TRANSCRIPT - PROPOSED PLAN PUBLIC MEETING FOR THE … · 2 I'm L'Tonya Spencer. I'm the Community...

27
U.S. Environmental Protection Agency Public IVIeeting September 7, 2011 U.S. ENVIRONMENTAL PROTECTION AGENCY SUPERFUND PROPOSED PLAN SAPP BATTERY SUPERFUND SITE OPERABLE UNIT 2 - GROUNDWATER DATE: TIME: PLACE: REPORTED BY: / PUBLIC MEETING September 1, 2011 6:06 p.m. to 7:06 p.m. Cottondale Community Center 2666 Front Street Cottondale, Florida 32431 Stephanie R. Zeitvogel Court Reporter Notary Public State of Florida at large Pagel U ORIGINAL REPORTED BY: Stephanie R. Zeitvogel www.fauseby.com HUSEBY, INC. - 555 North Point Center, E., #403, Alpharetta, GA 30022 (404) 875-0400

Transcript of TRANSCRIPT - PROPOSED PLAN PUBLIC MEETING FOR THE … · 2 I'm L'Tonya Spencer. I'm the Community...

Page 1: TRANSCRIPT - PROPOSED PLAN PUBLIC MEETING FOR THE … · 2 I'm L'Tonya Spencer. I'm the Community Involvement 3 Coordinator for the Sapp Battery site. I'm with 4 the Environmental

U.S. Environmental Protection Agency Public IVIeeting September 7, 2011

U.S. ENVIRONMENTAL PROTECTION AGENCY

SUPERFUND PROPOSED PLAN

SAPP BATTERY SUPERFUND SITE

OPERABLE UNIT 2 - GROUNDWATER

DATE:

TIME:

PLACE:

REPORTED BY:

/

PUBLIC MEETING

September 1, 2011

6:06 p.m. to 7:06 p.m.

Cottondale Community Center

2666 Front Street

Cottondale, Florida 32431

Stephanie R. Zeitvogel

Court Reporter

Notary Public

State of Florida at large

Pagel

U ORIGINAL

REPORTED BY: Stephanie R. Zeitvogel www.fauseby.com HUSEBY, INC. - 555 North Point Center, E., #403, Alpharetta, GA 30022 (404) 875-0400

Page 2: TRANSCRIPT - PROPOSED PLAN PUBLIC MEETING FOR THE … · 2 I'm L'Tonya Spencer. I'm the Community Involvement 3 Coordinator for the Sapp Battery site. I'm with 4 the Environmental

U.S. Environmental Protection Agency Public Meeting September? , 2011

2 (Pages 2 to 5)

10

11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

Page 2

PARTICIPANTS; ERIK SPALVTNS Remedial Project Manager [email protected]

-and-LTONYA SPENCER Community Involvement Coordinator spencer. I atonya@epa. gov U.S. EPA. Region 4 Superfund Remedial Branch Superfund Division 61 Forsyth Street, SW Atlanta, Georgia 30303 (800)435-9233 CHRIS PELLEGRINO (FDEP) ROY BAGGETT CHRIS RUTHERFORD LEIGH BROOKS

Page 4

1 cleanup. 2 This meeting is to discuss the proposed plan 3 for the site, and it's a proposed plan for the 4 cleanup. So we're at the stage where we are 5 prepared to make a decision about part of the 6 cleanup for the site. 7 We have in attendance here also from the 8 govermnent, from the State govemment, Chris 9 Pellegrino with DEP. He is the State counterpart.

10 On this site it's somewhat complicated site. 11 But the DEP is EPA's partner in paying for part of 12 the cleanup. So I wanted to recognize Chris. 13 Then, I guess, if there's no questions, I will 14 just start with my PowerPoint presentation. All 15 right? Good deal. 16 Basically, what we're going to have here Is a 17 very brief discussion of the history of the site, 18 how we got to where we are today, and the status of 19 the groundwater cleanup and what we're proposing to 20 do with this proposed plan. Then anybody — we've 21 gotten such a small crowd, I'd say, if anybody has 22 a question at any poinl, feel free to let me know 23 and we can have a conversation. When you've got a 2 4 small group like this, it's pretty easy to handle 2 5 it that way.

Page 3

1 MS. SPENCER: For those of you who are here, 2 I'm L'Tonya Spencer. I'm the Community Involvement 3 Coordinator for the Sapp Battery site. I'm with 4 the Environmental Protection Agency Region 4 out of 5 Atlanta, Georgia. Erik is the Remedial Project 6 Manager for the site. 7 I'm going to take the time to welcome you to 8 the Sapp Battery proposed planning meeting site. 9 We do have a transcriber here, and we are asking

10 that, at the end of Erik's presentation, ifyou 11 have questions, please introduce yourself first so 12 we can make sure to get your name on the 13 transcription for our records. 14 Did you want to introduce ~ 15 MR. SPALVTNS: Sure, I can do that. Thanks, 16 L'Tonya. 17 Well, my name is Erik, and 1 am the Project 18 Manager for the Superfund site here at Sapp Battery 19 Superfund site. Basically, my responsibilities are 20 to manage the site from investigation to trying to 21 decide what the options are, identifying exactly 2 2 what the problem is, what are the options to fix 23 the problem, and then how do you fi.x the problem. 2 4 Tlien, once we make that decision, then the project 2 5 manager is responsible for carrying out the

Pages

1 So I want to briefly cover the Superfund 2 process, which was discussed a little bit. This 3 site has been around for a while. It became a part 4 ofthe Superfund program back in the eighties. So 5 it's been around for a while, and there have been 6 some cleanup actions already at the site. So the 7 site has already been through this Superflind 8 process in some parts of the site. 9 So we have the — we have a cleanup of the

10 soil, we have a cleanup of the ~ 11 Oh, I'm sorry. 12 MS. BROOKS: You're fine where you are. 13 MR. SPAL\/TNS: Plenty of room to move around 14 on this one. 15 We have the soil cleanup, we have lhe cleanup 16 ofthe svi'amps, and we also have the cleanup ofthe 17 groundwater. So those are the three portions of 18 the site that we've got. 19 So what we have — the soil cleanup has 2 0 already been through this entire process; 21 investigation, which is where we identify exactly 22 what the problem is; feasibility studies, where we 23 lay out the options and we decide, you know, (he 2 4 pros and the cons of each of the options to fix the 25 problem.

R E P O R T E D B Y : S tephan ie R. Zeitvogel www.huseby . com H U S E B Y , I N C . - 555 N o r t h Poin t Cen t e r , E., #403 , A l p h a r e t t a , G A 30022 (404) 875-0400

Page 3: TRANSCRIPT - PROPOSED PLAN PUBLIC MEETING FOR THE … · 2 I'm L'Tonya Spencer. I'm the Community Involvement 3 Coordinator for the Sapp Battery site. I'm with 4 the Environmental

U.S. E n v i r o n m e n t a l Pro tec t ion Agency Publ ic Mee t ing S e p t e m b e r 7, 2011

3 (Pages 6 to 9)

Page 6

1 The proposed plan, which is where we are 2 today, leads into the Record of Decision. Those 3 two ~ that's the remedy selection process. So the 4 cleanup approach that we use, we call that the 5 "remedy." 6 So to select the remedy, the process is we 7 have a proposed plan that we issued to the public, 8 which we mailed out, and then we have a public 9 meeting, which is this meeting today. Then, after

10 we receive 30 days of public comments and comments 11 from the State, then we will issue the final Record 12 of Decision, which is the document the EPA uses to 13 document what we're planning to do to fix the 14 problem and why we're going to choose that. 15 So today we're talking about a proposed plan 16 for part of the cleanup, just the groundwater part. 17 After that we have the remedial design stage 18 where we lay out the details of how we're going to 19 fix the problem. Then remedial action is where we 2 0 carry out the cleanup. 21 Af\er that is over, then you enter the 2 2 operation and maintenance phase, which is something 2 3 that goes on for a long period of time, depending 24 on the remedy. 2 5 So this site, the Sapp Battery site, is about

Page 7

1 a 45-acre site. In the early seventies up until 2 1980, there was a battery recycling operation on 3 the site. So what happened was, the companies and 4 individuals would bring batteries to the site and 5 the company that was operating there would open up 6 the batteries, release the — and the sulfuric acid 7 would go into a drainage, into a holding pond, and 8 then they would take the lead from the batteries 9 and send it for recycling.

10 They didn't have very good controls over how 11 they were managing the waste, the sulfuric acid. 12 As a result, they had widespread contamination of 13 the soils on the site, with both heavy metals and 14 sulfuric acid. 15 iTie holding pond, at times, overflowed and 16 entered the swamp, and so there were fishkills and 17 there were some ~ where the swamp was killed 18 and ~ excuse me. So the acid impacted the swamp, 19 (he acid impacted the groundwater. 2 0 So the EPA and the State both spent some time 21 and energy out at the site cleaning up parts ofthe 2 2 site, trying to neutralize some ofthe acid that 2 3 had been spilled. 24 During the process of investigating that site, 2 5 they found some paperwork and documentation oflhe

Pages

1 companies that had been in business with the owner 2 ofthe property and the facility. So the EPA 3 pursued enforcement action against those companies 4 and individuals. As a result, we found a group of 5 people that became responsible parties for the 6 site, and they entered into an agreement wilh the 7 EPA to do part of the cleanup. 8 So the EPA managed that, the EPA supervised 9 that wdth the State's input, and they handled the

10 soil cleanup. 11 So I may have jumped ahead a little bit here. 12 I guess I should have said that before the 13 companies became responsible parties, the EPA 14 issued a Record of Decision, which is the ROD that 15 we talked about earlier. That was in 1986. 16 In that Record of Decision, the EPA identified 17 a cleanup remedy for lhe soil, for the sediments, 18 and for the ~ 19 (Door slams shut, interrupting the proceedings.) 2 0 The soil cleanup was to build a monolith 21 on-site ~ well, let me go to the next slide. 22 So the OUl is the soils that was — the remedy 2 3 for the OUl was to excavate the soils that had been 2 4 contaminated with lead and acid and then bring them 2 5 together on top of ~ at the site and build a

Page 9

1 monolith, mix it with some compounds that would 2 stabilize the soil and prevent the lead from 3 leaching into the groundwater, and then cover that 4 monolith with soils so that there would not be any 5 direct exposure to people that are woridng on the 6 site. So that was the soil cleanup. That was 7 completed by the ~ we call it — PRP is one terni. 8 That stands for Potentially Responsible Party. 9 The folks that we identified that had

10 contributed to the contamination, they coalesced 11 and formed a group called the Sapp Battery Group 12 that conducted that cleanup. 13 The planning for that took several years, but 14 they carried it out ~ they started it — or, they 15 finished it in September of 2001. 16 Then, in 1999, Congress passed the Superfund 17 Recycling Equities Act, which released certain 18 classes of people and companies from responsibility 19 for Superfund cleanups. The idea behind that was 2 0 that there were a lot of small companies that had 21 been impacted in that industry, the batteries 22 recycling industry. So Congress passed a law 2 3 speciflcally to give them some relief from the 2 4 Superfund liability. So the remainder of the site 2 5 was handled by the federal govermnent, based on

R E P O R T E D B Y : S tephan ie R. Zeitvogel www.huseby . com H U S E B Y , I N C . - 555 N o r t h Poin t Cen te r , E , , #403 , A l p h a r e t t a , G A 30022 (404) 875-0400

Page 4: TRANSCRIPT - PROPOSED PLAN PUBLIC MEETING FOR THE … · 2 I'm L'Tonya Spencer. I'm the Community Involvement 3 Coordinator for the Sapp Battery site. I'm with 4 the Environmental

U.S. Environmental Protection Agency Public iVIeeting September 7, 2011

4 (Pages 10 to 13)

1 2 3 4 5 6 7 8 9

10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

1 2 3 4 5 6 7 8 9

10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

Page 10

that act of Congress. So the next part ofthe site that underwent

construction was OU3, which was sediments. This was handled by the federal govemment with the State's help. The EPA finished the remedial design in 2005 and carried out the ~ and they carried out the cleanup and finished it in September 2008. Then they closed out lhe paperwork for that in 2009. That's why 1 have two different dates here.

But what they did for the swamp, basically, is they excavated the sediments in the swamps that were contaminated by heavy metals and hauled them to the landflll. And then, that restored the swamp.

Then the rest ofthe remediation oflhe swamp was to naturally attenuate it. 1 have some pictures ofthe swamp today, and it really has improved a lot. So where this excavator is in this photo, you can see back behind it the dead swamp as they were excavating it. This is right after the excavation was done and the swamp had filled with water. 1 will show you a picture later that has it restored with lily pads and plants growing in it again.

