The Use of Dynamic Simulation Techniques in Gas Lift ... - … · The Use of Dynamic Simulation...
Transcript of The Use of Dynamic Simulation Techniques in Gas Lift ... - … · The Use of Dynamic Simulation...
1
Gas Lift WorkshopGas Lift WorkshopDoha Doha –– QatarQatar
44--8 February 20078 February 2007
The Use of Dynamic SimulationThe Use of Dynamic SimulationTechniques in Gas Lift OptimisationTechniques in Gas Lift Optimisation
by Juan Carlos Mantecon
2
• Dynamic simulation techniques should be applied for the development of “offshore and subsea”fields, in order to effectively optimise the design and operation of the field during its productive life.
• The unique features and flow assurance requirements of offshore/subsea wells and flowlines, along with the high associated capital costs, clearly merit detailed dynamic analysis for design, operation and optimisation.
3
• Dynamic simulations provide valuable information for savings and reduction of potential problems (risk reduction) during well completions and production system kick-off operations.
• The knowledge of the minimum flow rates required to clean up the wells will have relevant implications on test equipment selection (size) and therefore cost minimisation.
• Furthermore, the ability to predict (what if cases) and be prepared to deal with potential problems (or GL need) not only can save millions of dollars but can minimise any environmental impact.
5
What’s a Dynamic 3-phase Flow Simulator
8 Field Equations
Fluid Properties
Conservation of mass (5)Conservation of Momentum (2)
Conservation of energy (1)
Closure Laws
Mass TransferMomentum Transfer
Energy Transfer
BoundaryConditions
Initial Conditions
A set of coupled first order non-linear, one dimensional partial differential equations, with rather complex coefficients
Numerical solution scheme: semi-implicit integration method –allows for relatively long time steps with efficient run times
Closure laws are semi-mechanistic and required experimental verification
Two momentum equations are used: 1) a combined one for the Gas and possible Liquid droplets, 2) a separate one for the Liquid film
Separate continuity equations for the Gas, Liquid bulk andLiquid dropletscoupled through interphasialmass transfer.
A mixture energy conservation equation is applied. Dynamic
Simulator
6
OLGA - Dynamic 3-phase Flow Simulator
• OLGA model has been tested against experimental data over a substancial range in:– geometrical scale
• diameters from 1” to 8”, some at 30”• pipeline length/diameter ratios up to 5000• pipe inclinations of –15 to +90 degrees)
– pressures (from 1 to 100 bar)– variety of different fluids
• The model has also been tested against a number of different oil-gas field lines. Predictions are in good agreement with the measurements
• Participants:Statoil, ConocoPhillips, Agis, Total, BP, Chevron, Shell Gas de France, ExxonMobil, Saudi Aramco
334 m
Mixing point 54 m
2 o
7
1 2 543
1 2 543
1,2,3,…,5 (inside) : section volumes
1,2,3,…,6 (outside): section boundaries
6
1 D - Well Dynamic Simulation
100m - 2 pipes - 8.861" 160 m MODU ID WallP13 P12
P11 8.861" Wall Riser-air130 m Sea Level
P10 8.861" Wall Riser-seaOlga 0 m SS Tree 7.0625"
Wellhead 6.25"Riser P9 6.184" Wall 1
70 SCSSV 6.25"Wellbore
P8 8.861" Wall 70345 m 20" Csg shoe
P7 8.861" Wall 3451100 m TOC
P6 8.861" Wall 11001950 m Mandrel 6.18"
P5 6.765" Wall 19502000 m Nipple 5.75"
P4 8.681" Wall 20002100 m
P3 8.681" Wall 21002850 m
P2 6.184" Wall 28503000 m
P1 6.184" Wall Reservoir3050 m
Well XX14 - OLGA Wellbore Model
Steel
Cement
Formation
MD 4935.9 m
MD 3153.8 m
BRANCH: WELL-LOWWALL: Tubing-3
MD 2766.1 m BRANCH: WELL-LOWWALL: Tubing-2
MD 1432.2 m
BRANCH: WELL-UPPWALL: Tubing-1
-3500
-3000
-2500
-2000
-1500
-1000
-500
0
-3500 -3000 -2500 -2000 -1500 -1000 -500 0
4
Convection
Conduction
Radiation in annulus (Minor Effect)P, T Q
9
Transient vs. Steady State
• The weak points of NODAL analysis SS software when compare with Dynamic (Transient) numerical simulation are:
• Slugging Prediction – terrain induced slugging• Flow Regime Map – inclination, horizontal flow, etc.• Black oil• Use of correlations• SS conditions only
• Flow assurance• Start-up / shut-down• Corrosion• Chemical injection
10
OLGAS vs Beggs & BrillOLGAS VS Beggs & Brill
7.5" ID 1deg incl
0.00
0.10
0.20
0.30
0.40
0.50
0.60
0.70
0.80
0.00 0.10 0.20 0.30 0.40 0.50 0.60 0.70 0.80
MEASURED LIQUID HOLDUP
PRED
ICTE
D L
IQU
ID H
OLD
UP
OLGASBeggs & Brill
11
Prudhoe Bay 1978 Pressure Drop Data vs. OVIP 1/02 Models, Slug Tracking with DC=182
0
50
100
150
200
250
300
350
400
450
0 50 100 150 200 250 300 350 400 450
Measured Pressure Drop, psi
Pred
icte
d Pr
essu
re D
rop,
psi
Pressure drop prediction for oil pipeline
12
Simulation vs. field data
Northeast Frigg, Liquid Inventory Comparison
0
50
100
150
200
250
300
350
400
450
0.0 1.0 2.0 3.0 4.0 5.0 6.0 7.0Gas Rate, mmSCM/d
Liqu
id In
vent
ory,
m3
Measured
OLGA
13
Why use a transient simulator?
