The Constructor Notes
-
Upload
sheikh-nouman-mohsin-ramzi -
Category
Documents
-
view
219 -
download
0
Transcript of The Constructor Notes
-
8/12/2019 The Constructor Notes
1/65
CONCRETE FORMWORK DESIGN CONSIDERATIONS
Designing and building formwork effectively requires a basic understanding of
howconcretebehaves as it exerts pressure on formwork.Concrete exerts lateral pressure on
the formwork. The formwork is designed based on these lateral forces.Lateral concrete pressure on formwork is affected by:
1) Height of concrete pour 2) Concrete pour rate 3) Weight of concrete 4) Temperature 5)
Type of cement 6) Vibration 7) Concrete slump (watercement ratio) 8) Chemical additives
1) Height of concrete pour:Before concrete hardens, it acts like a liquid and pushes
against the forms the way water presses against the walls of a storage tank. The amount of
pressure at any point on the form is directly determined by the height and weight of
concrete above it. Pressure is not affected by the thickness of the wall.
Fig: Lateral concrete pressure on formwork
2) Concrete pour rate:Concrete pressure at any point on the form is directly proportional
to the height of liquid concrete above it. If concrete begins to harden before the pour is
complete, the full liquid head will not develop and the pressure against the forms will be
less than if the pour were completed before any of concrete hardened.
Once concrete hardens it cannot exert more pressure on the forms even though liquid
concrete continues to be placed above it. The following diagrams illustrates how form
pressure varies when the pour rate is increased from one level to another level. For ease of
explanation, it is assumed that concrete hardens in one hour (typically) at 21C.
http://theconstructor.org/practical-guide/material-testing/concrete-material-testing/http://theconstructor.org/practical-guide/work-procedure/concrete-work-procedure/http://theconstructor.org/practical-guide/work-procedure/concrete-work-procedure/http://theconstructor.org/practical-guide/material-testing/concrete-material-testing/ -
8/12/2019 The Constructor Notes
2/65
Fig: Concrete pressure on formwork during hardening
When the pour rate is increased the pressure also increases as shown below:
Fig: Concrete pressure on formwork due to higher pour rate
3) Weight of Concrete:Pressure exerted against the forms is directly proportional to the
unit weight of concrete.Light weight concrete will exert less pressure than normal weight
concrete as shown below:
Fig: Pressure on formwork due to normal and lightweight concretes
4) Temperature:The time it takes concrete to harden is influenced greatly by its
temperature. The higher the temperature of the concrete, the quicker it will harden. Most
formwork designs are based on an assumed average air and concrete temperature of 21C.
http://theconstructor.org/concrete/light-weight/http://theconstructor.org/concrete/light-weight/ -
8/12/2019 The Constructor Notes
3/65
At low air temperatures, the hardening of concrete is delayed and you need to decrease
your pour rate or heat your concrete to keep the pressure against the formwork from
increasing. Ideally, concrete should be poured at temperatures between 16C and 38C.
Outside this temperature range there is often insufficient moisture available for curing. If
adequate water for curing is not available or freezes, the strength of the concrete will suffer.5) Type of Cement:The cement type will influence the rate at which concrete hardens. A
high early strength concrete will harden faster than normal concrete and will allow a faster
pour rate. When using a cement which alters the normal set and hardening time, be sure to
adjust the pour rate accordingly.
6) Vibration:Internal vibration consolidates concrete and causes it to behave like the pure
liquid. If concrete is not vibrated, it will exert less pressure on the forms. ACI recommended
formulas for form pressures may be reduced 10% if the concrete is spaded rather than
internally vibrated. Re-vibration and external vibration result in higher form loads than
internal vibration. These types of vibration require specially designed forms.7) Concrete Slump:When concrete has very low slump, it acts less like a liquid and will
transmit less pressure. When using concrete with a slump greater than 100 mm, the
formwork should be designed to resist full liquid head.
8) Chemical additives: When using chemical additives i.e. retarders, plasticizers, etc.
make sure to refer to the vendors application data.
-
8/12/2019 The Constructor Notes
4/65
METHODS OF INCREASING STRUCTURAL STIFFNESS
The methods of increasing structural stiffness oftall buildings are by providing central
core,shear walls,tubes, braced frame and double tube. These are discussed in detail below.
1. Central Core:
By constructing a central core, the stiffness of the building is
greatly increased. A central core is used to house stairs and
lifts and building services. This method allows the building to
keep an open facade. Following figure shows the central core
of a building with a 55 column.
2. Shear Walls:
Shear walls are constructed at opposite ends of a building to
provide stiffness in a particular direction. Shear walls are
particularly useful in non-squarebuildings,where the wind
forces predominantly come from one direction. The interior of
the building is kept clear. Shear walls only provide minimal
torsional stiffness.
3. Tube system:
A tube system is essentially two sets of shear walls. The tube
system allows the building to be stiff in all directions of
loading. The building will also have a high-torsional
resistance. The interior of the building is kept clear.
The tube system must be pierced for windows. These
openings must be kept to minimum.
4. Braced Frame:
Braced frame is the simple structure with bracing that help to increasethe structural stiffness. A braced frame is similar to floor bracing, but it
does not depend on the stiffness provided by the floor system, rather on
the addition of another diagonal cross members.
http://theconstructor.org/structural-engg/tall-buildings/http://theconstructor.org/structural-engg/shear-walls/http://theconstructor.org/building/buildings/http://theconstructor.org/building/buildings/http://theconstructor.org/structural-engg/shear-walls/http://theconstructor.org/structural-engg/tall-buildings/ -
8/12/2019 The Constructor Notes
5/65
This type of bracing is lighter than its counterpart with floor bracing. The building has good
stiffness.
Compared to the system with floor bracing, this system is less easy to construct. The faade
detailing can be interesting but also expensive.
5. Double Tube System:
A double tube system is a combination of the central core
and tube system as shown in figure below. This
combination of both systems allows the building to be
extremely stiff.
The building has high torsional resistance. For the tube
system, apertures for windows must be kept to minimum.
The central core take much valuable space. This type of
system is used for very tall building.
