The effect of Level of Effort EVT

61
The effect of Level of Effort EVT 1

description

The effect of Level of Effort EVT. introduction. LoE – This PMT is best used when it is impossible to determine progress for a task. - PowerPoint PPT Presentation

Transcript of The effect of Level of Effort EVT

Page 1: The effect of Level of Effort EVT

The effect of Level of Effort EVT

1

Page 2: The effect of Level of Effort EVT

introduction

• LoE – This PMT is best used when it is impossible to determine progress for a task.

• This only works in circumstances where the forecast dates are the same as the Baseline dates, and if you will never need to do work from a previous month which was not done

2

Page 3: The effect of Level of Effort EVT

Earned Value Techniques

• The CAM must allocate an appropriate Earned Value technique to the work

being performed

3

50 / 50

0/100

Physical % complete

Incremental Milestone

Equivalent Units

Level of Effort

50% is earned as soon as work starts & remaining 50% when work is complete

Nothing is earned until the work is complete.

A percentage method of assessment

Weighted budget values assigned to milestones within a work package

Places a given value on each unit completed

EV is equal to BCWS at all times

SOME EXAMPLE METHODS DESCRIPTION

Page 4: The effect of Level of Effort EVT

50/50 – xx/yy

When the work package begins in one period and completes in the next. No way of gaining credit between start and completion. Start and completion valued at 50% (or XX/YY). Completion should have criteria defined. Ideal when the plan consists of several short operations/activities.

4

30 70

P1 P2 P3 P4 P5

50 50

Total Budget 100

Page 5: The effect of Level of Effort EVT

0-100

No credit can be gained before completion.

Strictly limited to work packages starting and completing in the same reporting period.

5

P1 P2 P3 P4 P5

0 100

Page 6: The effect of Level of Effort EVT

Incremental Milestones

When work packages exceed 2 reporting periods. 1 milestone a month is ideal. Each milestone should have its own value defined discrete from others. This means that the milestones are not sequential.

6

P1 P2 P3 P4 P5

Budget 10

Budget 25

Budget 45

Budget 20

Total Budget 100

Page 7: The effect of Level of Effort EVT

Units Complete

For physical counts of product or outputs. Each element is given a value for completion and then the units calculated. This is ideal for measuring items like drawings.

7

P1 P2 P3 P4 P5

10 15 15 5 Budget Units 45Total £450

£10/unit

£100 £150 £150 £50

Page 8: The effect of Level of Effort EVT

Percent Complete

For long work packages > 3 periods – no quantities to count and no definable milestones. Forecast % complete at end of each period and apply to BAC.

Success criteria should be identified to justify the Percentage claimed. For example 25% can be claimed only when the first draft of a document has been completed.

8

Total Budget 1000

10%100

40%400

80%800

100%1000

Page 9: The effect of Level of Effort EVT

Apportioned EffortWhen activities are performed in support of other direct activities eg

Assembly work and the associated material. The effort is estimated and planned as a % of the production effort. There must be a method of determining this %.

9

50%

50%

Assembly work

Material Draw down

£10,000

£500,000

Page 10: The effect of Level of Effort EVT

Level of Effort•Level of Effort

When tasks are are difficult to quantify with respect to accomplishment. Supportive activities – no definable outputs – budget scheduled over the period of performance. EV based on passage of time – EV always equal to planned accomplishment. – There can be no schedule variance. Beware, where effort is not linear, may end up with cost variance if more hours booked than planned.

•LoE – This PMT is best used when it is difficult to track the progress of an activity.

•This only works in circumstances where the forecast dates are the same as the Baseline dates.

•Remember – Earned Value should be credited in the same way it is planned.

10

Page 11: The effect of Level of Effort EVT

Correctly profiled

11

Time nowBAC = 800

ACC BCWS = 400

ACC BCWP = 400

ACC ACWP = 400

Acc BCWS = 400Acc BCWP = 400Acc ACWP = 400Acc SV = 0Acc CV = 0

Page 12: The effect of Level of Effort EVT

Incorrectly profiled

• There may be circumstances where it may seem appropriate to re-forecast a LOE package before it starts.

• For example an activity was baselined to start month 1 and then forecasted to start now in month 5. The following slides explain the effect of this on the EV data.

