SOUTH FULTON TSPLOST PROJECT LIST August 2016

Transcript of SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk...

Page 1: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

SOUTH FULTON

TSPLOSTPROJECT LIST

August 2016

Page 2: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Resurfacing

City of Chattahoochee Hills

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$2,082,377

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Maintenance and Safety Enhancements in City of Chattahoochee Hills

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of Chattahoochee Hills

Maintenance and Safety Enhancements

Tier 1

CH-101

SOUTH FULTON TSPLOST

Page 3: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Quick Response Projects

City of Chattahoochee Hills

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$56,280

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Quick Response Projects in City of Chattahoochee HillsProject Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of Chattahoochee Hills

Quick Response Projects

Tier 1

CH-102

SOUTH FULTON TSPLOST

Page 4: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Resurfacing

City of College Park

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$716,447

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Maintenance and Safety Enhancements in City of College Park - Resurfacing

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of College Park

Maintenance and Safety Enhancements

Tier 1

CP-101

SOUTH FULTON TSPLOST

Page 5: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Bridge Improvement

City of College Park

Herschel Road

Herschel Road at Camp Creek South Fork

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$544,500

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Bridge Improvement in City of College Park - Herschel Road at Camp Creek, South Fork

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of College Park

Bridges

Tier 1

CP-102

SOUTH FULTON TSPLOST

Page 6: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Bridge Improvement

City of College Park

Camp Creek Pkwy Frontage Rd

Camp Creek Parkway Frontage Road at Camp Creek South Fork

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$356,400

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Bridge Improvement in City of College Park - Camp Creek Parkway Frontage Road at Camp Creek,South Fork

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of College Park

Bridges

Tier 1

CP-103

SOUTH FULTON TSPLOST

Page 7: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Operations and Safety

City of College Park

Old National Highway

From I-285 to Surrey Trail

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$45,280

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Old National Highway planning study (I/285 to Surrey Trail)Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of College Park

Operations and Safety

Tier 1

CP-104

SOUTH FULTON TSPLOST

Page 8: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Operations and Safety

City of College Park

Old National Highway

From I-285 to Surrey Trail

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$100,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Old National Highway signal timing maintenanceProject Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of College Park

Operations and Safety

Tier 1

CP-105

SOUTH FULTON TSPLOST

Page 9: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Intersection Improvements

City of College Park

Main Street at Virginia Avenue

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$176,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety in City of College Park - Main Street at Virgina Avenue

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of College Park

Operations and Safety

Tier 1

CP-106

SOUTH FULTON TSPLOST

Page 10: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Intersection Improvements

City of College Park

Harvard Avenue at Main Street

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$176,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety in City of College Park - Main Street at Harvard Avenue

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of College Park

Operations and Safety

Tier 1

CP-107

SOUTH FULTON TSPLOST

Page 11: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Intersection Improvements

City of College Park

Virginia Avenue at College Street

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$176,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety in City of College Park - Virginia Avenue at College Street

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of College Park

Operations and Safety

Tier 1

CP-108

SOUTH FULTON TSPLOST

Page 12: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Intersection Improvements

City of College Park

Virginia Avenue at Adams Street

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$176,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety in City of College Park - Virginia Avenue at Adams Street

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of College Park

Operations and Safety

Tier 1

CP-109

SOUTH FULTON TSPLOST

Page 13: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Intersection Improvements

City of College Park

Virginia Avenue at Madison Street

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$176,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety in City of College Park - Virginia Avenue at Madison Street

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of College Park

Operations and Safety

Tier 1

CP-110

SOUTH FULTON TSPLOST

Page 14: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Intersection Improvements

City of College Park

Conley Street at Columbia Avenue

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$176,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety in City of College Park - Conley Street at Columbia Avenue

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of College Park

Operations and Safety

Tier 1

CP-111

SOUTH FULTON TSPLOST

Page 15: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Intersection Improvements

City of College Park

Old National Highway at Codby Road

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$1,000,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety in City of College Park - Old National Highway at Godby Road

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of College Park

Operations and Safety

Tier 1

CP-112

SOUTH FULTON TSPLOST

Page 16: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Corridor Improvement

City of College Park

Rhodes Street Extension

From Camp Creek Pkwy to Yale Ave

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$1,600,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety in City of College Park - Rhodes Street Ext. from Camp Creek Parkway to Yale Avenue

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of College Park

Operations and Safety

Tier 1

CP-113

SOUTH FULTON TSPLOST

Page 17: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Intersection Improvements

City of College Park

Old National Highway at I-285

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$156,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Pedestrian / Bike Improvements in City of College Park - Old National Highway at I/285 (intersection only)

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of College Park

Pedestrian/Bike/Landscape/Streetscape Projects

Tier 1

CP-114

SOUTH FULTON TSPLOST

Page 18: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Sidewalk Improvements

City of College Park

Virginia Avenue

From Main Street to Harrison Road

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$166,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Pedestrian / Bike Improvements in City of College Park - Virginia Avenue bike lanes (Main Street to Harrison Road)

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of College Park

Pedestrian/Bike/Landscape/Streetscape Projects

Tier 1

CP-115

SOUTH FULTON TSPLOST

Page 19: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Sidewalk Improvements

City of College Park

Lake Shore Drive/Janice Drive

From Herschel Road to Sun Valley Blvd

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$374,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Pedestrian / Bike Improvements in City of College Park - Lake Shore Drive/Janice Drive (Herschel to Sun Valley)

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of College Park

Pedestrian/Bike/Landscape/Streetscape Projects

Tier 1

CP-116

SOUTH FULTON TSPLOST

Page 20: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Sidewalk Improvements

City of College Park

Camp Creek Parkway

From Herschel Road to Airport Drive

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$515,872

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Pedestrian / Bike Improvements in City of College Park - Camp Truitt (Herschel Road to Airport Drive)

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of College Park

Pedestrian/Bike/Landscape/Streetscape Projects

Tier 1

CP-117

SOUTH FULTON TSPLOST

Page 21: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Sidewalk Improvements

City of College Park

College Street

From Harvard Avenue to Oxford Avenue

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$908,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Pedestrian / Bike Improvements in City of College Park - College Street (Harvard Avenue to Oxford Avenue)

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of College Park

Pedestrian/Bike/Landscape/Streetscape Projects

Tier 1

CP-118

SOUTH FULTON TSPLOST

Page 22: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Sidewalks and Bike Lanes

City of College Park

Virginia Avenue

From Lee Street to Atlanta Street

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$1,288,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Pedestrian / Bike Improvements in City of College Park - Virginia Avenue (Lee Street to Atlanta Street)

