The Interconnection Process in New England Status Update
Transcript of The Interconnection Process in New England Status Update
ISO-NE PUBLIC
Al McBride D I R E C T O R , T R A N S M I S S I O N S T R A T E G Y & S E R V I C E S
The Interconnection Process in New England – Status Update
S E P T E M B E R 1 6 , 2 0 1 5 | W E S T B O R O U G H , M A
Planning Advisory Committee
ISO-NE PUBLIC
Purpose of This Presentation
• Provide an update regarding the status of the processing of new interconnections in New England – Discussion in the context of issues regarding the processing of wind
generation in Maine
2
ISO-NE PUBLIC
Summary of Issues
• The time taken to complete system impact studies for new wind generators – Particularly in Maine
• Curtailment and performance issues in system operations for inverter-based generators
• Modeling and performance requirements being introduced by new NERC standards
3
ISO-NE PUBLIC
Agenda
• Brief history of interconnection process developments in New England
• Discussion of the current status throughout New England
• Issues with inverter-based generators
• Discussion of the backlog in Maine
• Future considerations
4
ISO-NE PUBLIC
ISO-NE INTERNAL USE
ISO-NE PUBLIC
BRIEF HISTORY OF INTERCONNECTION PROCESS DEVELOPMENTS IN NEW ENGLAND
5
ISO-NE PUBLIC
Timeline of Interconnection Standard Development in New England
1998
• Minimum Interconnection Standard
2003/2004
• FERC Proforma LGIA/LGIP
2009
• FCM/Queue Reforms
2015
• Elective Transmission Upgrades
6
ISO-NE PUBLIC
Minimum Interconnection Standard
• Minimum required upgrades, consistent with: – No degradation in transfer capability – Maximum one-for-one displacement of existing/proposed generation – All reliability standards must be met – ISO can still operate and maintain the system
• Minimum Interconnection Standard – More stringent than “plug and play” – Does not assure incremental capacity to serve load – Assures no degradation to load-serving capability of the system – Consistent with market and Tariff constructs for Network Resources
7
ISO-NE PUBLIC
Observations on the Application of the MIS
• New generators are competing with conventional generators for transmission access
• New inverter-based generation has very different voltage support and inertial characteristics than conventional generators – Many are more distant from the stronger parts of the grid
• Hence, new inverter-based generators are not ready substitutes for many of the conventional generators they are competing with
• Many upgrades may still be required for basic interconnection pursuant to the MIS
8
ISO-NE PUBLIC
2008 FCM-Q Reforms: Summary of Objectives
• Improved coordination between the requirements of the Forward Capacity Market and the Generator Interconnection Process
• Addressed Intra-Zonal Deliverability in New England
• Addressed Interconnection Queue processing issues that had been observed across the industry and discussed at FERC
9
ISO-NE PUBLIC
Observations on the Implementation of FCM-Q
• Capacity Network Resource Interconnection Service (CNRIS) is achieved through successful participation in the FCM – Annual CNR Group study in FCA qualification to test for overlapping
impacts
• Integrating the Interconnection Queue with the FCM is a very complex undertaking for both the ISO and participants – There is more emphasis than ever on processing queue positions as
quickly as possible
• Queue processing reforms (increased deposits/requirements at key decision points) were successful in achieving queue discipline – Projects move to the next stage of the process, or withdraw
10
ISO-NE PUBLIC
Elective Transmission Upgrades
• In April 2015, FERC approved the interconnection procedures for Elective Transmission Upgrades (ETUs) – New Schedule 25 in the ISO OATT that governs the interconnection of
all forms of ETUs to the New England system • Closely modeled on, and integrated with, the generator interconnection
procedures
– Established interconnection service rights for certain ETU types • New controllable External ETUs
– Enabled an Internal ETU to become directly associated with a specific Generating Facility seeking CNRIS • So that it can be studied together with the Generating Facility and thereby
increase the Generating Facility’s ability to qualify for the FCM
– Did not alter the existing Tariff structure • ETUs must function within the existing dispatch, market and tariff
structure of the New England system
11
ISO-NE PUBLIC
ISO-NE INTERNAL USE
ISO-NE PUBLIC
DISCUSSION OF THE CURRENT STATUS OF THE INTERCONNECTION PROCESS THROUGHOUT NEW ENGLAND
12
ISO-NE PUBLIC
Current Queue Status
• At this time, with very specific exceptions, queue processing is up-to-date