-
8/12/2019 The Constructor Notes
6/65
COOLING TOWERS AND ITS SYSTEMS
Cooling towers are commonly used to remove excess heat that is generated in places such
as power stations, chemical plants and even domestically in air conditioning units. This
equipment has recently developed into an important part of many chemical plants. They
represent a relatively inexpensive and dependable means of removing low-grade heat from
cooling water.
Cooling towers might be classified into several types based on the air draft and based on
the flow pattern. Each type of cooling tower has its own advantages and disadvantages;
thus the proper selection is needed based on the system operation. Besides, the material
selection of cooling tower is also important. Cooling towers tends to be corrosive since it
always has direct contact with the water. Proper material selection or additional water
treatment is then needed to keep the cooling tower safe.
Cooling towers are heat removal devices used to transfer process waste heat to the
atmosphere. Cooling towers make use of evaporation whereby some of the water is
evaporated into a moving air stream and subsequently discharged into the atmosphere. As
a result, the remainder of the water is cooled down significantly.
Fig: Schematic Diagram of a Cooling Tower System
There are several important factors that govern the operation of cooling tower:
The dry-bulb and wet-bulb temperatures of the air.
-
8/12/2019 The Constructor Notes
7/65
The temperature of warm water. The efficiency of contact between air and water in terms of the volumetric mass transfer
coefficient and the contact time between the air and the water.
The uniformity of distribution of the phases within the tower. The air pressure drop. The desired temperature of the cooled water.
-
8/12/2019 The Constructor Notes
8/65
CALCULATE EARTHQUAKE FORCES ON BUILDINGS AND STRUCTURES
Earthquake resistant design of structures has become integral part ofstructural design of
any structure. The guide to earthquake resistant design of building and structures are given
by IS1893 2002 in India. Here we will talk about how to calculate theearthquake
forces for buildings and structures as per above mentioned code. First step to calculate earthquake loads onstructure is to identify the
earthquake zone for which structure needs to be designed. This earthquake zones
are displayed in a map on page 6 of the code.
After earthquake zone has been identified, the following steps are followed:
1. Calculate design horizontal seismic coefficient, Ah, which is given by (cl. 6.4.2 of
IS1893 2002:
Where, Z is the zone factor, given in table 2 of IS1893 2002.
I is the importance factor of the structure depending on the function or use. This factor can
be obtained from table 6 of the code.
R is response reduction factor. This value is obtained from table 7 of the code. The value of
1/R shall not be more than one.
Sa/g is average response acceleration coefficient. This value depends on time period of
structure and on soil type. This can be obtained from clause 6.4.5 of the code.
2. Calculate design seismic base shear for the structure (VB). This is the total design
lateral force along any principal direction. This is calculated as:
VB= Ahx W
Where Ah= horizontal seismic coefficient as calculated above in step 1.
W = Total weight of the structure.
3. Now calculate the distribution of design forces on the structure. The seismicdesign base shear calculated in step above is distributed on the structure as design seismic
forces. This is calculated as below:
http://theconstructor.org/structural-engg/structural-design/earthquake-resistant/http://theconstructor.org/structural-engg/structural-design/http://theconstructor.org/earthquake/forces/http://theconstructor.org/earthquake/forces/http://theconstructor.org/earthquake/forces/http://theconstructor.org/earthquake/forces/http://theconstructor.org/structural-engg/structural-design/http://theconstructor.org/structural-engg/structural-design/earthquake-resistant/ -
8/12/2019 The Constructor Notes
9/65
Where Qi = Design lateral force at floor i
Wi = seismic weight of the floor i
hi = height of the floor i from the base
n = number of storeys of the building at which masses are located.
4. Distribution of horizontal seismic forces on structure: These forces are
distributed on the vertical elements of the building resisting lateral forces.
Example:
Consider a two-bay two-storied building for which earthquake forces need to be calculated.
Consider total weight of the building as 1000 kN. Top roof has the weight of 200 kN and
both floors have weight of 400 kN as shown in figure below. The calculation of earthquake
seismic forces will be as shown below:
-
8/12/2019 The Constructor Notes
10/65
Total Weight of the Structure< ?xml:namespace prefix =
"o" /> Wi= 1000 kN
Zone Factor (Zone IV) Z = 0.24
Importance factor (Table6) I = 1
Response Reduction Factor R = 3
Average response acceleration coefficient
Let time
period T 0.373358 (Cl. 7.6)
Sa/g 2.5
Design Horizontal Seismic coefficient Ah 0.10
-
8/12/2019 The Constructor Notes
11/65
Base Shear 100 kN
Storey Base Shear Height Wi Wixhi2 Qi
Design
Force
3 100 8.5 200 14450 57.00197 9.50
2 100 5 400 10000 39.44773 6.57
1 100 1.5 400 900 3.550296 0.59
Total 25350 (in kN)
-
8/12/2019 The Constructor Notes
12/65
ROLE OF CONSTRUCTION SITE ENGINEER
On any one contract there may be a number of engineers with varying amounts and types
of experience. The duties and responsibilities of an engineer are typically as follows, many
of these will be delegated to other engineers on the site according to their experience and
ability:
Setting out the works in accordance with the drawings and specification Liaising with the project planning engineer regardingconstruction programmes Checking materials and work in progress for compliance with the specified requirements Observance of safety requirements Resolving technical issues with employers representatives, suppliers, subcontractors
and statutory authorities
Quality control in accordance with CSIs/procedures method statements, quality plansand inspection and test plans, all prepared by the project management team and bysubcontractors
Liaising with company or project purchasing department to ensure that purchase ordersadequately define the specified requirements
Supervising and counselling junior or trainee engineers Measurement and valuation (in collaboration with the project quantity surveyor where
appropriate)
Providing data in respect of variation orders and site instructions Preparing record drawings, technical reports, site diary Job review of subordinate staff
http://theconstructor.org/constrution/http://theconstructor.org/constrution/ -
8/12/2019 The Constructor Notes
13/65
SELF COMPACTING CONCRETE WITH TESTS
For several years beginning in 1983, the problem of thedurability of concrete structureswas a major topic of interest in Japan. The creation of durable concrete structures requires
adequate compaction by skilled workers. However, the gradual reduction in the number of
skilled workers in Japans construction industry has led to a similar reduction in the qualityof construction work. One solution for the achievement of durable concrete structures
independent of the quality of construction work is the employment of self-compacting
concrete, which can be compacted into every corner of a formwork, purely by means of its
own weight and without the need for vibrating compaction(Fig. 1). The necessity of this
type of concrete was proposed by Okamura in 1986. Studies to develop self-compacting
concrete, including a fundamental study on the workability of concrete, have been carried
out by Ozawa and Maekawa at the University of Tokyo. The prototype of self-compacting
concrete was first completed in 1988 using materials already on the market (Fig. 2). The
prototype performed satisfactorily with regard to drying and hardening shrinkage, heat ofhydration, denseness after hardening, and other properties. This concrete was named High
Performance Concreteand was defined as follows at the three stages of concrete:
(1) Fresh: self-compactable
(2) Early age: avoidance of initial defects
(3) After hardening: protection against external factors
At almost the same time, High Performance Concrete was defined as a concrete with high
durability due to a low water-cement ratio by Professor Atcin et al. Since then, the term
high performance concrete has been used around the world to refer to high durability
http://theconstructor.org/concrete/durability-of-concrete-structures/24/http://theconstructor.org/concrete/durability-of-concrete-structures/24/http://theconstructor.org/concrete/high-performance-concrete/304/http://theconstructor.org/concrete/high-performance-concrete/304/http://theconstructor.org/concrete/high-performance-concrete/304/http://theconstructor.org/concrete/high-performance-concrete/304/http://theconstructor.org/concrete/high-performance-concrete/304/http://theconstructor.org/concrete/durability-of-concrete-structures/24/ -
8/12/2019 The Constructor Notes
14/65
concrete. Therefore, the authors have changed the term for the proposed concrete to Self-
Compacting High Performance Concrete.
