DDMS ORBITER TURNAROUND BRIEFING DDMS ORBITER TURNAROUND BRIEFING.
-
Upload
lucinda-perry -
Category
Documents
-
view
267 -
download
5
Transcript of DDMS ORBITER TURNAROUND BRIEFING DDMS ORBITER TURNAROUND BRIEFING.
04/18/23 For Official Use Only
OVERVIEW
• DOD Mission• Turnaround Plan
– Command Relationships
– Plan Execution
– Support Forces and Resources
• Turnaround Layout
04/18/23 For Official Use Only
- JSCP/Charter Documents
S3005 - Support transfer of equipment from KSC/ DFRC to ELS
S3003 - Equipment and material record
S5044 - Post landing deservicing / mate toSCA - CLS
3611 - DOD turnaround plan 3611
36007 - DOD TPFDD
- Force Module Menu
- JSCP/Charter Documents
S3005 - Support transfer of equipment from KSC/ DFRC to ELS
S3003 - Equipment and material record
S5044 - Post landing deservicing / mate toSCA - CLS
3611 - DOD turnaround plan 3611
36007 - DOD TPFDD
- Force Module Menu
DELIBERATE PLANNING DOCUMENTS
DELIBERATE PLANNING DOCUMENTS
DOD MISSION
Support a NASA Led Orbiter Recovery from a Contingency Landing Site
(also Called a “Turnaround Operation”)• Provide Airlift and Sealift • Provide Bare Base Assets and Services
– Latrines, GP Shelters (9), Aircraft hangars (2), AM-2 matting– Power, GSE, vehicles, Air conditioning, communications
• Personnel and Equipment provided as available and without adversely impacting primary mission• All logistics support provided on a reimbursable basis
KEY ASSUMPTIONS
• Permissive Environment• No Competing Military Actions• NASA Equipment Readily Deployable• Int’l Agreements Remain Valid• Landing Site Ready to Receive Deployment Flow• NASA will make maximum use of host nation
support, local contracts, and commercial services
DDMS SPACE SHUTTLE OPERATIONS
• Initial Response (3610)– Locate/Search
– Rescue
– Deploy RRT/MIT
– Safe Orbiter/Secure Scene
• Recovery Operations (3611)– Requirements (PRD, RMT, MMT)
– Determine COA/Plan (FuncPlan 3611)
– Execute
HISTORY
• STS-3 Turnaround at WSSH in 1982– Stateside Operation Utilizing Rail and road
Transportation
– Augmented Site with In-Place Cool/Purge Units and Fixed Crane for Mating
• An Overseas Turnaround has Never Been Tested!• Renewed Interest within NASA, USA, and DDMS
• The DOD Manager (COMSTRAT), Manned Space Flight Support Operations, is the Supported Commander
• JTF-DDMS has TACON of Deployed DOD Forces
COMMAND RELATIONS
ASSET PROVIDER MISSION
JTF DDMS/Supported CC JTF Commander and staff
Strategic Airlift Elements AMC Strategic airlift
Fast Sealift Vessel MSC Strategic sealift
Tanker/Airlift Control Element AMC Airlift support / coordination
Bare Base (Large Facilities) 49 MMG, Holloman AFB Tech teams, hangars, A/C package, shelters
Bare Base Geographic CC Billeting, messing, hygiene
Red Horse/CE Geographic CC Site preparation
Prime Beef Geographic CC Construct Bare Base
Prime Rib Geographic CC Provide Bare Base services
Tactical Airlift Geographic CC Intratheater airlift
Communications Team Geographic CC JTF communications support
Security Forces Team Geographic CC Force protection (if required)
Airport Handlers Team AMC Airlift material processing
Longshore Team MSC Sealift material processing
Land Transportation Team MTMC Land transportation
SNAPSHOT OF DOD RESOURCES REQUIRED
COCOM/Direct Authority
OPCON
TACON
DIRLAUTH
CHAIN-OF-COMMAND
CINCsStaffs/CATs
USSTRATCOMStaff/CATDDMS
NASARMT
US AmbassadorTo Host Nation
JTF CC(DDMS)
SupportingDOD Units
JTF Staff
NASA DOTLeader
NASAMIT
Host NationLiaison Officer
DeputyDOD Mgr
NASAMMT
Secretary of State
NASADirector
SupportingCINCs
NCA
DOD Manager(USSTRATCOM)
JOINT TASK FORCE (JTF-DDMS)
OVERSEAS
JTF(DDMS-CC)
DEP JTF(BASE)
HOST NATIONLIAISON
COUNTRYTEAM REP
(DOS)
US BASECOMMANDER
