THEMIS Mission CDR Instrument I&T 1 UCB, June 14 - 18, 2004
Instrument Integration and Test
Rick Sterling / Sharon Jelinsky
University of California – Berkeley
Thm_CDR_IT_Revc
THEMIS Mission CDR Instrument I&T 2 UCB, June 14 - 18, 2004
Overview
Overview / Topics I&T Sequence
Facilities
Integration Platform
Instrument Requirements
Integration/Test Flow
Schedule Milestones
Transportation
THEMIS Mission CDR Instrument I&T 3 UCB, June 14 - 18, 2004
Sequence
LevelLevel LocationLocation StatusStatus
Instruments (ESA, SST, EFI, FGM, SCM, IDPU, BOOMS)
SSL, Europe
ETU Versions In Progress
Instrument Suite SSL ETU begins August
Instruments with Probe Swales,GSFC
First Probe begins February 2005
Probes with PCA Swales, GSFC
Begins December 2005
PCA with rocket KSC Begins August 2006
THEMIS Mission CDR Instrument I&T 4 UCB, June 14 - 18, 2004
Thermal Chambers• Space Sciences Lab • New Chamber for EFI Booms• Cal Chamber Upgrade for SST
Test Chamber Requirements• Pre-Test Clean• Pre-Test Bakeout• TQCM Monitoring• Cryo-Pump• Final Bakeout• GN2 Backfill
Calibration Chambers• Vacuum only• Ion Gun• Manipulator
Facilities - Environmental
Available Chambers Type HiBay L1 TV AXB Booms HiBay L2 TV STEREO320 T10 TV STEREO320 Cal Vac ESA Cal320 “Mini” TV SCM, Bake-outsB20-TV “Bayside” TV EFIB20-Large TV TV Payload TV B20-Cal VAC2 Vac SST Cal B20-TV “Snout” TV
Comment
339-TV CalSST, IDPU, EFI ESA MCPs
Vibration Facilities
• Wyle
• AMES
EMI/EMC
• EMCE Engineering – Fremont
THEMIS Mission CDR Instrument I&T 5 UCB, June 14 - 18, 2004
Room B20
3 T/V Test Chambers: Bayside, Snout, Bertha
High Vacuum Base Pressures of 1x10e-6 torr or better
Thermal Systems with LN2 cooling and IR heating
Thermal Controllers: Watlow hardware & Anawin Software
Test Chambers Certified prior to instrument testing
–Verify Outgassing levels less than 1% TML and 0.1% CVCM
–RGA measures of residual gasses to less than 1x10e-7 PP
–TQCM to measure condensable materials deposition rates
B20 T/V CHAMBERS
THEMIS Mission CDR Instrument I&T 6 UCB, June 14 - 18, 2004
Bertha - Large Thermal Vacuum Test Chamber• Dimensions: 9 ft. Diameter x 16 ft. Long• Accommodates 2 THEMIS Instrument Suites at once• Temperature cycles of -80C to +80C • Base Pressure of less than 1 x 10e-6 torr• Tests full ETU and 5 Flight Instruments
Chamber ‘Bertha’
THEMIS Mission CDR Instrument I&T 7 UCB, June 14 - 18, 2004
THEMIS Snout
•Dimensions: 3 ft. Diameter x 3 ft. Long
•Accommodate EFI Axial Boom
•Temperature cycles of -100C to +110C
•Base Pressure of less than 1 x 10e-6 torr
•Tests IDPU, AXB T/V, and Boom Deployment
Chamber ‘Themis Snout’
THEMIS Mission CDR Instrument I&T 8 UCB, June 14 - 18, 2004
Bayside
• 3 ft. Diam x 3 ft. Length
• Fits 2 Instruments
• Temp Range: –100 to +110C
• Base Pressure: <1 x 10e-6 torr
Chamber ‘Bayside’
THEMIS Mission CDR Instrument I&T 9 UCB, June 14 - 18, 2004
Thermal TestingTV Plan • 2 Component-Level TV Cycles Prior to Instrument-Level I&T• 6 Instrument Level TV Cycles at Instrument-Level• Survival, Cold Start, Cycles (Functional at extremes), Bake-out
Deployments in Vacuum• SPB: Full Deploy w Takeup reel• AXB: Deploy Hot & Cold• MAG: First Motion Hot & Cold
Typical TV Profile:Instrument
Profile (6cy)
-60
-40
-20
0
20
40
60
80
0 12 24 36 48 60 72 84 96 108