Self-compactability of fresh concrete
Mechanism for achieving self-compactabilityThe method for achieving self-compactability involves not only high deformability of pasteor mortar, but also resistance to segregation between coarse aggregate and mortar when
the concrete flows through the confined zone of reinforcing bars. Okamura and Ozawa have
employed the following methods to achieve self- compactability (Fig. 3) (1995):
(1) Limited aggregate content
(2) Low water-powder ratio
(3) Use of super-plasticizer
The frequency of collision and contact between aggregate particles can increase as the
relative distance between the particles decreases and then internal stress can increase when
concrete is deformed, particularly near obstacles. Research has found that the energy
required for flowing is consumed by the increased internal stress, resulting in blockage of
aggregate particles. Limiting the coarse aggregate content, whose energy consumption is
particularly intense, to a level lower than normal is effective in avoiding this kind of
blockage.
-
8/12/2019 The Constructor Notes
15/65
Highly viscous paste is also required to avoid the blockage of coarse aggregate when
concrete flows through obstacles (Fig. 4). When concrete is deformed, paste with a high
viscosity also prevents localized increases in internal stress due to the approach of coarse
aggregate particles. High deformability can be achieved only by the employment of a super-
plasticizer, keeping the water-powder ratio to a very low value.The mix proportioning of self-compacting concrete is shown and compared with those of
normal concrete and RCD (Roller Compacted concrete for Dams) concrete (Fig. 5). The
aggregate content is smaller than conventional concrete that requires vibrating compaction.
The ratios of the coarse aggregate volume to its solid volume (G/Glim) of each type of
concrete are shown in Fig. 6. The degree of packing of coarse aggregate in SCC is
approximately 50% to reduce the interaction between coarse aggregate particles when the
concrete deforms. In addition, the ratios of fine aggregate volume to solid volume (S/Slim)
in the mortar are shown in the same figure. The degree of packing of fine aggregate in SCC
mortar is approximately 60% so that shear deformability when the concrete deforms maybe limited. On the other hand, the viscosity of the paste in SCC is the highest among the
various types of concrete due to its lowest water-powder ratio (Fig. 7). This characteristic is
effective in inhibiting segregation.
Test for Self CompactibilityThere are three purposes for self-compactability tests relating to practical purposes.
Test (1): To check whether or not the concrete is self-compactable for the structure.
Test (2): To adjust the mix proportion when selfcompactability is not sufficient.
Test (3): To characterize materials.
As Test (1), the so-called U-flow test or Box test is recommended (Figs. 8, 9 and 10). The
U-flow test was developed by the Taisei Group (Hayakawa 1993). In this test, the degree of
compactability can be indicated by the height that the concrete reaches after flowing
through an obstacle. Concrete with a filling height of over 300 mm can be judged as self-
compacting. The Box-test is more suitable for detecting concrete with higher possibility of
segregation between coarse aggregate and mortar.
http://theconstructor.org/concrete/roller-compacted-concrete-pavement-dams/5863/http://theconstructor.org/concrete/roller-compacted-concrete-pavement-dams/5863/ -
8/12/2019 The Constructor Notes
16/65
If the concrete is judged to be having insufficient selfcompactability through test (1), the
cause has to be detected quantitatively so that the mix proportion can be adjusted. Slump-
flow and funnel tests (Fig. 11) have been proposed for testing deformability and viscosity,
respectively.
Flow and funnel tests for mortar or paste have been proposed to characterize materials
used in selfcompacting concrete, e.g. powder material, sand, and super-plasticizer. Testing
methods for the mortar properties were al so proposed and the indices for deformability and
viscosity were also defined as in (Figs. 12 and 13).
Factors of self-compactability in terms of testing results.The factors making up self-compactability were described in terms of the test results for
fresh concrete and mortar below.(1) Influence of coarse aggregate depending on spacing size.
-
8/12/2019 The Constructor Notes
17/65
It is not always possible to predict the degree of compaction into a structure by using the
test result on the degree of compaction of the concrete into another structure, since the
maximum size of coarse aggregate is close to the minimum spacing between the reinforcing
bars of the structure. For example, the relationship between coarse aggregate content in
concrete and the filling height of the Box-type test, which the standard index for self-
compactability of fresh concrete, is shown in Figs. 14 and 15. The relationship between the
filling height through obstacle R1 and that through R2 varied depending on the coarse
aggregate content. That test result shows that the influence of coarse aggregate on the
flowability of fresh concrete largely depends on the size of the spacing of the obstacle. It
can be said that the self-compactability of fresh concrete has to be discussed in terms of
solid particles as well as in terms of liquid.
