The Feasibility of Synchronous Interconnection … Feasibility of Synchronous Interconnection ......

18
union for the co-ordination of transmission of electricity The Feasibility of Synchronous Interconnection between IPS/UPS and UCTE Matthias Luther Black Sea Regional Transmission Planning Project Tbilisi, Georgia, 6 December 2007 Supported by:

Transcript of The Feasibility of Synchronous Interconnection … Feasibility of Synchronous Interconnection ......

union for the co-ordination of transmission of electricity

The Feasibility of Synchronous Interconnection between IPS/UPS and UCTE

Matthias Luther

Black Sea Regional Transmission Planning Project

Tbilisi, Georgia, 6 December 2007Supported by:

The Feasibility of Synchronous Interconnection between IPS/UPS and UCTE

page 2 Matthias Luther, Tbilisi, 6 December 2007

Presentation Themes

Introduction

Project Organisation

Investigation Program

Preliminary Findings and Outlook

The Feasibility of Synchronous Interconnection between IPS/UPS and UCTE

page 3 Matthias Luther, Tbilisi, 6 December 2007

UCTE-IPS/UPS Study – three major questions to answer

Is a synchronous coupling of IPS/UPS with UCTE feasible?

What are the mandatory measures and requirements on both sides?

What are the associated costs?

Considering technical, organisational and legal issues the study has to answer the following questions:

Additionally, market aspects and environmental issues are building the conditional framework.

First priority: maintaining the present performance of the systems with respect to system security and reliability.

The Feasibility of Synchronous Interconnection between IPS/UPS and UCTE

page 4 Matthias Luther, Tbilisi, 6 December 2007

Facts and framework of the project

The three years investigation is a joint project under the responsibility of UCTE

The project focus on a synchronous coupling of IPS/UPS and UCTE

Additionally, the consideration of non-synchronous link projects is foreseen

Budget: approximately 10 million €

Nearly 100 experts from both sides involved

a unique synchronous transmission system under investigation

- with 900 GW installed generation capacity

- serving 700 million customers

- in 10 time zones

The Feasibility of Synchronous Interconnection between IPS/UPS and UCTE

page 5 Matthias Luther, Tbilisi, 6 December 2007

The UCTE-Consortium of 11 TSOs

The Feasibility of Synchronous Interconnection between IPS/UPS and UCTE

page 6 Matthias Luther, Tbilisi, 6 December 2007

The IPS/UPS Group of 8 Companies

The Feasibility of Synchronous Interconnection between IPS/UPS and UCTE

page 7 Matthias Luther, Tbilisi, 6 December 2007

Thema Datum Bereich

IPS/UPS: parallel operation of 13 power systems

power systems of UCTE

power systems of IPS/UPS

other power systems

IPS/UPS3401.200280

Inst. Capacity/[GW]Consumption/[TWh]Consumers/[mio]

UCTE5602.500430

The Feasibility of Synchronous Interconnection between IPS/UPS and UCTE

The Feasibility of Synchronous Interconnection between IPS/UPS and UCTE

page 8 Matthias Luther, Tbilisi, 6 December 2007

Mandatoryinterconnection

rules

System integration vs. System coupling

System Arules

System Brules

System Arules System B

UCTErules

IPS/UPSrules

Integration

Allocation of corresponding and further mandatory

• technical• organisational • legal

measures and rules on both sides.

System coupling:UCTErules

IPS/UPSrules

Coupling

The Feasibility of Synchronous Interconnection between IPS/UPS and UCTE

page 9 Matthias Luther, Tbilisi, 6 December 2007

UCTE-IPS/UPS study – common project organisation

PM / PM UCTE PM IPS/UPS

Project Representative Board (PRB)

Project Management Board (PMB)

Technical Aspects

WG 1:Steady StateAnalysis

WG 2:System Dynamics

WG 3:Power System Control

WG 4:Operation and Organization

WG 5:Legal Aspects

The Feasibility of Synchronous Interconnection between IPS/UPS and UCTE

page 10 Matthias Luther, Tbilisi, 6 December 2007

Initial time schedule and project phases

pre-phase

phase 2Verification

and Simulation

phase 1Model

Preparation

April 20

08

Final Rep

ort

• verification ofmodels

• power system simulations

• sensitivity analyses

• ToR• TEN-E

Application• Set up of

consortia• Cooperation

Agreement

• Project kick-off• survey of IPS/UPS

system• installation of

measurement devices

• power system measurements

• data collection• preparation of

models

• further analyses • evaluation ofresults

• identification of measures and theircosts

• presentation of results

• preparation of draftof final report

phase 3Assessmentand Results

finalphase

• final report • final accounting• end of project

2005 2006 2007

Conceptual

Report

2004 April 20

05

2008

“go” for

simulat

ions

The Feasibility of Synchronous Interconnection between IPS/UPS and UCTE

page 11 Matthias Luther, Tbilisi, 6 December 2007

Summary of Analysis ProgramSteady State Analysis

Load flow simulation of nominal and emergency conditions Estimation of interface transmission capacityIdentification of most probable load flow scenarios

System DynamicsTransient and small signal stability analysisImpact of IPS/UPS Emergency Control Automatics

Power System ControlPower / frequency controlVoltage / reactive power controlAnalysis of defense, disconnection and restoration plans

Operation and OrganizationAnalysis of operational practiceGuidelines for interface proceduresCoordination of operation (i. e. data exchange, congestion management, etc.)