(LOCAL)
AOR CCCAT
J-3(DDMS)
J-4(Geo CC)
J-6(Geo CC)
SECURITY(Geo CC)
CIVIL ENG(Geo CC)
MEDICAL(Geo CC)
PAO(USSTRATCOM)
SERVICES(Geo CC)
ADMIN(Geo CC)
TURNAROUND PHASES
Deployment Schedule
Days
20 10040 80600
SAFING
DEPLOYMENT
TURNAROUND
REDEPLOY32
30
24
5
Phase IV
Phase III
Phase II
Phase I
PERSONNEL PLAN
85 89
# Of Days After Landing
1 5 9
13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81
DODDODDODDODDODDODDODDODDODDODDODDODDODDODDODDODDODDODDODDODDODDODDODDODDODDODDODDODDODDODDODDODDODDODDODDODDODDODDODDODDODDODDODDODDOD0
100
200
300
400
500
600
533364
Total
DOD
NASA
PHASE 1 SAFING
PHASE 3 TURNAROUND
PHASE 2 DEPLOYMENT
PHASE 4 REDEPLOY
# o
f P
erso
nn
el
PHASE I - ORBITER SAFING(C+0 THRU C+4)
• JTF Staff Forms and Deploys• TPFDD Scrubbed and Executed• RRT & MIT Airlifted• Deploy Critical Safing Equipment• TALCE/Prime BEEF Teams Deploy• Comm Teams Deploy• MSC Ship Mobilized• Stage Sealift Items
TRANSPORT SAFING EQUIPMENT
• Time Critical--Required 2-5 Days After a Contingency Landing– Equipment is bulky
– TALCE required to support airlift
– Airlift required to support OCONUS delivery
AIRCRAFT FLOW CONTINGENCY SITE
Day Support C-130 C-17 C-5 Total
C+0 RRT, Other TAL 2 1 3
C+1 Theater 1 1
C+2 TALCE 1 2 3
C+3 NASA Safing equip 1 1 4 6
C+4 NASA Safing equip, Bare Base 1 1 4 6
C+5 NASA Safing equip, Bare Base 1 1 1 3
C+6 Logistics, Bare base 3 3
PHASE II-DEPLOYMENT(C+5 THRU C+25)
• Bare Base Construction (As Required) • Prime RIB Deploys• Augment Security, Medical, and Weather• MSC Vessel Loads-Sails from POE• Sealift Vessel Arrives at POD Airlift NASA GSE
and Ops Team • TALCE and Prime BEEF Main Body Redeploys
CRANE REQUIREMENTS
• 800-ton Lattice-boom Truck Crane– DEMAG TC 4000 or equivalent– Crane-body is self-propelled
• Width approx 16’5”• Height approx 12’ 11”• 30+ flat-bed trailer loads accompany crane-body
• 250-ton lifting crane– American model 9520 or equivalent– Carrier width 13’– Carrier height 13’ 6 ½”
• NASA Begins 24-hour Turnaround Operations• JTF Staff Sustains Deployed Force• Pathfinder and Shuttle Carrier Aircraft (SCA)
Arrive• Orbiter Mated to SCA
PHASE III-TURNAROUND OPS(C+26 THRU C+56)
PHASE IV-FERRY FLIGHT & REDEPLOYMENT (C+57 THRU C+89)
• Pathfinder And SCA Depart On Ferry Flight to KSC
• Tear Down Bare Base Facilities• Redeploy NASA, DOD Personnel and
Equipment• Disestablish JTF
DOD SITE SUPPORT REQUIREMENTS
• Safing/Deservicing Area – 200 ft by 200 ft , taxiway access, 315 psi capable
• Mate/Demate Area– 200x200 ft, taxiway access, grounding system, 315 psi
capable
• Staging/Assembly Area– Hard surface, lighted, access to above areas
TEMPORARY FACILITIES SUPPORT
• Operational Support Facilities– Located near mate/demate area and servicing areas
– Total 12,000 square feet
• Equipment Storage/Processing Facilities– 8,000 sq ft for non-hazardous equipment storage
– 2,000 sq ft requires temperature control and will be used for HAZMAT processing
• Locate 1,250 ft from other facilities
• Supervisors Facility - Accommodate 6 personnel• Hangar Access (32h x 30w x 35l) for tailcone assembly
04/18/23 For Official Use Only
“Power Check Pad”
Orbiter Deservice Area
Operational Parking Apron
Taxiway D
Ball Bar
Taxiway C
Water
12345
6789GP
Shelters
GP Shelters
MobileLatrine
MobileKitchen
1
2Hangars
Power
Runway 02 / 20
MLMK
PrevailingWind
MateArea
TYPICAL TURNAROUND AREA
OTHER FORCES AND EQUIPMENT
• TALCE (C2, Aerial Port, Maintenance)• Bare Base Support
– Work Site Facilities • 2 Hangars; 9 General Purpose Shelters with Power
• On-Site Messing and Latrines
– Harvest Eagle Billeting if Required
– RED HORSE, Prime BEEF, Prime RIB
– Communications
• Medical (Joint DOD/NASA team)• Also: Fire, Security, Transportation