2) Role of mortar as fluid in flowability of fresh concrete
Sufficient deformability of the mortar phase in concrete is required so that concrete can be
compacted into structures by its self-weight without need for vibrating compaction. In
-
8/12/2019 The Constructor Notes
18/65
addition, moderate viscosity as well as deformability of the mortar phase is required so that
the relative displacement between coarse aggregate particles in front of obstacles when
concrete is to flow around such obstacles can be reduced and then segregation between
coarse aggregate and mortar can be inhibited. The necessity for viscosity was confirmed by
Hashimotos visualization test. The indices for mortar deformability and viscosity wereproposed by using mortar flow and funnel test results. The relationship between mortar
deformability and viscosity and the self-compactability of fresh concrete is shown assuming
a fixed coarse aggregate content (Fig. 15). The existence of an optimum combination of
deformability and viscosity of mortar for achieving self-compactability of fresh concrete was
demonstrated.
(3) Role of mortar as solid particles
In addition to its role as a liquid mentioned above, mortar also plays a role as solid
particles. This property is so-called pressure transferability, which can be apparent when
the coarse aggregate particles approach each other and mortar in between coarse
aggregate particles is subjected to normal stress (Fig. 16). The degree of the decrease in
the shear deformability of the mortar largely depends on the physical characteristics of the
solid particles in the mortar (Fig. 17) (Nagamoto 1997).
For example, the difference in the relationships between the funnel speeds of mortar and
concrete due to differences in the fine aggregate content in mortar are shown in Fig. 18. It
was found that the relationship between the flowability of mortar and concrete cannot
always be unique due to differences in the characteristics of the solid particles in the
mortar, even if the characteristics of the coarse aggregate and its content in concrete are
constant.
(4) Influence of coarse aggregate -Content, shape and grading-
The influence of coarse aggregate on the sel fcompactability of fresh concrete, especially
flowability through obstacles, can be equal despite the shape of the coarse aggregate
particles shape as long as the ratio of coarse aggregate content to its solid volume in
concrete is the same (Fig. 22). However, the influence of the grading of coarse aggregate
-
8/12/2019 The Constructor Notes
19/65
has also to be considered if the spacing of the obstacles is very close to the maximum size
coarse aggregate. For example, the relationships between the size of the concrete funnels
outlet and the flow speed through it depends on the fineness modulus of coarse aggregate
FM even if the property of the mortar phase is the same (Figs. 23 and 24). It was found out
that the flow speed of concrete through a funnel with an outlet width of 55 mm was largelyinfluenced by the grading of the coarse aggregate.
State of the art on Self-Compacting Concrete
Current status of Self-Compacting ConcreteSelf-compacting concrete has been used as a special concrete only in large general
construction companies in Japan. In order for self-compacting concrete to be used as a
standard concrete rather than a special one, new systems for its design, manufacturing and
construction of self-compacting concrete need to be established. Various committee
activities on self-compacting concrete have been carried out as a result. Among them, a
system by which the ready-mixed concrete industry can produce self-compacting concrete
as a normal concrete would seem the most effective since, in Japan, as much as 70% of all
concrete is produced by the ready-mixed concrete industry. Assuming a general supply from
ready-mixed concrete plants, investigations to establish the following items have been
carried out mainly at the University of Tokyo since the development of the prototype.
(1) Self-compactability testing method
(2) Mix-design method
(3) Acceptance testing method at job site
(4) New type of powder or admixture suitable for self-compacting concrete
Of those items, (1) has already been mentioned in this paper. (2), (3) and (4) are described
below.
Mix-design method(1) Rational mix-design method
Self-compactability can be largely affected by the characteristics of materials and the mix
proportion. A rational mix-design method for self-compacting concrete using a variety of
materials is necessary. Okamura and Ozawa (1995) have proposed a simple mix
proportioning system assuming general supply from ready-mixed concrete plants. The
coarse and fine aggregate contents are fixed so that self-compactability can be achieved
easily by adjusting the water-powder ratio and superplasticizer dosage only.
(1) The coarse aggregate content in concrete is fixed at 50% of the solid volume.
(2) The fine aggregate content is fixed at 40% of the mortar volume.
(3) The water-powder ratio in volume is assumed as 0.9 to 1.0, depending on the properties
of the powder.
(4) The superplasticizer dosage and the final water-powder ratio are determined so as to
ensure selfcompactability. In the mix proportioning of conventional concrete, the water-
-
8/12/2019 The Constructor Notes
20/65
cement ratio is fixed at first from the viewpoint of obtaining the required strength. With self-
compacting concrete, however, the water-powder ratio has to be decided taking into
account self-compactability because self-compactability is very sensitive to this ratio. In
most cases, the required strength does not govern the water-cement ratio because the
water-powder ratio is small enough for obtaining the required strength for ordinarystructures unless most of the powder materials in use is not reactive.
The mortar or paste in self-compacting concrete requires high viscosity as well as high
deformability. This can be achieved by the employment of a superplasticizer, which results
in a low water-powder ratio for high deformability.
(2) Adjustment of water-powder ratio and superplasticizer dosage
The characteristics of powder and superplasticizer largely affect the mortar property and so
the proper water powder ratio and superplasticizer dosage cannot be fixed without trial
mixing at this stage. Therefore, once the mix proportion is decided, self-compactability has
to be tested by U-flow, slump-flow and funnel tests. Methods for judging whether the water-powder ratio or superplasticizer dosage are larger or smaller than the proper value by using
the test results, and methods for estimating the proper values are necessary. The
relationships between the properties of the mortar in selfcompacting concrete and the mix
proportion have been investigated and then formulated. These formulae can be used to
establish a rational method for adjusting the water-powder ratio and superplasticizer dosage
to achieve appropriate deformability and viscosity.
4. Properties of Hardened SCC
Structural PropertiesThe basic ingredients used in SCC mixes are practically the same as those used in the
conventional HPC vibrated concrete, except they are mixed in different proportions and the
addition of special admixtures to meet the project specifications for SCC. The hardened
properties are expected to be similar to those obtainable with HPC concrete. Laboratory and
field tests have demonstrated that the SCC hardened properties are indeed similar to those
of HPC. Table 3 shows some of the structural properties of SCC.
