COLUMBUS TSPLOST PROJECT LISTING
TSPLOST PROJECTSBand 1CY 2013 - 2015
COLUMBUS RIVERWALK
Projected Costs: $10,000,000• PE - $1,000,000• CST - $9,000,000
Project Description:The extension of the Riverwalk behind Bibb and City Mills to complete the project
Riverwalk at Bibb Mills and North Highland Dam
Riverwalk at City Mills
Status:•Notice To Proceed – April 24, 2013•Hecht Burdeshaw is preparing construction plans
• All ROW has been identified. No additional property will be required
•Construction is anticipated by the first of 2015
As of February 20, 2014
INTERCITY EXPRESS BUSPARK-N-RIDE SERVICE
Projected Costs: $22,400,00• Costs to include design, maintenance
and operation• Budget for these items still to be
determined
Project Description:Construction of three express bus Park-N-Ride locations in Columbus using existing sites.
Proposed Trail From Infantry Museum to Levy Road
Status:• Notice To Proceed – April 24, 2013• Connectics Transportation Group was hired
in October 2013 to perform a Public Transit Needs Assessment
• Assessment needed to determine how best to serve our citizens
• Study includes route analysis, rider surveys• 2nd Public meeting to hear citizens needs and
concerns on May 8, 2014• No other activities will begin until study is
completed
Current METRA Route System
As of February 20, 2014
SOUTH LUMPKINMULTI-USE FACILITY
Projected Costs: $3,500,000• PE – $ 500,000• CST - $3,000,000
Project Description:A pedestrian/bicycle facility to be built along an abandoned rail road line. This linear greenway corridor is divided by Old Cusseta Road, Victory Drive, and Fort Benning Road
Status:• Notice To Proceed – September 10, 2013• Heath & Lineback Engineers are the lead
consultants on this project• Public meeting was held on January 16, 2014• Preliminary design – May 2014• Final design – November 2014• Project Bid & Construction – January 2015 • No other activities will begin until study is
completed
Proposed New Trail From Infantry Museum to Cusseta Road
As of February 20, 2014
US 27/CUSTER ROAD INTERCHANGERECONSTRUCTION/MODIFICATION
Projected Costs: $20,000,000• PE – $ 1,000,000• CST - $19,000,000
Project Description:This project will provide permanent public access to the proposed property bounded by US 27 to the south, I-185 to the west, and Cusseta Road to the north and east, which is the western boundary of Fort Benning
Status:• Notice To Proceed – April 19, 2013• MOU with Ft. Benning has been signed by all
parties• Wolverton & Associates have begun
preliminary design on project – expect completion by December
• Construction projected to begin Spring 2015
Proposed property to be accessed by project
As of February 20, 2014
TSPLOST PROJECTSBand 2CY 2016 - 2019
US 27/CUSTER ROAD INTERCHANGERECONSTRUCTION/MODIFICATION
Projected Costs: $47,670,000• ROW - $28,700,000• PE – GDOT Authorized in 2001• CST - $18,970,000
Project Description:The purpose of the project is to reconstruct the interchange of I-185 and Buena Vista Road
Status:• Notice To Proceed – Will not be authorized by
GDOT until 2016• GDOT has expressed an interest to accelerate
this project by authorizing the engineering to begin in 2014
Buena Vista Road Interchange
BUENA VISTA ROADINTERCHANGE
As of February 20, 2014
Project Description:The project will include road realignments and/or a possible overpass on Buena Vista Road
INTERSECTION IMPROVEMENTSALONG BUENA VISTA ROAD (Spider Web)
Projected Costs: $40,000,000• PE – $ 2,522,522 • ROW - $ 8,649,648• CST - $ 25,225,225• UTL - $ 3,603,605
Status:• Notice To Proceed – Will not be authorized by
GDOT until 2016• City has taken the initiative to fund the
preliminary concept and design of this project now
• Public hearing on this has been scheduled for May 12
• GDOT has expressed an interest to accelerate this project by authorizing the engineering to begin in 2014
Spider Web Area
As of February 20, 2014
SR 219 PASSING LANES FROM LUTHER LANDING BRIDGE TO HAPPY HOLLOW ROAD (River Road)
Project Description:A passing lane will constructed along SR 219 from Luther Road Bridge to Happy Hollow Road
Projected Costs: $17,690,438• PE – $ 1,597,736 • ROW - $ 403,427• CST - $ 14,187,438• UTL - $ 1,501,837
Status:• Notice To Proceed – Will not be authorized by
GDOT until 2016• This project will eventually be the sole
responsibility of GDOT
As of February 20, 2014
TSPLOST PROJECTSBand 3CY 2020 - 2022
Project Description:Project consists of improvements on Cusseta and Old Cusseta Road, from Fort Benning Road to Staunton Drive
Projected Costs: $58,289,412
• ROW - $ 41,402,448• CST - $ 16,866,964
Status:• Notice To Proceed – Will not
be authorized by GDOT until 2020
CUSSETA/OLD CUSSETA ROAD IMPROVEMENTS
As of February 20, 2014
DISCRETIONARY FUNDS
YTD Collections = $2,422,548
TSPLOST UPDATE April 24, 2014