MS. BROOKS: Wliat-

Page 11

MS. SPENCER: Could you state your name? MS. BROOKS: Oh, I'm sorry. Leigh Anna

Brooks, Chattahoochee, Florida. What is the distinction between soils and

sediments? MR. SPALVINS: That's a good question. Basically, it depends ifthey are wet, is

one — the simplest way to talk about it is if the — if it's in part of the body of water, if it's under there, that is considered the sediments. That's the most general description, the way to distinguish between the two.

MS. BROOKS: So what was under water, that was shifted to a landfill, that was hauled off-site?

MR. SPALVINS: Right. MS. BROOKS: The soil that was not under the

water, that was put into the monolith? MR. SPALVTNS: That was put into the monolith,

right. They did get some ofthe sediments, I think.

Or part of that cleanup. In fact, when they dug up the ~ when they did that first big soil remedy, part of fhe objective was to get ridof what might be considered "source material." So that would be stuff that had a lot of acid in it or had a lot of

1 2 3 4 5 6 7 8 9

10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

1 2 3 4 5 6 7 8 9

10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

Page 12

lead in it. So they dug pretty deep. They dug into the groundwater table in some

parts, so they did get some saturated soil, which we would consider part — maybe part ofthe aquifer or to be saturated soil. So —

MR. BAGGETT: Well, actually, wc dug down and ; pumped the water out and used it for fixated material. So we went down to where it tested below the target number. So we actually removed the soil that was contaminated and wet. We used the water that was wet into the fixated material, and then the soil was worked into that. It was used in a proprietary material called MAECTITE, which is like a cement.

MS. SPENCER: Could you stale your name for the record?

MR. BAGGEll: Yes, ma'am. I'm Roy Baggett. I'm a project ~ I'm the PRP project coordinator.

MR. SPALVINS: Does that answer your question? MS. BROOKS: Yes. MR. SPALVINS: The main reason that the

sediments were shipped to the landfill ~ one of the reasons, and there's a lot of different reasons. But from an economic standpoint, it was aflbrdable and it was a safe way to handle that

Page 13

material. There was not a lot of acid in that material,

and I believe most of it went to ~ 1 don't recall if it went to a hazardous waste landfill or to a normal landfill, so I probably shouldn't speculate. It's in the record, but I'm afraid I don't remember.

So when the soil cleanup was conducted, they handled a lot more material than was ~ than was involved when they dug out the sediments in the swamps. I think it was almost a hundred thousand cubic yards of material.

So treating it on-site and solidifying it on-site made a lot more sense to do it that way. Because there's a certain amount of infi^astructure that you mobilize to the site when you do on-site treatment, and it didn't make sense to do it for the sediments.

The sediments are a little different because there was a lot of organic matter. So you start trying lo figure out how to pile that into a stable unit on-site and it's a lot harder because the organic material is going lo decompose. So it made more sense to send that to a landfill.

So, like I said, the federal govemment

REPORTED BY: Stephanie R. Zeitvogel www.huseby.com HUSEBY, INC. - 555 North Point Center, E., #403, Alpharetta, GA 30022 (404) 875-0400

Page 5: TRANSCRIPT - PROPOSED PLAN PUBLIC MEETING FOR THE … · 2 I'm L'Tonya Spencer. I'm the Community Involvement 3 Coordinator for the Sapp Battery site. I'm with 4 the Environmental

U.S. E n v i r o n m e n t a l Protect ion Agency Publ ic Mee t ing S e p t e m b e r 7, 2011

5 (Pages 14 to 17)

Page 14

1 handled the sediment cleanup in the swamps, and the 2 groundwater cleanup is the last component of lhe 3 cleanup for this site. So we have already finished 4 the soil and the sediment. Both of those remedies 5 were carried out ~ both of those remedies were the 6 same remedies thai were in the 1986 ROD. 7 For groundwater, the 1986 ROD called for 8 something called "pump and treat" where you pump 9 out the groundwater, you run it through a treatmeni

10 system, and then you reinject it into the 11 groundwater or you discharge it to surface water. 12 What happened was, in brief— fll go into a 13 little bit more detail than this later — the EPA 14 started working under the design for that remedy in 15 2004. As you see here, we added some more wells in 16 2004 and started to look at, How could we design a 17 pump and treat system to handle the groundwater 18 contamination? 19 As we started to leam more about the 2 0 groundwater contamination, we realized that because 21 ofthe way the aquifer behaved, it would be very 2 2 difficult to pump out the groundwater and treat it 2 3 and get an effective cleanup. 2 4 Plus, we leamed that, over the years, the 2 5 contamination had decreased a lot. It decreased

Page 16

1 So what we're looking at ~ and I apologize 2 for the quality ofthe picture. Ifyou want lo 3 come up later and take a look at it on the 4 computer, you can. Or even now, you can. 5 Wliat we have — over here we have the original 6 facility and different buildings that were used in 7 the battery-cracking operation. This is a swamp 8 that existed until the eighties. Tliis is the 9 natural — this is the, what we call, the eastern

10 swamp. This swamp was dug out during the OUl 11 cleanup, the soil cleanup. That swamp was 12 excavated and removed and became part of the 13 monolith. 14 Again, I apologize for the quality of the 15 image we have here. We'll work with what we've 16 got. But this is just to show you what the site 17 looked like originally or during the early stages 18 of the cleanup. 1 9 This is the site, the swamp today. I'm going 20 to flip back here. This part of the swamp right 21 here is what you're looking at in this image here. 2 2 This was about, 1 think, a year ago, maybe. 1 was 2 3 down here and swung by and took a photo. You can 2 4 see lily pads throughout the swamp, big difference 25 compared to the photo with the excavator in it.

Page 15

1 tremendously in the aquifer. So we started looking 2 at other options. I'll show you some data in a 3 little bit, the different data from 1986 when pump 4 and treat was the clear choice, to today, where now 5 we think that, based on all the data we have, that 6 we can conclude that contamination will continue to 7 attenuate over time until natural attenuation 8 handles it. 9 The reason that that's possible is because of

10 the source control cleanup that was done by the PRP 11 group wilh the soils, because they dug out so much 12 soil and got so much ofthe material that was 13 contributing to the problem out of the aqui fer. 14 So this is a picture oflhe site. I don't 15 recall exactly when this was taken. This was in 16 the eighties. But I think it ~ I don't recall. 17 Roy, does this ring any bells to you? 18 MR. BAGGETT: Il appears to be familiar. But 19 if it's the one that has the mylar on it, it was 2 0 about in the area of, I would say, 1984 or '85. 21 MR. SPALVINS: Tliat sounds about right. 22 MR. BAGGETT: Because that was before anything 2 3 started being moved or anything started being 2 4 repaired. 25 MR. SPALVTNS: Yeah, that sound about right.

Page 17

1 Then — oh, that's a picture ofthe swamp 2 across the street from the south side. That's 3 Steele City Bay, which is this southem swamp area 4 here. 5 So I'm going to make some comparisons of— I 6 talked a lillie bit about how the source control 7 measures had improved the quality ofthe 8 groundwater over time. I tried to figure out how I 9 could talk about that in a way that makes sense,

10 and I hope that this does. 11 What I have here is the acreage of the 12 contamination, ofthe lead contamination in the 13 aquifer. You really can't make out the first 14 column, but this first column is in 1983. This is 15 1983 that the lead plume ~ this is the area of the 16 plume that was above the drinking water standard. 17 This is why there was a lol of concem about this 18 site. 19 In 1983 the surficial aquifer, which is about 2 0 lhe lop 10 or 20 feet in this area, there was about 21 a 20-acre lead plume. The intennediate aquifer, 22 there was about a 14-acre lead plume. The Floridan 2 3 aquifer, which is where most people get their 2 4 drinking water, there was about a 10-acre lead 2 5 plume.

R E P O R T E D BY: S t ephan i e R, Zeitvogel www.huseby . com

H U S E B Y , I N C . - 555 N or th Po in t Cen t e r , E., #403 , A l p h a r e t t a , G A 30022 (404) 875-0400

Page 6: TRANSCRIPT - PROPOSED PLAN PUBLIC MEETING FOR THE … · 2 I'm L'Tonya Spencer. I'm the Community Involvement 3 Coordinator for the Sapp Battery site. I'm with 4 the Environmental

U.S. Environmental Protection Agency PubUc Meeting September 7, 2011

6 (Pages 18 to 21)

1 2 3 4 5 6 7 8 9

10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

1 2 3 4 5 6 7 8 9

10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

Page 18

Now, when you're doing estimates like this, it's kind of ballpark, you know. This is a ~ you know, just to give this an idea, in 1985, the surficial aquifer had ~ there was a litfle less, a little smaller, maybe, that's just an — you know. maybe that just isn't a real difference. Maybe it was the same, but we're estimating 18 acres. Intermediate estimated a little bigger.

The big change is to the Floridan aquifer. In 1985, the area that was contaminated grew to about 35 acres. So it went from 10 acres to 35 acres. That's a pretty big increase.

So in 1986, when the original decision was made how to handle this groundwater problem, we were looking at a plume that was starting to grow. We had some modeling that was conducted in the eighties that estimated that the plume could move off-site and in a manner of— a period of years would be impacting some ofthe neiglibors' wells downgradient.

Now, what we know now is thai the models we were using in the 1980s were not very good at predicting lead movement in the aquifer. So it was eariy in that approach.

At any rate, in i 988, the groundwater in the

Page 19

surficial aquifer was down to 10 acres of area in '88. So we started to see the plume shrinking.

Tlie intennediate aquifer was about 14 acres, so it's about the same size.

But the contamination ofthe Floridan aquifer is down to 20 acres. So this is where we first started seeing that the Floridan contamination was staning to shrink. This is after some emergency response actions had been taken, but before the source control occurted.

So then the source control was carried out. It was finished in 2001. It was being planned in the nineties, and we are monitoring, as this is happening, the groundwater to make sure it's not getting out of control. They do the source area — the soil and the source area remediation, and then that removed a lot ofthe source oflhe groundwater contamination from the enviromnent.

And by 2005, the ~ there's no plume of ~ lead plume in the surficial aquifer, zero acres. In the Floridan aquifer, same, zero acres. There's just not much left. The intennediate aquifer, we sfill see about an acre of area where there's a small lead plume that remains.

Because what's happening is that the acid was

1 2 3 4 5 6 7 8 9

10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

1 2 3 4 5 6 7 8 9

10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

Page 20

removed and the natural attenuafion, the flushing ofthe groundwater, the aquifer maleriai is neutralizing the acid. As a result, the heavy metals contamination is coming to absolution because the heavy metals tend to dissolve more easily where you have acid PH. So as PH levels are going back to nomial, then the lead levels are going back to normal, too.

By 2011, we have continued monitoring and we '• have paid very special attention to the way we are doing the sampling to make sure we are getting good quality samples, and we are down to two points, the end of two wells that are giving us exceedances (sic) for lead, only in the intermediate aquifer.

So this is the way that I think 1 can best describe the magnitude of improvements that we have seen in terms ofthe lead contamination in the groundwaler over the years.

So to take it back to 1986, we have what looked ~ which was, we had a pretty serious problem. The groundwater remedy was we are going to get in here and pump out the water so it can't go very far, we are going lo treat it at the surface, and then we are going to discharge it clean.

Page 21

Today the lead problem has largely resolved itself as a result ofthe source control measures that were taken. This is part of the evidence, this is the largest part ofthe evidence that leads us to believe that natural attenuation will be appropriate for the remainder ofthe cleanup. ;

MS. BROOKS: Before you go on - j MR. SPALVTNS: Sure. MS. BROOKS: ~ how many acres are on the site

total? MR. SPALVINS: The site itself is about

45 acres. I have some maps that show the groundwater plumes coming up next.

MS. BROOKS: The plumes - the acreage ofthe plumes that you have on this slide, are those within that ownership or are they — any of them off-site?

MR. SPALVTNS: A little bit of bolh. Some of il was off-site at points.

MS. BROOKS: And then, how did you establish these acreage figures? Through monitoring wells o r~

MR. SPALVTNS; We have monitoring wells. There was a series of monitoring wells that was put in in the eighties. When they did the source

REPORTED BY: Stephanie R. Zeitvogel www.huseby.com HUSEBY, INC. - 555 North Point Center, E., #403, Alpharetta, GA 30022 (404) 875-0400

Page 7: TRANSCRIPT - PROPOSED PLAN PUBLIC MEETING FOR THE … · 2 I'm L'Tonya Spencer. I'm the Community Involvement 3 Coordinator for the Sapp Battery site. I'm with 4 the Environmental

U.S. Environmental Protection Agency Public Meeting September?, 2011

7 (Pages 22 to 25)

1 2 3 4 5 6 7 8 9

10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

1 2 3 4 5 6 7 8 9

10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

Page 22

removal and they excavated large parts ofthe site, they destroyed most of those moniloring wells. So we have gone back in and put in new monitoring wells. So we have a combination of old wells that were used back in the eighties, and we have the new wells thai are built now.