Table 3 Structural Properties of SCC2
Items SCC
Water-binder ratio (%) 25 to 40
Air content (%) 4.5-6.0
Compressive strength (age: 28 days) (MPa) 40 to 80
Compressive strength (age: 91 days) (MPa) 55 to 100
-
8/12/2019 The Constructor Notes
21/65
Splitting tensile strength (age:28 days) (MPa) 2.4 to 4.8
Elastic modulus (GPa) 30 to 36
Shrinkage strain (x 10-6) 600 to 800
Compressive StrengthSCC compressive strengths are comparable to those of conventional vibrated concrete made
with similar mix proportions and water/cement ratio. There is no difficulty in producing SCC
with compressive strengths up to 60MPa.
Tensile StrengthTensile strengths are based on the indirect splitting test on cylinders. For SCC, the tensile
strengths and the ratios of tensile and compressive strengths are in the same order of
magnitude as the conventional vibrated concrete.
Bond StrengthPull-out tests have been performed to determine the strength of the bond between concrete
and reinforcement of different diameters. In general, the SCC bond strengths expressed in
terms of the compressive strengths are higher than those of conventional concrete.
Modulus of ElasticitySCC and conventional concrete bear a similar relationship between modulus of elasticity and
compressive strength expressed in the form E/(fc)0.5, where E = modulus of elasticity, fc =
compressive strength. This is similar to the one recommended by ACI for conventional
normal weight concrete.
Acceptance test at job site
Since the degree of compaction in a structure mainly depends on the self-compactability of
concrete, and poor self-compactability cannot be compensated by the construction work,
self-compactability must be checked for the whole amount of concrete just before casting at
the job site. However, conventional testing methods for self-compactability require sampling
-
8/12/2019 The Constructor Notes
22/65
and this can be extremely laborious if the self-compactability acceptance test is to be
carried out for the whole amount of concrete. A suitable acceptance test method for
selfcompactability has been developed by Ouchi et al (1999).
(1) The testing apparatus is installed between the agitator truck and the pump at the job
site. The whole amount of concrete is poured into the apparatus.(2) If the concrete flows through the apparatus, the concrete is considered as self-
compactable for the structure. If the concrete is stopped by the apparatus, the concrete is
considered as having insufficient selfcompactability and the mix proportion has to be
adjusted.
Superplasticizer suitable for Self-Compacting ConcreteThere is more room for improvement for admixtures such as superplasticizer suitable for
self-compacting concrete. In order to achieve this purpose, characterization of materials is
indispensable. The requirements for superplasticizer in self-compacting concrete are
summarized below.
(1) High dispersing effect for low water/powder (cement) ratio: less than approx. 100% by
volume
(2) Maintenance of the dispersing effect for at least two hours after mixing
(3) Less sensitivity to temperature changes.
There have been many examples of the development of new type of superplasticizer for
self-compacting concrete. Characterization of the dispersing effect of superplasticizer
independent of the effect of water flow is indispensable.
Segregation-inhibiting agentIt has been found that it is possible to manufacture selfcompacting concrete with constant
quality, especially self-compactability. However, any variation in material characteristics can
affect self-compactability. The most influential variant is the water content of fine
aggregate, which results in variations in the water content of the concrete itself. To solve
this problem, some general construction companies employ a segregation-inhibiting agent.
This type of agent is effective in making selfcompactability less sensitive to the variation of
the water content in the concrete. Various agents are available for this purpose in Japan
(Hibino 1998).
Applications of Self-Compacting Concrete in Japan
Current condition on application of selfcompacting concrete in Japan
-
8/12/2019 The Constructor Notes
23/65
After the development of the prototype of selfcompacting concrete at the University of
Tokyo, intensive research was begun in many places, especially in the research institutes of
large construction companies. As a result, self-compacting concrete has been used in many
practical structures. The first application of selfcompacting concrete was in a building in
June 1990. Self-compacting concrete was then used in the towers of a prestressed concrete
cable-stayed bridge in 1991 (Fig. 29). Lightweight self-compacting concrete was used in the
main girder of a cable-stayed bridge in 1992. Since then, the use of self-compacting
concrete in actual structures has gradually increased. Currently, the main reasons for the
employment of self-compacting concrete can be summarized as follows.
(1) To shorten construction period.
(2) To assure compaction in the structure: especially in confined zones where vibrating
compaction is difficult.
(3) To eliminate noise due to vibration: effective especially at concrete products plants.
The volume of self-compacting concrete in Japan is shown in Fig. 30. The production of self-
compacting concrete as a percentage of Japanese ready-mixed concrete, which accounts for
70% of total concrete production in Japan, is only 0.1%. The current status of self-
compacting concrete is special concrete rather than standard concrete.
Other applications of self-compacting concrete are summarized below.
Bridge (anchorage, arch, beam, girder, tower, pier, joint between beam & girder)
Box culvert
Building
Concrete filled steel column
Tunnel (lining, immersed tunnel, fill of survey tunnel)
Dam (concrete around structure)
Concrete products (block, culvert, wall, water tank, slab, and segment)
Diaphragm wall
-
8/12/2019 The Constructor Notes
24/65
Tank (side wall, joint between side wall and slab)
Pipe roof
Large scale constructionSelf-compacting concrete is currently being employed in various practical structures in order
to shorten the construction period of large-scale constructions.
The anchorages of Akashi-Kaikyo (Akashi Straits) Bridge opened in April 1998, a suspension
bridge with the longest span in the world (1,991 meters), is a typical example (Fig. 31)
(Kashima 1999). Self-compacting concrete was used in the construction of the two
anchorages of the bridge. A new construction system that makes full use of the
performance of self-compacting concrete was introduced for this purpose. The concrete was
mixed at the batcher plant next to the site, and was then pumped out of the plant. It wastransported 200 meters through pipes to the casting site, where the pipes were arranged in
rows 3 to 5 meters apart. The concrete was cast from gate valves located at 5-meter
intervals along the pipes. These valves were automatically controlled so that the surface
level of the cast concrete could be maintained. The maximum size of the coarse aggregate
in the self-compacting concrete used at this site was 40 mm. The concrete fell as much as 3
meters, but segregation did not occur, despite the large size of coarse aggregate. In the
final analysis, the use of selfcompacting concrete shortened the anchorage construction
period by 20%, from 2.5 to 2 years.
