The hidden value of air transportation infrastructure
-
Upload
bruno-miller -
Category
Documents
-
view
217 -
download
1
Transcript of The hidden value of air transportation infrastructure
![Page 1: The hidden value of air transportation infrastructure](https://reader036.fdocuments.us/reader036/viewer/2022082522/575074701a28abdd2e947f6d/html5/thumbnails/1.jpg)
Technological Forecasting & Social Change 74 (2007) 18–35
The hidden value of air transportation infrastructureB
Bruno Miller a,*, John-Paul Clarke b,1
a 4313 42nd Ave. S., Minneapolis, MN 55406, USAb School of Aerospace Engineering, Georgia Institute of Technology, 270 Ferst Drive NW, Atlanta,
GA 30332-0150, USA
Received 31 July 2003; accepted 31 March 2004
Abstract
Air transportation is a key strategic asset in that it provides access to markets and thereby enables the
economic development of nations. Thus, in order to maintain their competitiveness in a global economy,
countries must invest in air transportation infrastructure to ensure their ability to meet current and future
demand for aviation services. The objective of this paper is to develop and illustrate a methodology for
evaluating the strategic value of air transportation infrastructure, in particular the benefits associated with
the ability to react quickly to changes in the market. The hypothesis is that by recognizing and taking
advantage of this strategic value, it may be possible to design better policies for aviation infrastructure
delivery.
The methodology developed here uses system dynamics to model different strategies for infrastructure
delivery. These strategies are defined by three variables: the amount of capacity increase, the time to
deliver the capacity and the congestion threshold that triggers the need for capacity delivery. Monte
Carlo simulation is used to take into account multiple sources of uncertainty. The model shows that a
strategy of capacity delivery based on small increments and short response times can yield more benefits
than strategies that consider large capacity increases and long response times. Furthermore, in the specific
airport example considered here, it was found that a congestion threshold of 75% should be the trigger
for capacity enlargements if strategies based on small capacity increments and 1 or 5 years to increase
0040-1625/$ -
doi:10.1016/j.t
B Presented a
2003. Selected
* Correspond
E-mail add1 Tel.: +1 40
see front matter D 2006 Published by Elsevier Inc.
echfore.2004.03.011
t the 7th International Conference on Technology Policy and Innovation in Monterrey, Mexico, June 10th–13th,
for publication in a special volume of the journal Technological Forecasting and Social Change.
ing author. Tel.: +1 617 291 6352.
resses: [email protected] (B. Miller)8 [email protected] (J.-P. Clarke).
4 385 7206.
![Page 2: The hidden value of air transportation infrastructure](https://reader036.fdocuments.us/reader036/viewer/2022082522/575074701a28abdd2e947f6d/html5/thumbnails/2.jpg)
B. Miller, J.-P. Clarke / Technological Forecasting & Social Change 74 (2007) 18–35 19
capacity are considered. The lesson for decision-makers is that congestion delays must be addressed with
foresight.
D 2006 Published by Elsevier Inc.
Keywords: Investments in air transportation infrastructure; Strategic value of infrastructure; Air transportation
1. Introduction
Air transportation is a key strategic asset in that it provides access to markets and thereby enables
the economic development of nations and regions [1]. Thus, in order to maintain their
competitiveness in a global economy, countries must invest in air transportation infrastructure to
ensure their ability to meet current and future demand for aviation services.
Investments in air transportation infrastructure are difficult to evaluate for a variety of reasons, but
two are especially worth noting. First, investments in aviation infrastructure must be considered as part
of a wider national strategy that involves many other sectors [2]. Second, the size of these investments
is typically large and the time for implementation is also usually long. Thus, the benefits of the
investment may not be realized for many years [3]. Given these difficulties, investments in air
transportation infrastructure are often not implemented or are implemented too late relative to the
needs of society.
The methodology presented in this paper is based on the assumption that it is useful to consider
investments in aviation infrastructure not as an end in themselves, but rather as a way to provide
options to accommodate future growth scenarios. In general, current thinking considers the benefits of
infrastructure in terms of the function it was built to perform; however, there are at least three other
types of benefits that infrastructures can provide: a) the ability to respond quickly to changes in the
market, b) the ability to explore markets, and c) the ability to influence markets. By considering the
strategic value of these three benefits, decision-makers can better understand the overall benefits of
the infrastructure and justify its delivery.
2. Objective
The objective of this paper is to develop and illustrate a methodology for evaluating the strategic
value of air transportation infrastructure, i.e. the benefits associated with the ability to react quickly to
changes in the market, to explore new markets and to stimulate existing markets. The hypothesis is
that by recognizing and taking advantage of this strategic value, it may be possible to design better
policies for aviation infrastructure delivery.
The simulation developed in this study focuses primarily on capturing the benefits due to the
ability to react quickly to changes in the market. The simulation can be enhanced to also
incorporate the benefits from exploring and stimulating markets. These enhancements have not
been elaborated here mostly to simplify the calculations and the presentation of the results;
however, at the end of the paper, we indicate how the model could be expanded to incorporate
these other benefits.