So we have to make a best professional judgment. We have some specific areas where there was an old well that gave us a certain result. That well was destroyed and another well was put in. In some instances we decided we wanted to put another well in next to that well to doublecheck it, and we leamed a lol through that process.

But yeah, we use monitoring wells. A lot of this is computer modeling, and it's basically an eslimale. If one well is very high, then it kind of estimates a large area around it. If there's another well next lo it ihaf s high, then it estimates that it's probably connected.

MS. BROOKS: How many monitored wells are out there?

MR. SPALVINS: Right now, I think we have -MR. PELLEGRINO: Around 60. MR. SPALVINS: ~ about 60. MS. BROOKS: Wow.

Page 23

MR. SPALVINS: So this is a figure that shows the - in 1985 ~ well, let me orient everybody.

All right. So this is the facility, the fenced in property boundary right here. Then the original operations were on this parcel here in this area. You may be able to see a little gray oufline here. Tlie gray outline is where the monolith is. So a lot of this monolith, rather than being a pyramid that's tall and huge, most of it is pretty low to the ground, 10 feet, maybe 5 feet in some areas.

It does two things. Wlien you build it that way it's easier to build because you don't have lo build it so high, but it also covers the area and keeps rain from infiltrafing into the groundwater in that area. So waler hits it, it mns off of il and goes into the surface water. So that's why we have a pretty large monolith that covers this area.

Part of this includes the old swamp. This is where a lot of the acid ended up draining to, into this swamp. Then il drained into this swamp, and some of it drained this way into the swamp south of the site. So that's kind of orientation.

Wlien the swamp cleanup was conducted, it involved digging up a lot ofihis area here. So

1 2 3 4 5 6 7 8 9

10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

1 2 3 4 5 6 7 8 9

10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

Page 24

this area, largely, was the OUl cleanup, and this was 0U2. Then more further to the south, and 0U2 involved some cleanup up here, too.

Now, the box here is the 45 acres. The pink oufline is based on the wells in 1985. Wliat it showed, what it is describing here is the estimate of how big the plume in the Floridan aquifer was. about — I guess this was the one that was about 35 acres. So you can see that we have some wells thai are ~ some estimates that are coming 1 off-site. Now, there's a railroad track over here. 1 Obviously, we didn't have ~ I don't believe we had any wells over on the other side oflhe railroad track. This is an esflmale. This is where it's kind ofa professional judgment.

Now, what I have on the next slide shows an overlay of the new data. I'm going to apologize for the pictures here. The proposed plan that we \ mailed out has more detailed images.

Do you have it? MR. PELLEGRINO: Yeah. MR. SPALVINS: Thank you. Did you get one? MS. SPENCER: No. ' MR. SPALVINS: It's got a DEP stamp on it. So

this is what we're talking about right here. This l

Page 25 \

is the same image here. j So these are the new wells. So what we have \

done is, we have the sampling history on these 1 wells. So this is '04, '05, '08, '05, '08, '04, '05,'06,'08. Someof these are newer wells that | we installed recently. i

These are the test results for different 1 parameters; aluminum, iron, lead, manganese. vanadium, pH and turbidity.

Turbidity is important at this site because some of the stuff that we are trying to clean up for, it is elevated when there's a lot of— ; turbidity is a measure of the clarity.

You know what ~ MS. BROOKS: Uh-huh. MR. SPALVTNS: It's a measure of the clarity

ofthe water sample. So when turbidity is elevated ~ sometimes you get elevated numbers for certain results.

Like this turbidity is 35. This is EW2D in 2005, and the lead number was 310 micrograms per liter, which is pretty high. That's the cleanup -the groundwater, I'm sorry ~ the drinking water standard for lead is 15. So that's pretty high.

Now, when you see that you think, well, then, j

REPORTED BY: Stephanie R. Zeitvogel www.huseby.com HUSEBY, INC. - 555 North Point Center, E., #403, Alpharetta, GA 30022 (404) 875-0400

Page 8: TRANSCRIPT - PROPOSED PLAN PUBLIC MEETING FOR THE … · 2 I'm L'Tonya Spencer. I'm the Community Involvement 3 Coordinator for the Sapp Battery site. I'm with 4 the Environmental

U.S. E n v i r o n m e n t a l Pro tec t ion Agency Publ ic Mee t ing S e p t e m b e r 7, 2011

8 (Pages 26 to 29)

Page 26

1 that's a real problem. But then you have to ~ you 2 know, we started paying more attention to the 3 turbidity, and we realized that maybe il was an 4 issue wilh the quality of the sample. So we 5 sampled again in 2008 and we got a more clear 6 sample. When we analyzed for lead, it was 7 below detecfion level. That's what the U stands 8 for. It means undetected. The 4 that's there is 9 the detecfion level.

10 So what we — there's a lot of data on this 11 site, but what we tried to do is present the data 12 we had in '86 we based that infonnation on, and 13 then the new data is what we are basing our current 14 information on. So this 8L is one that we'll talk 15 about a litfle bit later. You can have this copy 16 of this. 17 MS. BROOKS: Okay, thank you. 18 MR. SPALVTNS: And there's, 1 believe - we 19 have more groundwater data ~ 2 0 MS. SPENCER: Okay. 21 MR. SPALVTNS; ~ for the other figure. So at 22 least you can see what is on my projector. We're 2 3 going to have to buy a screen, I guess. 2 4 All right. So I mentioned 8L to you. The 2 5 thing about this site, the main characteristic of

Page 27

1 this site is that there are sinkholes at the site. 2 The swamps are where the sinkholes have filled in 3 over the eons with sand and clay and peat and 4 plants and big alligators and all kinds of stuff. 5 So what we have at some ofthe wells like that 6 8L, continues to have high iron numbers. One of 7 the reasons is because ~ and you can't see it on 8 the projector maybe, but you can see it in the 9 proposed plan. 8L is this well here. 8L is a

10 screen in a zone of the aquifer that is comprised 11 of silts, clays, sands, but you have a lot of silts 12 and clays that are mixed in there with some organic 13 matter. As a result, the permeability of that 14 aquifer material is lower, so the water is going to 15 move slower through it. 16 Basically, whafs happening is, there is some 17 low PH groundwater in pockets in these low 18 permeabihty zones. It's there. We couldn't pump 19 it out because the permeability is so low that it 2 0 comes out as a slow trickle. We could try to 21 inject, but we wouldn't be very successful, again, 2 2 because we wouldn't be able to push much water into 2 3 it because there's low pemieability. 2 4 The good news is that, because it's a low 2 5 penneability, it's very ~ the water that's in

Page 28

1 there is only going to release into the rest of the 2 aquifer very, very slowly. So it's not going to 3 impact the rest of the aquifer in temis of creafing 4 an ongoing groundwater problem. 5 But it's bad that the permeability is low on 6 one hand because if it was higher it already would 7 have attenuated, the water would have flushed 8 through and the PH would have gone to neutral and 9 the metals would have decreased. But it hasn't

10 because it's low pemieability. So it's kind of a 11 good thing from the standpoint of not impacting the 12 groundwater but a bad thing because there continues 13 to be contaminafion there. 14 The good news for us is, at this site, it's 15 not enougji that it's going to make the plume get 16 bigger. If it was a different type of contaminate, 17 we might have to take acfion to go in and get it. 18 But at this site, we're going to let natural ~ 1 9 what ~ we would like to let natural attenuation 2 0 take its course. 21 So this is another slide that just shows 2 2 another cross-section of the aquifer. So you have 23 the ground surface here and then different layers 24 of geological material. Undemeath all of it is 2 5 lhe limestone. But in some places you have

Page 29

1 sinkholes that have fomied, I don't know how many 2 thousands of years ago, where the limestone was ate 3 away and then everything collapsed into it and then 4 it just filled up over the years. 5 This slide is the intermediate aquifer. Same 6 basic concept that we talked about before. This is 7 the north half of it because it's a litfle larger, 8 a lot more wells so it's hard to talk about. The 9 pink, again, is the lead plume, and then all this

10 data is here. 11 Again, it's in the proposed plan ifyou would 12 like to look al it more closely. I'll sum it up by 13 saying that as we worked on the site since 2004, we 14 leamed that we have to be sure that we get low 15 turbidity samples so that we are getting quality 16 samples. 17 We also identified some areas that we thought 18 were source areas where we thought we had a lot of 19 lead contaminafion. Butthe wells that were there 2 0 were not really producing the right quality data, 21 so we went in next to those wells and we put in new 2 2 wells and we sampled the new wells and we didn't 2 3 find the lead contaminafion. 2 4 So the bottom line was, we had other wells 2 5 that were screened and the material had low

R E P O R T E D BY: S tephan ie R. Zeitvogel www.huseby . com

H U S E B Y , I N C . - 555 N o r t h Po in t Cen t e r , E. , #403, A l p h a r e t t a , G A 30022 (404) 875-0400

Page 9: TRANSCRIPT - PROPOSED PLAN PUBLIC MEETING FOR THE … · 2 I'm L'Tonya Spencer. I'm the Community Involvement 3 Coordinator for the Sapp Battery site. I'm with 4 the Environmental

U.S. E n v i r o n m e n t a l Pro tec t ion Agency Publ ic Mee t ing S e p t e m b e r 7, 2011

9 (Pages 30 to 33)

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

Page 30

penneability. Some of it was actually peat that was down in the bottom ofthe sinkhole. Peats, clays, sills, things that do two things really well; ihey hold on lo lead well, and ihey also get in the water well and they don't let water through. So when you're pumping out waler, you gel turbid a sample that has a lot of particulates in il that hold on lo lead really well.

So basically we're getfing the wrong picture about the aquifer. It looked like we had an aquifer where you had mobile lead moving. But in reality, we didn't have that. So we verified that with new wells, and we are a lot more comfortable with attenuation now.

This is the bottom half of the intermediate aquifer. 1 told you eariier we had two points in the intemiediate aquifer where we had lead contaminafion above the cleanup number, which is the drinking water standard for lead. It's these two points here; they are both part of that sinkhole phenomenon. One of them, I believe, the lead contamination is 18. The olher one, the lead level is 17. This compares to the drinking water standard, which is 15.

The numbers are decreasing over fime. The

Page 32

1 they get a pennit in such a radius. 2 MR. SPALVTNS; It's a zone that is restricted 3 in terms of water use. So if somebody pulls a 4 pennit to put in a well, the Water Managemenl 5 District is going to tell them. No, you can't build 6 a well there because you can't drink that water. 7 On top of that control, we plan on ~ we will 8 have a restrictive covenant if we can negotiate 9 with the landowner. So we'll have a legal

10 agreement with the landowner that ihey won't let 11 anybody pul a well in it. 12 Then, the other thing that's — one ofthe 13 most effective controls, though, is that there's a 14 monolith over most of this. So a typical well 15 driller would hit that monolith and ihey would be 15 spinning their ~ their bit would be ~ it would be 17 like trying to go through a sidewalk. So that's 18 the main ~ one of the other controls to prevent 1 9 people from drinking this water thaf s contaminated 20 until it cleans up. 21 MS. BROOKS: The restricted area, how far does 2 2 that go out? 2 3 MR. SPALVINS: It's several hundred feet away 2 4 from the property. I have a diagram of it, but I 2 5 don't have it wilh me. But it is on the website on

Page 31

1 turbidities are better so we are very comfortable 2 we have good data now, and we are almost at the 3 cleanup number for lead. So we are pretty 4 comfortable that we are going to achieve that over 5 lime. It may take some time. 6 But we also have cleanup numbers for iron, 7 manganese and vanadium. The trend is the same for 8 those metals, that if s decreasing over time. In 9 some places it's slower than others to decrease

10 because ofthe effect ofthe pH, bul the trend is 11 that it will decrease overtime. So we will 12 eventually achieve those cleanup numbers. 13 In the meantime, unfil that time, we have ~ 14 this area is in a groundwater restricted ~ 15 Whafs it called, Chris? 16 MR. PELLEGRINO: Oh, um ~ 17 MR. SPALVINS: Delineated area? 18 MR. PELLEGRINO: Well, yeah, it's definitely 19 delineated. But it's ~ whafs the term? The 2 0 Water Management District uses that tenn within our 21 memorandum of agreenient wilh them or — 22 MR. BAGGETT: It's a covenant? Like a 2 3 covenant? 24 MR. PELLEGRINO: It's similar. It comes 2 5 with — the Water Management District flags it when

