The Role of Quality in Risk Management v4a

download The Role of Quality in Risk Management v4a

of 24

Transcript of The Role of Quality in Risk Management v4a

  • 8/14/2019 The Role of Quality in Risk Management v4a

    1/24

    Joseph W. Mayo

    Program ManagerManTech International

  • 8/14/2019 The Role of Quality in Risk Management v4a

    2/24

    Definition of risk

    Websters defines risk as exposure to the chanceof injury or loss; a hazard or dangerous chance.

    ANZ-4360 defines risk as the chance of somethinghappening that will have an impact on objectives.

    PMBOK defines project risk as an uncertain eventor condition that, if it occurs, has a positive ornegative effect on at least one project objective,

    such as time, cost, scope or quality.

  • 8/14/2019 The Role of Quality in Risk Management v4a

    3/24

    PMIs Project Management Body of Knowledge(PMBOK)

    ISO 31000 Risk Management

    NIST 800-30

    FAIRANZ-4360 (superseded by ISO 16085)

    IEEE 1540 (superseded by ISO 16085)

    ISO 16085:2004

  • 8/14/2019 The Role of Quality in Risk Management v4a

    4/24

    Both PMBOK, ANZ-4360, IEEE-1540, and ISO16085 focus primarily on project riskmanagement whereas NIST 800-30, ISO 31000,and FAIR have a much broader scope and focusprimarily on organizational or Enterprise riskmanagement.

  • 8/14/2019 The Role of Quality in Risk Management v4a

    5/24

    Risk

    Management

    Planning

    Risk

    Identification

    Qualitative

    Analysis

    Quantitative

    Analysis

    Risk Response

    Planning

    Communicate

    and Consult

    Establish

    Context

    Identify

    Risks

    Analyze

    Risks

    Evaluate

    Risks

    Treat

    Risks

    Monitory

    and Review

    Plan and Implement

    Risk Management

    Manage the Project

    Risk Profile

    Risk

    Analysis

    Monitor

    Risks

    Treat

    Risks

    Evaluate RiskManagement

    Process

    P

    M

    B

    O

    K

    A

    N

    Z

    4

    36

    0

    I

    S

    O

    16

    0

    8

    5

  • 8/14/2019 The Role of Quality in Risk Management v4a

    6/24

    Risk management is not complex but is difficultto do well because of the nebulous nature ofrisks.

    An effective project risk management process

    consists of six discrete process stepsestablish the context, identify risks, quantify riskimpact, prioritize risks, treat risks, and monitor risktreatment.

    Establish

    Context

    Identify

    Risks

    Quantify

    Impact

    Prioritize

    Risks

    Treat

    Risks

    Monitor

    Risk

    Treatment

  • 8/14/2019 The Role of Quality in Risk Management v4a

    7/24

    In addition to the discrete process stepseffective project risk management must includethree processes that transcend the entire riskmanagement lifecycle;

    oversight to ensure compliance, develop riskmodels, and feedback loop.

    Oversight to ensure compliance

    Develop Risk Models

    Feedback loop

    Establish

    Context

    Identify

    Risks

    Quantify

    Impact

    Prioritize

    Risks

    Treat

    Risks

    Monitor

    Risk

    Treatment

  • 8/14/2019 The Role of Quality in Risk Management v4a

    8/24

    Plan and Implement

    Risk Management

    Manage the Project

    Risk Profile

    Risk

    Analysis

    Monitor

    Risks

    Treat

    Risks

    Evaluate Risk

    Management

    Process

    I

    S

    O

    1

    6

    08

    5

    Oversight to ensure compliance

    Develop Risk Models

    Feedback loop

    EstablishContext

    IdentifyRisks

    QuantifyImpact

    PrioritizeRisks

    TreatRisks

    Monitor

    RiskTreatment

  • 8/14/2019 The Role of Quality in Risk Management v4a

    9/24

    Establish Context

    Objectives

    Assumptions

    Constraints

    Risk Thresholds

    Schedule

    BudgetQuality

    Mission Accomplishment

    Initial Risk Profile

    Communicate Risk Status

    Identify Risks

    Dont confuse symptoms,conditions, events, etc. with theactual risk

    Dont confuse issues with risks

    Define risks based on thepreviously established context

    Proper risk identification is oneof the most important criticalsuccess factors in riskmanagement

    Quantify Impact

    Objectively quantify impact(e.g. three-week scheduledelay, $50,000 budget overrun,500 hours of rework, etc.