12

Page 13: The effect of Level of Effort EVT

Incorrectly profiled Month 1

13

Time now

ACC BCWS = 100

ACC BCWP = 0

ACC ACWP = 0Acc BCWS = 100Acc BCWP = 0Acc ACWP = 0Acc SV = -100Acc CV = 0BAC = 800EAC = 800

Re-forecast start date

Page 14: The effect of Level of Effort EVT

Incorrectly profiled Month 2

14

Time now

ACC BCWS = 200

ACC BCWP = 0

ACC ACWP = 0Acc BCWS = 200Acc BCWP = 0Acc ACWP = 0Acc SV = -200Acc CV = 0BAC = 800EAC = 800

Page 15: The effect of Level of Effort EVT

Incorrectly profiled Month 3

15

Time now

ACC BCWS = 300

ACC BCWP = 0

ACC ACWP = 0Acc BCWS = 300Acc BCWP = 0Acc ACWP = 0Acc SV = -300Acc CV = 0BAC = 800EAC = 800

Page 16: The effect of Level of Effort EVT

Incorrectly profiled Month 4

16

Time now

ACC BCWS = 400

ACC BCWP = 0

ACC ACWP = 0Acc BCWS = 400Acc BCWP = 0Acc ACWP = 0Acc SV = -400Acc CV = 0BAC = 800EAC = 800

Page 17: The effect of Level of Effort EVT

Incorrectly profiled Month 5

17

Time now

ACC BCWS = 500

ACC BCWP = 500

ACC ACWP = 120Acc BCWS = 500Acc BCWP = 500Acc ACWP = 120Acc SV = 0Acc CV = 380BAC = 800EAC = 800

Page 18: The effect of Level of Effort EVT

WHY!

• This is a strange effect of Earned Value and the PMT of LOE. Although the actual performance has not been worth 500, LOE means that the total performance will equal the value of the Baseline (BCWS) at time now.

18

Page 19: The effect of Level of Effort EVT

Incorrectly profiled Month 6

19

Time now

ACC BCWS = 600

ACC BCWP = 600

ACC ACWP = 240Acc BCWS = 600Acc BCWP = 600Acc ACWP = 240Acc SV = 0Acc CV = 360BAC = 800EAC = 800

Page 20: The effect of Level of Effort EVT

Incorrectly profiled Month 7

20

Time now

ACC BCWS = 700

ACC BCWP = 700

ACC ACWP = 360Acc BCWS = 700Acc BCWP = 700Acc ACWP = 360Acc SV = 0Acc CV = 340BAC = 800EAC = 800

Page 21: The effect of Level of Effort EVT

What does these mean• Looking at the data as it stands now it tells us:

– We have only one month of work left to do – We are on target to complete with no schedule variance– We have been very efficient we have done £700 for only £360 (positive CV of

£340)– We should under spend on completion and therefore the EAC is to high

• How real are these conclusions:

– Because we know the work was started late, we know more than 1 months work is needed.

– We also know the work is behind schedule, but not from the EV data– As the CAM we would know that only £100 of performance is being achieved

for a cost of £120 per month so we are not efficient– This efficiency in fact means that the EAC is too low.

21

Page 22: The effect of Level of Effort EVT

Incorrectly profiled Month 8

22

Time now

ACC BCWS = 800

ACC BCWP = 800

ACC ACWP = 480Acc BCWS = 800Acc BCWP = 800Acc ACWP = 4800Acc SV = 0Acc CV = 320BAC = 800EAC = 800