Page 33

1 one of DEP's databases called Map Direct, I think 2 is what it's called, and it's there. 3 It's several hundred feet off of the property, 4 and we don't have any groundwater contamination 5 outside of that zone. 6 So this is the surficial aquifer, it's the 7 last one I'll show you. I'm just going to pop up 8 the boxes here. 9 One ofthe features ofthe soil cleanup was

10 that most ofthe surficial aquifer was actually 11 excavated and solidified and then put right back in 12 place, but no water is going into it. So 13 basically, when rain hits it, it mns off the top. 14 So most of the surficial aquifer is gone. 15 Then we have our monitoring wells around the 16 monolith thai show that the water in the surficial 17 aquifer has attenuated very nicely. 18 So the risk at the site at this point is that 19 there's a potential risk if people use the 2 0 groundwaler in the future. There's no current 21 exposure, no current health risk because nobody is 22 using the groundwater. But EPA has the Superfund, 23 and the law sets the standard of protection, which 2 4 is that in the future people might use ihis and we 2 5 are going to protect against that potential future

R E P O R T E D BY: S t ephan i e R. Zeitvogel www.huseby .com

H U S E B Y , I N C . - 555 N o r t h Poin t Cen t e r , E . , #403, A l p h a r e t t a , G A 30022 (404) 875-0400

Page 10: TRANSCRIPT - PROPOSED PLAN PUBLIC MEETING FOR THE … · 2 I'm L'Tonya Spencer. I'm the Community Involvement 3 Coordinator for the Sapp Battery site. I'm with 4 the Environmental

U.S. E n v i r o n m e n t a l Pro tec t ion Agency Publ ic Mee t ing S e p t e m b e r 7, 2011

10 (Pages 34 to 37)

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

Page 34

use. The direct exposure to the contaminated soils

and the control oflhe source ofthe groundwater contamination was addressed during the OUl soil cleanup, and the ecological risk was handled in the sediment cleanup when ihey cleaned up the wetlands. So the only remaining risk is potential future exposure to groundwater contamination.

So what — after we identify what the risk is, we set the remedial acfion objective, which is, basically, What we do we want to accomplish with this cleanup?

The first one for this site is to prevent exposure to contaminated groundwater above acceptable risk levels, which are your drinking water standards. So this would be the level of chemicals that would be allowed lo be in a city water system.

Then, the second remedial action objective is to remm groundwater to the beneficial reuse wherever we can. So that's the general principle of aquifer restoration, which basically is the same as the first one with a different employment.

So then, based on the remedial acfion objectives, is the cleanup goals for the

Page 36

1 standard, but not a primary drinking water 2 standard. 3 So the secondary drinking water standards are 4 established based on taste or esthetics or 5 discolorafion. Like iron, iron will lum a sink 6 brovm over fime if there's alot of iron in the 7 water. So we calculated numbers for those. 8 For vanadium, we used a State regulation or a 9 State mie ~ I guess it's a regulafion.

10 MR. PELLEGRINO: Regulation. 11 MR. SPALVINS: Regulafion. Then, we based the 12 vanadium cleanup on Florida Administrative Code 13 62-777.170. Table I in that contains the State 14 regulations that EPA has detennined are applicable 15 lo the ~ to this ~ what is it ~ applicable or 16 relevant in appropriate standards. 17 It's a legal term, basically. Tt means that 18 we are going to defer to the State in 19 certain-situations. WTien they have a cleanup 2 0 number and maybe the EPA or the federal govemment 21 doesn't have a standard, we can defer to those 22 standards. So on vanadium, thafs what we are 23 doing. 24 So then we have developed remedial 25 altematives, which are the cleanup options we have

Page 35

1 contamination — pardon me, I'm sorry. Just a 2 second. Sorry, I have been a little under the 3 weather. 4 We set cleanup goals based on remedial action 5 objecfives. For this site, the remaining 6 groundwaler constituents that are of concem are 7 aluminum, iron, lead, manganese and vanadium. Tlie 8 cleanup goals, we get those cleanup goals from 9 different places depending on the chemical and the

10 law and State regulafions and different sources of 11 cleanup goals so that it's protected. 12 One ofthe main ones we use is the 13 groundwater ~ I'm sorry ~ is the drinking water 14 standard. For lead, we have ~ if s called an EPA 15 action level for lead. That is set at 16 15 micrograms per liter. So that's oneof our 17 cleanup goals. 18 We have three chemicals where the EPA 19 calculated a site-specific number based on our risk 2 0 assessment, guidance. Basically, we calculate how 21 much chemical would be in waler over a certain 2 2 period of exposure without causing a health impact. 2 3 We did that for aluminum, iron and nianganese. 2 4 These are chemicals that don't have drinking water 2 5 standards. They have a secondary drinking water

Page 37

1 for achieving those cleanup goals. 2 The original groundwater remedy here ~ I will 3 just review ~ was pump-and-treat; pump it out of 4 the ground and treat it out ofthe ground and use 5 chemical precipitation, and reinject the treated 6 water into the groundwater or discharging it into 7 the surface water. 8 Tlie original remedy did not mention the 9 nahiral attenuafion, it did not menfion

10 institutional controls. We are adding 11 institutional controls to this, because it didn't 12 mention these things and we can no longer - we 13 have evidence that shows we don't need to do 14 pump-and-treat to achieve the goals and the 15 pump-and-treat is not pracfical based on the 16 aquifer characteristics. 17 This proposed plan is proposbig a new remedy 18 that is documented in a ROD amendment. So we don't 19 issue a new ROD. We issue a ROD amendment, which 20 just changes part of the original remedy. 21 Tlie three opfions that we evaluated in detail 22 in the proposed plan are the no-action ROD, which 2 3 is something that we have to ~ that is mandated by 2 4 law. You know, if you're going to - if s the 2 5 baseline, Wliat would happen if you didn't do

R E P O R T E D BY: S tephan ie R. Zeitvogel www.huseby . com H U S E B Y , INC. - 555 N o r t h Po in t Cen t e r , E. , #403 , A l p h a r e t t a , G A 30022 (404) 875-0400

Page 11: TRANSCRIPT - PROPOSED PLAN PUBLIC MEETING FOR THE … · 2 I'm L'Tonya Spencer. I'm the Community Involvement 3 Coordinator for the Sapp Battery site. I'm with 4 the Environmental

U.S. E n v i r o n m e n t a l Pro tec t ion Agency Publ ic Mee t ing S e p t e m b e r 7, 2011

11 (Pages 38 to 41)

Page 38

1 anything? 2 Tf we didn't do anything, if we just walked 3 away from the site, there is potential that there 4 would continue lo be a risk for future users ofthe 5 groundwater, we wouldn't know, we wouldn't do 6 anything. That's not something we are going to do 7 seriously, but it's baseline. 8 Tn situ treatment would monitor natural 9 attenuation, and it's something that we evaluated.

10 ll was developed ~ an option developed since 2004, 11 injecfing chemicals into the aquifer to adjust the 12 pH and precipitate out the chemicals in-situ. 13 There are some implementability problems with that 14 because of the low permeability nature of the 15 aquifer. It makes it very difficult to inject 16 stuffin there at all. 17 Monitor natural attenuafion is the third 18 remedy that we evaluated, which is, you develop a 19 moniloring plan to look at — to make sure you're 20 monitoring the groundwater. You have to 21 demonstrate that you know whafs happening or you 2 2 know what attenuafion processes are occurring in 2 3 the aquifer, and you can measure them and track how 2 4 the cleanup is proceeding using monitoring natural 25 attenuation. You have a monitoring plan and you

Page 39

1 carry it out. So that was the third option we 2 looked at. 3 One of the componenis we look at when we 4 compare remedies is the lotal cost, and so we have 5 some cost numbers here. I can tell you that the 6 moniloring natural attenuation costs won't cost as 7 much. Under the current budget environment, we are 8 looking for ways to do this at a lower cost than 9 this. We have EPA personnel that we hope we can

10 bring the cost dovra. This is the cost, it's 11 $319,000 is the cost, the present cost, is the cost 12 to continue moniloring natural attenuation for ten 13 or 15 years, in terms of dollars today. 14 Tlie in-situ treatment followed by natural 15 attenuation is about $890,000. So monitoring 16 natural attenuation is a clear winner on cosls. 17 But what this table doesn't capture is that, 18 because ofthe implementability issues with 19 injecfing into this aquifer, that opfion would be a 2 0 waste of money. It would not be effecfive much 21 more quickly than monitoring natural attenuafion 22 would be, because in such an aquifer, you can build 23 a well and you can inject it but if s only going to 24 go a certain distance from the well because the 25 well — the aquifer is so tight and so low

Page 40

1 pemieability. 2 So this proposed plan lays out in more detail 3 the comparison oflhe altematives, but the 4 preferred remedy that we are proposing is 5 monitoring natural attenuation wilh institutional 6 controls. 7 We have evidence that our off-site wells have 8 already reached our cleanup goals. The cleanup 9 goals for lead are reached on-site with the

10 exception of two wells that are problematic because 11 ofthe turbidity issues and the complications of 12 the way they were built and the material they were 13 screened in. 14 The transfer of iron, manganese and vanadium 15 are improving as the pH is remming to a more 16 neutral level. Some of these wells, it may take 17 ten years more, it may lake 20 years, it may take 18 30 years for the levels to reach where they need to 19 be. 2 0 But the set of tradeoffs, over all, the EPA is 21 making the recommendation that natural attenuation 22 is the way lo go. 23 So with that, I will open the floor to open 2 4 discussion or questions. The details are all in 2 5 the proposed plan, and we are accepting comments

Page 41

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

unfil, I think, the 25lh of September. MS. BROOKS: At the time of, I guess, in the

eighties, when this pian was being worked on, the initial, you know, trying to develop the remedies, were there discharges to surface water and how far did the contaminafion go?

MR. SPALVINS: There had been discharges to surface waler and a large part of the swamp to the south oflhe east/west road, that Steele City Bay, a large part of that had been impacted. Steele City Bay drains to a creek south of Steele City Bay, and there were reports in the late seventies that there were fishkills and that there were animals that were drinking lhe water that died from drinking the water. So there had been discharge to surface water in the seventies.

Now, there were invesfigations of those discharges, and I'm trying to recall exactly when those reports were completed. Tt was in the eighfies. What ~ T do recall that there were studies looking at lead, the lead contaminafion in the sediments and down in the creeks that are downstream ofihis area. The conclusion was that the lead contamination didn't go very far. So 1 believe Dry Creek is dov^aigradient.

R E P O R T E D B Y : S tephan ie R. Zeitvogel www.huseby . com H U S E B Y , I N C . - 555 Nor th Po in t Cen te r , E., #403 , A l p h a r e t t a , G A 30022 (404) 875-0400

Page 12: TRANSCRIPT - PROPOSED PLAN PUBLIC MEETING FOR THE … · 2 I'm L'Tonya Spencer. I'm the Community Involvement 3 Coordinator for the Sapp Battery site. I'm with 4 the Environmental

U.S. E n v i r o n m e n t a l Pro tec t ion Agency Publ ic Mee t ing S e p t e m b e r 7, 2011

12 (Pages 42 to 45

Page 42

1 There were a lot of studies of Dry Creek, not 2 just because ofihis site, but because of— I 3 think there was another battery-cracker site that 4 drained into the watershed. So the studies that 5 were conducted of Dry Creek were for both of those, 6 and for other upgradient, upstream industries. 7 But I ~ my best recollection is that there 3 was not a lot of downgradient impact of lead for 9 very far. But it was looked at, and it was ~ all

10 that was documented in the eighties. 11 We have a lol of those documents in Aflanta. 12 They were part of the administrative record for the 13 0U3 cleanup, which was the sediment cleanup. We 14 have some of those. I don't think ~ I don't know 15 ifwe have any of those online. But if you're 16 really interested in ihem, I can certainly forward 17 them to you. 18 MS. BROOKS: I'm interested in Dry Creek and 19 learning more about the story, the impacts to Dry 2 0 Creek. 1 guess tha f s -21 MR. PELLEGRINO: The State has a database that 22 you - an OCULUS database. It has some - 1 don't 23 think all - o f t h e old Sapp stuff, but it does 2 4 have a lot of the old Cohee-Bams smff. 25 MS. BROOKS: Cohee-Bams?

Page 44

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

know, was in that drainage until I saw the EPA nofice. I looked it up on the map to see where it was. I thought. Oh, I wonder if that affected Dry Creek? I've got to leam more.

MR. SPALVTNS: Yeah, ihey did look at that. Tliey did look at it, and it did impact dovm the river or downstream a little ways. I don't know exactly hovi' far.