Self-compacting concrete was used for the wall of a large LNG tank belonging to the OsakaGas Company. The adoption of self-compacting concrete in this particular project had the
following merits.
(1) The number of lots decreased from 14 to 10 as the height of one lot of concrete was
increased.
(2) The number of concrete workers was reduced from 150 to 50.
(3) The construction period of the structure decreased from 22 months to18 months.
-
8/12/2019 The Constructor Notes
25/65
In addition, a rational acceptance test for self-compactability at the job site was newly
introduced. The concrete casting was completed in June 1998.
Concrete productsSelf-compacting concrete is often employed in concrete products to eliminate vibration noise
(Fig. 32). This improves the working environment at plants and makes the location ofconcrete products plants in urban areas possible. In addition, the use of self-compacting
concrete extends the lifetime of mould for concrete products (Uno 1999). The production of
concrete products using self-compacting concrete has been gradually increasing.
Necessity for new structural design and construction systems.Using self-compacting concrete saves the cost of vibrating compaction and ensures the
compaction of the concrete in the structure. However, total construction cost cannot always
be reduced, except in large-scale constructions.This is because conventional construction
systems are essentially designed based on the assumption that vibrating compaction of
concrete is necessary. Self-compacting concrete can greatly improve construction systems
previously based on conventional concrete that required vibrating compaction. This sort of
compaction, which can easily cause segregation, has been an obstacle to the rationalization
of construction work. Once this obstacle is eliminated, concrete construction can be
rationalized and a new construction system, including formwork, reinforcement, support and
structural design, can be developed. One example of this is the so-called sandwich
structure, where concrete is filled into a steel shell. Such a structure has already been
completed in Kobe, and could not have been achieved without the development of self-
compacting concrete (Shishido et al. 1999).
Summary
Since a rational mix-design method and an appropriate acceptance testing method at the
job site have both largely been established for self-compacting concrete, the main obstacles
for the wide use of self-compacting concrete can be considered to have been solved. The
next task is to promote the rapid diffusion of the techniques for the production of self-
compacting concrete and its use in construction. Rational training and qualification systems
for engineers should also be established. In addition, new structural design and construction
systems making full use of self-compacting concrete should be introduced.
When self-compacting concrete becomes so widely used that it is seen as thestandard
concrete rather than a special concrete, we will have succeeded in creating durable and
reliable concrete structures that require very little maintenance work.
-
8/12/2019 The Constructor Notes
26/65
AERATED CONCRETE & ITS PROPERTIES
Aeratedconcrete is made by introducing air or gas into a slurry composed of
Portlandcement or lime and finely crushed siliceous filler so that when the mix sets and
hardens, a uniformly cellular structure is formed. Though it is called aeratedconcrete it is
really not a concrete in the correct sense of the word. As described above, it is a mixture ofwater, cement and finely crushed sand. Aerated concrete is also referred to as gas concrete,
foam concrete, cellular concrete. In India we have at present a few factories manufacturing
aerated concrete.
A common product of aerated concrete in India is Siporex.
Manufacturing of Aerated ConcreteThere are several ways in which aerated concrete can be manufactured.
(a) By the formation of gas by chemical reaction within the mass during liquid or plastic
state.(b) By mixing preformed stable foam with the slurry.(c) By using finely powdered
metal (usually aluminium powder) with the slurry and made to react with the calcium
hydroxide liberated during the hydration process, to give out large quantity of hydrogen
gas. This hydrogen gas when contained in the slurry mix, gives the cellular structure.
Powdered zinc may also be added in place of aluminum powder. Hydrogen peroxide and
bleaching powder have also been used instead of metal powder. But this practice is not
widely followed at present.
In the second method preformed, stable foam is mixed with cement and crushed sand slurry
thus causing the cellular structure when this gets set and hardened. As a minor modification
some foam-giving agents are also mixed and thoroughly churned or beaten (in the same
http://theconstructor.org/practical-guide/material-testing/concrete-material-testing/http://theconstructor.org/building/building-material/cement/http://theconstructor.org/practical-guide/work-procedure/concrete-work-procedure/http://theconstructor.org/practical-guide/work-procedure/concrete-work-procedure/http://theconstructor.org/building/building-material/cement/http://theconstructor.org/practical-guide/material-testing/concrete-material-testing/ -
8/12/2019 The Constructor Notes
27/65
manner as that of preparing foam with the white of egg) to obtain foam effect in the
concrete. In a similar way, air entrained agent in large quantity can also be used and mixed
thoroughly to introduce cellular aerated structure in the concrete. However, this method
cannot be employed for decreasing the density of the concrete beyond a certain point and
as such, the use of air entrainment is not often practised for making aerated concrete.
Gasification method is of the most widely adopted methods using aluminium powder or such
other similar material. This method is adopted in the large scale manufacture of aerated
concrete in the factory wherein the whole process is mechanised and the product is
subjected to high pressure steam curing i.e., in other words, the products are autoclaved.
Such products will suffer neither retrogression of strength nor dimensional instability.
The practice of using preformed foam with slurry is limited to small scale production and in
situ work where small change in the dimensional stability can be tolerated. But the
advantage is that any density desired at site can be made in this method.
Properties of Aerated ConcreteUse of foam concrete has gained popularity not only because of the low density but also
because of other properties mainly the thermal insulation property. Aerated concrete is
made in the density range from 300 kg/m3 to about 800 kg/m3. Lower density grades are
used for insulation purposes, while medium density grades are used for the manufacture of
building blocks or load bearing walls and comparatively higher density grades are used in
the manufacture of prefabricated structural members in conjunction with steel
reinforcement.
COMPRESSIVE STRENGTH OF CONCRETE CUBES
Compressive strength ofconcrete:Out of many test applied to theconcrete,this is the
utmost important which gives an idea about all the characteristics of concrete. By this single
test one judge that whether Concreting has been done properly or not. For cube test two
types of specimens either cubes of 15 cm X 15 cm X 15 cm or 10cm X 10 cm x 10 cm
depending upon the size of aggregate are used. For most of the works cubical moulds of
size 15 cm x 15cm x 15 cm are commonly used.This concrete is poured in the mould and tempered properly so as not to have any voids.