Page 23: The effect of Level of Effort EVT

Graph data Cum Performance

23

100

200

300

400

500

600

700

800

900

1,000

2004JAN

BMT Sigma Example 1 OC Element: 1 Name: LOECum Element Performance

Time N

ow

Dollars in Thousands

BCWS100BCWP 0ACWP 0

Page 24: The effect of Level of Effort EVT

Graph data Cum Performance

24

100

200

300

400

500

600

700

800

900

1,000

2004JAN FEB

BMT Sigma Example 1 OC Element: 1 Name: LOECum Element Performance

Time N

ow

Dollars in Thousands

BCWS 200100BCWP 00ACWP 00

Page 25: The effect of Level of Effort EVT

Graph data Cum Performance

25

100

200

300

400

500

600

700

800

900

1,000

2004JAN FEB MAR

BMT Sigma Example 1 OC Element: 1 Name: LOECum Element Performance

Time N

ow

Dollars in Thousands

BCWS 300200100BCWP 000ACWP 000

Page 26: The effect of Level of Effort EVT

Graph data Cum Performance

26

100

200

300

400

500

600

700

800

900

1,000

2004JAN FEB MARAPR

BMT Sigma Example 1 OC Element: 1 Name: LOECum Element Performance

Time N

ow

Dollars in Thousands

BCWS 400300200100BCWP 0000ACWP 0000

Page 27: The effect of Level of Effort EVT

Graph data Cum Performance

27

100

200

300

400

500

600

700

800

900

1,000

2004JAN FEB MARAPR MAY

BMT Sigma Example 1 OC Element: 1 Name: LOECum Element Performance

Time N

ow

Dollars in Thousands

BCWS 500400300200100BCWP 5000000ACWP 1200000

Page 28: The effect of Level of Effort EVT

Graph data Cum Performance

28

100

200

300

400

500

600

700

800

900

1,000

2004JAN FEB MARAPR MAY JUN

BMT Sigma Example 1 OC Element: 1 Name: LOECum Element Performance

Time N

ow

Dollars in Thousands

BCWS 600500400300200100BCWP 6005000000ACWP 2401200000

Page 29: The effect of Level of Effort EVT

Graph data Cum Performance

29

100

200

300

400

500

600

700

800

900

1,000

2004JAN FEB MARAPR MAY JUN JUL

BMT Sigma Example 1 OC Element: 1 Name: LOECum Element Performance

Time N

ow

Dollars in Thousands

BCWS 700600500400300200100BCWP 7006005000000ACWP 3602401200000

Page 30: The effect of Level of Effort EVT

Graph data Cum Performance

30

100

200

300

400

500

600

700

800

900

1,000

2004JAN FEB MARAPR MAY JUN JUL AUG

BMT Sigma Example 1 OC Element: 1 Name: LOECum Element Performance

Time N

ow

Dollars in Thousands

BCWS 800700600500400300200100BCWP 8007006005000000ACWP 4803602401200000

Page 31: The effect of Level of Effort EVT

Graph data Cum Performance

31

100

200

300

400

500

600

700

800

900

1,000

2004JAN FEB MARAPR MAY JUN JUL AUGSEP

BMT Sigma Example 1 OC Element: 1 Name: LOECum Element Performance

Time N

ow

Dollars in Thousands

BCWS 800800700600500400300200100BCWP 8008007006005000000ACWP 6004803602401200000

Page 32: The effect of Level of Effort EVT

Graph data Cum Performance

32

100

200

300

400

500

600

700

800

900

1,000

2004JAN FEB MARAPR MAY JUN JUL AUGSEP OCT

BMT Sigma Example 1 OC Element: 1 Name: LOECum Element Performance

Time N

ow

Dollars in Thousands

BCWS 800800800700600500400300200100BCWP 8008008007006005000000ACWP 7206004803602401200000

Page 33: The effect of Level of Effort EVT

Graph data Cum Performance

33

100

200

300

400

500

600

700

800

900

1,000

2004JAN FEB MARAPR MAY JUN JUL AUGSEP OCT NOV

BMT Sigma Example 1 OC Element: 1 Name: LOECum Element Performance

Time N

ow

Dollars in Thousands

BCWS 800800800800700600500400300200100BCWP 8008008008007006005000000ACWP 8407206004803602401200000

Page 34: The effect of Level of Effort EVT

Graph data Cum Performance

34

100

200

300

400

500

600

700

800

900

1,000

2004JAN FEB MARAPR MAY JUN JUL AUGSEP OCT NOVDEC

BMT Sigma Example 1 OC Element: 1 Name: LOECum Element Performance

Time N

ow

Dollars in Thousands

BCWS 800800800800800700600500400300200100BCWP 8008008008008007006005000000ACWP 9608407206004803602401200000

Page 35: The effect of Level of Effort EVT

Questions

• At what month could you determine that an over spend was going to happen, and by how much did you expect it to be.