Hours
Temp
CPT
CPT
LPT LPT LPT LPT LPT
LPT LPTLPTLPT LPT
BAKEOUT
THEMIS Mission CDR Instrument I&T 10 UCB, June 14 - 18, 2004
Bertha Vacuum Chamber in full working order
Thermal System designed; Baseplate and Shroud in production
Thermal Controller off the shelf & on order
Snout Vacuum Chamber manufacture complete and under test
Thermal System designed; Baseplate and Shroud in production
Thermal Controller off the shelf & on order
Bayside Vacuum Chamber in full working order
Thermal System designed and built
Thermal Baseplate and Shroud under installation and test
Status of Chamber Upgrades
THEMIS Mission CDR Instrument I&T 11 UCB, June 14 - 18, 2004
Clean Room Features
Requirement: 100K Class
Nitrogen Gas purge available
Continuous Oxygen Monitoring
Temperature and Humidity Monitoring
Weekly Air Quality sampling
Controlled Access
Crane Certification
Staff Training
Clean Rooms SSL
THEMIS Mission CDR Instrument I&T 12 UCB, June 14 - 18, 2004
Clean Room B20
THEMIS Mission CDR Instrument I&T 13 UCB, June 14 - 18, 2004
Clean Room 125
THEMIS Mission CDR Instrument I&T 14 UCB, June 14 - 18, 2004
Integration Platform
Instrument Suite on Platform Platform is same size as s/c deck Framing supports platform to set comfortable work height Metal rack alongside holds GSE and support equipment GSE communicates with BAU Simulator via hardwire or ethernet
INSTRUMENT PAYLOAD ASSEMBLY PLATE
THEMIS Mission CDR Instrument I&T 15 UCB, June 14 - 18, 2004
Parallel Integration and Test of S/C Platforms
Parallel Integration/Test
THEMIS Mission CDR Instrument I&T 16 UCB, June 14 - 18, 2004
Instrument Cleanliness/Contamination Requirements• ESA and SST require continual nitrogen gas purge• Oxygen meter following instruments and gas purge equipment• Normal ESD concerns• Magnetometer sensors to be boxed except when under test and before flight
Instrument-Provided GSE Accommodation• Mu-Metal Enclosures for FGM & SCM• N2 Purge Systems for ESA, SST• Sphere Sensor Boxes for EFI
Instrument Red/Green Tag Items Tracking• IDPU - Arming plug enables actuators causing boom deployment• EFI - Electrical: 4 SPB Test/enable plugs plus one AXB test/enable plug• EFI - Mechanical: 4 SPB Snout Covers plus 2 AXB Tube Covers• SST - Covers to be removed before flight• ESA - Cover; Arming plug; purge fitting;cocking pin nut
Instrument Requirements
THEMIS Mission CDR Instrument I&T 17 UCB, June 14 - 18, 2004
Instrument Payload I&T Flow
FGMFunctional(Level 2)
SCMFunctional(Level 2)
SSTFunctional(Level 2)
HarnessBake-out
IDPU-HarnessSafe-to-Mate
PayloadEMC/EMI/MAGl
PayloadT-V
ESAFunctional(Level 2)
• Test Review
InstrumentPER
MAG INTEGRATION
EFI INTEGRATION
ESA/SST INTEGRATION
PAYLOAD ENVIRONMENTALPayloadPayloadVibrationVibration
PayloadAcceptance
• ONLY if req’d (workmanship)
MagAlignment
EFI AXBDeploy
EFI SPBDeploy
Mag BoomDeploy
EFIFunctional(Level 1)
EFIFunctional(Level 2)
EFI/SCM/FGMPhasing
ESA/SSTTiming
PayloadCPT
THEMIS Mission CDR Instrument I&T 18 UCB, June 14 - 18, 2004
FGM I&T Flow
FGSVibration
FGSThermal
IDPUSafe-to-Mate
IDPU/ESA/SCM Pre-Amp
Vibration
FGSAcceptance
FGMFunctional(Level 2)
• Inspection• Mass Properties• DC Magnetics
• 2 cycles T-V• Bake-out +60C
• Sensor in TCU
FGEAcceptance
FGMFunctional(Level 0)