• Normal production– Sizing – diameter, insulation requirement– Stability - Is flow stable? – Gas Lifting / Compressors– Corrosion
• Transient operations– Shut-down and start-up, ramp-up (Liquid and Gas surges)– Depressurisation (tube ruptures, leak sizing, etc.)– Field networks (merging pipelines/well branches with different fluids)
• Thermal-Hydraulics – Rate changes– Shut-in, blow down and start-up / Well loading or unloading– Flow assurance: Wax, Hydrate, Scale, etc.
When things are frozen in time
When not to use dynamic simulation?
Photo: T. Husebø
When things are frozen in time
When not to use dynamic simulation?
Photo: T. Husebø
14
• Pipeline with many dips and humps:– high flow rates: stable flow is possible– low flow rates: instabilities are most likely
(i.e. terrain induced) • Wells with long horizontal sections – Extended Reach• Low Gas Oil Ratio (GOR):
– increased tendency for unstable flow• Gas-condensate lines (high GOR):
– may exhibit very long period transients due to low liquid velocities• Low pressure
– increased tendency for unstable flow • Gas Lift Injection
– Compressors problems, well interference, etc.• Production Chemistry Problems
– Changes in ID caused by deposition• Smart Wells – Control (Opening/Closing valves/sliding sleeves)
Unstable vs. Stable Flow Situations
Multiphase Flow is Transient !Multiphase Flow is Transient !Well Production is Dynamic!Well Production is Dynamic!
15
Usual Potential problems for Stable multiphase flow
• Inclination / Elevation • “Snake” profile• Risers• Rate changes• Condensate – Liquid content in gas• Shut-in / Start up
16
P/T Development – Flow AssuranceTotal System Integration
Oil
Gas Condensate
Pres
sure
Temperature
LIQUID
GAS
GAS + LIQUID
Typical phase envelopes
Gas OilReservoir Temperature
70 -110 oC /160 - 230oF
Emulsion 40oC/104o
F30oC/86oF
20oC/68oF
WaxWater
HydrateHydrate
< 0oC/32oF(Joule Thompson)
~ +4oC/39oF
Temperature effects
OLGA OLGA
OLGA RES ERVOIRS IM U LATOR(ECLIPS E)
OLGA/ D-S PICE
17
OPERATING ENVELOPE
0
100
200
300
400
500
600
700
800
900
1000
0 100 200 300 400 500 600 700 800 900 1000
STANDARD LIQUID RATE [Sm³]
GA
S O
IL R
AT
IO [S
m³/S
m³]
Stable Operating Envelope
Standard Liquid Rate [ Sm³/d]
Gas
Oil
Rat
io [S
m³/
Sm³]
Hydrate Formation Temp. – 18°C
Wax Appearance Temp. – 32°C
Riser Stability – ΔP = 1 bar
Riser Stability – ΔP = 6 bar
Reservoir Pressure – 80 bara Riser Stability – ΔP = 12 bar
Gas Velocity Limit – 12 m/s
Erosional Velocity Limits
18
WELL DYNAMICS • Minimum stable flow rates / Slug Mitigation• Tubing sizing• Flow assurance, Wax , Hydrates / Corrosion rates• Artificial Lift design and optimisation
– Gas Lift Unloading– Compressors shut-down– ESP sizing / Location
• Start-up/Shut-in• Commingling Fluids
– Multiple completions / Multilateral Wells / Smart Wells
• Loading/unloading – Condensate/Water• Well Clean-up• Water accumulation studies• Location of SCSSV• MeOH/Glycol requirements• Well Testing
– Wellbore Storage effects / Segregation effects
19
DYNAMIC GAS LIFT APPLICATIONS
• Well Clean-up using Gas Lift• Well Kick-off using Gas Lift• Gas Lift Unloading• Continuous Gas Lift• Subsea Wellhead Gas Lift• Riser Gas Lift• Single Point (Orifice) Gas Lift
O LG A O LG A
O LG A R ES ER V O IRS IM U L A T O R(EC LIP S E)
O LG A / D -S P IC E
T im e (m in .)