35

Page 36: The effect of Level of Effort EVT

Cumulative variances

36

-350

-250

-150

-50

50

150

250

350

2004JAN

BMT Sigma Example 1 OC Element: 1 Name: LOECumulative Variance

Dollars in Thousands

COST 0.0SCHED-100.0

Page 37: The effect of Level of Effort EVT

Cumulative variances

37

-350

-250

-150

-50

50

150

250

350

2004JAN FEB

BMT Sigma Example 1 OC Element: 1 Name: LOECumulative Variance

Dollars in Thousands

COST 0.00.0SCHED -200.0-100.0

Page 38: The effect of Level of Effort EVT

Cumulative variances

38

-350

-250

-150

-50

50

150

250

350

2004JAN FEB MAR

BMT Sigma Example 1 OC Element: 1 Name: LOECumulative Variance

Dollars in Thousands

COST 0.00.00.0SCHED -300.0-200.0-100.0

Page 39: The effect of Level of Effort EVT

Cumulative variances

39

-350

-250

-150

-50

50

150

250

350

2004JAN FEB MARAPR

BMT Sigma Example 1 OC Element: 1 Name: LOECumulative Variance

Dollars in Thousands

COST 0.00.00.00.0SCHED -400.0-300.0-200.0-100.0

Page 40: The effect of Level of Effort EVT

Cumulative variances

40

-350

-250

-150

-50

50

150

250

350

2004JAN FEB MARAPR MAY

BMT Sigma Example 1 OC Element: 1 Name: LOECumulative Variance

Dollars in Thousands

COST 380.00.00.00.00.0SCHED 0.0-400.0-300.0-200.0-100.0

Page 41: The effect of Level of Effort EVT

Cumulative variances

41

-350

-250

-150

-50

50

150

250

350

2004JAN FEB MARAPR MAY JUN

BMT Sigma Example 1 OC Element: 1 Name: LOECumulative Variance

Dollars in Thousands

COST 360.0380.00.00.00.00.0SCHED 0.00.0-400.0-300.0-200.0-100.0

Page 42: The effect of Level of Effort EVT

Cumulative variances

42

-350

-250

-150

-50

50

150

250

350

2004JAN FEB MARAPR MAY JUN JUL

BMT Sigma Example 1 OC Element: 1 Name: LOECumulative Variance

Dollars in Thousands

COST 340.0360.0380.00.00.00.00.0SCHED 0.00.00.0-400.0-300.0-200.0-100.0

Page 43: The effect of Level of Effort EVT

Cumulative variances

43

-350

-250

-150

-50

50

150

250

350

2004JAN FEB MARAPR MAY JUN JUL AUG

BMT Sigma Example 1 OC Element: 1 Name: LOECumulative Variance

Dollars in Thousands

COST 320.0340.0360.0380.00.00.00.00.0SCHED 0.00.00.00.0-400.0-300.0-200.0-100.0

Page 44: The effect of Level of Effort EVT

Cumulative variances

44

-350

-250

-150

-50

50

150

250

350

2004JAN FEB MARAPR MAY JUN JUL AUGSEP

BMT Sigma Example 1 OC Element: 1 Name: LOECumulative Variance

Dollars in Thousands

COST 200.0320.0340.0360.0380.00.00.00.00.0SCHED 0.00.00.00.00.0-400.0-300.0-200.0-100.0

Page 45: The effect of Level of Effort EVT

Cumulative variances

45

-350

-250

-150

-50

50

150

250

350

2004JAN FEB MARAPR MAY JUN JUL AUGSEP OCT

BMT Sigma Example 1 OC Element: 1 Name: LOECumulative Variance

Dollars in Thousands

COST 80.0200.0320.0340.0360.0380.00.00.00.00.0SCHED 0.00.00.00.00.00.0-400.0-300.0-200.0-100.0

Page 46: The effect of Level of Effort EVT

Cumulative variances

46

-350

-250

-150

-50

50

150

250

350

2004JAN FEB MARAPR MAY JUN JUL AUGSEP OCT NOV

BMT Sigma Example 1 OC Element: 1 Name: LOECumulative Variance

Dollars in Thousands

COST -40.080.0200.0320.0340.0360.0380.00.00.00.00.0SCHED 0.00.00.00.00.00.00.0-400.0-300.0-200.0-100.0

Page 47: The effect of Level of Effort EVT

Cumulative variances

47

-350

-250

-150

-50

50

150

250

350

2004JAN FEB MARAPR MAY JUN JUL AUGSEP OCT NOVDEC

BMT Sigma Example 1 OC Element: 1 Name: LOECumulative Variance

Dollars in Thousands

COST -160.0-40.080.0200.0320.0340.0360.0380.00.00.00.00.0SCHED 0.00.00.00.00.00.00.00.0-400.0-300.0-200.0-100.0

Page 48: The effect of Level of Effort EVT

Other Effects• Where you are in a situation where more performance is being claimed

than the spend incurred a positive Cost Performance Index (CPI) is created, meaning you are efficient than expected. Where the performance is due to the incorrect LOE re-forecast, an artificial variance has been created. Some Independent Estimates at completion (IEAC) formulas use the CPI, and if this is artificial then the IEAC will not be correct.