• Without FGS• Inspection
IDPUThermal
• 2 cycles T-V• Bake-out +60C• FGS Functional (Level 1)
FGBVibration
FGB/SCBThermal
• 1 cycle T-V• Hot/Cold Deploy
FGBAcceptance
• Inspection• Mass Properties• DC Magnetics
• Backplane
Alignment EFI/SCM/FGM
Phasing Mag Boom
Deploy Payload
Safe-to-Mate
• Harness
PayloadEMI/EMC/MAGl
PayloadT-V
• 6 cycles T-V• FGM Functional Lev1)
IDPUAcceptance
• Inspection• Mass Properties• DC Magnetics
• Test Review
• Boom Levels
InstrumentPER
FGM BOOM (FGB)
FGM SENSOR (FGS)
FGM ELECTRONICS (FGE)
FGM / PAYLOAD INTEGRATION
PAYLOAD ENVIRONMENTALPayloadVibration
PayloadAcceptance
• ONLY if req’d (workmanship)
THEMIS Mission CDR Instrument I&T 19 UCB, June 14 - 18, 2004
FGM Level 0 – Without Sensor (Aliveness)• B-field about zero if FGM in Cal Mode (preferred mode)
• B-field saturated if feedback is closed
• Interface full functional
• Power consumption reduced by about 200mW
FGM Level 1 – Sensor in Mu-metal cap (Limited Performance Test)• B-field about 10,000nT, Noise about 1nT
• Full functionality,
but B-field not representative
FGM Level 2 – Sensor in TCU (Comprehensive Performance Test) • B-field < 10nT, Noise <10pT/sqrt (Hz)
• B-field has to be available in full quality
• Delta in calibration coefficients known
FGM Test Configurations
THEMIS Mission CDR Instrument I&T 20 UCB, June 14 - 18, 2004
SCM I&T Flow
SCM SensorVibration
SCM SensorThermal
SCM Pre-AmpBake-out
IDPU/ESA/SCM Pre-Amp
Vibration
SCM SensorBake-out
Functional(Level 3)
• Bake-out +60C• 3 cycles (air)
• SCM Sensor in Mu Metal
SCM Pre-AmpThermal
SCM Pre-AmpAcceptance
IDPUThermal
• 2 cycles T-V• Bake-out +60C• SCM Functional (Level 1)
SCBVibration
• 14.1g RMS
FGB/SCBThermal
• 1 cycle T-V• Hot/Cold Deploy
SCBAcceptance
• Inspection• Mass Properties• DC Magnetics
• Bake-out +60C
Alignment EFI/SCM/FGM
Phasing Mag Boom
Deploy Payload
Safe-to-Mate
• Harness
PayloadEMI/EMC/MAGl
PayloadTV
• 6 cycles T-V• SCM Functional (Lev 2)
IDPUAcceptance
• Inspection• Mass Properties• DC Magnetics
• Test Review
• Boom Levels
InstrumentPER
SCM BOOM (SCB)
SCM SENSOR (SCM)
SCM PRE-AMP
SCM / PAYLOAD INTEGRATION
PAYLOAD ENVIRONMENTALPayloadVibration
PayloadAcceptance
• ONLY if req’d (workmanship)
SCM SensorAcceptance
• Inspection• Mass Properties• DC Magnetics
• 3 cycles (air) • Inspection• Mass Properties• DC Magnetics
THEMIS Mission CDR Instrument I&T 21 UCB, June 14 - 18, 2004
SCM Test Configurations
SCM Safety – Feedback Plug• Required when SCM Pre-Amp is powered and sensor is not connected
SCM Level 0 – With SCM EGSE I/F Box (Aliveness)• Same Power, Command, Analog output interfaces
• Power and Cal Mode identification by LED
• Cal Signal re-injected to the input
• Signal generator connected to input
• Validation by analysis of data
SCM Level 1, 2 – Sensor in Mu Metal Box (Comprehensive Performance Test) • Sensor kept in mu metal box during integration
• Axis identification
• Re-verification of end-to-end calibration
• Phase relation
• Check of conducted noise
• SCM/EField timing reference
THEMIS Mission CDR Instrument I&T 22 UCB, June 14 - 18, 2004
ESA I&T Flow
ESAFunctional(Level 2)
• Instrument Functional• Cover Simulator Test
ESAThermal
ESAAcceptance
• Inspection• Mass Properties• DC Magnetics
ESA/SSTTiming
PayloadSafe-to-Mate
• Harness
