Transport & Handling of Detectors TAN Workshop S. Prodon – 10.03.2006.
-
Upload
marcia-newman -
Category
Documents
-
view
215 -
download
1
description
Transcript of Transport & Handling of Detectors TAN Workshop S. Prodon – 10.03.2006.
Transport & Handling of DetectorsTAN Workshop S. Prodon – 10.03.2006
Table of contentUnloading at CERNUnloading at CERNHandling at test facilitiesHandling at test facilitiesSurface TransportSurface TransportLowering into the LHC tunnelLowering into the LHC tunnelUnderground TransportUnderground TransportDetector installationDetector installation
- Removal of copper barsRemoval of copper bars- Detector insertion into the TANDetector insertion into the TAN
Handling operations after 1Handling operations after 1stst beam beam
Detector unloading at CERN
Option 1: Unloading at the place of destination on CERN site- Condition: single element on the truck- Procedure:
Custom duties Registration at CERN goods reception Unloading of the truck at the place of destination
- Handling means: forklift- Recommendations:
Be present during the unloading Inform the forklift driver of the fragility of the detector
Detector unloading at CERN
Option 2: Unloading at CERN goods reception- Condition: standard procedure- Procedure:
Custom duties Unloading at CERN goods reception CERN transport from the goods reception to the place of
destination- Handling means:
lowered truck 24 hour delivery time
- Recommendations: Inform our service of the fragility of the detector
Handling at test facilityAre you going to test your detectors
at CERN ?If the answer is yes
- Handling conditions at CERN:Need of an authorisation to drive forklifts
and overhead travelling craneSupport form handling teams at request
(EDH)- Handling specifications: see
specifications for installation
Surface transport Journeys
- Goods reception -> Test facility- Test facility -> Storage facility- Storage facility -> Lowering point
Transport specification- Procedure:
internal transport request (EDH) Delivery time: 5 working days
- Transport conditions: Conditioning (preferably original conditioning from
arrival at CERN) Vibration and acceleration specifications ? Shock monitoring system ?
Lowering into the LHC tunnel
Lowering points- SD1 for point 1- SDX5 or SD6 for point 5 (depending on
detector conditioning)Handling means
- Lift
Underground transport Journey
- Lift -> installation placeTransport specification
- Procedure: internal transport request (EDH)Delivery time: 5 working days
- Transport meansLHC trailer
- Transport conditions:Risk of vibrationPossibility of special rubber if necessary
Detector InstallationHandling means: LHC special forklift
Detector InstallationHandling simulations
Detector InstallationHandling simulations
Detector InstallationHandling simulations
Detector InstallationHandling simulations
Detector installationRemoval of copper bars
- Handling meansLHC forkliftSlingsDedicated lifting hook
- InterfacesLifting hook to be defined
o Simple to useo Easy and fast to enter in the copper baro Limit human interventions in the vicinity of the
TAN
Detector installationDetector insertion into the TAN
- Handling meansLHC forkliftSlings
- PrerequisitesIdentification of the center of gravity 2 lifting points on the top of the detector
Preferably slewing rings Location: each side of the center of gravity (in the
longitudinal direction) Maximum distance between the 2 lifting points: 200
mm Allow a flat lifting of the detector
3 mm clearance
Handling operations after 1st beam
Limit staff exposure to radiations:- Efficient lifting hook for copper bars- No jamming during lifting operation (need of
precise lifting points)- Transport conditioning for copper bars and
detector (i.e. lead storage compartment)
Conclusion Anticipate lifting interfaces Simple lifting systems Anticipate handling operations after 1st
beam (radiations)