![Page 3: The hidden value of air transportation infrastructure](https://reader036.fdocuments.us/reader036/viewer/2022082522/575074701a28abdd2e947f6d/html5/thumbnails/3.jpg)
B. Miller, J.-P. Clarke / Technological Forecasting & Social Change 74 (2007) 18–3520
The next section explains the methodology employed to analyze the strategic value of air
transportation infrastructure. Then, numerical results and sensitivity analysis for the specific example
considered here are presented. The paper concludes with a summary of the main points and a discussion
of the implications of the results for policy-making.
3. Methodology to calculate the strategic value of aviation infrastructure
The methodology presented here is based on a combination of system dynamics and Monte Carlo
simulation. The first step is to model the infrastructure delivery problem using system dynamics tools.
The main advantage of this approach is that it captures the feedback loops and delays that occur in
complex systems, such as air transportation. The next step is to determine different strategies for
infrastructure delivery and implement them in the system dynamics model. Finally, Monte Carlo
simulation is used to take into account multiple sources of uncertainty.
3.1. Modeling the infrastructure delivery problem with system dynamics
3.1.1. Overview of the model
The example considered in this study is a hypothetical yet common situation in many airports around
the world. Here, it is assumed that an element of the air transportation infrastructure (e.g. a runway or a
passenger building) is reaching saturation, and, thus, depending on the level of traffic, may lead to
congestion (see Fig. 1).
In this particular example, Runway capacity2 is the limiting factor that leads to congestion. As
demand for air travel (Aircraft per hour) increases, the total number of aircraft requesting service on this
runway (Total aircraft) also increases. If Runway capacity is held constant, the increase in demand
slowly leads to Congestion, which raises the direct operating costs of airlines (Airline congestion cost).
The higher operating costs are passed on to the passenger in terms of higher airfares (Airfare impact)
and this leads to less demand for travel (Congestion cost loop). In addition, congestion decreases the
level of service by lengthening passenger travel time (Level of service impact) which also results in
less demand for aviation services (Passenger comfort loop). Once Congestion reaches a certain limit
(Congestion threshold), a certain amount of capacity (Capacity increase) is delivered after a certain
period of time (Years to increase capacity). These three variables (Congestion threshold, Capacity
increase, and Years to increase capacity) are specified by the user and they characterize the different
infrastructure delivery strategies. Once capacity is added to the runway, Congestion decreases, thus,
stimulating demand by reducing the Airfare impact and Level of service impact. The model assumes
that congestion occurs only at a given number of Peak hours per year.
There are two main outputs from this model. The first are the benefits accrued to the airport
operator in terms of Airport revenues. Here, it is assumed that they consist mainly of Landing fees
paid by the airlines and passenger facility charges (PFC) paid by each traveler. The second output is
the cost of infrastructure construction (Delivery cost). Together, these two outputs determine the cash
flows of the airport operator and form the basis for calculating the net present value (NPV) for the
different strategies.
2 Model variables are written in Italics throughout the whole paper.
![Page 4: The hidden value of air transportation infrastructure](https://reader036.fdocuments.us/reader036/viewer/2022082522/575074701a28abdd2e947f6d/html5/thumbnails/4.jpg)
Fig. 1. System dynamics model of the hypothetical situation considered in this study.
B. Miller, J.-P. Clarke / Technological Forecasting & Social Change 74 (2007) 18–35 21
3.1.2. Main relationships of the model
The main relationships used in the model are explained below:
a) Congestion
Congestion in this model is defined as the waiting time, Wq, for each user (aircraft) that wants to land
on the runway. The waiting time is obtained by modeling this situation as a M/G/1 queuing system (i.e. a
system with Poisson demand, any type of service time, one server and infinite capacity) [4]:
Wq ¼kd 1
l
� �2þ r2
t
� �
2d 1� qð Þ ð1Þ
where k is the average demand rate over a specified period of time determined by the Poisson
distribution, l is the capacity of the system over the same period of time, rt is the standard deviation of
service times and q is the butilization ratioQ. The metric for congestion used in this study is bhours perpeak hourQ, i.e. hours of waiting time per peak hour of traffic.
The utilization ratio q can be defined as the average demand rate over system capacity [5]:
q ¼ kl
ð2Þ
In the model, k is given by Total aircraft and l is Runway capacity. A key characteristic of this
queuing system is that as k approaches l, i.e. as demand approaches capacity, the numerator of Eq. (1)
![Page 5: The hidden value of air transportation infrastructure](https://reader036.fdocuments.us/reader036/viewer/2022082522/575074701a28abdd2e947f6d/html5/thumbnails/5.jpg)
50%
55%
60%
65%
70%
75%
80%
85%
90%
95%
98%
Utilization ratio
Co
ng
esti
on
[hr/
hr]
0.00
0.10
0.20
0.30
0.40
0.50
0.60
Fig. 2. Waiting time (in terms of bhours of waitingQ per hour) of an M/G/1 system as a function of utilization ratio for the
parameters (k, l and r) chosen in this model.