48

Page 49: The effect of Level of Effort EVT

IEAC based on Cur/Cum CPI

49

200

300

400

500

600

700

800

900

1,000

2004JAN

BMT Sigma Example 1 OC Element: 1 Name: LOEIEAC Based on CPI

Dollars in Thousands

IEAC_Cum800IEAC_Curr800BAC 800

Page 50: The effect of Level of Effort EVT

IEAC based on Cur/Cum CPI

50

200

300

400

500

600

700

800

900

1,000

2004JAN FEB

BMT Sigma Example 1 OC Element: 1 Name: LOEIEAC Based on CPI

Dollars in Thousands

IEAC_Cum 800800IEAC_Curr 800800BAC 800800

Page 51: The effect of Level of Effort EVT

IEAC based on Cur/Cum CPI

51

200

300

400

500

600

700

800

900

1,000

2004JAN FEB MAR

BMT Sigma Example 1 OC Element: 1 Name: LOEIEAC Based on CPI

Dollars in Thousands

IEAC_Cum 800800800IEAC_Curr 800800800BAC 800800800

Page 52: The effect of Level of Effort EVT

IEAC based on Cur/Cum CPI

52

200

300

400

500

600

700

800

900

1,000

2004JAN FEB MAR APR

BMT Sigma Example 1 OC Element: 1 Name: LOEIEAC Based on CPI

Dollars in Thousands

IEAC_Cum 800800800800IEAC_Curr 800800800800BAC 800800800800

Page 53: The effect of Level of Effort EVT

IEAC based on Cur/Cum CPI

53

BCWPCPI= ACWP

BCWP = 500ACWP = 120

CPI = 4.2

200

300

400

500

600

700

800

900

1,000

2004JAN FEB MAR APR MAY

BMT Sigma Example 1 OC Element: 1 Name: LOEIEAC Based on CPI

Dollars in Thousands

IEAC_Cum 192800800800800IEAC_Curr 192800800800800BAC 800800800800800

Page 54: The effect of Level of Effort EVT

IEAC based on Cur/Cum CPI

54

200

300

400

500

600

700

800

900

1,000

2004JAN FEB MAR APR MAY JUN

BMT Sigma Example 1 OC Element: 1 Name: LOEIEAC Based on CPI

Dollars in Thousands

IEAC_Cum 320192800800800800IEAC_Curr 480192800800800800BAC 800800800800800800

Page 55: The effect of Level of Effort EVT

IEAC based on Cur/Cum CPI

55

200

300

400

500

600

700

800

900

1,000

2004JAN FEB MAR APR MAY JUN JUL

BMT Sigma Example 1 OC Element: 1 Name: LOEIEAC Based on CPI

Dollars in Thousands

IEAC_Cum 411320192800800800800IEAC_Curr 480480192800800800800BAC 800800800800800800800

Page 56: The effect of Level of Effort EVT

IEAC based on Cur/Cum CPI

56

200

300

400

500

600

700

800

900

1,000

2004JAN FEB MAR APR MAY JUN JUL AUG

BMT Sigma Example 1 OC Element: 1 Name: LOEIEAC Based on CPI

Dollars in Thousands

IEAC_Cum 480411320192800800800800IEAC_Curr 480480480192800800800800BAC 800800800800800800800800

Page 57: The effect of Level of Effort EVT

IEAC based on Cur/Cum CPI

57

200

300

400

500

600

700

800

900

1,000

2004JAN FEB MAR APR MAY JUN JUL AUG SEP

BMT Sigma Example 1 OC Element: 1 Name: LOEIEAC Based on CPI

Dollars in Thousands

IEAC_Cum 600480411320192800800800800IEAC_Curr 800480480480192800800800800BAC 800800800800800800800800800

Page 58: The effect of Level of Effort EVT

IEAC based on Cur/Cum CPI

58

200

300

400

500

600

700

800

900

1,000

2004JAN FEB MAR APR MAY JUN JUL AUG SEP OCT

BMT Sigma Example 1 OC Element: 1 Name: LOEIEAC Based on CPI

Dollars in Thousands

IEAC_Cum 720600480411320192800800800800IEAC_Curr 800800480480480192800800800800BAC 800800800800800800800800800800

Page 59: The effect of Level of Effort EVT

IEAC based on Cur/Cum CPI

59

200

300

400

500

600

700

800

900

1,000

2004JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV

BMT Sigma Example 1 OC Element: 1 Name: LOEIEAC Based on CPI

Dollars in Thousands

IEAC_Cum 840720600480411320192800800800800IEAC_Curr 840800800480480480192800800800800BAC 800800800800800800800800800800800

Page 60: The effect of Level of Effort EVT

IEAC based on Cur/Cum CPI

60

200

300

400

500

600

700

800

900

1,000

2004JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

BMT Sigma Example 1 OC Element: 1 Name: LOEIEAC Based on CPI

Dollars in Thousands

IEAC_Cum 960840720600480411320192800800800800IEAC_Curr 960840800800480480480192800800800800BAC 800800800800800800800800800800800800

Page 61: The effect of Level of Effort EVT

Questions?

• Presented by:– Russell Berkeley– Tel: 07515 685458

61