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of College Park

Pedestrian/Bike/Landscape/Streetscape Projects

Tier 1

CP-119

SOUTH FULTON TSPLOST

Page 23: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Intersection Improvements

City of College Park

Buffington Road at South Fulton Parkway

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$502,500

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Landscape/Streetscape in City of College Park - Buffington Road at South Fulton Parkway (PARTIAL FUNDING)

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of College Park

Pedestrian/Bike/Landscape/Streetscape Projects

Tier 1

CP-120

SOUTH FULTON TSPLOST

Page 24: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Landscape/Streetscape

City of College Park

Old National Hwy

Old National Hwy at I-285

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$502,500

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Pedestrian/Bike/Landscape/Streetscape in City of College Park - Old National Highway at I/285 (PARTIAL FUNDING)

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of College Park

Pedestrian/Bike/Landscape/Streetscape Projects

Tier 1

CP-121

SOUTH FULTON TSPLOST

Page 25: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Quick Response Projects

City of College Park

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$819,231

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Quick Response Projects in City of College Park - Quick Response Projects - To Be Determined

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of College Park

Quick Response Projects

Tier 1

CP-122

SOUTH FULTON TSPLOST

Page 26: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Resurfacing

City of East Point

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$18,540,200

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Maintenance and Safety Enhancements in City of East Point - Resurfacing

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of East Point

Maintenance and Safety Enhancements

Tier 1

EP-101

SOUTH FULTON TSPLOST

Page 27: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Pedestrian/Bike/Streetscape Projects

City of East Point

Ben Hill Road

From Dodson Drive to Dobbs Way

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$1,160,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Pedestrian/Bike/Landscape/Streetscape Projects in City of East Point - Ben Hill Road (Dodson Drive to Dobbs Way)

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of East Point

Pedestrian/Bike/Landscape/Streetscape Projects

Tier 1

EP-176

SOUTH FULTON TSPLOST

Page 28: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Pedestrian/Bike/Streetscape Projects

City of East Point

Washington Road

From I-285 to Delowe Drive

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$1,249,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Pedestrian/Bike/Landscape/Streetscape Projects in City of East Point - Washington Road (I-285 to Delowe Drive)

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of East Point

Pedestrian/Bike/Streetscape Projects

Tier 1

EP-177

SOUTH FULTON TSPLOST

Page 29: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Pedestrian/Bike/Streetscape Projects

City of East Point

Headland Drive

From City of Atlanta to Kimmeridge Drive

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$1,433,966

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Pedestrian/Bike/Landscape/Streetscape Projects in City of East Point - Headland Drive (City of Atlanta to Kimmeridge Drive)

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of East Point

Pedestrian/Bike/Streetscape Projects

Tier 1

EP-178

SOUTH FULTON TSPLOST

Page 30: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Pedestrian/Bike/Streetscape Projects

City of East Point

Delowe Drive

From Washington Road to SR 166

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$1,122,644

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Pedestrian/Bike/Landscape/Streetscape Projects in City of East Point - Delowe Drive (Washington Rd to SR 166)

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of East Point

Pedestrian/Bike/Streetscape Projects

Tier 1

EP-179

SOUTH FULTON TSPLOST

Page 31: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Pedestrian/Bike/Streetscape Projects

City of East Point

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$2,949,652

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Pedestrian/Bike/Landscape/Streetscape Projects in City of East Point - Master Trail System

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of East Point

Pedestrian/Bike/Streetscape Projects

Tier 1

EP-180

SOUTH FULTON TSPLOST

Page 32: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Intersection Improvements

City of East Point

Washington Road at Camp Creek Parkway

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$200,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety in City of East Point - Washington Road at Camp Creek Parkway Intersection Improvements

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of East Point

Operations and Safety

Tier 1

EP-181

SOUTH FULTON TSPLOST

Page 33: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Intersection Improvements

City of East Point

Ale Circle at Washington Road

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$550,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety in City of East Point - Ale Circle at Washington Road Intersection Improvements

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of East Point

Operations and Safety

Tier 1

EP-182

SOUTH FULTON TSPLOST

Page 34: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Operations and Safety

City of East Point

Ben Hill Road

From Will Lee Road to Unincorporated Fulton County

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$712,500

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety in City of East Point - Ben Hill Road (Will Lee Road to Unincorporated Fulton County) (Traffic Calming and Lane Widening)

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of East Point

Operations and Safety

Tier 1

EP-183

SOUTH FULTON TSPLOST

Page 35: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Quick Response Projects

City of East Point

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$873,355

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Quick Response Projects in City of East Point Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of East Point

Quick Response Projects

Tier 1

EP-184

SOUTH FULTON TSPLOST

Page 36: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Resurfacing

City of Fairburn

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$7,737,167

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Maintenance and Safety Enhancements in City of Fairburn - Resurfacing (Phase 1)

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of Fairburn

Maintenance and Safety Enhancements

Tier 1

FA-101

SOUTH FULTON TSPLOST

Page 37: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Pedestrian/Bike

City of Fairburn

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$136,891

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Pedestrian/Bike Improvements in City of Fairburn - Pedestrian/Bike Improvements (Phase 1)

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of Fairburn

Pedestrian/Bike/Landscape/Streetscape Projects

Tier 1

FA-102

SOUTH FULTON TSPLOST

Page 38: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Roadway Project

City of Fairburn

Howell Avenue Extension

From Howell Avenue to Bohannon Road

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$738,602

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Roadway Projects in City of Fairburn - Howell Avenue Extension from Howell Avenue to Bohannon Road; Intersection Improvements, Striping, ADA Compliance

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of Fairburn

Congestion Relief/Roadway Projects

Tier 1

FA-103

SOUTH FULTON TSPLOST

Page 39: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Roadway Project

City of Fairburn

Rivertown Connector

From Rivertown Road to Victoria Drive

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$937,240

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Roadway Projects in City of Fairburn - Rivertown Connector from Rivertown Road to Victoria Drive; Intersection Improvements, Striping, ADA Compliance

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of Fairburn

Congestion Relief/Roadway Projects

Tier 1

FA-104

SOUTH FULTON TSPLOST

Page 40: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Roadway Project

City of Fairburn

Park Road Extension

From Park Road to Frankie Arnold Drive

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$722,685

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Roadway Projects in City of Fairburn - Park Road Extension from Park Road to Frankie Arnold Drive; Intersection Improvements, Striping, ADA Compliance