After 24 hours these moulds are removed and test specimens are put in water for curing.
The top surface of these specimen should be made even and smooth. This is done by
puttingcement paste and spreading smoothly on whole area of specimen.
These specimens are tested by compression testing machine after 7 days curing or 28 days
curing. Load should be applied gradually at the rate of 140 kg/cm2 per minute till the
http://theconstructor.org/practical-guide/material-testing/concrete-material-testing/http://theconstructor.org/practical-guide/material-testing/concrete-material-testing/http://theconstructor.org/practical-guide/work-procedure/concrete-work-procedure/http://theconstructor.org/building/building-material/cement/http://theconstructor.org/building/building-material/cement/http://theconstructor.org/practical-guide/work-procedure/concrete-work-procedure/http://theconstructor.org/practical-guide/material-testing/concrete-material-testing/ -
8/12/2019 The Constructor Notes
28/65
Specimens fails. Load at the failure divided by area of specimen gives the compressive
strength of concrete.
Following are the procedure for Compressive strength test of Concrete Cubes
APPARATUSCompression testing machine
PREPARATION OF CUBE SPECIMENS
The proportion and material for making these test specimens are from the same concrete
used in the field.
SPECIMEN
6 cubes of 15 cm size Mix. M15 or above
MIXING
Mix the concrete either by hand or in a laboratory batch mixer
HAND MIXING
(i)Mix the cement and fine aggregate on a water tight none-absorbent platform until the
mixture is thoroughly blended and is of uniform color
(ii)Add the coarse aggregate and mix with cement and fine aggregate until the coarse
aggregate is uniformly distributed throughout the batch
(iii)Add water and mix it until the concrete appears to be homogeneous and of the desired
consistency
SAMPLING
(i) Clean the mounds and apply oil
(ii) Fill the concrete in the molds in layers approximately 5cm thick
(iii) Compact each layer with not less than 35strokes per layer using a tamping rod (steel
bar 16mm diameter and 60cm long, bullet pointed at lower end)
(iv) Level the top surface and smoothen it with a trowel
CURING
-
8/12/2019 The Constructor Notes
29/65
The test specimens are stored in moist air for 24hours and after this period the specimens
are marked and removed from the molds and kept submerged in clear fresh water until
taken out prior to test.
PRECAUTIONSThe water for curing should be tested every 7days and the temperature of water must be at
27+-2oC.
PROCEDURE
(I) Remove the specimen from water after specified curing time and wipe out excess water
from the surface.
(II) Take the dimension of the specimen to the nearest 0.2m
(III) Clean the bearing surface of the testing machine
(IV) Place the specimen in the machine in such a manner that the load shall be applied to
the opposite sides of the cube cast.
(V) Align the specimen centrally on the base plate of the machine.
(VI) Rotate the movable portion gently by hand so that it touches the top surface of the
specimen.
(VII) Apply the load gradually without shock and continuously at the rate of
140kg/cm2/minute till the specimen fails
(VIII) Record the maximum load and note any unusual features in the type of failure.
NOTE : Minimum three specimens should be tested at each selected age. If
strength of any specimen varies by more than 15 per cent of average strength,
results of such specimen should be rejected. Average of there specimens gives the
crushing strength of concrete. The strength requirements of concrete.CALCULATIONS
Size of the cube =15cm x15cm x15cm
Area of the specimen (calculated from the mean size of the specimen )=225cm2
Characteristic compressive strength(f ck)at 7 days =
-
8/12/2019 The Constructor Notes
30/65
Expected maximum load =fck x area x f.s
Range to be selected is ..
Similar calculation should be done for 28 day compressive strength
Maximum load applied =.tones = .N
Compressive strength = (Load in N/ Area in mm2)=N/mm2
=.N/mm2
REPORT
a) Identification mark
b) Date of test
c) Age of specimen
d) Curing conditions, including date of manufacture of specimen
f) Appearance of fractured faces of concrete and the type of fracture if they are unusual
RESULT
Average compressive strength of the concrete cube = .N/ mm2(at 7 days)
Average compressive strength of the concrete cube =. N/mm2(at 28 days)
Percentage strength of concrete at various ages:The strength of concrete increases with age. Table shows the strength of concrete at
different ages in comparison with the strength at 28 days after casting.
Age Strength per cent
1 day 16%
3 days 40%
7 days 65%
14 days 90%
28 days 99%
-
8/12/2019 The Constructor Notes
31/65
Compressive strength of different grades of concrete at 7 and 28 days
Grade of
Concrete
Minimum compressive
strength N/mm2at 7 days
Specified characteristic compressive
strength (N/mm2) at 28 days
M15 10 15
M20 13.5 20
M25 17 25
M30 20 30
M35 23.5 35
M40 27 40
M45 30 45
PILES AND PILE CAPS
When the bearing capacity ofsoil immediately below the structure is insufficient for a
spread footing, then piles are used to transfer the load to deeper, firmer strata. Piles may
also be used where the soil is particularly affected by seasonal changes, to transfer the load
below the level of such influence.
The load carrying (bearing) capacity of a pile is the sum of the end bearing capacity and the
skin friction capacity between the peripheral area of the pile and the surrounding soil. The
contribution of each differs widely depending on the ground conditions. For example, the
skin friction resistance in sandy soils is small compared to clayey soils.
Usually, the load to be supported exceeds the bearing capacity of a single pile, and so a
group of similar piles is used.
The group is capped by a spread footing or a cap to distribute the load to all piles in the
group. Where there are a large number of closely spaced piles, rather than provide
individual caps, it may be more economical to provide just one large cap, thus forming apiled raft.
http://theconstructor.org/practical-guide/material-testing/soil/http://theconstructor.org/practical-guide/material-testing/soil/ -
8/12/2019 The Constructor Notes
32/65
RETAINING WALL DESIGN PRINCIPLES
Retaining structures
Generally speaking, any wall that sustains significant lateral soil pressure is a retaining wall.
However, the term is usually used with reference to acantilever retaining wall,which is a
freestanding wall without lateral support at its top. For such a wall, the major design
consideration is for the actual dimensions of the ground-level difference that the wall serves
to facilitate. The range of its dimensions establishes some different categories for the
retaining structure as follow
(a) Curbs
Curbs are the shortest freestanding retaining structures. The two most common forms are
as shown in Figure 1(a), the selection being made on the basis of whether or not it is
necessary to have a gutter on the how side of the curb. Use of these structure is typically
limited to grade level changes of about 0.6m or less.