    Subjective impact terms such assignificant delays, reduced

    quality, substantial cost overrunare extremely problematic

    Quantifiable impact is a criticalsuccess factor affecting allaspects of risk management

  • 8/14/2019 The Role of Quality in Risk Management v4a

    10/24

    Treat Risks

    Select one of the four risktreatment strategies; Avoid,Accept ,Mitigate, orTransfer.

    Treat risks based on

    previously prioritized risks Assumptions

    Constraints

    Risk Thresholds

    Schedule

    Monitor Treatment

    Monitor risks throughoutthe life cycle

    Monitor previouslyestablished contextelements for changes

    Monitor and evaluate theeffectiveness of risktreatments

    Look for new risks

    Prioritize Risks

    Risks should be prioritizedbased on impact to theproject followed byprobability of occurrence.

    Evaluate risks against

    previously established riskthresholds

    Evaluate each riskindependently

  • 8/14/2019 The Role of Quality in Risk Management v4a

    11/24

    Oversight

    Inadequate oversight leadsto rapid degradation ofeffective risk management

    Oversight is required at bothtactical and strategic levels

    Make risk management anintegral part of all lessonslearned and processimprovement activities

    Risk Models

    Risk models are one of themost valuable outcomes ofrisk management

    A risk model is a risktreatment plan that has

    been proven to be effective Risk models should include

    risk treatments that wereapplied but were found tobe ineffective

    Feedback Loop

    Involve all stakeholders

    Provide feedback constantly

    Substantiate feedback withquantifiable results

  • 8/14/2019 The Role of Quality in Risk Management v4a

    12/24

    Risk Management at a Glance

    Implement a defined process

    Properly identify project risks

    Quantify risk impact using objective measures

    Prioritize risks based on impact and probability

    Develop a treatment plan

    Monitor risk treatments

    Develop reusable risk models

    Provide oversight to ensure compliance

    Implement an active feedback loop

  • 8/14/2019 The Role of Quality in Risk Management v4a

    13/24

    A Work Breakdown Structure (WBS) is

    What is going to be builtA project management technique fordefining and organizing the total scope of a

    project, using a hierarchical tree structureA defined a set of planned outcomes thatcollectively and exclusively represent 100%

    of the project scope

  • 8/14/2019 The Role of Quality in Risk Management v4a

    14/24

    A WBS is

    A hierarchical structure where the first twolevels of the WBS (the root node and Level 2)represent 100% of the scope

    A scope management tool that describesplanned outcomes (e.g. deliverables,milestones) not planned actions

    Not overly prescriptive of methods

  • 8/14/2019 The Role of Quality in Risk Management v4a

    15/24

    A WBS is not

    A description of how the product is going to bebuilt

    An exhaustive list of work or activities to perform

    A project schedule

  • 8/14/2019 The Role of Quality in Risk Management v4a

    16/24

    1.0

    Bicycle

    1.1

    Frame Set

    1.1.1

    Frame

    1.1.2Handlebar

    1.1.3

    Fork

    1.1.4

    Seat

    1.2

    Crank Set

    1.3

    Wheels

    1.3.1

    Front Wheel

    1.3.2Rear Wheel

    1.4

    Braking System

    1.5

    Shifting System

    1.5.1

    De-railer

    1.5.2Shift Levers

    1.6

    Integration

    1.7

    ProjectManagement

    1.7.1

    Status Reports

    1.7.2

    FinancialReports

    1.7.3

    Risk Register

    1.7.4

    Schedule

  • 8/14/2019 The Role of Quality in Risk Management v4a

    17/24

    One of the most important WBS designprinciples is called the 100% Rule.

    The Practice Standard for Work BreakdownStructures (Second Edition), published by the(PMI) defines the 100% Rule as follows:

    The 100% Rule...states that the WBS includes 100%of the work defined by the project scope andcaptures ALL deliverables internal, external,

    interim in terms of the work to be completed,including project management.

  • 8/14/2019 The Role of Quality in Risk Management v4a

    18/24

    100% rule continued

    The 100% rule is one of the most importantprinciples guiding the development, decompositionand evaluation of the WBS.