Legal AspectsAnalysis of legal frameworksLegal case studiesIdentification of legal requirements for synchronous operation

The Feasibility of Synchronous Interconnection between IPS/UPS and UCTE

page 12 Matthias Luther, Tbilisi, 6 December 2007

Merged UCTE-IPS/UPS load flow study model

Load flow model includes representation for the planning horizon 2008 of

HV and UHV network (220 kV and above)

Important transmission lines of lower voltages (inter-system transmission lines, generator lines of large power stations)

Significant power stations in the interface area

Volume of load flow model

3,910 nodes

9,730 ties (lines and transformers)

770 generator nodes

Total load (winter peak load 10 GMT): 530 GW

The Feasibility of Synchronous Interconnection between IPS/UPS and UCTE

page 13 Matthias Luther, Tbilisi, 6 December 2007

Fran

ce

Transfer scenarios for load flow analysis

The Feasibility of Synchronous Interconnection between IPS/UPS and UCTE

page 14 Matthias Luther, Tbilisi, 6 December 2007

1 Cartelle2 Montearenas3 Aldeadavila4 San Sebastian de las Reyes5 Hernani6 Arkale7 Biescas8 Vic9 Rubi10 Benejama11 Puerto de la Cruz12 Cedillo13 Saucelle14 Albertville15 Tavel16 Saucats17 Tabarderie18 Lonny19 Uchtelfangen20 Hagenwerder21 Röhrsdorf22 Krajnik23 Wielopole24 Rogowiec25 Polaniec26 Györ27 Göd28 Sajoszöged29 Heviz30 Paks

31 Portile de Fier

32 Tantareni33 Blagoevgrad34 Ag.Stefanos35 Bassecourt36 Mettlen37 Lavorgo38 Soazza39 Rondissone40 Redipuglia41 Aurelia42 Brindisi43 Sorgente44 Avelgem

measuring devices:installedplanned

Wide Area Measuring System (WAMS)in UCTE

) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) )

) ) ) )

) ) )

(

(

(

( (

(

(

(

(

(

(

(

( (

(

( ( (

) ) )

) ) )

) ) )

( (

( (

( (

( (

(

time synchronisationby GPS

1

2

3

4 5 6 7

14

19

( (

(

2022 24

25

26

29

31

32

33

34

36

3738

40

35(

(

(

(

(

(

( ( (

( (

(

( (

44

( ( (

( ( (

( (

) ) ) ) ) ) ) ) ) ) ) ) ) ) )

( (

(

( (

(

4549

53

46 47 48 51 5250

15

16

17

18

21

39

4142

43

3

13

1110

912

23

2728

30

8

45 Oujda46 Ghazaouet47 Tlemcen48 Oued Sly49 Jijel50 Biskra51 El Aouinet52 Tajerouine53 Tataouine

The Feasibility of Synchronous Interconnection between IPS/UPS and UCTE

page 15 Matthias Luther, Tbilisi, 6 December 2007

Thu, 2006-02-09; 11:26:47 - Generation Outage: NUEVA ESCOMBRERAS (ES) dPa=-1200 MW

49,930

49,940

49,950

49,960

49,970

49,980

49,990

50,000

50,010

50,020

50,030

11:26:35 11:26:40 11:26:45 11:26:50 11:26:55 11:27:00 11:27:05 11:27:10 11:27:15 11:27:20

f [Hz]

Portile de Fier (RO)

SS Reyes (ES)

Uchtelfangen (D) Röhrsdorf (D)

49,93

49,95

49,97

49,99

50,01

50,03

0,00 2,00 4,00 6,00 8,00 10,00 12,00 14,00 16,00 18,00 20,00 22,00 24,00 26,00 28,00 30,00

Time [s]

freq

uenc

y [H

z]

ES/PORGERPortile de FierRöhrsdorf

Verification of UCTE dynamic study model:Outage of 1200 MW generation capacity in Spain (9 February 2006)

recordings simulations with study model

The Feasibility of Synchronous Interconnection between IPS/UPS and UCTE

page 16 Matthias Luther, Tbilisi, 6 December 2007

Preliminary findings

the necessity of the transmission network re-enforcements mainly dedicated to the IPS/UPS interface area

a higher potential risk for the dynamic stability of the coupled systems compared to the present performance in the individual synchronous areas

the adaptation and harmonisation of today’s existing defence and restoration plans in both synchronous areas

the need for interzonal, bilateral and multilateral agreements in order to setup a legal basis for a future reliable market platform with the focus on necessary organisational and operational issues under the framework of EU-market requirements and standards

The preliminary results underline that - even if a synchronous coupling mode of operation may appear viable under the implementation of certain pre-conditions - it can only be understood as a long term option for creating a joint electricity market platform.

The Feasibility of Synchronous Interconnection between IPS/UPS and UCTE

page 17 Matthias Luther, Tbilisi, 6 December 2007

Outlook: expected results in 2008An evaluation of the feasibility considering technical, operational, organisational and legal aspects based on available results

An allocation of necessary measures and their associated costs to be made on both sides of the interface.

An open outlook on non-synchronous system coupling possibilities aiming at an economic comparison for the investigated system coupling and an indication for the time horizon for a possible implementation for both variants.

The final study results may form a basis for further steps under supervision of the European Commission and other stakeholders.

Nevertheless, any decision need to be made by stakeholders taking into account the two further fundamental pillars

- reciprocity in market conditions

- compatibility of environmental standards including nuclear safety

The Feasibility of Synchronous Interconnection between IPS/UPS and UCTE

page 18 Matthias Luther, Tbilisi, 6 December 2007

Visit us: www.ucte-ipsups.org