• With the exception of the North and Western Maine portion of the system (which has experienced a backlog of mostly wind interconnection requests), substantially all the generator interconnection requests made through 2014 have completed the system impact study phase or have moved to the Interconnection Agreement and commercialization phases
• Note that the ISO has also identified other parts of the system that would face significant challenges to adding new generation – Northern Vermont – Northern New Hampshire
13
ISO-NE PUBLIC
Status of Queued Requests
2012 2013 2014
Wind Project In Maine 3 4 12
Not a Wind Project In Maine 1 1
0
2
4
6
8
10
12
14
Co
un
t
Year of Original Interconnection Request
Active Interconnection Requests Without a Completed System Impact Study
14
ISO-NE PUBLIC
Other Recent Queue Observations
• Recent upturn in proposals in Southern New England – Appear to have been timed with FCM Show of Interest window – Many new proposals in Southeast New England (SEMA/RI) – Mostly gas-fired (primary fuel) – Studies proceeding well overall
• Recent activity with large solar project applications – ~20 MW and larger
15
ISO-NE PUBLIC
Drivers of the Backlog in Maine
1. Issues with Inverter Based Generators
2. Characteristics of the Maine system
3. Requests far beyond the capability of the existing Maine system
16
ISO-NE PUBLIC
New Wind Farms are located far from the transmission system
Electrical Distance
Large reactive losses incurred with flow over long distances This results in the addition of significant reactive upgrades for voltage and stability FERC exemption on Wind reactive requirement means that every wind farm study must individually identify the reactive requirement (there is no reactive margin left on the Maine system)
Low short circuit ratios of remote locations mean that wind farm models often do not perform as expected This results in the need to perform electromagnetic transient analysis (PSCAD) in addition to steady state and dynamic stability analysis
18
ISO-NE PUBLIC
Wind Farms provide little inertia or voltage support
Wind Performance
Changes to wind generator parameters are frequently proposed because of a change in manufacturer or a change in technology/control design
Upgrades needed for earlier wind farms, such as series capacitor and/or dynamic reactive devices, further complicate the analysis of later wind farms
•Sub-synchronous analysis •PSCAD analysis
19
ISO-NE PUBLIC
Interconnection Process – Basic Flow
Interconnection Request
Scoping Meeting
Feasibility Study (Optional)
System Impact Study
Facilities Study (Optional)
Construction
Interconnection Agreement Development
Commercial Operations
Interconnection Agreement
20
ISO-NE PUBLIC
System Impact
Study Process
“Conventional” Generation
Identify system
upgrades
Create load
flow base cases
Create Stability
base cases
Identify Issues
Affected Parties
review results
Create
contingency list
Define potential
solutions
Identify Issues
Define potential
solutions
Identify system
upgrades
Create
contingency list
Develop detailed
SIS technical
assumptions
Draft System
Impact Study
Report
Customer signs
SIS Agreement
21
ISO-NE PUBLIC
System Impact
Study Process
Wind/Inverter-based Generation
Identify system
upgrades
Create load
flow base cases
Create Stability
base cases
Identify Issues
Affected Parties
review results
Create
contingency list
Define potential
solutions
Identify Issues
Define potential
solutions
Identify system
upgrades
Create
contingency list
Develop detailed
SIS technical
assumptions
Draft System
Impact Study
Report
Customer signs
SIS Agreement
Collector System Design
Address Low Short Circuit
Solve Interactions Between Upgrades & Generators
PSCAD Analysis
Address Issues with Dynamic Model Performance
Identify Required Reactive Capability
22
ISO-NE PUBLIC ISO-NE PUBLIC
REACTIVE PERFORMANCE REQUIREMENTS Considerations to improve study time-frames for inverter-based generators
23
ISO-NE PUBLIC
Reactive Performance Requirements
• Recently approved PJM requirement1 – All new non-synchronous resources should: (1) have the capability to
autonomously provide dynamic reactive support within a range of 0.95 leading to 0.95 lagging at inverter terminals; (2) adhere to NERC Reliability Standard PRC-024-1 with respect to voltage and frequency ride-through capabilities, irrespective of resource size • Previously, in accordance with FERC Order No. 661, wind resources were
not required to provide reactive power unless a system impact study shows that reactive power is needed from that resource to maintain grid reliability
• ERCOT requirement – Power factor capability of +/-0.95 (or less) determined at the
generating unit's maximum net power to be supplied to the ERCOT Transmission Grid and at the transmission system Voltage Profile established by ERCOT, both measured at the POI
1. Docket No: ER15-1193-000: Conditionally Approved May 05, 2015
24
ISO-NE PUBLIC
Benefits of Reactive Performance Requirement