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of Fairburn

Congestion Relief/Roadway Projects

Tier 1

FA-105

SOUTH FULTON TSPLOST

Page 41: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Roadway Project

City of Fairburn

Oakley Industrial Boulevard

From Stalwart Drive to Bohannon Road

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$897,309

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Roadway Projects in City of Fairburn - Oakley Industrial Boulevard Full-Depth Reclamation on Oakley Industrial Boulevard from Stalwart Drive to Bohannon Road; Intersection Improvements, Resurfacing, Regional Project

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of Fairburn

Congestion Relief/Roadway Projects

Tier 1

FA-106

SOUTH FULTON TSPLOST

Page 42: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Quick Response Projects

City of Fairburn

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$233,775

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Quick Response Projects in City of Fairburn - To Be DeterminedProject Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of Fairburn

Quick Response Projects

Tier 1

FA-107

SOUTH FULTON TSPLOST

Page 43: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Railroad Crossing Improvement

City of Hapeville

Norfolk Southern Railroad

South St, Perkins St, Dogwood Dr, Virginia Ave, Sylvan Rd

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$1,600,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations & Safety Improvements in City of Hapeville - Silent/Quiet Zone Railroad Crossings

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of Hapeville

Operations and Safety

Tier 1

HA-101

SOUTH FULTON TSPLOST

Page 44: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Pedestrian Improvements

City of Hapeville

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$1,900,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Pedestrian Improvements in City of Hapeville - Sidewalks, Curb/Gutter, Bike Lanes

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of Hapeville

Pedestrian/Bike/Landscape/Streetscape Projects

Tier 1

HA-102

SOUTH FULTON TSPLOST

Page 45: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Maintenance and Safety

City of Hapeville

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$1,400,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Maintenance & Safety in City of Hapeville - Paving & DrainageProject Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of Hapeville

Maintenance and Safety Enhancements

Tier 1

HA-103

SOUTH FULTON TSPLOST

Page 46: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Resurfacing

City of Palmetto

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$2,770,344

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Maintenance and Safety Enhancements in City of PalmettoProject Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of Palmetto

Maintenance and Safety Enhancements

Tier 1

PA-101

SOUTH FULTON TSPLOST

Page 47: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Operations and Safety

City of Palmetto

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$102,671

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety in City of PalmettoProject Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of Palmetto

Operations and Safety

Tier 1

PA-111

SOUTH FULTON TSPLOST

Page 48: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Pedestrian/Bike/Streetscape Projects

City of Palmetto

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$401,850

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Pedestrian/Bike/Landscape/Streetscape Projects in City of PalmettoProject Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of Palmetto

Pedestrian/Bike/Streetscape Projects

Tier 1

PA-112/113

SOUTH FULTON TSPLOST

Page 49: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Quick Response Projects

City of Palmetto

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$425,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Quick Response Projects in City of PalmettoProject Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of Palmetto

Quick Response Projects

Tier 1

PA-114

SOUTH FULTON TSPLOST

Page 50: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Intersection Improvements

Union City

I-85 at Jonesboro Road (SR 138)

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$5,000,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Congestion Relief in Union City - I-85/SR 138 Interchange (PARTIAL FUNDING)

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Union City

Congestion Relief/Roadway Projects

Tier 1

UC-101

SOUTH FULTON TSPLOST

Page 51: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Maintenance and Safety

Union City

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$9,511,322

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Maintenance and Safety Enhancements in Union City - ResurfacingProject Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Union City

Maintenance and Safety Enhancements

Tier 1

UC-102

SOUTH FULTON TSPLOST

Page 52: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Corridor Improvement

Union City

Flat Shoals Rd

From Westbrook Street to Oakley Rd

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$418,624

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety in Union City - Flat Shoals Road (Westbrook St to Oakley Rd)

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Union City

Operations and Safety

Tier 1

UC-103

SOUTH FULTON TSPLOST

Page 53: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Corridor Improvement

Union City

Lancaster Lane

From Shannon Pkwy to Shannon Way

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$274,010

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety in Union City - Lancaster Lane (Shannon Pkwy to Shannon Way)

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Union City

Operations and Safety

Tier 1

UC-104

SOUTH FULTON TSPLOST

Page 54: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Corridor Improvement

Union City

Londonderry Way

From Jonesboro Rd to Mall Blvd

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$566,210

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety in Union City - Londonderry Way (SR 138 to Mall Blvd)

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Union City

Operations and Safety

Tier 1

UC-105

SOUTH FULTON TSPLOST

Page 55: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Operations and Safety

Union City

Goodson Rd

From Union City Limits to Jonesboro Rd (SR 138)

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$587,591

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety in Union City - Goodson Rd from Union City Limits to Jonesboro Rd

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Union City

Operations and Safety

Tier 1

UC-106

SOUTH FULTON TSPLOST

Page 56: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Pedestrian/Bike/Streetscape

Union City

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$525,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Pedestrian/Bike/Landscape/Streetscape in Union City - Christian City Multi-Use Trail

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Union City

Pedestrian/Bike/Landscape/Streetscape

Tier 1

UC-107

SOUTH FULTON TSPLOST

Page 57: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Pedestrian/Bike/Streetscape

Union City

Lower Dixie Lake Rd

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$203,500

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Pedestrian/Bike/Landscape/Streetscape in Union City - Lower Dixie Lake Rd Sidewalks

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Union City

Pedestrian/Bike/Landscape/Streetscape

Tier 1

UC-108

SOUTH FULTON TSPLOST

Page 58: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Quick Response Projects

Union City

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$235,686

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Quick Response Projects in Union City - Quick Response ProjectsProject Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Union City

Quick Response Projects

Tier 1

UC-109

SOUTH FULTON TSPLOST

Page 59: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Resurfacing

Unincorporated Fulton County

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$9,803,915

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Maintenance and Safety Enhancements - Resurfacing of Corridors in Unincorporated Fulton

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Unincorporated Fulton

Maintenance and Safety Enhancements

Tier 1

UFC-101

SOUTH FULTON TSPLOST

Page 60: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Proposed Subdivision Improvements

Unincorporated Fulton County

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$1,625,475

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Maintenance and Safety Enhancements - Subdivision Toppings in Unincorporated Fulton

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Unincorporated Fulton

Maintenance and Safety Enhancements

Tier 1

UFC-102

SOUTH FULTON TSPLOST

Page 61: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Proposed Subdivision Improvements

Unincorporated Fulton County

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$23,021,489

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Maintenance and Safety Enhancements - Subdivision Resurfacing in Unincorporated Fulton