B. Miller, J.-P. Clarke / Technological Forecasting & Social Change 74 (2007) 18–3522
tends to zero and the waiting time grows non-linearly [5]. For our example, this means that when aircraft
demand per hour approaches runway capacity per hour, and, hence the utilization ratio approaches 1,
Congestion becomes critical (see Fig. 2):
b) Annual demand growth rate
Demand for air travel is very volatile and cyclical [6]. In order to capture this behavior, Annual
demand was modeled as a mean reverting stochastic process of the form shown in Eq. (3):
dx ¼ gd X � xð Þdt þ rddz ð3Þ
where dx is the change in demand x over a time interval dt, g is the speed of reversion, i.e. a metric that
represents how fast the process returns to its long-term trend, X is the level to which x tends to revert, r is
the variance parameter and dz represents a Wiener process, i.e. a normally distributed random process (for
more details, please consult [7]). This equation was calibrated with historical data for air travel demand in
the Unites States between 1979 and 2001 contained in the Form 41 database [8] and using the method
Annual growth rate0.2
0.1
0
-0.1
-0.20 5 10 15 20 25 30 35 40 45 50
Time (Year)
Annual growth rate : sample run Dmnl
Annual growth rate : sample run 2 Dmnl
Fig. 3. Sample paths for air travel demand growth rate as modeled in this study.
![Page 6: The hidden value of air transportation infrastructure](https://reader036.fdocuments.us/reader036/viewer/2022082522/575074701a28abdd2e947f6d/html5/thumbnails/6.jpg)
B. Miller, J.-P. Clarke / Technological Forecasting & Social Change 74 (2007) 18–35 23
outlined in Ref. [7]. The long-term annual demand growth rate found was on the order of 3.8% per year.
Two sample paths of this mean reverting process are illustrated in Fig. 3:
c) Airfare impact and Level of service impact
The Airfare impact and the Level of service impact on air travel demand were determined using the
concepts of price and time elasticities, respectively [9]. The price elasticity of demand is defined as the
percentage change in total demand that occurs with a 1% change in average airfare. Similarly, time
elasticity of demand is the percentage change in total travel demand that occurs with a 1% change in
travel time. In this study, the Airfare impact is the change in demand from a percentage change in
average travel cost times price elasticity (see Eq. (4)):
Airfare impact ¼ epricedDCostTravel ð4Þ
where eprice is the price elasticity of demand and DCostTravel is the percentage increase in travel cost due
to the congestion costs that the airlines are able to pass on to the consumers. Historically, price elasticity
of demand has been estimated at approximately �1.6 for leisure passengers and on the order of �0.8 forbusiness passengers [9]. DCostTravel is given by Eq. (5):
DCostTravel ¼CostCongestion=passenger
AirfareAveragedCostTransfer ð5Þ
where CostCongestion/passenger is the average airline operating cost per hour divided by an average
number of passengers per flight, AirfareAverage is the average air fare charged per passenger, and
CostTransfer is the percentage of CostCongestion that the airline is able to pass on to the travelers.
The Level of service impact is the change in demand from a percentage change in average travel time
times time elasticity (see Eq. (6)):
Level of service impact ¼ eTimedDTimeTravel ð6Þwhere etime is the time elasticity of demand and DTimeTravel is the percentage change in travel time due to
congestion. Time elasticity of demand is nominally considered to be around �0.8 for leisure passengers
and approximately �1.6 for business passengers [9].
d) Capacity delivery costs
In this model, airport capacity is given in terms of aircraft per hour. Capacity delivery costs are
obtained by multiplying Capacity increase times a unit capacity delivery cost in US$/aircraft per hour.
Here, the unit capacity delivery cost is assumed to be US$5 million/aircraft per hour. For example,
this means that an increase of 20 aircraft per hour (i.e. 50% of the assumed runway capacity of the
airport in the model) requires an investment of US$100 million. Runway construction costs vary
substantially from airport to airport, ranging anywhere from US$60 million to US$300 million, and
even more in some particular cases [10]. Thus, the unit capacity delivery cost of US$5 million/aircraft
per hour is just meant to be an approximation to costs in the real world.
e) Congestion threshold, Capacity increase, Years to increase capacity
These constants are the main control parameters to specify the different infrastructure development
strategies. Congestion threshold is the maximum level of congestion allowed before the airport
operator decides to add more capacity. Capacity increase is the amount of capacity to be added once
the decision has been taken to deliver more capacity. Finally, Years to increase capacity determine the
delay in supplying the desired capacity once the decision has been made to deliver it.
![Page 7: The hidden value of air transportation infrastructure](https://reader036.fdocuments.us/reader036/viewer/2022082522/575074701a28abdd2e947f6d/html5/thumbnails/7.jpg)
B. Miller, J.-P. Clarke / Technological Forecasting & Social Change 74 (2007) 18–3524
3.1.3. Model calibration
The numbers used to calibrate the model are meant to illustrate a realistic situation but they do not
represent an actual airport. The airport in this study is assumed to be a one runway facility that
serves primarily narrow-body aircraft. The current runway capacity was set at 40 aircraft per hour.
Landing fees were estimated at $200 per aircraft based on data in Ref. [5] and the typical weight of
narrow-body aircraft. It is further assumed that congestion occurs only at peak hours and there are
1000 peak hours in a year. The simulation time period is in years and each run covers 50 years.
3.1.4. Infrastructure delivery strategies
For the purposes of this study, each infrastructure delivery strategy is defined by three parameters:
1) Congestion threshold
This constant determines the maximum level of congestion allowed (btriggerQ) before the airport
operator decides to put more capacity in place. A low threshold reflects a proactive strategy by which the
operator intends to have enough capacity to meet demand and, thus, be able to capture more revenues.