• Reduce the reliance on the design of reactive solutions in the interconnection system impact study – Expected to help to reduce time to complete studies
• Capture the benefits of widely available technology improvements
• Can result in fewer operating restrictions
• Anticipate the increasing number of non-synchronous interconnection requests (combined with anticipated resource retirements) – Necessitates the availability of reactive power on a presumptive basis
to ensure the safety and reliability of the transmission system as a whole
25
ISO-NE PUBLIC ISO-NE PUBLIC
DEFINING A COMPLETE INTERCONNECTION REQUEST Considerations to improve study time-frames for inverter-based generators
26
ISO-NE PUBLIC
Detailed Representation of Wind Farms
• System Impact Studies have required full modeling of the wind farm in steady state analysis – Single-turbine equivalents are
used in stability analysis
• A standard wind farm data set has been drafted and has been used in the collection of data from some existing and new wind farms
27
ISO-NE PUBLIC
Initial Steps in Wind Farm Electrical Design
• Identify tap settings for the unit step-up transformers and the station step-up transformers – Tap settings correspond to the most reasonable voltage conditions on
the collector system and the turbine terminals for a range of different voltage conditions at the POI
• The detailed representation provides direction to the tap settings to be used in the equivalent models used in stability analysis
• These analyses can be time-consuming and have been included in the ISO system impact study analysis
28
ISO-NE PUBLIC
Inverter-Based Interconnections in Weak Portions of the System
• A low short circuit ratio (SCR) is a commonly used indicator of a “weak” system
• In a weak system, the following problems can be associated with inverter-based interconnections: – Steady state voltage violations – Voltage instability – Oscillations
• Power system analysis models provided by manufacturers do not represent actual performance under weak system conditions – Reduced confidence in the models – Reduced confidence in the ability of turbines to operate reliably in these weak
conditions
• Customized generator-specific changes are typically inadequate due to operational system changes and system evolution
29
ISO-NE PUBLIC
Appropriate Design level of an Interconnection Request for an Inverter-Based Generator
• The detailed project design could be provided by the developer as part of Interconnection Request – Developer would provide comprehensive documentation demonstrating
conformance with performance requirements
• Interconnection Request submittal could address weak grid performance – Certify the lowest acceptable level of short circuit ratio, or provide
correction to an acceptable level – Provide electromagnetic transient (PSCAD) model – Provide documentation of acceptable power system analysis model
performance • Verify using benchmark comparison with PSCAD
30
ISO-NE PUBLIC
Benefits of Up-Front Design
• Increased readiness to initiate the system impact analysis of the effect of the project on the network – Expected to help to reduce time to complete studies
• Reduced need to consider modifying the project after the interconnection process has begun
31
ISO-NE PUBLIC
NERC Proposal for Standardized Models
• In November 2013, NERC issued a “Proposal for Use of Standardized Component Models in Powerflow and Dynamics Cases”
• NERC Planning Committee (PC) directed the NERC Modeling Working Group (MWG) to develop, validate, and maintain a library of standardized component models and parameters for powerflow and dynamics cases
• The proposal requires that user‐defined models should be placed on a swift path to inclusion in the library of standardized models – Once a corresponding standardized model is developed and validated,
the regions should shift to the standardized model
33
ISO-NE PUBLIC
Benefits of Using Standardized Models
• Reduces the time required to set-up new study cases – Expected to help to reduce time to complete studies
• Eliminates the need for generator owners to update user models when power system analysis software is updated
• Eliminates the use of ISO/Transmission Provider engineering resources in the testing and troubleshooting of user models
34
ISO-NE PUBLIC
Material Modification Background
• In response to customer requests and to address the backlog in its generator interconnection queue, ISO has reviewed how it administers the process of making a Material Modification determination
• ISO has been implementing procedural rules to add more structure to the process that should expedite the studies of projects in the queue and provide notification to customers on key times to update the technical data for their project
36
ISO-NE PUBLIC
Material Modification Background, cont.
