIRIESUse [email protected] mailbox for general enquiries
0303
0202
0101
![Page 41: TWRP Industry Briefing 28Nov2018 revFINAL upload version · TUAS WRP DTSS2 Industry Briefing SAFETY SCHEDULE BUDGET QUALITY 28 November 2018](https://reader033.fdocuments.us/reader033/viewer/2022061617/5c0ced9e09d3f208568cd041/html5/thumbnails/41.jpg)
Q&AsQ&As
41SAFETY ● SCHEDULE ● BUDGET ● QUALITY
![Page 42: TWRP Industry Briefing 28Nov2018 revFINAL upload version · TUAS WRP DTSS2 Industry Briefing SAFETY SCHEDULE BUDGET QUALITY 28 November 2018](https://reader033.fdocuments.us/reader033/viewer/2022061617/5c0ced9e09d3f208568cd041/html5/thumbnails/42.jpg)
Reminder: Ground RulesReminder: Ground Rules
SAFETY ● SCHEDULE ● BUDGET ● QUALITY 42
Second
NO QUESTIONSor information to be asked pertaining to ongoing TWRP tenders.
ACTUAL CONTRACT INFORMATIONshall derive from respective tender documents issued by the Board.
INFORMATION SHARED
in this briefing / presentation is only
meant for your guidance and
planning purpose.
![Page 43: TWRP Industry Briefing 28Nov2018 revFINAL upload version · TUAS WRP DTSS2 Industry Briefing SAFETY SCHEDULE BUDGET QUALITY 28 November 2018](https://reader033.fdocuments.us/reader033/viewer/2022061617/5c0ced9e09d3f208568cd041/html5/thumbnails/43.jpg)
Thank youThank you
43SAFETY ● SCHEDULE ● BUDGET ● QUALITY