PayloadEMI/EMC/MAG
PayloadT-V
• 6 cycles T-V• ESA Functional (Lev 1)
• Test Review
InstrumentPER
ESA SENSOR
ESA ELECTRONICS (ETC)
ESA / PAYLOAD INTEGRATION
PAYLOAD ENVIRONMENTAL PayloadVibration
PayloadAcceptance
• ONLY if req’d (workmanship)
• 2 cycles T-V• Bake-out +60C
IDPUSafe-to-Mate
IDPU/ESA/SCM Pre-Amp
Vibration
ESAFunctional(Level 0)
IDPUThermal
• 2 cycles T-V• Bake-out +60C
• Backplane
IDPUAcceptance
• Inspection• Mass Properties• DC Magnetics
ETCAcceptance
• Inspection
THEMIS Mission CDR Instrument I&T 23 UCB, June 14 - 18, 2004
SST I&T Flow
SSTFunctional(Level 2)
• SST w/ Radiation Source• Attenuator Test
SST Vibration
SSTThermal
SSTAcceptance
• Inspection• Mass Properties• DC Magnetics
ESA/SSTTiming
PayloadSafe-to-Mate
• Harness
PayloadEMI/EMC/MAGl
PayloadT-V
• 6 cycles T-V• SST Functional (Level 1)
• Test Review
InstrumentPER
SST SENSOR
SST ELECTRONICS(DAP and ETC)
SST / PAYLOAD INTEGRATION
PAYLOAD ENVIRONMENTAL PayloadVibration
PayloadAcceptance
• ONLY if req’d (workmanship)
• 2 cycles T-V• Bake-out +60C
IDPUSafe-to-Mate
IDPU/ESA/SCM Pre-Amp
Vibration
DAPAcceptance
SSTFunctional(Level 0)
• Without SST
• InspectionIDPU
Thermal
• 2 cycles T-V• Bake-out +60C
• Backplane
IDPUAcceptance
• Inspection• Mass Properties• DC Magnetics
ETCAcceptance
• Inspection
THEMIS Mission CDR Instrument I&T 24 UCB, June 14 - 18, 2004
EFI I&T Flow
EFI Pre-AmpBake-out
EFI AXBDeploy
• Sensor in Mu Metal
EFI Pre-AmpThermal
EFI Pre-AmpAcceptance
AXBVibration
AXBThermal
• 1 cycle T-V• Hot/Cold Deploy
AXBAcceptance
• Inspection• Mass Properties• DC Magnetics
• Bake-out +60C
EFI Functional(Level 2)
EFI/SCM/FGMPhasing
EFI SPBDeploy
PayloadSafe-to-Mate
• Harness
PayloadEMI/EMC/MAGl
PayloadT-V
• 6 cycles T-V• EFI Functional (Lev 1)
• Test Review
InstrumentPER
EFI AXIAL BOOM (AXB)
EFI RADIAL BOOM (SPB)
EFI PRE-AMP
EFI / PAYLOAD INTEGRATION
PAYLOAD ENVIRONMENTAL PayloadVibration
PayloadAcceptance
• ONLY if req’d (workmanship)
• 3 cycles (air) • Inspection• Mass Properties• DC Magnetics
EFI ELECTRONICS(BEB and DFB)
SPBVibration
SPBThermal
• 1 cycle T-V• Hot/Cold Deploy
SPBAcceptance
• Inspection• Mass Properties• DC Magnetics
EFI Pre-AmpVibration
IDPUSafe-to-Mate
IDPU/ESA/SCM Pre-Amp
Vibration
BEBAcceptance EFI
Functional(Level 0)
• Without sensors
• Inspection
IDPUThermal
• 2 cycles T-V• Bake-out +60C
• Backplane
IDPUAcceptance
• Inspection• Mass Properties• DC Magnetics
DFBAcceptance
• Inspection
THEMIS Mission CDR Instrument I&T 25 UCB, June 14 - 18, 2004
ETU Instruments Suite Level T/V 9/2/2004
P1 Instruments Suite Level T/V 12/29/2004Delivery to Swales 2/11/2005
P2 Instruments Suite Level T/V 2/9/2005Delivery to Swales 4/7/2005
P3 Instruments Suite Level T/V 2/25/2005Delivery to Swales 5/5/2005
P4 Instruments Suite Level T/V 4/1/2005Delivery to Swales 6/7/2005
P5 Instruments Suite Level T/V 4/14/2005Delivery to Swales 6/14/2005
Upcoming Integration/Test Milestones
Upcoming Milestones
THEMIS Mission CDR Instrument I&T 26 UCB, June 14 - 18, 2004
Transportation
Transportation and Logistics Air Transport of Instrument Suites from Berkeley to Swales
Fed Ex Critical/Specialty Freight Overnight
Point to Point, Highest Security
Transport Berkeley’s spacecraft platform to Swales also
Post-Transport Acceptance Test at Swales