The disadvantage of such approach is that if demand does not grow as expected, the new capacity may
remain unused. A high threshold represents a reactive strategy. Here, an airport operator would wait until
it is obvious that the current levels of demand require more capacity. The disadvantages of this strategy
are the negative effects of congestion on travel demand explained above.
Each congestion threshold corresponds to a given utilization ratio, q, as determined by Eq. (1) and
shown in Fig. 2. Five congestion thresholds were considered and are presented in Table 1.
2) Capacity increase
Another strategic decision by the airport operator is how much capacity to add. In order to simplify
the analysis, only three cases were considered: 10%, 25% and 50% increase of existing capacity. The
first alternative (10%) represents a very incremental approach, in which little additions to capacity are
made at any given time. For example, modifications to existing approach procedures and/or better
sequencing of arriving aircraft enabled by automation support tools may lead to these small increments.
The second alternative (25%) may include the installation or upgrade of Instrument Landing Systems
(ILS) and/or expansion of taxi-ways and holding areas, for example. The third case (50%) represents a
larger investment like a completely new taxi-way or runway.
The advantage of small capacity increments is that demand may be matched more closely to capacity,
thus, avoiding the delivery of unnecessary infrastructure. In addition, capital expenditures are smaller
and spread over time, which may be easier to finance and justify than large investments performed at
once. Even though it may not be entirely realistic to have a purely incremental strategy throughout the
life of an airport, as it is not possible to add incremental capacity by building little pieces of runway at a
time, for example, this strategy illustrates a limiting case. The medium and large capacity increments
Table 1
Relationship between congestion threshold and utilization ratio for the example analyzed in this study
Congestion threshold (hr/peak hr) Utilization ratio, q (%)
0.019 60
0.029 70
0.038 75
0.113 90
0.239 95
![Page 8: The hidden value of air transportation infrastructure](https://reader036.fdocuments.us/reader036/viewer/2022082522/575074701a28abdd2e947f6d/html5/thumbnails/8.jpg)
Table 2
Hypothetical relationship between Years to increase capacity and level of preparedness for the process of building a runway
Years to increase capacity Level of preparedness
A priori investments Outstanding tasks
1 – Purchase land – Install navigation aids
– Permitting process completed
– Runway is built
5 – Own land – Build runway
– Permitting process completed – Install navigation aids
10 – Purchase land – Permitting process
– Build runway
– Install navigation aids
15 – Purchase land
– Permitting process
– Build runway
– Install navigation aids
B. Miller, J.-P. Clarke / Technological Forecasting & Social Change 74 (2007) 18–35 25
lead to more significant investments at particular points in time. These are more representative of what is
seen in practice, as airport capacity enhancements projects tend to be large.
3) Years to increase capacity
The time that it takes to increase capacity reflects how fast the airport operator can react to changes in
the market place. Four cases are considered in this study: 1, 5, 10 and 15 years. It is assumed that the
time to increase capacity depends on the blevel of preparednessQ of the operator to respond to changes. Ashort time to increase capacity means that the airport operator has invested resources a priori to prepare
its facilities for expansion. If we consider the example of building a new runway, the different Years to
increase capacity may correspond to the level of preparedness shown in Table 2.
The implication with these assumptions is that in order to be able to respond faster, the operator of the
facility must have invested some resources beforehand. Two important considerations arise from this
observation. First, the level of a priori investment depends on the benefits that reacting quickly brings.
Consequently, if the purpose of the a priori investment is to maximize the economic returns of the whole
project, the maximum amount that somebody should be willing to invest a priori for the ability to react
quickly is the difference between the benefits derived from reacting quickly compared to the benefits
under the bbusiness-as-usualQ scenario.The second consideration is that the a priori investment may lower the cost of reacting quickly in the
future. For example, buying land for another runway may be less expensive before traffic levels require
the addition of this extra runway. If the airport waits until its demand requires another runway, the
current owner of the land intended for the extra runway is likely to increase the price of the land because
Table 3
Differences in capacity delivery cost for the Moderate cost difference scheme
Years to increase capacity Reduction in capacity delivery cost/unit of capacity (%)
1 �505 �2510 0
15 +25
![Page 9: The hidden value of air transportation infrastructure](https://reader036.fdocuments.us/reader036/viewer/2022082522/575074701a28abdd2e947f6d/html5/thumbnails/9.jpg)
Capacity increase (% of current capacity)
1
5
10
15
60% 70% 75% 90%
10% 25%
50%
Years to increasecapacity(Years)
95%
Congestion threshold(utilization ratio)
Fig. 4. Matrix of the delivery strategies analyzed in the study.
B. Miller, J.-P. Clarke / Technological Forecasting & Social Change 74 (2007) 18–3526
this situation represents a seller’s market. Consequently, the premium associated with the a priori
investment to obtain the ability to react quickly may be compensated with lower capacity delivery costs.
In order to illustrate this point, two different construction cost schemes were considered. The first one,
the so-called bZero cost differenceQ, assumes no difference in capacity delivery costs. The second one,
the so-called bModerate cost differenceQ, assumes the following reductions in capacity delivery costs per
unit of capacity (see Table 3).
Notice that there is no difference in delivery cost for 10 years to increase capacity because this is the
bbusiness-as-usualQ scenario. In addition, it is assumed that having a longer time to deliver capacity (15
years) increases the delivery costs.