But what happens, there was — at a site like this, you have the nomial kind of trickle of contaminafion that leads to the site.

But then, maybe there's a storm or maybe there's an accident al the site and there's a large release all at once, and that's the kind of thing that has the maximum — the maximum reach downstream.

It's a very limited ~ at this site, at any rate, il was the limited-type events that were high-volume releases into the creek. I think that is where you saw the most extent of impacts. The chronic release or the longlenn releases that were occurring, I think, were more limited.

I don't think that there will be any lasting impact at Dry Creek as a result of this site. Nothing ~ I don't know of anything that you would

Page 43

1 MR. PELLEGRINO: Cohee-Bams is another 2 battery cracker that's under the State-funded 3 cleanup program. I believe thafs lhe one that 4 was ~ you referred to ~ 5 MR. SPALVINS: May have been. 6 MS. BROOKS: Is that a public website, OCULUS? 7 MR. PELLEGRINO: Yes, ma'am. Ifyou go onto 8 our DEP website you can access OCULUS through that 9 and it's a public log-in.

10 MS. BROOKS: Okay. 11 MR. SPALVTNS: Ifyou leave your e-mail on the 12 contact list, I can e-mail you something. 13 MS. BROOKS: Okay, yeah. Actually, if s on 14 there. 15 MR. SPALVTNS: Yeah, 1 read through a lot of 16 those documents. I had someone call me with some 17 questions about Dry Creek about six months ago and 18 I looked into someof those documents. So we 19 definitely have some of those. Someof those were 2 0 not studies the EPA conducted. They were studies 21 that were conducted by other govemment agencies. 2 2 1 don't recall exacfiy who. 2 3 MS. BROOKS: My interest is, as a paddler, I 2 4 like to kayak and canoe on Dry Creek and Spring 2 5 Lake. I didn't even realize this plant had ~ you

Page 45

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 13 19 20 21 22 23 24 25

be able to see today. Any questions? All right. Well, I think we

will call it ~ this is end ofthe public meefing. MS. SPENCER: Thank you, everybody, for

coming. MR. SPALVINS: Thank you-all.

(Off the record.)

R E P O R T E D BY: S t ephan i e R. Zeitvogel www.huseby . com H U S E B Y , I N C . - 555 N o r t h Po in t Cen t e r , E. , #403, A l p h a r e t t a , G A 30022 (404) 875-0400

Page 13: TRANSCRIPT - PROPOSED PLAN PUBLIC MEETING FOR THE … · 2 I'm L'Tonya Spencer. I'm the Community Involvement 3 Coordinator for the Sapp Battery site. I'm with 4 the Environmental

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 13 19 20 21 22 23 24 25

U.S. Environmental Protection Agency Public Meeting September? , 2011

13 (Page 46)

Page 46

REPORTER'S CERTIFICATE

STATE OF FLORIDA COUNTY OF BAY

I, Stephanie R. Zeitvogel, do hereby cenify that I was authorized to and did report the foregoing proceedings, and that the transcript, pages 1 through 46, is a tme and correct record ofthe proceedings lo the best of my ability.

Done and dated this i 9th day of September, 2011, at Bay County, Florida.

STEPHANIE R. ZEITVOGEL

REPORTED BY: Stephanie R. Zeitvogel www.huseby.com HUSEBY, INC. - 555 North Point Center, E., #403, Alpharetta, GA 30022 (404) 875-0400

Page 14: TRANSCRIPT - PROPOSED PLAN PUBLIC MEETING FOR THE … · 2 I'm L'Tonya Spencer. I'm the Community Involvement 3 Coordinator for the Sapp Battery site. I'm with 4 the Environmental

1

2 IMPORTER' S "GERTI FiCATE

.3

STATE QF, FLOt&ph. }

'COI-JNTY W B'fiii- )

6

7

8' .1 , Step'tiaaie R,. .Zei typgel , do- h'^retiy" q^rt.i.fy tHa.t .[

9 was a u t h o r i z e d t o and: d i d r e p o r t t h e fo regdi-fiinf;

10' p roceed ings , ao^ tha^t t h s . t . rah ' scr ip t , pages 1.

1.1, through 46, i s a-true.- ai3d, c o r r e c t record of t h e

12 proCeectings t o tlte' beSt iif iity ' afe-ili'ty,.

13'

14 Dph^. .ahd.:d,at.ed thi .s 19th ^dr^y'.of 'September>, 2QII7; -at

15 -Bay Gpunty; I?'lo,ridf.,,

1.6:

17

IB.

19

20

21

2'2

23

24

25;

..ST.Epfc^XE ITVOG,l;.l,

Page 15: TRANSCRIPT - PROPOSED PLAN PUBLIC MEETING FOR THE … · 2 I'm L'Tonya Spencer. I'm the Community Involvement 3 Coordinator for the Sapp Battery site. I'm with 4 the Environmental

A ability 46:11 able 23:6 27:22 45:1 absolution 20:4 acceptable 34:15 accepting 40:25 access 43:8 accident 44:13 accomplish 34:11 achieve 31:4,1237:14 achieving 37:1 acid 7:6,11,14,18,19,22

8:24 11:25 13:2 19:25 20:3,6 23:20

acre 19:23

acreage 17:11 21:14,21

acres 18:7,11,11,11 19:1

19:3,6,20,21 21:9 21:12 24:4,9

act 9:17 10:1 action 6:198:3 28:17

34:10,19,24 35:4 35:15

actions 5:6 19:9 added 14:15

HUS

U.S. Environmental Protection Agency

adding 37:10 addressed 34:4 adjust 38:11 administrative 36:1242:12 affordable 12:25

afraid 13:6

agencies 43:21 Agency 1:1 3:4

ago 16:22 29:2 43:17

agreenient 8:631:21 32:10 ahead 8:11 alligators 27:4 allowed 34:17 alternatives 36:25 40:3 aluminum 25:8 35:7,23 amendment 37:18,19 amount 13:15

analyzed 26:6 animals 41:14 Anna 11:2

answer 12:19

anybody 4:20,21 32:11

REPORT EBY, INC. - 555 Nor

Public Meeting

apologize 16:1,1424:17

appears 15:18

applicable 36:14,15 approach 6:4 18:24 appropriate 21:6 36:16 aquifer 12:4 14:21 15:1,13

17:13,19,21,23 18:4,9,23 19:1,3,5 19:20,21,22 20:2 20:1424:7 27:10 27:14 28:2,3,22 29:5 30:10,11,16 30:17 33:6,10,14 33:17 34:22 37:16 38:11,15,23 39:19 39:22,25

area 15:20 17:3,15,20

18:1019:1,15,16 19:23 22:17 23:6 23:14,16,18,25 24:1 31:14,17 32:2141:23

areas 22:8 23:11 29:17

29:18 asking 3:9 assessment 35:20 ate 29:2 Atlanta 2:103:5 42:11 attendance 4:7 attention 20:10 26:2

ED BY: Stephanie R th Point Center, E., #

attenuate 10:16 15:7

attenuated 28:7 33:17 attenuation 15:720:1 21:5 28:1930:1437:9 38:9,17,22,25 39:6,12,15,16,21 40:5,21

authorized 46:8

1 ^

B back 5:4 10:19 16:20

20:7,8,19 22:3,5 33:11

bad 28:5,12 Baggett 2:13 12:6,17,17

15:18,22 31:22

ballpark 18:2

based 9:25 15:5 24:5

26:12 34:24 35:4 35:19 36:4,11 37:15

baseline 37:25 38:7

basic 29:6 basically 3:194:16 10:10

11:722:15 27:16 30:9 33:13 34:11 34:22 35:20 36:17

basmg 26:13 batteries 7:4,6,8 9:21 battery

. Zeitvogel 403, Alpharetta, GA

September 7, 2011 Page 47

1:3 3:3,8,18 6:25 7:2 9:11 43:2

battery-cracker 42:3 battery-cracking 16:7

Bay 17:341:9,11,12 46:4,14

behaved 14:21

believe 13:3 21:5 24:12

26:18 30:2141:25 43:3

bells 15:17

beneficial 34:20 best 20:15 22:7 42:7

46:11 better 31:1 big 11:22 16:24 18:9

18:12 24:7 27:4 bigger 18:8 28:16

bit 5:28:11 14:13 15:3

17:621:1826:15 32:16

body 11:9

bottom 29:24 30:2,15 boundary 23:4 box 24:4 boxes 33:8 Branch

www.huseby.conf

1 i

1

30022 (404)875-0400

Page 16: TRANSCRIPT - PROPOSED PLAN PUBLIC MEETING FOR THE … · 2 I'm L'Tonya Spencer. I'm the Community Involvement 3 Coordinator for the Sapp Battery site. I'm with 4 the Environmental

U.S. Environmental Protection Agency Public Meeting September 7, 2011

Page 48

2:9 brief 4:17 14:12 briefly 5:1 bring 7:4 8:24 39:10 Brooks 2:15 5:12 10:25

11:2,3,13,16 12:2021:7,9,14 21:20 22:20,25 25:15 26:17 32:21 41:2 42:18,25 43:6,10,13,23

brown 36:6 budget 39:7 build 8:20,25 23:12,13

23:14 32:5 39:22 buildings 16:6

built 22:6 40:12 business 8:1 buy 26:23

y ^

C calculate 35:20 calculated 35:19 36:7 call 6:4 9:7 16:9 43:16

45:3 called 9:11 12:13 14:7,8

31:1533:1,2 35:14

canoe

43:24 capture 39:17 carried 9:14 10:6,6 14:5

19:11 carry 6:20 39:1 carrying 3:25 causing 35:22 cement 12:14

Center 1:10

certain 9:17 13:15 22:9

25:19 35:21 39:24 certainly 42:16 certain-situations 36:19 CERTIFICATE 46:1 certify 46:7 change 18:9

changes 37:20 characteristic 26:25 characteristics 37:16 Chattahoochee 11:3

chemical 35:9,21 37:5 chemicals 34:17 35:18,24

38:11,12 choice 15:4

choose 6:14 Chris 2:12,144:8,12

31:15 chronic 44:21 city 17:3 34:17 41:9,11 41:11

clarity 25:13,16 classes 9:18 clay 27:3 clays 27:11,12 30:3 clean 20:25 25:11 cleaned 34:6 cleaning 7:21 cleans 32:20 cleanup 4:1,4,6,12,19 5:6,9

5:10,15,15,16,19 6:4,16,20 8:7,10 8:17,20 9:6,12 10:7 11:21 13:8 14:1,2,3,23 15:10 16:11,11,1821:6 23:24 24:1,3 25:22 30:18 31:3 31:6,12 33:9 34:5 34:6,12,25 35:4,8 35:8,11,17 36:12 36:19,25 37:1 38:24 40:8,8 42:13,13 43:3

cleanups 9:19

clear 15:4 26:5 39:16

closed 10:8

closely 29:12 coalesced 9:10 Code 36:12 Cohee-Barns 42:24,25 43:1 collapsed 29:3 column 17:14,14

combination 22:4 come 16:3

comes 27:20 31:24 comfortable 30:1331:1,4 coming 20:421:13 24:10

45:5 comments 6:10,10 40:25 Community 1:102:73:2

companies 7:3 8:1,3,13 9:18

9:20 company 7:5 compare 39:4 compared 16:25

compares 30:23 comparison 40:3

comparisons 17:5

completed 9:7 41:19 ^ complicated 4:10 complications 40:11 ^ component 14:2

components i 39:3 ^ compounds 9:1 comprised 27:10 : computer 16:4 22:15 j

concept 29:6 • concern 17:17 35:6 !

conclude | 15:6 i

conclusion ^ 41:23 I conducted 9:12 13:8 18:16

23:24 42:5 43:20 . 43:21

Congress | 9:16,22 10:1 J connected 22:19 ] cons 5:24 consider ^ 12:4 j

considered J 11:10,24 j

constituents ^ 35:6 construction i 10:3 i

REPORTED BY: Stephanie R. Zeitvogel www.huseby.com HUSEBY, INC. - 555 North Point Center, E., #403, Alpharetta, GA 30022 (404) 875-0400

Page 17: TRANSCRIPT - PROPOSED PLAN PUBLIC MEETING FOR THE … · 2 I'm L'Tonya Spencer. I'm the Community Involvement 3 Coordinator for the Sapp Battery site. I'm with 4 the Environmental