    The 100% rule applies at all levels within the

    hierarchy: the sum of the work at the child levelmust equal 100% of the work represented by theparent and the WBS should not include any work

    that falls outside the actual scope of the project

  • 8/14/2019 The Role of Quality in Risk Management v4a

    19/24

    WBS Tips

    Do not carry action oriented details in the WBSAn action oriented WBS will likely include eithertoo many actions or too few actions. Too manyactions will exceed 100% of the parent's scope and

    too few will fall short of 100% of the parent'sscope.

    The best way to adhere to the 100% Rule is to

    define WBS elements in terms of outcomes orresults. Focus on progress not, activity

  • 8/14/2019 The Role of Quality in Risk Management v4a

    20/24

    WBS Dictionary

    Fully describes each component of the WBS

    Includes at least the following:

    Brief definition of the scope, Deliverable(s), List ofactivities, and Milestone(s)

    Optionally can include the following:Quality requirements, responsible individual /organization, start and end dates, resources required,estimated cost, estimated effort, basis of estimate (BOE)and charge number.

  • 8/14/2019 The Role of Quality in Risk Management v4a

    21/24

    Attribute Definition

    WBS ID 1.9.3

    Control Code 9502-001C

    Name Time Management

    Description Manage the project schedule to assure that deliverables, work products,milestones, etc. are on schedule to be delivered on time

    Deliverables Updated schedule

    Work Package(s) Weekly Effort Variance Analysis Report

    Basis of Estimate (BOE)

    Activity List Collect actual effort from team members

    Apply actuals to the schedule

    Conduct effort variance analysis

    Submit Change Request (CR) to the CCB based on variance analysis

    Input(s) Schedule

    ISR

    Timesheets

    Dependencies

    Resource Requirements Project Control Specialist

  • 8/14/2019 The Role of Quality in Risk Management v4a

    22/24

    Attribute Definition

    WBS ID 1.9.4Control Code 9502-001DName Cost ManagementDescription Manage the project budget to assure that deliverables, work products, milestones, etc.

    are delivered within budget. Reconcile project budget with accounting system andprepare financial reports

    Deliverables Updated schedule

    Monthly EVM Report

    Monthly Program Review Briefing

    Work Package(s) Weekly Project Labor Report

    Weekly Project Travel Report

    Weekly Variance Analysis Report

    Monthly Reconciliation Report

    Basis of Estimate (BOE)Activity List Update weekly financial data

    Conduct weekly financial variance analysis

    Reconcile project financials with labor, travel, and ODC accounting reports

    Prepare weekly financial report

    Input(s) Schedule

    Monthly Forecast ReportMonthly Accounting Reports

    ISR

    Timesheets

    Dependencies 9502-001CResource Requirements Project Control Specialist

  • 8/14/2019 The Role of Quality in Risk Management v4a

    23/24

    Attribute DefinitionWBS ID 15.3.2Control Code 1802-001CName JAD WorkshopDescription Facilitate Joint Application Development (JAD) workshops and document the

    workshop resultsDeliverables JAD Workshop DocumentationWork Package(s) Workshop #1, Workshop #2, Workshop #3, Workshop #4, Workshop #5

    Basis of Estimate (BOE) 6 hrs / workshop * 5 workshops * 7 resources = 210 hrs

    8 hrs / workshop to consolidate documentation * 5 workshops * 3 resources =120 hrs

    330 hrs totalActivity List Collect background information

    Plan workshop interviews

    Schedule workshop

    Prepare for workshop

    Conduct workshop

    Document workshop results

    Prepare workshop documentation

    Distribute workshop documentationInput(s) Project ScheduleDependenciesResource Requirements Business Analyst

  • 8/14/2019 The Role of Quality in Risk Management v4a

    24/24

    Attribute DefinitionWBS ID 2.1.3Control Code 9502-002GName Program Management Plan EvaluationDescription Evaluate Program Management Plan (PMP) in accordance with PMBOK

    Deliverables PMP Evaluation Report Draft 1Final PMP Evaluation Report

    Work Package(s) PMP Evaluation Report Template

    Evaluation Plan

    Evaluation Schedule

    Interview Notes

    Evaluation Checklists

    Basis of Estimate (BOE)

    Activity List Secure consensus on report formatPrepare list of artifacts to review

    Prepare interview schedule

    Coordinate personal interviews

    Prepare artifact evaluation checklists

    Evaluate project management artifactsUpdate evaluation checklists

    Prepare initial draft report

    Peer review draft report

    Prepare final evaluation report

    Input(s) Project Management Plan

    PMBOK, 4th Edition

    DependenciesResource Requirements Project Manager