3.1.5. Summary of delivery strategies
The study considered all possible combinations of the above parameters (Congestion threshold,
Capacity increase and Years to increase capacity) for a total of 60 delivery strategies (see Fig. 4). Even
though it may lead to some unlikely scenarios, such as adding 50% of capacity every year, the test
matrix does span a representative sample of realistic strategies with some limiting cases. Typical
strategies seen in the real world arguably fall between 25% and 50% Capacity increase with 10 to 15
Years to increase capacity, with a Congestion threshold of 90% to 95%.
3.1.6. Monte Carlo simulation
Monte Carlo simulation is used to incorporate multiple sources of uncertainty into the calculations.
Here, the main uncertainties considered were related to Annual demand growth rate, Air fare impact and
Level of service impact. Table 4 shows the variables selected for the Monte Carlo simulation along with
their assumed probability distributions and limiting values.
Table 4
Variables considered for the Monte Carlo simulation and their assumed probability distributions
Variable Units Probability distribution Min. value Max. value
Annual demand growth rate seed N/A Uniform 1 10,000
Average travel time Hours Uniform 2 4
Time elasticity N/A Uniform �1.6 �0.8Price elasticity N/A Uniform �1.6 �0.8Costtransfer % Uniform 60% 90%
![Page 10: The hidden value of air transportation infrastructure](https://reader036.fdocuments.us/reader036/viewer/2022082522/575074701a28abdd2e947f6d/html5/thumbnails/10.jpg)
B. Miller, J.-P. Clarke / Technological Forecasting & Social Change 74 (2007) 18–35 27
As explained above, Annual demand growth rate is modeled stochastically. In order to get different
random distributions of this variable, the seed parameter is changed between the limits shown in Table
4. Average time refers to the assumed average trip time to the hypothetical airport, which is the basis to
calculate the time sensitivity of demand and, hence, the Level of service impact. The time and price
elasticities determine the impact of congestion on travel demand because of increased travel time and
higher airfares. The elasticities are assumed to be between �1.6 and �0.8 [9]. Costtransfer reflects the
proportion of the increased operating costs due to congestion that the airlines are able to pass on to the
passengers. It is assumed that this value oscillates between 60% and 90%.
A Monte Carlo simulation was run for each of the delivery strategies shown in Fig. 4. Each
simulation consisted of 7500 runs. The output of each simulation is a distribution of Airport revenues
and Delivery costs, which are then used to calculate the net present value of each delivery strategy.
3.1.7. Evaluation of the delivery strategies
The Monte Carlo simulation generates a distribution of Airport revenues and Delivery costs for
each delivery strategy considered. For each run in the simulation, the present value of Airport
revenues and Delivery costs is calculated, thus, a distribution of present values of revenues and
present values of costs is obtained. The expected net present value for each delivery strategy i is the
difference between the mean of the present value of revenues minus the mean of the present value of
costs (see Eq. (7)):
Expected NPVi ¼ E Present Value ðRevenuesÞi� �
� E Present ValueðDelivery CostsÞi� �
ð7Þ
The standard deviation of the net present value for each strategy i is given by Eq. (8):
ri ¼ffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffir2Revenues;i þ r2
Del:Costs;i þ 2dCovRevenues;i;Del:Costs;i
qð8Þ
where rRevenues,i and rDel.Costs,i are the standard deviations of the present values of Airport revenues and
Delivery costs for strategy i, respectively, and CovRevenues,i; Del.Costs,i is the covariance between the
present value of Airport revenues and Delivery costs for strategy i.
The calculation of the present values requires the selection of a discount rate. For the purposes of this
study, a discount rate of 10% was chosen. There is always some uncertainty about what the discount rate
should be, therefore, sensitivity analyses were also performed.
In order to determine the strategic value of being able to react quickly, the expected NPV for each
delivery strategy was compared to a baseline case that exemplifies a bbusiness-as-usualQ situation. Thebaseline case was assumed to be the strategy were 50% of the current capacity is delivered every 10
years after a congestion threshold of 90% has been reached. Consequently, the expected value of quick
reaction for strategy i is given by Eq. (9):
Expected Value of quick reactioni ¼ Expected NPVi � Expected NPVBaseline ð9Þ
Remember that the expected value of quick reaction is also the maximum amount of a priori
investment that an airport operator is willing to spend to implement strategy i. The standard deviation of
the expected value for strategy i is given by Eq. (10):
rExpected Value of quick reaction ¼ffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffir2i þ r2
Baseline
qð10Þ
![Page 11: The hidden value of air transportation infrastructure](https://reader036.fdocuments.us/reader036/viewer/2022082522/575074701a28abdd2e947f6d/html5/thumbnails/11.jpg)
B. Miller, J.-P. Clarke / Technological Forecasting & Social Change 74 (2007) 18–3528
where ri and rBaseline are the standard deviations of the expected NPV of strategy i and the expected
NPV of the baseline scenario, respectively.
For delivery strategies that consider 15 years to increase capacity, Eqs. (9), (10) would compute
the bexpected value of delayed reactionQ and its standard deviation, respectively, as opposed to the
value to react quickly. These cases are considered here because there may be advantages to delaying
investments.