LIQ U ID F L O W IN T O S EP A R A T O R(m / s )3
S LU G F LO W
Fr o n t T a i l F r o n t
S e p a r a t e d f l o w D is p e r se db u b b le
20
Typical Gas Lift Well Configuration
Mud line
Sea level
Injection Gas
Production Fluid
Production Fluid + Injection Gas
Orifice at Injection Point
Unloading Valves
21
Modelling concerns:
Mud line
Sea level
a) Annular Flow
b) Heat Transfer
c) Non-constant Composition in Tubing above Injection Point
d) Unloading Valves Operation
Typical Gas Lift Well Configuration
Gas Lift is clearly a transient problem
22
Modelling concerns:
a) Annular Flow
b) Heat TransferProduction
Branch = “GASINJ”
Branch = “WELLH”NodeBranch = “WELLB”
Gas Injection
Casing
Full description of annular / tubingflow interactions for flow and heat transfer phenomena
ANNULUS flow model gives very exact counter-current heat exchange
23
c) Non-constant Composition in Tubing above Injection Point
Trend data
Standard OLGACompTrack OLGA
kg/s
40
35
30
25
20
15
10
5
0
Time [h]76.565.554.543.5
Liquid unloading (form of slugging) – Fluid composition varies
Liquid Flowrate at the Wellhead
CompTrack will better account for effects of changing composition in the tubing
Modelling concerns:
24
Mud line
Sea level
Previously modelled as CONTROLLERs
d) Unloading ValvesOperation
Unloading valve tables -VPC can be incorporated
Modelling concerns:
25
Well Unloading Dynamic Simulation
• Following a well workover, tubing and casing are frequently filled with liquid
• Liquid unloaded by injection of gas at casing-head
• Placement and sizing of unloading valves currently performed by approximate steady-state methods
• A transient multiphase simulation can permit more detailed simulation of unloading process
• Troubleshooting can be more efficient using dynamic simulation
26
AC PC
PT
PD
AD
AT
• Valve open when tubing above is full of liquid (liquid weight > opening pressure)
• Valve closes when liquid column weight above location is reduced (< closing pressure)
• Controlled (mostly) by casing pressure
• Valve closure “ripples” down string
• When well unloaded, only orifice at bottom open
Gas Lift Valves (Most Common Configuration)
27
Graphical Steady-State Method
P. Gradient in the Tubingat desired conditions
P. Gradient in the Casing (gas-filled)
P. Gradient of liquid-filledcolumn in the tubing
Safety MarginAPI
28
Gas Lift Valve Performance
Orifice RegionThrottling Region
1 curve per each Casing Injection Pressure
API
29
Tabular Valve Performance
!*******************************************************************************!- TABLE Definition!-------------------------------------------------------------------------------!TABLE LABEL=GLV-1, XVARIABLE=PRODUCTIONPRESS PSIA, YVARIABLE=STDGASFLOW MMSCF/D, INJECTIONPRESS=2600 PSIATABLE POINT=(1600,0)TABLE POINT=(1700,0.2)TABLE POINT=(1800,0.4)TABLE POINT=(1900,0.6)TABLE POINT=(2000,0.8)TABLE POINT=(2100,1)TABLE POINT=(2200,.8)TABLE POINT=(2300,.6)TABLE POINT=(2400,.4)TABLE POINT=(2500,.2)TABLE POINT=(2600,0)! API
30
0
1000
2000
3000
4000
5000
6000
0 5 10 15 20 25 30
Time [h]
Oil
rate
[bbl
/d]
0.0
0.5
1.0
1.5
2.0
2.5
Gas
lift
[MM
scfd
]
Gas lift rate Oil rate
Gas Lift – One Injection Point - CGLOil Production
60°F
250°F, 3300 psia and 3 bbl/psi
10000 ft
GOR = 500 scf/bbl
3 1/2”
5 1/2”
500 psia sep press
Choke at injection point
31
Conclusions• Steady-state methods do not capture the transients that inevitably
occur in an operating gas lifted well
• Transient well response occurs during:- Unloading the well - Well shut-down- Normal well operation- Compressor shut-down and injection fluctuations
• Dynamic Simulation can be used to simulate wellbore unloading (gas lift valve tables can be used as input)
• Hydraulics, heat transfer and changes in fluid composition are also taken into account
• Dynamic (flow) Modelling can be an invaluable tool when properly applied (flow assurance, predict fluid properties, etc.) – standard best practice recommendations are required
32
Integrated Modelling ApplicationGas Lift ExampleReservoir-Well-Gas Lift-Flowline-Riser-Separator-Facilities Pigging-405.plt
W1 W2 W3 W4
PCV
LCV
Production Separator
PC
LC
Gas Outlet
Liquid Outlet
Emergency Liquid Outlet
Emergency Drain Valve
ID=2 m, Length=6 mNLL=0.842 mHHLL=1.687LLLL=0.315
Riser
Annulus
Gas LiftID=8-in, Depth=120 m
ID=8-in, Length=4.6 km
Depth=2840 m
Tubing ID=0.1143 m
ID=0.2159 m
• Reservoir: incorporated explicitly
• Facilities: Simple model