• Interconnection Customers request changes to their existing or proposed generating facilities for a wide variety of reasons
• These changes can have no impact, can have a large impact on the studies of other proposed projects or can have a significant impact on the reliability of the New England’s transmission system
• Proposed changes that may cause a large/significant impact are deemed to be Material Modifications and require submission of a new Interconnection Request and a new queue position
• ISO’s Tariff provides a definition of Material Modification in Schedule 22 and provides further information on modifications in Section 4 of the LGIP and Article 5.19 of the LGIA
37
ISO-NE PUBLIC
Data Refresh at the beginning of the System Impact Study
• ISO-NE will notify the Interconnection Customer 30 days before the study begins and allow the Interconnection Customer 30 days to refresh its data to the degree allowed under the same materiality standards for changes prior to execution of the System Impact Agreement
• Once the System Impact Study Study has started, it will be completed without making any changes except those based on study results that were not anticipated and are agreed to by the System Operator and the Interconnecting Transmission – Screening criteria on the following slide
38
ISO-NE PUBLIC
Screening Criteria for Project Changes
• Changes will be deemed material and require a new Interconnection Request when: – A restudy is needed to determine if the change has a significant
impact on the reliability of the transmission system, or, – A restudy is needed to re-determine the system upgrades and/or the
allocation of system upgrade costs, or, – A restudy will result in a delay of the study of a later-queued project
• Changes will not be deemed material and will not require a new Interconnection when: – There are no performance problems that may be affected by the
change to the project that is found in any base cases for the most severe N-1 and N-1-1 contingencies, and,
– Similar or better performance can be confirmed based on a very limited review
39
ISO-NE PUBLIC
Benefits of Additional Structure in Material Modification Determinations
• Reduced delay in the conduct of queued studies – Expected to help to reduce time to complete studies
40
ISO-NE PUBLIC
Consideration of Network Upgrades
• The selection and design of reactive upgrades can take a significant amount of study effort – Sufficient descriptive detail of the proposed reactive upgrades must be
available for modeling and analysis – Must coordinate with other existing and proposed devices – Long time to collect cost estimates
• A request by the developer to consider a different reactive upgrade than the proposed upgrade can cause a significant amount of study re-work
• Static shunt compensation can be inoperable for intermittent resources due to quickly changing output conditions and can be infeasible from an operating standpoint due to frequent switching operations
42
ISO-NE PUBLIC
Benefits of Focusing on Operable Solutions
• Reduced iterations in the study of upgrade alternatives – Expected to help to reduce time to complete studies
• Some scalability of upgrades to build upon in the evaluation of later queue positions – Expected to help to reduce time to complete studies
43
ISO-NE PUBLIC ISO-NE PUBLIC
THE STANDARD SCOPE OF A FEASIBILITY STUDY
Applicable to all generator types
44
ISO-NE PUBLIC
Feasibility Study Scope
• In New England, the Feasibility Study scope has corresponded to a complete steady-state portion of the overall System Impact Study – Complete thermal analysis – Complete steady state voltage analysis – Complete short circuit analysis
• Propose to modify the standard scope of Feasibility Studies to provide screening analysis of the expected areas of concern – Benefit is expected to be a high-level study in a shorter amount of
time that focuses on the expected problems
45
ISO-NE PUBLIC
Examples of Reactive Power Screening Tools
• Surge Impedance Loading and VAR Losses – Overview of the VAR burden introduced by the interconnection
• “PV” (Power-Voltage) Analysis – Voltage feasibility pretest – Worst scenario and contingency screening – Critical voltage location (bus) searching – Understand the voltage profile in the facility and the region
• “QV” (Reactive-Voltage) Analysis – Evaluate reactive margin and high/low voltage potential – Evaluate the amount and type of reactive compensation needed
• Short Circuit Ratio – Evaluate potential issues and recommend focus of study
46
ISO-NE PUBLIC
Multiple Communications Regarding the Severe Challenges in Maine
• “New England Wind Integration Study” (the “NEWIS”) – to assess the effects of large-scale wind penetration in New England (2009)
• Northern Maine System Performance, Planning Advisory Committee (PAC) presentation (September 21, 2010)
• Wind Development in Constrained Areas, PAC presentation (March 21, 2013)
• Strategic Transmission Analysis: Wind Integration Study, PAC Presentation (December 18, 2013)
• Strategic Transmission Analysis: Wind Integration Study – Stage 1- Maine, Regional Constraints, PAC Presentation (May 21, 2014)
• Strategic Transmission Analysis: Wind Integration Study – Stage 2- Maine, Interface Constraints, PAC Presentation (December 18, 2014)
48
ISO-NE PUBLIC
–
The Existing Maine System Three existing Special Protection Systems (SPS) associated with actions to reduce North-South flows under contingency conditions
Maine corridor experiences severe voltage sags for faults in Southern New England
Maine Voltages
The Maine system has long transmission lines with relatively little load
Multiple Major Interfaces to manage North-South flows
Multiple Local Interfaces to manage local constraints (Not Shown)
49
ISO-NE PUBLIC
Requests Far Beyond the Existing Capability of the Maine Transmission System
Maine System Approximate (MW)
Forecast 2015 Summer Peak Load1 (net) 2,300
Maine Export Capability 1,900
Load + Export Capability 4,200
Existing Generation Capacity (Summer 2015) 3,100
New Brunswick Import Capability 1,000
New Requests (September 2015)1 3,600
Resource Totals 7,700
1. Note that most of the proposals are located north of Orrington – where there is only approximately 300 MW of load
50
ISO-NE PUBLIC
Considerations
• Interconnection issues in the identified remote areas of the system are not caused by, nor can they be addressed by, queue process changes – The existing transmission system was built to serve minimal system load
and is at its limit • As noted above, studies since 2009 have shown the need for significant
transmission system expansion • Even if small incremental amounts of wind can be added, it is clear that the
existing system cannot support hundreds or thousands of proposed MWs – If individual projects are not able or willing to make the scale of system
upgrade investments now required; key issue becomes infrastructure
• How to address the infrastructure issues? – Additional wind integration analysis to identify the overall upgrades
required to interconnect the levels of MW that are proposed? • Such an approach is essentially a clustering study and only appears to be a way
forward if coupled with cost allocation to queue projects to share costs • Interconnection cost allocation alternatives?