4. Results
4.1. Zero cost difference
The results for the situations where there are no cost difference for delivering capacity quicker are
shown below. For the case of 1 year to deliver capacity, the results suggest that strategies involving small
increments (10% capacity increase) lead to higher expected values to react quickly than strategies with
larger capacity increments (see Fig. 5). For example, for a Congestion threshold of 90%, the ability to
react quickly provides benefits on the order of $14.2 millionF14 million. Thus, the airport operator
should be willing to spend up to this amount a priori to have the ability to react quickly. Large increases
in capacity (25% or 50% capacity increase) generate, on average, negative expected values for the ability
to react quickly. The intuition behind this is that larger expansions may result in over-capacity that is not
utilized until some years after it has been delivered and, thus, the investment is more difficult to recover.
The results further show a large standard deviation and a strong dependence on the Congestion
threshold. The large standard deviation can be explained by the fact that since capacity is being delivered
very quickly, the system is better able to accommodate increases in demand. This is a reinforcing loop in
which the system delivers more capacity as demand grows, thereby stimulating even more traffic. When
the time to deliver capacity is longer, the system cannot react as quickly to changes in demand and,
therefore, the variability of traffic is reduced. The dependence of the results on the Congestion threshold
Fig. 5. Results showing the expected value of quick reaction for strategies with Years to increase capacity equal to 1 as a
function of increases in capacity and utilization ratio (Congestion threshold) with the assumption that there is no difference in
the delivery costs.
![Page 12: The hidden value of air transportation infrastructure](https://reader036.fdocuments.us/reader036/viewer/2022082522/575074701a28abdd2e947f6d/html5/thumbnails/12.jpg)
Fig. 6. Results showing the expected value of quick reaction for strategies with Years to increase capacity equal to 5 as a
function of increases in capacity and utilization ratio (Congestion threshold) with the assumption that there is no difference in
the delivery costs.
B. Miller, J.-P. Clarke / Technological Forecasting & Social Change 74 (2007) 18–35 29
arises from the way that present values are determined. Higher Congestion threshold means that capital
expenditures come further in the future and, thus, they get discounted more. The extra revenues from an
earlier capacity expansion are not large enough to offset the higher present cost of the earlier investment.
Therefore, with higher Congestion threshold and 1 year to increase capacity, the expected value of the
ability to react quickly increases.
As the time to deliver capacity increases from 1 to 5 years, small capacity increments still lead to
higher expected values than larger capacity increments (see Fig. 6). Notice, however, that the standard
deviation and the dependence on the Congestion threshold are less than in the case of 1 year to increase
capacity. Because the response time to deliver capacity is longer, demand growth has is limited and,
therefore, it does not vary as much as when capacity can be delivered within a year. Furthermore, the
longer time to add capacity allows demand to grow to levels that make more use of the new capacity.
Fig. 7. Results showing the expected value of delayed reaction for strategies with Years to increase capacity equal to 15 as a
function of increases in capacity and utilization ratio (Congestion threshold) with the assumption that there is no difference in
the delivery costs.
![Page 13: The hidden value of air transportation infrastructure](https://reader036.fdocuments.us/reader036/viewer/2022082522/575074701a28abdd2e947f6d/html5/thumbnails/13.jpg)
B. Miller, J.-P. Clarke / Technological Forecasting & Social Change 74 (2007) 18–3530
Therefore, on average, the expected value to react quickly is larger for strategies that have 5 years to
increase capacity compared to strategies with 1 year to increase capacity.
For longer times to deliver capacity (15 years), similar observations as in the previous cases can be
made. Smaller capacity increases lead to higher expected values for the ability to delay reaction than
larger capacity increases (see Fig. 7). Furthermore, the variability of the results and the dependence on
the Congestion threshold are also less. Notice that the expected value of delayed reaction is positive in
almost all cases. Because it takes so long to deliver the new capacity, demand is very likely to grow to
levels where the added capacity will be completely utilized in almost all cases, thus, recovering the
investment very quickly.
In summary, for a capacity delivery scheme in which there is no cost reductions associated with
delivering capacity quickly, the strategy that results in the highest value for the ability to react quickly is
to increase capacity in small increments (10% capacity increase) with 5 years to deliver capacity,
regardless of the congestion threshold. Lower time to increase capacity, i.e. 1 year, may lead to positive
values for the ability to react quickly only if the congestion threshold is high. For strategies with 15 years
to deliver capacity, the expected value of delayed reaction is similar to the expected value of the ability to
react quickly with 5 years to deliver capacity, independent of the congestion threshold.
4.2. Moderate cost difference
The results for the cases where there is a moderate difference in the delivery costs per unit of capacity
for strategies with lower time to increase capacity are shown below. For example, for strategies with 1
year to deliver capacity, the ability to react quickly becomes very valuable in all cases (see Fig. 8).
Similarly to what was shown in the previous sub-section, the expected value of the ability to react
quickly increases and has lower variability with smaller capacity increases.
Notice that the expected value of quick reaction depends significantly on the Congestion threshold. In
fact, there seems to be an optimal Congestion threshold of approximately 75% utilization ratio for all of
the capacity increases with 1 year to deliver capacity. This is explained by the observation that
Fig. 8. Results showing the expected value of quick reaction for strategies with Years to deliver capacity equal to 1 as a function
of increases in capacity and utilization ratio (Congestion threshold) with the assumption that there is moderate difference in the
delivery costs.