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Unincorporated Fulton

Maintenance and Safety Enhancements

Tier 1

UFC-103

SOUTH FULTON TSPLOST

Page 62: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Bridge Improvement

Unincorporated Fulton County

Butner Rd

Butner Road SW at Camp Creek

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$1,600,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Bridge Improvement in Unincorporated Fulton County, Butner Road at Camp Creek

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Unincorporated Fulton

Bridges

Tier 1

UFC-104

SOUTH FULTON TSPLOST

Page 63: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Bridge Improvement

Unincorporated Fulton County

Enon Rd

Enon Road at Camp Creek Tributary

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$600,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Bridge Improvement in Unincorporated Fulton County, Enon Road at Camp Creek Tributary (Timber Bridge)

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Unincorporated Fulton

Bridges

Tier 1

UFC-105

SOUTH FULTON TSPLOST

Page 64: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Intersection Improvements

Unincorporated Fulton County

Bethsaida Road at Creel Road

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$1,353,600

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety Improvements in Unincorporated Fulton, Bethsaida Road at Creel Road

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Unincorporated Fulton

Operations and Safety

Tier 1

UFC-106

SOUTH FULTON TSPLOST

Page 65: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Intersection Improvements

Unincorporated Fulton County

Butner Road at Camp Creek Parkway

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$3,174,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety Improvements in Unincorporated Fulton, Butner Road at Camp Creek Parkway

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Unincorporated Fulton

Operations and Safety

Tier 1

UFC-107

SOUTH FULTON TSPLOST

Page 66: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Intersection Improvements

Unincorporated Fulton County

Butner Road at Union Road

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$1,986,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety Improvements in Unincorporated Fulton, Butner Road at Union Road

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Unincorporated Fulton

Operations and Safety

Tier 1

UFC-108

SOUTH FULTON TSPLOST

Page 67: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Intersection Improvements

Unincorporated Fulton County

Butner Road at Pittman Road

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$1,412,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety Improvements in Unincorporated Fulton, Butner Road at Pittman Road

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Unincorporated Fulton

Operations and Safety

Tier 1

UFC-109

SOUTH FULTON TSPLOST

Page 68: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Intersection Improvements

Unincorporated Fulton County

Campbellton Road at Stonewall Tell Road

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$1,422,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety Improvements in Unincorporated Fulton, Campbellton Road at Stonewall Tell Road

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Unincorporated Fulton

Operations and Safety

Tier 1

UFC-110

SOUTH FULTON TSPLOST

Page 69: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Intersection Improvements

Unincorporated Fulton County

Campbellton-Fairburn Road at Jones Road

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$1,464,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety Improvements in Unincorporated Fulton, Campbellton-Fairburn Road at Jones Road

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Unincorporated Fulton

Operations and Safety

Tier 1

UFC-111

SOUTH FULTON TSPLOST

Page 70: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Intersection Improvements

Unincorporated Fulton County

Cascade-Palmetto Highway at West Stubbs Road

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$1,554,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety Improvements in Unincorporated Fulton, Cascade-Palmetto Highway at West Stubbs Road

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Unincorporated Fulton

Operations and Safety

Tier 1

UFC-112

SOUTH FULTON TSPLOST

Page 71: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Intersection Improvements

Unincorporated Fulton County

Demooney Road at West Stubbs Road

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$1,422,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety Improvements in Unincorporated Fulton, Demooney Road at West Stubbs Road

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Unincorporated Fulton

Operations and Safety

Tier 1

UFC-113

SOUTH FULTON TSPLOST

Page 72: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Intersection Improvements

Unincorporated Fulton County

Enon Road at Stonewall Tell Road

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$1,674,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety Improvements in Unincorporated Fulton, Enon Road at Stonewall Tell Road

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Unincorporated Fulton

Operations and Safety

Tier 1

UFC-114

SOUTH FULTON TSPLOST

Page 73: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Intersection Improvements

Unincorporated Fulton County

Feldwood Road at Morning Creek Drive

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$952,800

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety Improvements in Unincorporated Fulton, Feldwood Road at Morning Creek Drive

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Unincorporated Fulton

Operations and Safety

Tier 1

UFC-115

SOUTH FULTON TSPLOST

Page 74: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Intersection Improvements

Unincorporated Fulton County

Feldwood Road at Bench Mark Drive

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$775,200

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety Improvements in Unincorporated Fulton, Feldwood Road at Bench Mark Drive

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Unincorporated Fulton

Operations and Safety

Tier 1

UFC-116

SOUTH FULTON TSPLOST

Page 75: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Landscape/Streetscape

Unincorporated Fulton County

Fulton Industrial Boulevard

From Frederick Drive to Martin Luther King Jr Drive

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$1,000,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Fulton Industrial Boulevard- Streetscapes and pedestrian upgrades from Frederick Dr. to MLK Jr. Dr inc. I-20 Interchange Ramps

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Unincorporated Fulton

Operations and Safety

Tier 1

UFC-117

SOUTH FULTON TSPLOST

Page 76: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Intersection Improvements

Unincorporated Fulton County

Fulton Industrial Boulevard at Cascade Road

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$1,000,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety Improvements in Unincorporated Fulton, Fulton Industrial Boulevard at Cascade Road

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Unincorporated Fulton

Operations and Safety

Tier 1

UFC-118

SOUTH FULTON TSPLOST

Page 77: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Intersection Improvements

Unincorporated Fulton County

Old Fairburn Road at Union Road

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$1,464,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety Improvements in Unincorporated Fulton, Old Fairburn Road at Union Road

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Unincorporated Fulton

Operations and Safety

Tier 1

UFC-119

SOUTH FULTON TSPLOST

Page 78: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Intersection Improvements

Unincorporated Fulton County

Rivertown Road at Cedar Grove Road

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$1,310,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety Improvements in Unincorporated Fulton, Rivertown Road at Cedar Grove Road

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Unincorporated Fulton

Operations and Safety

Tier 1

UFC-120

SOUTH FULTON TSPLOST

Page 79: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Intersection Improvements

Unincorporated Fulton County

Stonewall Tell Road at Union Road

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$1,488,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety Improvements in Unincorporated Fulton, Stonewall Tell Road at Union Road

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Unincorporated Fulton

Operations and Safety

Tier 1

UFC-121

SOUTH FULTON TSPLOST

Page 80: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Intersection Improvements

Unincorporated Fulton County

Stonewall Tell Road at Jones Road/Pittman Road

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$1,608,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety Improvements in Unincorporated Fulton, Stonewall Tell Road at Jones Road/Pittman Road

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Unincorporated Fulton

Operations and Safety

Tier 1

UFC-122

SOUTH FULTON TSPLOST

Page 81: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Intersection Improvements

