THRISSUR RAILWAY STATION DEVELOPMENT
NAISON P SUNNY ROLL NO 12
INTRODUCTION• Thrissur Railway Station – commenced on June
2, 1902 • A-1 category railway station located in Thrissur
City.• It lies on the busy Shoranur – Cochin Harbour
section.• Also connects to the temple town of Guruvayur.• 65 pairs of trains passes through the station on
an average day. • Have a traffic of 20,000 passengers per day.
NEED ANALYSIS • Growth of passenger traffic.• New trains are coming – Budget 2013.• Ernakulam - Thrissur MEMU will start running.• 3rd and 4th rails have been started using.• Passengers have to cross the rail to reach 4th
platform.• Passengers have to walk a lot of distance to get
bus towards North stand or Sakthan stand.
SUMMARY• Development of Thrissur railway station.• To supply necessary facilities for the comfort of
increasing passengers.• To provide platform facilities for increasing
number of trains and passengers.
OBJECTIVES• Development of 4th platform
▫ Shops and Benches▫ Flooring▫ Structure▫ Roofing▫ Lighting▫ Drinking Water Supply▫ Cctv cameras▫ Announcement System
• Foot over bridge• Bus service
First and Second platform, of Thrissur Railway Station
Fourth Platform
TECHNICAL FEASIBILITY
• Foot over bridge from fourth platform can be connected to the existing bridge.
• Buses doesn’t have a much difference in their travel distance and time.
SOCICAL FEASIBILITY• No need of acquiring land.
• Useful for People
FINANCIAL FEASIBILTY• Source of income – Palghat Railway division• Secondary source - Budget
BUDGET AND DURATION• Estimated Cost = 2 Crore• Estimated Time = 10 Months
5%
75%
15%
5%
Work Cost(Lakhs)
Design 10
Bus service system 10
Shops and Benches 10
Flooring Works 30
Plumbing Works for water supply 10
Foot Over bridge Construction 30
Roofing Works, Structure 80
Lighting, Announcement sys,CCtv 20
Total 200
Activity Work Time in months
A Design of Overall Plan 2
B Approval 1
C Tender 2
D Bus service system 2
E Shops and Benches 2
F Flooring Works 2
G Plumbing Works for water supply 2
H Foot Over bridge Construction 2
I Roofing Works, Structure 4
J Lighting, Announcement sys,CCtv 1
MASTER SCHEDULE
GANTT CHART
0 1 2 3 4 5 6 7 8 9 10
TIME IN MONTHS
WORK PACKAGES
Approval (B)
Plumbing Works(G)
Structure, Roofing Works(I)
Lighting, CCtv(J)
Bus service (D)
Design of Overall Plan (A)
Over bridge (H)
Tender (C)
Shops and Benches(E)
Flooring Works(F)
WORK BREAK DOWN STRUCTURE
Development Project
Over bridgeConstruction
Bus Service
Shops and Benches
ProjectDevelopment
Platform Construction
Data collection Waiting Shed
Flooring,Plumbing
Structure,Roofing
Lighting, Cctv, Announcement sys.
Analysis
Feasibility study
Structure
Roof
Approval
Sanction
Tender
General Manager(Southern Railway)
Electrical engineer
Civil engineer
Finance officerSupervisor
Chief Administrative Officer
Project Committee
Administrative manager
Office staff
Assistants
supervisor
WorkersOffice staffWorkers
Ex. Engineer
PROJECT ORGANISATION STRUCTURE
Project Manager
ADVANTAGES• A new development for the station.• Improves comfort of passengers.• Improves safety of passengers.
CONCLUSION• Simple• Executable