U.S. Environmental Protection Agency Public Meeting September 7, 2011

Page 49

contact 43:12 contains 36:13 contaminate 28:16 contaminated 8:24 10:12 12:10

18:1032:1934:2 34:14

contamination 7:12 9:10 14:18,20

14:25 15:6 17:12 17:12 19:5,7,18 20:4,17 28:13 29:19,23 30:18,22 33:4 34:4,8 35:1 41:6,21,24 44:11

continue 15:6 38:4 39:12

continued 20:9 continues 27:6 28:12 contributed 9:10 contributing 15:13

control 15:10 17:6 19:10

19:11,1521:2 32:7 34:3

controls 7:10 32:13,18

37:10,1140:6 conversation 4:23 coordinator 2:73:3 12:18 copy 26:15 correct 46:10 cost

39:4,5,6,8,10,10,11 39:11,11

costs 39:6,16 Cottondale 1:10,11 counterpart 4:9 County 46:4,14 course 28:20 Court 1:12

covenant 31:22,23 32:8 cover 5:1 9:3 covers 23:14,18 cracker 43:2 creating 28:3 creek 41:11,25 42:1,5,18

42:20 43:17,24 44:4,19,24

creeks 41:22 cross-section 28:22 crowd 4:21 cubic 13:12

current 26:13 33:20,21

39:7

D

data 15:2,3,5 24:17

26:10,11,13,19

29:10,20 31:2 database 42:21,22 databases 33:1 DATE 1:8

dated 46:13 dates 10:9

day 46:13 days 6:10 dead 10:19

deal 4:15 decide 3:21 5:23 decided 22:11 decision 3:244:5 6:2,12

8:14,16 18:13 decompose 13:23

decrease 31:9,11 decreased 14:25,25 28:9 decreasing 30:25 31:8 deep 12:1

defer 36:18,21 definitely 31 • 18 43 • 19 delineated 31:17,19 demonstrate 38:21

DEP 4:9,11 24:24 43:8 depending 6:23 35:9 depends 11:7

DEP's 33:1 describe 20:16 describing 24:6 description 11:11 design 6:17 10:5 14:14,16 destroyed 22:2,10 detail 14:13 37:21 40:2

detailed 24:19 details 6:18 40:24 detection 26:7,9 determined 36:14 develop 38:1841:4 developed 36:24 38:10,10 diagram 32:24 died 41:14 difference 16:24 18:6

different 10'9 12-^3 13-19

15:3 16:6 25:7 28:16,23 34:23 35:9,10

difficult

14:22 38:15 digging 23:25 direct 9:5 33:1 34:2 discharge 14:11 20:2441:15

discharges 41:5,7,18 discharging 37:6 discoloration 36:5 discuss 4:2 discussed 5:2 discussion 4:17 40:24 dissolve 20:5 distance 39:24 distinction 11:4

distinguish 11:12

District 31:20,25 32:5 Division 2:9 document 6:12,13 documentation 7:25 documented 37:1842:10 documents 42:1143:16,18 doing 18:1 20:11 36:23 dollars 39:13 Door

REPORTED BY: Stephanie R. Zeitvogel www.huseby.com HUSEBY, INC. - 555 North Point Center, E., #403, Alpharetta, GA 30022 (404) 875-0400

Page 18: TRANSCRIPT - PROPOSED PLAN PUBLIC MEETING FOR THE … · 2 I'm L'Tonya Spencer. I'm the Community Involvement 3 Coordinator for the Sapp Battery site. I'm with 4 the Environmental

U.S. Environmental Protection Agency Public Meeting September 7, 2011

Page 50

8:19 doublecheck 22:12 downgradient 18:20 41:25 42:8

downstream 41:23 44:7,16 drainage 7:7 44:1 drained 23:21,22 42:4 draining 23:20 drains 41:11 driller 32:15 drink 32:6 drinking 17:16,24 25:23

30:19,23 32:19 34:15 35:13,24,25 36:1,341:14,15

Dry 41:25 42:1,5,18,19

43:17,24 44:4,24 dug 11:21 12:1,2,6

13:1015:11 16:10

E earlier 8:15 30:16 early 7:1 16:17 18:24 easier 23:13 easily 20:6 eastern 16:9

east/west 41:9

easy 4:24 ecological 34:5 economic 12:24

effect 31:10 effective 14:23 32:13 39:20

eighties 5:4 15:16 16:8

18:17 21:25 22:5 41:3,2042:10

elevated 25:12,18,18 emergency 19:8

employment 34:23' ended 7300 energy 7:21 enforcement 8:3 enter 6:21 entered 7:16 8:6 entire 5*20 environment 19:18 39:7

Environmental 1:1 3:4

eons 27:3 EPA 2:8 6:12 7:20 8:2,7

8:8,8,13,16 10:5 14:13 33:22 35:14 35:18 36:14,20 39:9 40:20 43:20

44:2 EPA's 4:11 Equities 9:17 Erik 2:2 3:5,17 Erik's 3:10 establish 21:20 established 36:4 esthetics 36:4 estimate 22:16 24:6,14 estimated 18:8,17

estimates 18:1 22:17,19 24*10

estimating 18:7

evaluated 37:21 38:9,18 events 44:18 eventually 31:12 everybody 23-2 45-4 evidence 21:3,4 37:13 40:7 EW2D 25:20 exactly 3:21 5:21 15:15

41:18 43:22 44:8 excavate 8:23 excavated 10:11 16:1222:1 33:11

excavating 10:20 excavation 10:21

excavator 10:18 16:25

exceedances 20:13 exception 40:10 excuse 7:18 existed 16:8

exposure 9:5 33:21 34:2,8,14

35:22 extent 44:20 e-mail 43:11,12

F

faciUty 8:2 16:6 23:3 fact 11:21

familiar 15:18

far 20:23 32:2141:5

41:24 42:9 44:8 FDEP 2:12 feasibility 5:22 features 33:9 federal 9:25 10:4 13:25

36:20 feel 4:22 feet

17:20 23:10,11 32:23 33:3

fenced 23:4 : figure j 13:21 17:823:1 26:21

figures 21:21 filled 10:21 27:2 29:4

final 6:11 find 29:23 j fine 5:12 finished 9:15 10:5,7 14:3

19:12 first 3-11 11-22 17-13

17:14 19:634:13 ' 34:23

fishkills 7:1641:13 fix 3:22,23 5:24 6:13

6:19 fixated 12:7,11

flags 31:25 flip i 16:20 !

floor 40:23 Florida 1:11,13 11:3 36:12 46:3,14

Floridan 17:22 18:9 19:5,7

19:21 24:7 flushed

REPORTED BY: Stephanie R. Zeitvogel www.huseby.com HUSEBY, INC. - 555 North Point Center, E., #403, Alpharetta, GA 30022 (404) 875-0400

Page 19: TRANSCRIPT - PROPOSED PLAN PUBLIC MEETING FOR THE … · 2 I'm L'Tonya Spencer. I'm the Community Involvement 3 Coordinator for the Sapp Battery site. I'm with 4 the Environmental

U.S. Environmental Protection Agency Public Meeting September 7, 2011

Page 51

28:7 flushing 20:1 folks 9:9 followed 39:14 foregoing 46:8 formed 9:11 29:1 Forsyth 2:10 forward 42:16 found 7-25 8-4 1 , ^ ^ \ j ^ ^

free 4:22 Front 1:10

further 24:2 future 33:20,24,25 34:7

38:4

G

general 11:11 34:21

geological 28:24 Georgia 2:103:5 getting 19:15 20:11 29:15

30:9 give 9:23 18:3 giving 20:13 go 7:7 8:21 14:12

20:23 21:7 28:17

32:17,22 39:24 40:22 41:6,24 43:7

goals 34:25 35:4,8,8,11

35:1737:1,14 40:8,9

goes 6:23 23:17 going 3:74:166:14,18

13:23 16:19 17:5 20:7,8,21,23,24 24:17 26:23 27:14 28:1,2,15,18 31:4 32:5 33:7,12,25 36-18 37-24 38'6 39:23

good 4:157:10 11:6

18:22 20:11 27:24 28:11,1431:2

gotten 4:21 government 4:8,8 9:25 10:4

13-^5 36-20 43-21 gray 23:6,7 grew 18:10

ground 23:10 28:23 37:4,4 groundwater 1:44:195:176:16

7:199:3 12:2 14:2,7,9,11,17,20 14:22 17:8 18:14 18:25 19:14,17 20:2,18,21 21:13 23:15 25:23 26:19 27:17 28:4,12 31:14 33:4,20,22 34:3,8,14,20 35:6

35:13 37:2,6 38:5 38:20

group 4:248:4 9:11,11

15:11 grow 18:15

growing 10:23

guess 4:13 8:12 24:8

26:23 36:9 41:2 42:20

guidance 35:20

H half 29:7 30:15 hand 28:6 handle 4:24 12:25 14:17

18:14 handled 8:9 9:25 10:4 13:9

14:1 34:5 handles 15:8

happen 37:25 happened 7:3 14:12 happening 19:14,25 27:16

38:21 happens 44:9 hard 29:8 harder 13:22

hauled 10:12 11:14

hazardous 13:4

health 33:21 35:22 heavy 7:13 10:12 20:3,5 help 10:5

high 22:16,1823:14

25:22,24 27:6 higher 28:6 high-volume 44:19 history 4-17 25-3 ^ 9 X I ^ mJ wmJ

hit 32:15 hits 23:16 33:13 hold 30:4,8 holding 7:7,15 hope 17-10 39-9 1 / l i V / i - J J - J '

huge 23:9 hundred 13:11 32:23 33:3

I

idea 9:19 18:3 identified 8:169:9 29:17 identify 5:21 34:9 identifying 3:21 image 16:15,21 25:1

images

24:19 impact 28:3 35:22 42:8

44:6,24 ! impacted 7:18,199:2141:10 impacting 18:1928:11

impacts 42:19 44:20 implementability 38:13 39:18 important 25:10 improved 10:18 17:7

improvements 20:16 improving 40:15 includes 23:19 increase 18:12

individuals 7:4 8:4 inHii^frif^^

42:6 industry 9:21,22 ; infiltrating 23-15 information 26:12,14 infrastructure 13:15

initial ; 41:4 inject 27:21 38:15 39:23 injecting 38:11 39:19 input 8:9

REPORTED BY: Stephanie R. Zeitvogel www.huseby.com HUSEBY, INC. - 555 North Point Center, E., #403, Alpharetta, GA 30022 (404) 875-0400

Page 20: TRANSCRIPT - PROPOSED PLAN PUBLIC MEETING FOR THE … · 2 I'm L'Tonya Spencer. I'm the Community Involvement 3 Coordinator for the Sapp Battery site. I'm with 4 the Environmental

U.S. Environmental Protection Agency Public Meeting September?, 2011

Page 52

installed 25:6

22-11 institutional 37:10,11 40:5 interest 43:23 interested 42:16,18 intermediate 17:2] 18:8 19:3,22 20:1429:5 30:15 30:17

interrupting 8:19 introduce 3:11,14 investigating 7:24 investigation 3:20 5:21

investigations 41:17 involved 13:1023:25 24:3

Involvement 2:7 3:2 in-situ 38:12 39:14 iron 25:8 27:6 31:6 35:7

35:23 36:5,5,6 40:14

issue 6:11 26:4 37:19,19 issued 6:7 8:14 issues 39:18 40:11

J judgment 22:8 24:15

jumped 8:11

K kayak 43:24 keeps 23:15 killed 7:17 kind 18:2 22:16 23:23 24:15 28:1044:10 44:14

kinds 27:4 know 4:22 5:23 18:2,3,5

18:21 25:14 26:2 29:1 37:24 38:5 38:21,22 41:4 42:14 44:1,7,25

L

Lake 43:25 landfill 10:13 11:14 12:22

13:4,5,24 landowner 32:9,10 large 1:1322:1,1723:18

41:8,1044:13 largely 21:1 24:1 larger 29:7 largest 21:4 lasting 44:23 late 41:12 law

9:22 33:23 35:10 37:24

lay 5:23 6:18 layers 28:23 lays 40:2 leaching 9:3 lead 7:8 8:24 9:2 12:1

17:12,15,21,22,24 18:23 19:20,24 20:7,14,1721:1 25:8,21,24 26:6 29:9,19,23 30:4,8 30:11,17,19,22,22 31:3 35:7,14,15 40:941:21,21,24 42:8

leads 6:2 21:4 44:11 learn 14:19 44:4

learned 14:24 22:13 29:14

learning 42:19 leave 43:11 lefi 19:22 legal 32:9 36:17 Leigh 2:15 11:2 level 26:7,9 30:23 34:16

35:15 40:16 levels 20:6,7 34:15 40:18 liability 9:24

lily 10:23 16:24

limestone 28:25 29:2 limited 44:17,22 limited-type 44:18 line 29:24 list 43:12 liter 25:22 35:16 little 5:2 8:11 13:19