52
ISO-NE PUBLIC
Next Steps
• Introduce proposed Tariff changes at the September Transmission Committee
• Transmission Committee action in October
53
ISO-NE PUBLIC ISO-NE PUBLIC
APPENDIX - PHASOR MEASUREMENT UNITS Discussed at the July Reliability/Transmission Committee
Applicable to all generator types
55
ISO-NE PUBLIC
Model Validation: NERC MOD-026 and MOD-027
• MOD-026 will require generators equal to or greater than 100 MVA to verify the generator excitation control system or plant volt/var control function model (including the power system stabilizer model and the impedance compensator model) and the model parameters used in dynamic simulations accurately represent the generator excitation control system or plant volt/var control function behavior when assessing Bulk Electric System reliability
• MOD-027 will require generators equal to or greater than 100 MVA to verify the turbine/governor and load control or active power/frequency control model and the model parameters, used in dynamic simulations that assess BES reliability, accurately represent generator unit real power response to system frequency variations
56
ISO-NE PUBLIC
Model Validation: MOD-033
• Requirement
Each Planning Coordinator shall implement a documented process to validate steady-state and dynamics Planning models by comparing performance with actual system behavior
• Compliance measure
Each Planning Coordinator shall provide evidence that it has a documented validation process according to Requirement R1 as well as evidence that demonstrates the implementation of the required components of the process
57
ISO-NE PUBLIC
PJM Tariff Language
• 8.5.3. Phasor Measurement Units (PMUs):
An Interconnection Customer entering the New Services Queue on or after October 1, 2012 with a proposed new Customer Facility that has a Maximum Facility Output equal to or greater than 100 MW shall install and maintain, at its expense, phasor measurement units (PMUs). PMUs shall be installed on the Customer Facility low side of the generator step-up transformer, unless it is a non-synchronous generation facility, in which case the PMUs shall be installed on the Customer Facility side of the Point of Interconnection. The PMUs must be capable of performing phasor measurements at a minimum of 30 samples per second which are synchronized via a high-accuracy satellite clock. To the extent Interconnection Customer installs similar quality equipment, such as relays or digital fault recorders, that can collect data at least at the same rate as PMUs and which data is synchronized via a high-accuracy satellite clock, such equipment would satisfy this requirement. As provided for in the PJM Manuals, an Interconnection Customer shall be required to install and maintain, at its expense, PMU equipment which includes the communication circuit capable of carrying the PMU data to a local data concentrator, and then transporting the information continuously to the Transmission Provider; as well as store the PMU data locally for thirty days.
58
ISO-NE PUBLIC
PJM Tariff Language (Cont’)
Interconnection Customer shall provide to Transmission Provider all necessary and requested information through the Transmission Provider synchrophasor system, including the following: (a) gross MW and MVAR measured at the Customer Facility side of the generator step-up transformer (or, for a non-synchronous generation facility, to be measured at the Customer Facility side of the Point of Interconnection); (b) generator terminal voltage; (c) generator terminal frequency; and (d) generator field voltage and current, where available. The Transmission Provider will install and provide for the ongoing support and maintenance of the network communications linking the data concentrator to the Transmission Provider. Additional details regarding the requirements and guidelines of PMU data and telecommunication of such data are contained in the PJM Manuals.
59
ISO-NE PUBLIC
Benefits of PMUs
• The traditional off-line staged generator tests are costly and time consuming
• With high-resolution PMU data from generators, model validations may more readily be performed online or using system disturbance data, without taking generation outages – Opportunity to detect failures, changed adjustments, drifting, and
improper operation of equipment
• Enhanced ability to verify dynamic models using PMU measurements
• Validation and benchmarking system wide models (MOD-033)
60