Unincorporated Fulton County

Welcome All Road at Jailette Road

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$1,070,400

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety Improvements in Unincorporated Fulton, Welcome All Road at Jailette Road

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Unincorporated Fulton

Operations and Safety

Tier 1

UFC-123

SOUTH FULTON TSPLOST

Page 82: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Intersection Improvements

Unincorporated Fulton County

Welcome All Road at Scarboro Road

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$1,556,400

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety Improvements in Unincorporated Fulton, Welcome All Road at Scarboro Road

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Unincorporated Fulton

Operations and Safety

Tier 1

UFC-124

SOUTH FULTON TSPLOST

Page 83: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Intersection Improvements

Unincorporated Fulton County

West Stubbs Road at Butner Road

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$1,722,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety Improvements in Unincorporated Fulton, West Stubbs Road at Butner Road

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Unincorporated Fulton

Operations and Safety

Tier 1

UFC-125

SOUTH FULTON TSPLOST

Page 84: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Intersection Improvements

Unincorporated Fulton County

Signal Upgrades

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$2,750,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety Improvements in Unincorporated Fulton, Signal Upgrades

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Unincorporated Fulton

Operations and Safety

Tier 1

UFC-126

SOUTH FULTON TSPLOST

Page 85: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Sidewalk Improvements

Unincorporated Fulton County

Danforth Road

From Rehoboth Circle to Cascade Road

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$2,250,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Pedestrian / Bike Improvements in Unincorporated Fulton, Danforth Road (Rehoboth Circle to Cascade Road)

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Unincorporated Fulton

Pedestrian/Bike/Landscape/Streetscape Projects

Tier 1

UFC-127

SOUTH FULTON TSPLOST

Page 86: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Sidewalk Improvements

Unincorporated Fulton County

Enon Road

From Lynarbor Lane to Sanford J. Jones

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$2,000,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Pedestrian / Bike Improvements in Unincorporated Fulton, Enon Road (Lynarbor Lane to Sanford J. Jones)

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Unincorporated Fulton

Pedestrian/Bike/Landscape/Streetscape Projects

Tier 1

UFC-128

SOUTH FULTON TSPLOST

Page 87: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Airport Improvement

Unincorporated Fulton County

Fulton County Airport / Charlie Brown Field

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$1,000,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Fulton County Airport Improvements in Unincorporated Fulton - Charlie Brown Airport - MATCHING FUNDS

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Unincorporated Fulton

Fulton County Airport

Tier 1

UFC-129

SOUTH FULTON TSPLOST

Page 88: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Airport Improvement

Unincorporated Fulton County

Aviation Circle

Fulton County Airport / Charlie Brown Field

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$189,500

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Fulton County Airport Improvements in Unincorporated Fulton - Aviation Circle Paving

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Unincorporated Fulton

Fulton County Airport

Tier 1

UFC-130

SOUTH FULTON TSPLOST

Page 89: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Quick Response Projects

Unincorporated Fulton County

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$1,648,045

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Quick Response Projects in Unincorporated FultonProject Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Unincorporated Fulton

Quick Response Projects

Tier 1

UFC-131

SOUTH FULTON TSPLOST

Page 90: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Resurfacing

City of Chattahoochee Hills

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$369,464

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Maintenance and Safety Enhancements in City of Chattahoochee Hills

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of Chattahoochee Hills

Maintenance and Safety Enhancements

Tier 2

CH-201

SOUTH FULTON TSPLOST

Page 91: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Quick Response Projects

City of Chattahoochee Hills

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$7,945

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Quick Response Projects in City of Chattahoochee HillsProject Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of Chattahoochee Hills

Quick Response Projects

Tier 2

CH-202

SOUTH FULTON TSPLOST

Page 92: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Sidewalk Improvements

City of College Park

South Fulton Parkway

From Buffington Road to Welcome All Road

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$425,248

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Pedestrian/Bicycle in City of College Park - South Fulton Parkway (Buffington Road to Welcome All Road)

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of College Park

Pedestrian/Bike/Landscape/Streetscape Projects

Tier 2

CP-201

SOUTH FULTON TSPLOST

Page 93: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Intersection Improvements

City of College Park

Camp Creek Parkway at I-85

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$502,500

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Landscape/ Streetscape in City of College Park - Camp Creek Parkway at I/85 (PARTIAL FUNDING)

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of College Park

Pedestrian/Bike/Landscape/Streetscape Projects

Tier 2

CP-202

SOUTH FULTON TSPLOST

Page 94: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Intersection Improvements

City of College Park

College Street at Harvard Avenue

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$176,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety in City of College Park - College Street at Harvard Avenue

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of College Park

Operations and Safety

Tier 2

CP-203

SOUTH FULTON TSPLOST

Page 95: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Operations and Safety

City of College Park

Washington Rd

From Carriage Way to Lyle Terrace

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$352,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety in City of College Park - Washington Rd From Carriage Way to Lyle Terrace (along College Park city boundary)

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of College Park

Operations and Safety

Tier 2

CP-204

SOUTH FULTON TSPLOST

Page 96: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Quick Response Projects

City of College Park

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$423,793

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Quick Response Projects in City of College Park - Quick Response Projects - To Be Determined

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of College Park

Quick Response Projects

Tier 2

CP-205

SOUTH FULTON TSPLOST

Page 97: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Resurfacing

City of East Point

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$4,408,500

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Maintenance and Safety Enhancements in City of East Point - Resurfacing

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of East Point

Maintenance and Safety Enhancements

Tier 2

EP-201

SOUTH FULTON TSPLOST

Page 98: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Pedestrian/Bike/Streetscape Projects

City of East Point

Dobbs Way

From Washington Road to Ben Hill Road

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$210,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Pedestrian/Bike/Landscape/Streetscape Projects in City of East Point - Dobbs Way (Washington Rd to Ben Hill Rd)

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of East Point

Pedestrian/Bike/Streetscape Projects

Tier 2

EP-214

SOUTH FULTON TSPLOST

Page 99: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Pedestrian/Bike/Streetscape Projects

City of East Point

Redwine Road

From City of Atlanta to North Commerce Drive

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$218,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Pedestrian/Bike/Landscape/Streetscape Projects in City of East Point - Redwine Road (City of Atlanta to North Commerce Drive)

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of East Point

Pedestrian/Bike/Streetscape Projects

Tier 2

EP-215

SOUTH FULTON TSPLOST

Page 100: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Operations and Safety

