TR Reinert Ritz Turkey Project
-
Upload
thanos-tsirkos -
Category
Documents
-
view
213 -
download
0
Transcript of TR Reinert Ritz Turkey Project
-
8/20/2019 TR Reinert Ritz Turkey Project
1/3
-
8/20/2019 TR Reinert Ritz Turkey Project
2/343 SPECIAL 01 | 2014
TECHNICAL REPORT JOINING TECHNOLOGY
Figure 2: Left: completed stub end at Reinert-Ritz right: stub end, complete with steel encapsulation, pipe extension and bracing
months. Three extrusion machines have been operating in
parallel in this purpose-built facility. This system not only achie-
ves cost benefits, but also for many projects, it provides an
assurance factor both desirable and in many cases mandatory.The pipe length results from the fact that PE pipes, due to
their specific gravity of less than 1 g/cm3, would normally
float on the surface of the water. This fact, in combination
with the lower relative density of freshwater compared to
seawater, causes enormous positive buoyancy forces. These
are counteracted by the pipe joining yokes, each consisting of
two flanged connectors and a steel pipe bend to which the
flanged connector is fixed. The steel yokes have an outside
diameter of 1,514 mm, a curvature radius of 8,000 mm with a
bend angle of 30°, and weigh around 10 tonnes without the
connecting elements. Total weight including the two connec-
ting elements is around 13 tonnes. The steels yokes, which alsoact as fixing and anchoring points, are subsequently drawn
down to a depth of 250 m by means of steel cables and then
anchored to the seabed (Figure 1), illustrating even better the
special features of this project.
The specially made flange connectors are welded on to the
long PE pipes on site and bolted to the steel pipe yokes by
means of a steel flange provided specifically for this purpose.
This yoke is then anchored to the seabed by means of steel
Figure 3: Pipe sections waiting for transport
-
8/20/2019 TR Reinert Ritz Turkey Project
3/3 SPECIAL 01 | 2014 44
JOINING TECHNOLOGY TECHNICAL REPORT
cables to the securing and anchoring point. The challenge
for Reinert-Ritz was that of providing a product to join the
PE pipes and steel yokes durably and securely such order that
even the most adverse conditions encountered underwater
in the Mediterranean could not impair the connection. At a
depth of around 250 m, this design involves the following
technical challenges: buoyancy forces exerted by the PE 100
pipeline; powerful and dynamic sea currents, high shipping
(and submarine) traffic frequency, potential of earthquakes,
and the 7 bar operating pressure.
Decision for high quality and safety
The Nordhorn company is the specialist for semi-finished
products and full pressure rated fittings conforming to the
specified pressure classification for large dimensions up to an
outside diameter of d 2000 mm; hence the right address for
solutions to demanding problems. With over forty years ofexperience in plastics and the company’s pronounced qua-
lity awareness, the definitive arguments are established for
initiating the co-operation between the project planner and
Reinert-Ritz. From the high-quality granulate, used for produc-
tion of the semi-finished products, through to the machining
of the finished stub ends, the company was able, with its
all- encompassing Quality Assurance system, to guarantee
the high production standards vital for the performance and
completion of this demanding project. This high quality con-
sciousness has been shaped, in particular, by work for the gas
industry in Germany, one of the first customers for PE, which
makes use of this material and its high flexural strength in areassubject to mining subsidence. Only then did the safety and
cost benefits result - within just fifty years - in PE‘s leadership
on the supply-systems market.
It is therefore not surprising that ever more positive experience
is being accumulated, with the application of PE pressure-pipe
systems in large-scale industrial fire-extinguishing installations
and power-generation plants, including the nuclear-energy
industry.
There are two production routes for these full pressure- rated
fittings: injection moulding and machining. The hollow bars
and solid rods made by Reinert-Ritz are used in the latter
process. This method assures a product free of voids and
incorporating more than forty years of design and processingexperience.
Solution of the complex flange concept
Production of hollow bars of 1,900/1,400 mm, with a wall
thickness of approx. 250 mm, is the first stage in the fabri-
cation of the special flanged connection. Subsequent machi-
ning takes place on a milling machine capable of processing
material up to sizes of 2,800 x 1,500 x 4,800 mm. A particular
challenge was presented by the large dimensions of the PE
pipeline fitting and the extremely high dimensional accuracy
demanded; tolerances of 0.0 mm and +0.5 mm. On site in
Turkey, the finished PE 100 stub end is enclosed geometri-cally secured in two steel clamping assemblies, into which it
must fit perfectly. The high-precision flanged connectors are
assembled on a special installation ship, with twenty-four
connecting bolts, on both ends of the steel yoke. The yoke is
then anchored to the seabed, to enable the pressure pipeline
to „float“ at an average depth of 250 m.
ConclusionThe precondition for the success of this project was the suc-
cessful evolution for the ultra-demanding innovative flange
design of a PE 100 fitting which would durably join steel and
PE 100. The extreme dynamic loads to which the flanged
connection is exposed in underwater service were, above all,
taken into account in development. Excel- lent communica-
tions and co-operation between Reinert-Ritz and the project
planners achieved successful in-company installation and have
generated an extremely high level of confidence for the long-
term tightness and safety of the flanged connection.
CONTACT: REINERT-RITZ GmbH, Nordhorn, GermanyTel. +49 5921 83470, E-Mail: [email protected]
www.reinert-ritz.com
B6, 143
Figure 4: A 500 m pipe section in Turkey connecting bolts, on both
ends of the steel yoke. The yoke is then anchored to the seabed, to
enable the pressure pipeline to „float“ at an average depth of 250 m