14:13 15:3 17:6 18:4,5,8 21:18 23:6 26:15 29:7 35:2 44:7

log-in 43:9 long 6:23 longer 37:12 longterm 44:21 look 14:16 16:3 29:12 38:19 39:3 44:5,6

looked 16:17 20:20 30:10

39:2 42:9 43:18 44:2

looking 15:1 16:1,21 18:15 39:8 41:21

lot 9:20 10:18 11:25

11:25 12:23 13:2 13:9,14,20,22 14:25 17:17 19:17 22:13,14 23:8,20

23:25 25:12 26:10 27:11 29:8,18 30:7,13 36:6 42:1 42:8,11,24 43:15

low 23:1027:17,17,19

27:23,24 28:5,10 29:14,25 38:14 39:25

lower 27:14 39:8 L'Tonya 2:6 3:2,16

M MAECTITE 12:13 magnitude 20:16 mailed 6:8 24:19 main 12:21 26:25 32:18

35:12 maintenance 6:22 making 40:21 manage 3:20 managed 8:8 Management 31:20,25 32:4 manager 2:3 3:6,18,25 managing 7:11 mandated 37:23 manganese 25:8 31:7 35:7,23

40:14 manner

REPORTED BY: Stephanie R. Zeitvogel www.huseby.com HUSEBY, INC. - 555 North Point Center, E., #403, Alpharetta, GA 30022 (404) 875-0400

Page 21: TRANSCRIPT - PROPOSED PLAN PUBLIC MEETING FOR THE … · 2 I'm L'Tonya Spencer. I'm the Community Involvement 3 Coordinator for the Sapp Battery site. I'm with 4 the Environmental

U.S. Environmental Protection Agency Public Meeting September?, 2011

Page 53

18:18 map 33:1 44:2 maps 21:12 material 11:24 12:8,11,13

13:1,2,9,12,23 15:12 20:2 27:14 28:24 29:25 40:12

matter 13:20 27:13

maximum 44:15,15 ma'am 12:17 43:7

means 26:8 36:17 measure 25:13,16 38:23 measures 17:721:2 meeting 1:7 3:8 4:2 6:9,9 45:3

memorandum 31:21 mention 37:8,9,12 mentioned 26:24 metals 7:13 10:12 20:4,5

28:931:8 micrograms 25-21 35-16 miv

9:1 mixed 27:12 mobile 30:11 mobilize 13:16

modeling 18:1622:15

models 18:21

money 39:20 monitor 38:8,17 monitored 22:20 monitoring 19:13 20:921:21 21:23,24 22:2,3 22:1433:15 38:19 38:20,24,25 39:6 39:12,15,21 40:5

monolith 8:20 9:1,4 11:17,18

16:13 23:8,8,18 32:14,1533:16

months 43:17 move 5:13 18:1727:15 moved 15:23

movement 18:23

moving 30:11 mylar 15:19

N name 3:12,17 11:1 12:15 natural 15:7 16:9 20:1 21:5 28:18,19 37:9 38:8,17,24 39:6 39:12,14,16,21 40:5,21

naturally 10:16

nature 38:14 need 37:13 40:18 negotiate 32:8 neighbors 18:19

neutral 28:8 40:16 neutralize 7:22 neutralizing 20:3 new 22:3,5 24:17 25:2

26:13 29:21,22 30:13 37:17,19

newer 25:5 news 27:24 28:14 nicely 33:17 nineties 19:13

normal 13:5 20:7,8 44:10

north 29:7 Notary 1:13

notice 44:2 no-action 37-22 n i i n i h p r ' 1 1 U l I l C . f V I

12:9 25:21 30:18 31:3 35:19 36:20

numbers 25:18 27:6 30:25

31:6,1236:7 39:5

O

objective 11:23 34:10,19

objectives 34:25 35:5 Obviously 24:12 occurred 19:10

occurring 38:22 44:22 OCULUS 42:22 43:6,8 off-site 11:1418:1821:17 21:1924:11 40:7

oh 5:11 11:2 17:1

31:1644:3 Okay 26:17,20 43:10,13 old 22:4,9 23:19 42:23

42:24 once 3:24 44:14 ones 35:12 ongoing 28:4 online 42:15 on-site 8:21 13:13,14,16

13:22 40:9 open 7:5 40:23,23 OPFRABLF V ^ • M S J M . ^ . ^ ^ M ^ M ^ K : J

1:4 operating 7:5 operation 6:22 7:2 16:7 operations 23:5

option 38:1039:1,19 options 3:21,22 5:23,24

15:2 36:25 37:21 organic 13:20,23 27:12

orient 23:2 orientation 23:23 original 16:5 18:13 23:5 37:2,8,20

originally 1 16:17

outline 23:7,7 24:5 1 outside 33:5 OUl 8:22,23 16:10 24:1

34:4 OU2 24:2,2 OU3 10:3 42:13

overflowed 7:15 overlay 24:17 owner 8:1 ownership 21:16

P paddler 43:23 1 pads 10:23 16:24

pages 46:9 paid

REPORTED BY: Stephanie R. Zeitvogel www.huseby.com HUSEBY, INC. - 555 North Point Center, E., #403, Alpharetta, GA 30022 (404) 875-0400

Page 22: TRANSCRIPT - PROPOSED PLAN PUBLIC MEETING FOR THE … · 2 I'm L'Tonya Spencer. I'm the Community Involvement 3 Coordinator for the Sapp Battery site. I'm with 4 the Environmental

U.S. Environmental Protection Agency Public Meeting September 7, 2011

Page 54

20:10 paperwork 7:25 10:8 parameters 25:8 parcel 23:5 pardon 35:1 part 4:5,11 5:3 6:16,16

8:7 10:2 11:9,21 11:23 12:4,4 16:12,20 21:3,4 23:19 30:20 37:20 41:8,1042:12

PARTICIPANTS 2:1 particulates 30:7 parties 8:5,13 partner 4:11 parts 5:8 7:21 12:3 22:1 Party 9:8 passed 9:16,22 paying 4:11 26:2 peat 27:3 30:1 Peats 30:2 Pellegrino 2:12 4:9 22:23

24:21 31:16,18,24 36:1042:2143:1 43:7

people 8:5 9:5,18 17:23

32:19 33:19,24

period 6:23 18:18 35:22 permeability 27:13,18,19,23,25

28:5,1030:1 38:14 40:1

permit 32:1,4 personnel 39:9 pH 20:6,6 25:9 27:17

28:831:1038:12 40:15

phase 6:22 phenomenon 30:21 photo 10:19 16:23,25

picture 10:22 15:14 16:2

17:1 30:9 pictures 10:1724:18

pile 13:21

pink 24:4 29:9 place 1:1033:12

places 28:25 31:9 35:9 plan 1:2 4:2,3,20 6:1,7

6:15 24:18 27:9 29:11 32:7 37:17 37:22 38:19,25 40:2,25 41:3

planned 19:12

planning 3:8 6:13 9:13 plant

43:25 plants 10:23 27:4

please 3:11 Plenty 5:13 plume 17:15,16,21,22,25

18:15,17 19:2,19 19:20,24 24:7 28:15 29:9

plumes 21:13,14,15 Pius 14:24

pockets 27:17 point 4:22 33:18 points 20:1221:1930:16

30:20 pond 7:7,15 pop 33:7 portions 5:17 possible 15:9

potential 33:19,25 34:7 38:3 Potentially 9:8 PowerPoint 4:14 practical 37:15 precipitate 38:12 precipitation 37:5 predicting

18:23 preferred 40:4 prepared 4:5 present 26:11 39:11 presentation 3:104:14 pretty 4:24 12:1 18:12

20:20 23:10,18 25:22,24 31:3

prevent 9:2 32:18 34:13 primary 36:1 principle 34:21 probably 13:5 22:19

problem 3:22,23,23 5:22,25

6:14,19 15:13 18:1420:21 21:1 26:1 28:4

problematic 40:10 problems 38:13 proceeding 38:24 proceedings 8:19 46:9,11 process 5:2,8,20 6:3,6 7:24

22:13 processes 38:22 producing 29:20 professional 22:7 24:15 program

5:4 43:3 project 2:3 3:5,17,24 12:18 ^

12:18 projector j 26:22 27:8 property 8:2 23:4 32:24 33:3 proposed | 1:2 3:8 4:2,3,20 6:1

6:7,15 24:18 27:9 i 29:11 37:17,22 i 40:2,25 J

proposing \ 4:19 37:17 40:4 proprietary ^ 12:13

pros 5:24 i protect 33:25 j protected 1 35:11 j protection 1:1 3:4 33:23 '

PRP j 9:7 12:18 15:10 ' public 1:7,13 6:7,8,10 43:6,9 45:3

pulls 32:3 pump ^ 14:8,8,17,22 15:3

20:22 27:18 37:3 pumped 12:7 1

pumping 30:6 I pump-and-treat 37:3,14,15 pursued % 8:3 i push J

REPORTED BY: Stephanie R. Zeitvogel www.huseby.com HUSEBY, INC. - 555 North Point Center, E., #403, Alpharetta, GA 30022 (404) 875-0400

Page 23: TRANSCRIPT - PROPOSED PLAN PUBLIC MEETING FOR THE … · 2 I'm L'Tonya Spencer. I'm the Community Involvement 3 Coordinator for the Sapp Battery site. I'm with 4 the Environmental

U.S. Environmental Protection Agency Public Meeting September?, 2011

Page 55

27:22 put 11:17,1821:24 22:3,10,11 29:21 32:4,11 33:11

pyramid 23:9 p.m 1:9,9

rf-x

0 quality 16:2,14 17:7 20:12 26:4 29:15,20

question 4:22 11:6 12:19 questions 3:11 4:13 40:24

43:1745:2 quickly 39:21

R f-fc

R 1:1246:7,17

radius 32:1 railroad 24:11,13 rain 23:15 33:13

rate 18:25 44:18

reach 40:18 44:15 reached 40:8,9

1

read A '^ 1 C 43:15 real 18:6 26:1

1 * J.

reahty 30:12

* ^ 1 • _

realize 43:25

realized 14:20 26:3

really 10:17 17:13 29:20

30:3,8 42:16 reason 12:21 15:9

reasons 12:23,24 27:7

recall 13:3 15:15,16 41:18,20 43:22

receive 6:10 recognize 4:12 recollection 42:7 recommendation 40:21 fpcnrH 1 W \ J 1 \ M

6:2,11 8:14,16 12:16 13:6 42:12 45:7 46:10

records 3:13 recycling 7:2,9 9:17,22 referred 43:4 Region 2:8 3:4 regulation 36:8,9,10,11 regulations 35:1036:14 reinject 14:1037:5

release 7:6 28:1 44:14,21 released 9:17 releases 44:19,21

relevant 36:16 relief 9:23 remainder 9:24 21:6 remaining 34:7 35:5 remains 19:24

remedial 2:3,9 3:5 6:17,19

10:5 34:10,19,24 35:4 36:24

remediation 10:15 19:16

remedies 14:4,5,6 39:4 41:4

remedy 6:3,5,6,24 8:17,22

11-22 14-14 20-21 37:2,8,17,20 38:18 40:4

remember 13:7

removal 22:1 removed 12:9 16:12 19:17

20:1 repaired 15:24

report 46:8 REPORTED 1:12

Reporter 1:12

REPORTER'S 46:1 reports 41:12,19 resolved 21:1

response 19:9

responsibilities 3:19 responsibility 9:18 responsible 3:25 8:5,13 9:8 rest 10:15 28:1,3

restoration 34:22 restored 10:13,23

restricted 31:1432:2,2! restrictive 32:8 result 7:12 8:4 20:3 21:2

29*9 27'] 3 44-74 results 25:7,19 return 34:20 returning 40:15 reuse 34:20 review 37:3 rid 11:23

right 4:15 10:20 11:15

11:19 15:21,25 16:20 22:22 23:3 23:4 24:25 26:24 29:20 33:11 45:2

ring 15:17

risk 33:18,19,21 34:5,7

34:9,15 35:19

38:4 river 44:7 road 41:9 ROD 8:14 14:6,737:18

37:19,19,22 room 5:13 Roy 2:13 12:17 15:17 rule 36:9 run 1 14:9 1

runs 23:1633:13 | RUTHERFORD ! 2:14

S

safe 12:25

sample 25:17 26:4,6 30:7 sampled 26:5 29:22 samples 20:1229:15,16 sampling 20:1125:3 sand 27:3 sands 27:11 i Sapp 1:3 3:3,8,18 6:25

9:11 42:23 saturated

12:3,5 saw 44:1,20 i saying ;

i

REPORTED BY: Stephanie R. Zeitvogel www.huseby.com HUSEBY, INC. - 555 North Point Center, E., #403, Alpharetta, GA 30022 (404) 875-0400