City of East Point

Ben Hill Road

From Will Lee Road to Unincorporated Fulton County

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$237,500

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety in City of East Point - Ben Hill Road (Will Lee Road to Unincorporated Fulton County) Traffic Calming and Lane Widening

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of East Point

Operations and Safety

Tier 2

EP-216

SOUTH FULTON TSPLOST

Page 101: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Resurfacing

City of Fairburn

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$552,987

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Maintenance and Safety Enhancements in City of Fairburn - Road Resurfacing (Phase 2)

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of Fairburn

Maintenance and Safety Enhancements

Tier 2

FA-201

SOUTH FULTON TSPLOST

Page 102: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Railroad Crossing Improvement

City of Fairburn

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$750,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety in City of Fairburn - Quiet Zone Railroad Crossings

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of Fairburn

Operations and Safety

Tier 2

FA-202

SOUTH FULTON TSPLOST

Page 103: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Pedestrian/Bike

City of Fairburn

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$353,171

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Pedestrian/Bike Improvements in City of Fairburn - Pedestrian/Bike Improvements (Phase 2)

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of Fairburn

Pedestrian/Bike/Landscape/Streetscape Projects

Tier 2

FA-203

SOUTH FULTON TSPLOST

Page 104: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Roadway Project

City of Fairburn

Oakley Industrial Blvd Extension

From Creekwood Road to Collinsworth Road

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$315,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Roadway Projects in City of Fairburn - Oakley Industrial Boulevard Extension (DESIGN ONLY) on Oakley Industrial Boulevard from Creekwood Road to Collinsworth Road; Intersection Improvements, Striping, Regional Project, ADA Compliance

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of Fairburn

Congestion Relief/Roadway Projects

Tier 2

FA-204

SOUTH FULTON TSPLOST

Page 105: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Quick Response Projects

City of Fairburn

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$41,254

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Quick Response Projects in City of Fairburn - To Be DeterminedProject Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of Fairburn

Quick Response Projects

Tier 2

FA-205

SOUTH FULTON TSPLOST

Page 106: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Maintenance and Safety

City of Hapeville

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$600,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Maintenance & Safety in City of Hapeville - Paving & DrainageProject Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of Hapeville

Maintenance and Safety Enhancements

Tier 2

HA-201

SOUTH FULTON TSPLOST

Page 107: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Operations and Safety

City of Hapeville

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$382,108

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety Improvements (Traffic & Street Signage) in City of Hapeville - Operations and Safety Improvements (Traffic & Street Signage)

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of Hapeville

Operations and Safety

Tier 2

HA-202

SOUTH FULTON TSPLOST

Page 108: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Resurfacing

City of Palmetto

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$488,884

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Maintenance and Safety Enhancements in City of PalmettoProject Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of Palmetto

Maintenance and Safety Enhancements

Tier 2

PA-201

SOUTH FULTON TSPLOST

Page 109: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Operations and Safety

City of Palmetto

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$18,118

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety in City of PalmettoProject Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of Palmetto

Operations and Safety

Tier 2

PA-202

SOUTH FULTON TSPLOST

Page 110: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Pedestrian/Bike/Streetscape Projects

City of Palmetto

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$70,915

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Pedestrian/Bike/Landscape/Streetscape Projects in City of PalmettoProject Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of Palmetto

Pedestrian/Bike/Streetscape Projects

Tier 2

PA-203

SOUTH FULTON TSPLOST

Page 111: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Quick Response Projects

City of Palmetto

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$75,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Quick Response Projects in City of PalmettoProject Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of Palmetto

Quick Response Projects

Tier 2

PA-204

SOUTH FULTON TSPLOST

Page 112: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Maintenance and Safety

Union City

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$300,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Maintenance and Safety Enhancements in Union City - ResurfacingProject Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Union City

Maintenance and Safety Enhancements

Tier 2

UC-201

SOUTH FULTON TSPLOST

Page 113: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Corridor Improvement

Union City

Jonesboro Rd

From Roosevelt Hwy to Buffington Rd

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$841,152

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety in Union City - Jonesboro Road (SR 14 to Buffington Rd )

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Union City

Operations and Safety

Tier 2

UC-202

SOUTH FULTON TSPLOST

Page 114: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Corridor Improvement

Union City

Highpoint Rd

From Roosevelt Hwy to Dodson Rd

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$711,150

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety in Union City - Highpoint Road (SR 14 to Dodson Rd)

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Union City

Operations and Safety

Tier 2

UC-203

SOUTH FULTON TSPLOST

Page 115: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Operations and Safety

Union City

Oakley Rd

From Jonesboro Rd (SR 138) to the Union City limits

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$295,775

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety in Union City - Oakley Rd from Jonesboro Rd/SR 138 south to the city limits

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Union City

Operations and Safety

Tier 2

UC-204

SOUTH FULTON TSPLOST

Page 116: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Operations and Safety

Union City

Gresham St at Jonesboro Rd

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$558,831

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety in Union City - Gresham St at Jonesboro Rd Improvements

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Union City

Operations and Safety

Tier 2

UC-205

SOUTH FULTON TSPLOST

Page 117: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Quick Response Projects

Union City

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$235,686

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Quick Response Projects in Union City - Quick Response ProjectsProject Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Union City

Quick Response Projects

Tier 2

UC-206

SOUTH FULTON TSPLOST

Page 118: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Resurfacing

Unincorporated Fulton County

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$1,778,326

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Maintenance and Safety Enhancements in Unincorporated Fulton - Resurfacing of Corridors

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Unincorporated Fulton

Maintenance and Safety Enhancements

Tier 2

UFC-201

SOUTH FULTON TSPLOST

Page 119: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Bridge Improvement

Unincorporated Fulton County

Bethsaida Rd

Bethsaida Road at Morning Creek

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$1,500,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Bridge Improvement in Unincorporated Fulton County, Bethsaida Rd at Morning Creek

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Unincorporated Fulton

Bridges

Tier 2

UFC-202

SOUTH FULTON TSPLOST

Page 120: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Intersection Improvements

Unincorporated Fulton County

Aldredge Road at Merk Road

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$984,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety Improvements in Unincorporated Fulton, Aldredge Road at Merk Road

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Unincorporated Fulton

Operations and Safety

Tier 2

UFC-203

SOUTH FULTON TSPLOST

Page 121: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Intersection Improvements

Unincorporated Fulton County

Bethsaida Road at Old National Hwy.

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$1,788,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety Improvements in Unincorporated Fulton, Bethsaida Road at Old National Hwy.