![Page 14: The hidden value of air transportation infrastructure](https://reader036.fdocuments.us/reader036/viewer/2022082522/575074701a28abdd2e947f6d/html5/thumbnails/14.jpg)
Fig. 9. Results showing the expected value of quick reaction for strategies with Years to deliver capacity equal to 5 as a function
of increases in capacity and utilization ratio (Congestion threshold) with the assumption that there is moderate difference in the
delivery costs.
B. Miller, J.-P. Clarke / Technological Forecasting & Social Change 74 (2007) 18–35 31
Congestion thresholds lower than 75% probably lead to more capacity delivered than what is needed to
meet demand, thus resulting in expensive over-capacity. Moreover, higher Congestion thresholds imply
that the negative effects of increased congestion are larger than the savings in present delivery costs
accrued by delaying the investment. Thus, if it takes 1 year to deliver capacity, the optimal strategy for
an airport operator would be to increase capacity in small to medium increments (10% or 25%) with a
Congestion threshold of 75%.
Similar observations can be made when there are 5 years to deliver capacity (see Fig. 9). Here, the best
strategies would also be to deliver small or medium increments of capacity with a Congestion threshold
Fig. 10. Results showing the expected value of delayed reaction for strategies with Years to deliver capacity equal to 15 as a
function of increases in capacity and utilization ratio (Congestion threshold) with the assumption that there is moderate
difference in the delivery costs.
![Page 15: The hidden value of air transportation infrastructure](https://reader036.fdocuments.us/reader036/viewer/2022082522/575074701a28abdd2e947f6d/html5/thumbnails/15.jpg)
B. Miller, J.-P. Clarke / Technological Forecasting & Social Change 74 (2007) 18–3532
of 75%. Notice, however, that the expected values to react quickly in these cases are much lower than in
the case when there is 1 year to deliver capacity. This is probably a reflection of the assumption that the
delivery cost per unit of capacity is less for strategies with 1 year to increase capacity; however,
remember that in order to gain the ability to react within 1 year, the airport operator would also have to
make a larger a priori investment. Thus, the net benefits of both strategies may be comparable.
For strategies with 15 years to deliver capacity, the value of delayed reaction is positive for small and
medium increments in capacity (see Fig. 10). Contrary to the two cases discussed above, there is not an
optimal Congestion threshold here. The only observation that can be made is that a higher Congestion
threshold seems to yield higher values of delayed reaction. Notice that, overall, the expected value of
delayed reaction is much lower than the expected value to react quicklywith 1 or 5 years to deliver capacity.
In summary, if there are moderate cost reductions associated with faster capacity delivery, the
optimal policies would be to deliver small to medium capacity increases with a congestion threshold
of approximately 75%. The strategies with 1 year to deliver capacity generate the most expected
value of quick reaction, but the net benefits may be comparable to strategies with 5 years to increase
capacity because the a priori investment for being able to react within 1 year should be larger.
5. Sensitivity analysis
The main reason to perform sensitivity analysis in this study is to determine the effect of changes in
the discount rate on the expected values of the ability to react quickly or delay reaction. The other
principal sources of uncertainty are taken into account in the Monte Carlo simulation and require no
further testing. The sensitivity analysis measures the percentage change on the expected value to react
quickly or delay reaction due to a 1% change in the discount rate. A sensitivity on the order of 1 means
that the results are very sensitive and a sensitivity of zero denotes no impact of the discount rate on the
results. A negative sensitivity implies that the change is in the opposite direction as the change in the
discount rate.
The sensitivity analysis was performed by considering the effect of a �20% and +20% change in
the discount rate, i.e. changes due to a discount rate of 8% and of 12%, respectively (recall that the
Fig. 11. Effect of a discount rate of 8% on the value to react quickly for all strategies considering 5 years to deliver capacity.
![Page 16: The hidden value of air transportation infrastructure](https://reader036.fdocuments.us/reader036/viewer/2022082522/575074701a28abdd2e947f6d/html5/thumbnails/16.jpg)
Fig. 12. Effect of a discount rate of 12% on the value to react quickly for all strategies considering 5 years to deliver capacity.
B. Miller, J.-P. Clarke / Technological Forecasting & Social Change 74 (2007) 18–35 33
baseline discount rate was 10%). The analysis was performed on all strategies with 5 years to deliver
capacity.
Fig. 11 shows the sensitivity to a discount rate of 8%. In general terms, the sensitivity of the
results is very high and this sensitivity increases with larger capacity increments and with decreasing
congestion thresholds. For small capacity increments, the sensitivity is on the order of �0.9 for low
congestion thresholds and 0.1 for a congestion threshold of 95%. Large capacity increments show
high sensitivity, especially the case for a congestion threshold of 60% which has a sensitivity on the
order of �35.It is not surprising that the larger capacity increments are more sensitive to the discount rate
because they imply the largest capital expenditures and, thus, their absolute change in magnitude is
larger. Lower congestion thresholds mean that there may be more investments, all else held equal, and,
therefore, the absolute change in the magnitude of the investments will also be larger.
The sensitivity to a discount rate of 12% is shown in Fig. 12. The same observations as for the case of
an 8% discount rate hold: sensitivity is very high and it increases with larger capacity increments and
lower congestion thresholds.