Page 24: TRANSCRIPT - PROPOSED PLAN PUBLIC MEETING FOR THE … · 2 I'm L'Tonya Spencer. I'm the Community Involvement 3 Coordinator for the Sapp Battery site. I'm with 4 the Environmental

U.S. Environmental Protection Agency Public Meeting September 7, 2011

Page 56

29:13 screen 26:23 27:10 screened 29:25 40:13 second 34:19 35:2 secondary 35:25 36:3 sediment 14:1,4 34:6 42:13

sediments 8:17 10:3,11 11:5

11:10,20 12:22 13:10,18,1941:22

see 10:19 14:15 16:24

19:2,23 23:6 24:9 25:25 26:22 27:7 27:8 44:2 45:1

seeing 19:7

seen 20:17 select 6:6 selection 6:3 send 7:9 13:24 sense 13:14,17,24 17:9

September 1:8 9:15 10:7 41:1 46:13

series 21:24 serious 20:20 seriously 38:7 set 34:10 35:4,15

40:20

sets 33:23 seventies 7:1 41:12,16 shifted 11:14

shipped 12:22

show 10:22 15:2 16:16 21:1233:7,16

showed 24:6 shows 23:1 24:16 28:21

37:13 shrink 19:8

shrinking 19:2

shut 8:19 sic 20:14 side 17:2 24:13

sidewalk 32:17 silts 27:11,11 30:3 similar 31:24 simplest 11:8

sink 36:5 sinkhole 30:2,21 sinkholes 27:1,2 29:1 site 1:3 3:3,6,8,18,19 3:204:3,6,10,10 4:17 5:3,6,7,8,18

6:25,25 7:1,3,4,13 7:21,22,24 8:6,25 9:6,24 10:2 13:16 14:3 15:14 16:16 16:19 17:1821:9 21:11 22:1 2>3:23 25:10 26:11,25 27:1,1 28:14,18 29:13 33:18 34:13 35:5 38:3 42:2,3 44:9,11,13,17,24

site-specific 35:19 situ 38:8 SL\

43:17 size 19:4

slams 8:19 slide 8:21 21:15 24:16

28:21 29:5 slow 27:20 slower 27:15 31:9 slowly 28:2 small 4:21,24 9:20 19:24 smaller 18:5

soil 5:10,15,19 8:10,17

8:20 9:2,6 11:16 11:22 12:3,5,9,12 13:8 14:4 15:12 16:11 19:1633:9 34:4

soils 7:13 8:22,23 9:4

11:4 15:11 34:2

solidified 33:11 solidifying 13:13

somebody 32:3 somewhat 4:10 sorry 5:11 11:2 25:23

35:1,2,13 sound 15:25

sounds 15:21

source 11:24 15:10 17:6

19:10,11,15,16,17 21:2,25 29:18 34:3

sources 35:10 south 17:2 23:22 24:2 41:9,11

southern 17:3 SPALVINS 2:23:155:13 11:6

11:15,18 12:19,21 15:21,2521:8,11 21:18,23 22:22,24 23:1 24:22,24 25:1626:18,21 31:17 32:2,23 36:11 41:7 43:5 43:11,1544:5 45:6

spalvins.enk@ep... 2:4 special 20:10 specific 22:8

specifically 9:23 speculate 13:5

Spencer 2:63:1,2 11:1

12:15 24:23 26:20 • 45:4

spencer.latonya... 2:8 spent 7:20 spilled 7:23 spinning 32:16 Spring 43:24 stabilize 9:2 j stable \ 13:21

stage 4:4 6:17 stages 16:17 stamp 24:24 standard 17:1625:2430:19 | 30:24 33:23 35:14 36:1,2,21

standards 34:16 35:25 36:3

36:16,22 standpoint 12:24 28:11

stands ! 9:8 26:7 start 4:14 13:20 started 9:14 14:14,16,19

15:1,23,23 19:2,7

•J

: — '.y.^. ' i

REPORTED BY: Stephanie R. Zeitvogel www.huseby.com HUSEBY, INC. - 555 North Point Center, E., #403, Alpharetta, GA 30022 (404) 875-0400

Page 25: TRANSCRIPT - PROPOSED PLAN PUBLIC MEETING FOR THE … · 2 I'm L'Tonya Spencer. I'm the Community Involvement 3 Coordinator for the Sapp Battery site. I'm with 4 the Environmental

U.S. Environmental Protection Agency Public Meeting September?, 2011

Page 5?

26:2 starting 18:15 19:8

state 1:134:8,96:11

7:20 11:1 12:15 35:10 36:8,9,13 36:18 42:21 46:3

State's 8:9 10:5 State-funded 43:2 status 4:18 Steele 17:3 41:9,10,11

Stephanie 1:1246:7,17

storm 44:12 story 42:19 street 1:102:10 17:2

studies 5:22 41:2142:1,4

43:20,20 stuff 11:25 25:11 27:4

38:16 42:23,24 successful 27:21 sulfuric 7:6,11,14 sum 29:12 Superfund 1:2,3 2:9,9 3:18,19

5:1,4,7 9:16,19,24 33:22

supervised 8:8 sure 3:12,15 19:14

20:11 21:8 29:14 38:19

surface 14:11 20:24 23:17

28:23 37:7 41:5,8 41:16

surficial 17:19 18:4 19:1,20 33:6,10,14,16

SW 2:10 swamp 7;]6,17,18 10:10

10:14,15,17,19,21 16:7,10,10,11,19 16:20,24 17:1,3 23:19,21,21,22,24 41:8

swamps 5:16 10:11 13:11

14:127:2 swung 16:23

system 14:10,1734:18

T

table 12:2 36:13 39:17

take 3:7 7:8 16:3 20:19

28:17,20 31:5 40:16,17,17

taken 15:15 19:921:3

talk 11:8 17:9 26:14

29:8 talked 8:15 17:6 29:6 talking 6:15 24:25 tall 23:9

target 12:9

taste 36:4 tell 32:5 39:5 ten 39:1240:17 tend 20:5 term 9:7 31:19,20 36:17 terms 20:17 28:3 32:3

39:13 test 25:7 tested 12:8

thank 24:22 26:17 45:4,6 Thanks 3:15 thing 26:25 28:11,12

32:12 44:14 things 23:12 30:3,3 37:12 think 11:20 13:11 15:5

15:16 16:22 20:15 99-22 "^5-25 33-1 41:1 42:3,14,23 44:19,22,23 45:2

third 38:17 39:1 thought 29:17,18 44:3 thousand 13:11

thousands 29:2 three 5:1735:18 37:21

tight 39:25 time 1:9 3:7 6:23 7:20

15:7 17:8 30:25 31:5,5,8,11,13 36:6 41:2

times 7:15 today 4:18 6:2,9,15 10:17

15:4 16:1921:1 39:13 45:1

told 30:16 top 8:25 17:20 32:7

33:13 total 21:1039:4 track 24:11,1438:23 tradeoffs 40:20 transcriber 3:9 transcript 46:9 transcription 3:13 transfer 40-14 t rpa t 1 1 W*l !•

14:8,17,22 15:4 20:23 37:4

treated 37:5 treating 13:13

treatment 13:17 14:9 38:8

39:14 tremendously 15:1

trend 31:7,10 trickle 27:20 44:10 tried 17:8 26:11

true 46:10 try 27:20 trying 3:20 7:22 13:21

25:11 32:1741:4 41:18

turbid 30:6

turbidities 31:1 turbidity ; 25:9,10,13,17,20 !

26:329:1540:11 \ turn \ 36:5 two 6:3 10:9 11:12

20:12,13 23:12 30:3,16,20 40:10

type 28:16 \ typical (• 32:14

U

U 26:7 Uh-huh 25:15 j

um 31:16 Underneath 28:24 underwent 10:2

undetected

REPORTED BY: Stephanie R. Zeitvogel www.huseby.com HUSEBY, INC. - 555 North Point Center, E., #403, Alpharetta, GA 30022 (404) 875-0400

Page 26: TRANSCRIPT - PROPOSED PLAN PUBLIC MEETING FOR THE … · 2 I'm L'Tonya Spencer. I'm the Community Involvement 3 Coordinator for the Sapp Battery site. I'm with 4 the Environmental

U.S. Environmental Protection Agency Public Meeting September?, 2011

Page 58

26:8 unit 1:4 13:22

upgradient 42:6 upstream 42-6 use 6:4 22:1432:3

33:19,24 34:1 35:12 37:4

users 38:4 uses 6:12 31:20 IJ S 1:1 2:8

V vanadium 25:9 31:7 35:7 36:8

36:12,22 40:14 verified 30:12

W

walked 38:2 want 3:145:1 16:2 34:11 wanted 4:1222:11 waste 7:11 13:4 39:20 water 10:22 11:9,13,17

12:7,10 14:11 17:16,24 20:22 23:16,17 25:17,23 27:14,22,25 28:7 30:5,5,6,19,23 31:20,25 32:3,4,6 32:1933:12,16 34:16,18 35:13,21 35:24,25 36:1,3,7

37:6,741:5,8,14 41:15,16

watershed 42:4 way 4:25 11:8,11 12:25

13-14 14-21 17-9 k •_/ • 1 r 1 r 1 ^ ^ I L 1 t . ^

20:10,15 23:13,22 40:12,22

ways 39:8 44:7 weather 35:3 website 32:25 43:6,8

wf^lrniTip TT ^ l \ . ^ f I I I ^

3:7 wells 1415 18-19 20-13 21:21,23,24 22:2 22:4,4,6,14,20 24:5,9,13 25:2,4,5 27:5 29:8,19,21 29:22,22,24 30:13 33:15 40:7,10,16

went 12:8 13:3,4 18:11 29:21

wet 11:7 12:10,11

wetlands 34:6 we'll 16:1526:1432:9

we're 4:4,16,19 6:13,14

6:15,18 16:1 18:7 24:25 26:22 28:18 30:9

we've 4:20 5:18 16:15 widespread 7:12 winner

39:16 wonder 44:3 work 16:15

worked 12-12 29-13 41'3

working 9:5 14:14 wouldn't 27:21,22 38:5,5 Wow 22:25 wrong 30:9

Y yards 13:12

yeah 15:25 22:14 24:21 31:1843:13,15 44:5

year 16:22

years 9:13 14:24 18:18

20:18 29:2,4 39:1340:17,17,18

you-all 45:6

Z Zeitvogel 1:12 46:7,17

zero 19:20,21

zone 27:10 32:2 33:5 zones 27:18

$

$319,000 39:11

$890,000 39:15

0 04 25:4,4 05 25:4,4,5 06 25:5 08 25:4,4,5

1 -•

1 36:13 46:9 10 17:20 18:11 19:1 23:10

10-acre

17:24 14 19:3 14-acre 17:22 15 25:24 30:24 35:16

39:13 1? 30:23 18 18:7 30:22 19th 46:13 1980 7:2 1980s 18:22 1983 17:14,15,19 1984 15:20 1985 18:3,10 23:2 24:5 1986

8:15 14:6,7 15:3 18:13 20:19

1988 18:25 1999 9:16

2

2 1:4

20 17:20 19:6 40:17

20-acre 17:21

2001 9:15 19:12 2004 14:15,1629:13

38:10 2005 10:6 19:1925:21

2008 10:7 26:5

2009 10:9 :

2011 1 1:8 20:9 46:13 •

25th 41:1 2666 j 1:10 ;

3 30 6:1040:18 30303 2:10 310 25:21 32431 1:11

35 18:11,11 24:9 25:20

REPORTED BY: Stephanie R. Zeitvogel www.huseby.com HUSEBY, INC. - 555 North Point Center, E., #403, Alpharetta, GA 30022 (404) 875-0400

Page 27: TRANSCRIPT - PROPOSED PLAN PUBLIC MEETING FOR THE … · 2 I'm L'Tonya Spencer. I'm the Community Involvement 3 Coordinator for the Sapp Battery site. I'm with 4 the Environmental

U.S. Environmental Protection Agency Public Meeting September 7,2011

Page 59

4 4 2:8 3:4 26:8 45 21:12 24:4 45-acre 7:1 46 46:10

5 5 23:10

6 6:06 1:9

60 22:23,24 61 2:10 62-777.170 36:13

? 7 1:8

7:06 1:9

8 8L 26:14,24 27:6,9,9 800)435-9233 2:11 85 15:20

86 26:12 88 19:2

:

1

:

'

REPORTED BY: Stephanie R. Zeitvogel www.huseby.com HUSEBY, INC. - 555 North Point Center, E., #403, Alpharetta, GA 30022 (404) 875-0400