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Unincorporated Fulton

Operations and Safety

Tier 2

UFC-204

SOUTH FULTON TSPLOST

Page 122: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Intersection Improvements

Unincorporated Fulton County

Butner Road at Aldredge Road

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$1,434,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety Improvements in Unincorporated Fulton, Butner Road at Aldredge Road

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Unincorporated Fulton

Operations and Safety

Tier 2

UFC-205

SOUTH FULTON TSPLOST

Page 123: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Sidewalk Improvements

Unincorporated Fulton County

Fulton Industrial Boulevard

From Camp Creek Parkway to Martin Luther King Jr Drive

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$500,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety Improvements in Unincorporated Fulton, Fulton Industrial Boulevard-Sidewalks corridor-wide

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Unincorporated Fulton

Operations and Safety

Tier 2

UFC-206

SOUTH FULTON TSPLOST

Page 124: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Intersection Improvements

Unincorporated Fulton County

Washington Road at Roosevelt Highway

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$2,449,200

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety Improvements in Unincorporated Fulton, Washington Road at Roosevelt Highway

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Unincorporated Fulton

Operations and Safety

Tier 2

UFC-207

SOUTH FULTON TSPLOST

Page 125: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Intersection Improvements

Unincorporated Fulton County

Welcome All Road at Will Lee Road

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$1,669,200

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety Improvements in Unincorporated Fulton, Welcome All Road at Will Lee Road

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Unincorporated Fulton

Operations and Safety

Tier 2

UFC-208

SOUTH FULTON TSPLOST

Page 126: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

ATMS

Unincorporated Fulton County

Flat Shoals Road

From Oakley Road to Clayton County Line

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$1,000,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety Improvements in Unincorporated Fulton, Flat Shoals Road ATMS

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Unincorporated Fulton

Operations and Safety

Tier 2

UFC-209

SOUTH FULTON TSPLOST

Page 127: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Quick Response Projects

Unincorporated Fulton County

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$290,831

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Quick Response Projects in Unincorporated FultonProject Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Unincorporated Fulton

Quick Response Projects

Tier 2

UFC-210

SOUTH FULTON TSPLOST

Page 128: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Resurfacing

City of Chattahoochee Hills

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$369,464

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Maintenance and Safety Enhancements in City of Chattahoochee Hills

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of Chattahoochee Hills

Maintenance and Safety Enhancements

Tier 3

CH-301

SOUTH FULTON TSPLOST

Page 129: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Quick Response Projects

City of Chattahoochee Hills

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$9,514

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Quick Response Projects in City of Chattahoochee HillsProject Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of Chattahoochee Hills

Quick Response Projects

Tier 3

CH-302

SOUTH FULTON TSPLOST

Page 130: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Quick Response Projects

City of College Park

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$1,887,271

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Quick Response Projects in City of College Park - Quick Response Projects - To Be Determined

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of College Park

Quick Response Projects

Tier 3

CP-301

SOUTH FULTON TSPLOST

Page 131: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Resurfacing

City of East Point

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$3,375,976

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Maintenance and Safety Enhancements in City of East Point - Resurfacing

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of East Point

Maintenance and Safety Enhancements

Tier 3

EP-303

SOUTH FULTON TSPLOST

Page 132: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Intersection Improvements

City of East Point

Janice Drive at Washington Road

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$250,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety in City of East Point - Janice Drive at Washington Road Intersection Improvements

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of East Point

Operations and Safety

Tier 3

EP-324

SOUTH FULTON TSPLOST

Page 133: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Intersection Improvements

City of East Point

North Commerce Drive at Redwine Road

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$350,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety in City of East Point - North Commerce Drive at Redwine Road Intersection Improvements

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of East Point

Operations and Safety

Tier 3

EP-325

SOUTH FULTON TSPLOST

Page 134: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Intersection Improvements

City of East Point

North Desert Drive Extension to Ale Circle

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$1,100,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety in City of East Point - North Desert Drive Extension to Ale Circle - Intersection Improvements

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of East Point

Operations and Safety

Tier 3

EP-326

SOUTH FULTON TSPLOST

Page 135: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Congestion Relief

City of Fairburn

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$450,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Congestion Relief in City of Fairburn - To Be DeterminedProject Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of Fairburn

Congestion Relief/Roadway Projects

Tier 3

FA-301

SOUTH FULTON TSPLOST

Page 136: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Operations and Safety

City of Fairburn

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$541,902

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operation and Safety Improvements in City of Fairburn - To Be Determined

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of Fairburn

Operations and Safety

Tier 3

FA-302/303

SOUTH FULTON TSPLOST

Page 137: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Pedestrian/Bike

City of Fairburn

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$184,316

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Pedestrian/Bike Improvements in City of Fairburn - Pedestrian/Bike Improvements (Phase 3)

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of Fairburn

Pedestrian/Bike/Landscape/Streetscape Projects

Tier 3

FA-304

SOUTH FULTON TSPLOST

Page 138: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Roadway Project

City of Fairburn

Dodd Street Roundabout

Dodd Street at Orchard Street and Aderhold Street

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$802,717

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Roadway Projects in City of Fairburn - Dodd Sreet Roundabout, Dodd Street at Orchard Street and Aderhold Street

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of Fairburn

Congestion Relief/Roadway Projects

Tier 3

FA-305

SOUTH FULTON TSPLOST

Page 139: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Quick Response Projects

City of Fairburn

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$41,417

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Quick Response Projects in City of Fairburn - To Be DeterminedProject Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of Fairburn

Quick Response Projects

Tier 3

FA-306

SOUTH FULTON TSPLOST

Page 140: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Pedestrian Improvements

City of Hapeville

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$500,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Pedestrian Improvements in City of Hapeville - Sidewalks, Curb/ Gutter, Bike Lanes

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of Hapeville

Pedestrian/Bike/Landscape/Streetscape Projects

Tier 3

HA-301

SOUTH FULTON TSPLOST

Page 141: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Maintenance and Safety

City of Hapeville

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$485,983

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Maintenance & Safety in City of Hapeville - Paving and DrainageProject Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of Hapeville

Maintenance and Safety Enhancements

Tier 3

HA-302

SOUTH FULTON TSPLOST

Page 142: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Resurfacing

City of Palmetto

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$488,884

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Maintenance and Safety Enhancements in City of PalmettoProject Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of Palmetto

Maintenance and Safety Enhancements

Tier 3

PA-301

SOUTH FULTON TSPLOST

Page 143: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Operations and Safety

City of Palmetto

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$18,118

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety in City of PalmettoProject Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of Palmetto

Operations and Safety

Tier 3

PA-302

SOUTH FULTON TSPLOST

Page 144: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Pedestrian/Bike/Streetscape Projects