The sensitivity analysis clearly shows that the choice of discount rate is of critical importance. This
is an aspect that deserves further investigation; however, rather than a weakness of the system
dynamics and Monte Carlo simulation methodology presented here, the high sensitivity to the discount
rate is a reflection of the great care that must be taken when using discounted cash flow and net
present value to evaluate investments. Furthermore, this analysis shows that larger investments are
more sensitive to the discount rate than smaller investments, which may be a further argument towards
smaller-scale capacity enhancements.
6. Conclusions
The model results suggest that the strategic value of air transportation infrastructure can be significant.
By adopting strategies that take advantage of the ability to react quickly to changes in the market, the value
of a piece of infrastructure can be increased. In this study, it was shown that a strategy of capacity delivery
based on small increments and short response times can yield more benefits than strategies that consider
![Page 17: The hidden value of air transportation infrastructure](https://reader036.fdocuments.us/reader036/viewer/2022082522/575074701a28abdd2e947f6d/html5/thumbnails/17.jpg)
B. Miller, J.-P. Clarke / Technological Forecasting & Social Change 74 (2007) 18–3534
large capacity increases and long response times; however, the ability to react quickly implies an a priori
investment. The difference between the expected value from the strategy with the ability to react quickly
and the bbusiness as usualQ strategy is the maximum that a rational investor should be willing to invest a
priori. The strategic value of reacting quickly increases if there is a moderate cost reduction in the delivery
costs as compared to strategies with long time to increase capacity.
A critical decision in any infrastructure capacity investments is when to begin work to add the capacity.
This study shows that there may be an optimal congestion threshold to begin adding capacity depending on
what strategy is being followed. In the specific airport example considered here, it was found that a
Congestion threshold of 75% should be the trigger for capacity enlargements if strategies based on small
capacity increments and 1 or 5 years to increase capacity are considered. The lesson for decision-makers is
that congestion delaysmust be addressedwith foresight. It may be too late to do something once congestion
becomes critical. Thus, depending on the expectations for future growth in air travel, the value of being able
to react quickly to changes in the market may be substantial.
The methodology described here can be expanded to evaluate the other two components of the strategic
value of air transportation infrastructure identified above, i.e. the ability to create and to stimulate markets.
The key is to introduce these processes into the system dynamics model, because once this is
accomplished, theMonte Carlo simulation and the evaluation of strategies as described above can be used.
The ability to create markets can be investigated by simulating the demand for air travel within a
competitive market that allows airlines to enter and leave the market served by the airport in the system
dynamics model. The entry/exit of airlines would depend, among other factors, on the congestion levels at
the airport and, thus, on the infrastructure investments. Moreover, the ability to stimulate markets can be
analyzed by allowing airlines in the competitive market model to expand and contract flight schedules.
Again, congestion levels at the airport would be a key element in the airline’s decision to alter its
operations.
References
[1] ICAO, Impact of Civil Aviation on State’s Economies. World-wide CNS/ATM Systems Implementation Conference, Rio
de Janeiro, 1998.
[2] Christine Kessides, A review of Infrastructure’s Impact on Economic Development, Infrastructure and the Complexity of
Economic Development, Springer Verlag, Berlin, 1996.
[3] Anil Kapur, Airport Infrastructure: The Emerging Role of the Private Sector, World Bank Technical Paper, vol. 313, The
World Bank, Washington D. C., USA, 1995.
[4] Richard Larson, Amedeo R. Odoni, Urban Operations Research, Prentice-Hall, New Jersey, 1981.
[5] Richard de Neufville, Amedeo Odoni, Airport Systems — Planning, Design and Management, McGraw-Hill, 2003.
[6] Steve Skinner, Alex Dichter, Paul Langley, Hendrik Sabert, Managing Growth and Profitability across Peaks and Troughs
of the Airline Industry Cycle — An Industry Dynamics Approach, in: Gail F. Butler, Martin R. Keller (Eds.), Handbook of
Airline Finance, MacGraw-Hill, 1999.
[7] Avinash K. Dixit, Robert S. Pindyck, Investment under Uncertainty, Princeton University Press, Princeton, New Jersey,
1994.
[8] USDOT, Form 41, US Department of Transportation, Bureau of Transportation Statistics, Office of Airline Information,
1979–2001.
[9] Peter Belobaba, Characteristics of Air Transportation Markets and Demand for Air Travel. Lecture notes from The Airline
Industry course taught at the Massachusetts Institute of Technology, 2001.
[10] FAA, Aviation Capacity Enhancement Plan, Federal Aviation Administration, Office of System Capacity, Washington,
D. C, 1992–2001, Available at: http://www1.faa.gov/ats/asc/ACE.html.
![Page 18: The hidden value of air transportation infrastructure](https://reader036.fdocuments.us/reader036/viewer/2022082522/575074701a28abdd2e947f6d/html5/thumbnails/18.jpg)
B. Miller, J.-P. Clarke / Technological Forecasting & Social Change 74 (2007) 18–35 35
Bruno Miller finished a doctoral degree in Air Transportation Systems at the Department of Aeronautics and Astronautics at
the Massachusetts Institute of Technology in Cambridge, MA, United States in June, 2005. He is now with Northwest Airlines
in Eagan, Minnesota, United States.
John-Paul Clarke is an Associate Professor in the School of Aerospace Engineering at the Georgia Institute of Technology
(Georgia Tech) where his research and teaching address issues of optimization and robustness in Aircraft and Airline
Operations, Air Traffic Management and the Environmental Impact of Aviation.