City of Palmetto

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$70,915

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Pedestrian/Bike/Landscape/Streetscape Projects in City of PalmettoProject Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of Palmetto

Pedestrian/Bike/Streetscape Projects

Tier 3

PA-303

SOUTH FULTON TSPLOST

Page 145: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Quick Response Projects

City of Palmetto

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$77,577

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Quick Response Projects in City of PalmettoProject Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

City of Palmetto

Quick Response Projects

Tier 3

PA-304

SOUTH FULTON TSPLOST

Page 146: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Maintenance and Safety

Union City

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$1,715,484

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Maintenance and Safety Enhancements in Union City - ResurfacingProject Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Union City

Maintenance and Safety Enhancements

Tier 3

UC-301

SOUTH FULTON TSPLOST

Page 147: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Bridge Improvement

Union City

McClure Road

McClure Road at Line Creek

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$44,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Bridge Improvement in Union City - McClure at Line CreekProject Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Union City

Bridges

Tier 3

UC-302

SOUTH FULTON TSPLOST

Page 148: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Bridge Improvement

Union City

Peters Road

Peters Road at Broadnax Creek

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$44,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Bridge Improvement in Union City - Peters Rd at Broadnax CreekProject Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Union City

Bridges

Tier 3

UC-303

SOUTH FULTON TSPLOST

Page 149: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Bridge Improvement

Union City

Highpoint Road

Highpoint Road at Deep Creek

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$44,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Bridge Improvement in Union City - Highpoint Rd at Deep CreekProject Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Union City

Bridges

Tier 3

UC-304

SOUTH FULTON TSPLOST

Page 150: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Bridge Improvement

Union City

Buffington Road

Buffington Road at Shannon Creek

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$44,000

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Bridge Improvement in Union City - Buffington Rd at Shannon Creek

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Union City

Bridges

Tier 3

UC-305

SOUTH FULTON TSPLOST

Page 151: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Corridor Improvement

Union City

Buffington Rd

From Jonesboro Rd to Flat Shoals Rd

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$670,350

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Operations and Safety in Union City - Buffington Road (SR 138 to Flat Shoals Rd)

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Union City

Operations and Safety

Tier 3

UC-306

SOUTH FULTON TSPLOST

Page 152: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Sidewalk Improvements

Union City

Roosevelt Hwy

From Lower Dixie Lake Road to Stonewall Tell Road

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$496,069

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Pedestrian/Bike Improvements in Union City - Roosevelt Hwy (US29) (Lower Dixie Lake Road to Stonewall Tell Road)

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Union City

Pedestrian/Bike/Landscape/Streetscape Projects

Tier 3

UC-307

SOUTH FULTON TSPLOST

Page 153: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Quick Response Projects

Union City

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$26,814

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Quick Response Projects in Union City - Quick Response ProjectsProject Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Union City

Quick Response Projects

Tier 3

UC-308

SOUTH FULTON TSPLOST

Page 154: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Proposed Subdivision Improvements

Unincorporated Fulton County

Various Extents

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$124,513

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Maintenance and Safety Enhancements in Unincorporated Fulton, Subdivision Resurfacing

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Unincorporated Fulton

Maintenance and Safety Enhancements

Tier 3

UFC-301

SOUTH FULTON TSPLOST

Page 155: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Sidewalk Improvements

Unincorporated Fulton County

Stonewall Tell Road

From Roosevelt Highway to Campbellton Road

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$2,995,641

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Pedestrian / Bike Improvements in Unincorporated Fulton, Stonewall Tell Sidewalks

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Unincorporated Fulton

Pedestrian/Bike/Landscape/Streetscape Projects

Tier 3

UFC-303

SOUTH FULTON TSPLOST

Page 156: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Sidewalk Improvements

Unincorporated Fulton County

Creel Road

From Old National Highway to West Road

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$1,995,643

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Pedestrian / Bike Improvements in Unincorporated Fulton, Creel Road Sidewalks

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Unincorporated Fulton

Pedestrian/Bike/Landscape/Streetscape Projects

Tier 3

UFC-304

SOUTH FULTON TSPLOST

Page 157: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Sidewalk Improvements

Unincorporated Fulton County

Bethsaida Road

From Connell Rd to Old National Hwy

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$1,995,643

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Pedestrian / Bike Improvements in Unincorporated Fulton, Bethsaida Road Bike/Sidewalks

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Unincorporated Fulton

Pedestrian/Bike/Landscape/Streetscape Projects

Tier 3

UFC-305

SOUTH FULTON TSPLOST

Page 158: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Sidewalk Improvements

Unincorporated Fulton County

Welcome All Road

From Camp Creek Parkway to Roosevelt Highway

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$2,995,643

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Pedestrian / Bike Improvements in Unincorporated Fulton - Welcome All Road Sidewalks

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Unincorporated Fulton

Pedestrian/Bike/Landscape/Streetscape Projects

Tier 3

UFC-306

SOUTH FULTON TSPLOST

Page 159: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Sidewalk Improvements

Unincorporated Fulton County

Cascade Rd

From Danforth Road to Fulton Industrial Boulevard

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$2,995,643

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Pedestrian / Bike Improvements in Unincorporated Fulton, Cascade Road Sidewalks

Project Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Unincorporated Fulton

Pedestrian/Bike/Landscape/Streetscape Projects

Tier 3

UFC-307

SOUTH FULTON TSPLOST

Page 160: SOUTH FULTON TSPLOST - Fulton County, Georgia€¦ · CP-116 SOUTH FULTON TSPLOST. Sidewalk Improvements City of College Park Camp Creek Parkway From Herschel Road to Airport Drive

Quick Response Projects

Unincorporated Fulton County

Various Locations

MAIN ROUTE

TYPE

GDOT / ARC ID

LENGTH (miles)

EXTENTS

Project Details

LOCATION

Project Cost Estimate

$346,755

OTHER COSTS

CONSTRUCTION COST

TOTAL CAPITAL COST

ENGINEERING COST

RIGHT-OF-WAY COST

TOTAL TSPLOST FUNDS

CONSTRUCTION

DESIGN

LOCAL LEAD

RIGHT-OF-WAY

Quick Response Projects in Unincorporated FultonProject Description

Funding Partners

Project Status

ROW

CONSTRUCTION

ENVIRONMENTAL

LENGTH OF CONSTR.

READY FOR CONSTR.

Project Timeline

DESIGN

Notes:

Project Implementation

Unincorporated Fulton

Quick Response Projects

Tier 3

UFC-308

SOUTH FULTON TSPLOST