(b) Short retaining walls
Vertical walls up to about 3m in height are usually built as shown in Figure 1(b). these
consists of a concrete or masonry wall of uniform thickness, vertical wall reinforcing, and
transverse footing reinforcing are all designed for the lateral shear and cantilever bending
movement plus the vertical weights of the wall, footing, and earth fills.
When the bottom of the footing is a show distance below grade on the low side of the wall
and/or the lateral passive resistance of the soil is low, it may be necessary to use anextension below the footing called a shear key to increase the resistance to sliding. The
form of such a key is shown in Figure 1(c)
http://theconstructor.org/geotechnical/cantilever-retaining-wall/1991/http://theconstructor.org/geotechnical/cantilever-retaining-wall/1991/ -
8/12/2019 The Constructor Notes
33/65
Figure 1:- Retaining Structure
(c)Tall retaining walls
As the wall height increase it become less feasible to use the simple construction shown in
Figure 1(b) or (c). The overturning moment increases sharply with the increase in height of
the wall. For very tall walls one modification used is to taper the wall thickness. This permits
the development of a reasonable cross section for the high bending stress at the base
without an excessive amount of concrete. However, as the wall becomes really tall, it is
often necessary to consider the use of various bracing technique, as shown in Figure 2.
-
8/12/2019 The Constructor Notes
34/65
Figure 2:- Tall Retaining Walls
Design Considerations.
In the design of free-standing retaining walls, the following aspects need to be investigated:
(a) the stability of soil around the wall;
(b) the stability of retaining wall itself;
(c) the structural strength of the wall;
(d) damage to adjacent structures due to wall construction.
The magnitude of the earth pressure which will be exerted on a wall is dependent on the
amount of movement that the wall undergoes.
It is usual to assume for free-standing retaining walls that sufficient outward movement
occurs to allow active (minimum) earth pressures to develop. The designer must ensure
that sufficient movement can take place without affecting the serviceability or appearance of
the wall.
-
8/12/2019 The Constructor Notes
35/65
Where it is not possible for the required outward movement to occur, for instance due to
wall or foundation rigidity, higher pressures will develop and the wall must be designed for
these.
Basic LoadingThe basic pressure loading to be considered for the design is:
Normal Loading = static earth pressure + water pressure + pressure due to live loads or
surcharge.
In general, the resulting design pressure for earth retaining structures should not be less
than the pressure due to a fluid of unit weight 5kN/m3.
Other considerations
The possible occurrence of other design cases, or variation of the one above, caused by
construction sequence or future development of surrounding areas should also be
considered. For instances, additional surcharges may need to be considered and allowance
made for any possible future removal of ground in front of the wall in connection with
services, particularly if the passive resistance of this material is included in the stability
calculations. The effect of excavation on the wall bearing capacity may also need to be
considered.
For the determination of earth pressure, it is usual to consider a unit length of the cross-
section of the wall and retained soil. A unit length is also used in the structural design of
cantilever walls and other walls with a uniform cross-section.
Support of existing fill slopes
Fill slopes constructed in Hong Kong prior to 1977 are likely to have been end tipped or
inadequately compacted. Such slopes may be subject to liquefaction under conditions of
heavy rainfall, vibration or leakage from services, and resulting mud flows may have serious
consequences. Undercutting of the slope toe, for retaining wall construction, will increase
the risk of failure.
Soil PropertiesGeneralFor all walls higher than 5 meters, especially those with sloping backfill, the soil properties
of natural ground and backfill should be estimated in advance of design from tests on
samples of the material involved. In addition, special attention should be paid to the
determination of ground water levels, particularly with respect to maximum probable
values.
-
8/12/2019 The Constructor Notes
36/65
For less important walls, an estimation of the soil properties may be made from previous
tests on similar materials. A careful visual examination of the materials, particularly that at
the proposed foundation level, should be made and index tests carried out to ensure that
the assumed material type is correct.
Selection and use of backfill
The ideal backfill for a minimum section wall is a free draining granular material of high
shearing strength. However, the final choice of material should be based on the costs and
availability of such materials balanced against the cost of more expensive walls.
In general, the use of fine-grained clayey backfills is not recommended. Clays are subjected
to seasonal variation in moisture content and consequent swelling and shrinkage. This effect
may lead to an increase in pressure against a wall when these soils are used as backfill. Due
to consolidation, long term settlement problems are considerably greater than with cohesion
less materials.
For cohesive backfills, special attention must be paid to the provision of drainage to prevent
the built-up water pressure. Free draining cohesionless materials may not require the same
amount of attention in this respect. They may still require protection by properly designed
filter layers.
In Hong Kong, backfill for retaining walls usually comprises selected decomposed grainite or
decomposed volcanic rock. This material is in general suitable for backfill provided that it is
properly compacted and drainage measures are carefully designed and properly installed to
prevent build-up of water pressure.
In fact, rock fill is a very suitable material for use as a backfill to retaining walls and
consideration should be given to its use when available. In general, the rockfill should be
well graded and have a nominal maximum size of 200mm. A well-graded densely
compacted rockfill should not have more than about 2% finer than if it is to remain
free-draining.
Earth Pressure
The earth pressure which acts on an earth retaining structure is strongly dependent on the
lateral deformations which occur in the soil. Hence, unless the deformation condition can be
estimated with reasonable accuracy, rational prediction of the magnitude and distribution of
each pressure in the structure is not possible.
-
8/12/2019 The Constructor Notes
37/65
The minimum active pressure which can be exerted against a wall occurs when the wall moves sufficiently for
outwards for the soil behind the wall to expand laterally and reach a state of plastic
equilibrium.Similarly, the maximum passive pressure occurs when the wall movement is towards the
soil. The amount of movement necessary to reach these failure conditions is dependent
primarily on the type of backfill material. Some guidance on the movements is given inTable 1.
Table 1:- Wall displacements required to develop active and passive earth
pressure
Soil State of Stress Type of
Movement
Necessary
Displacement
Sand Active Parallel to wall 0.001H
Active Rotation about base 0.001H
Passive Parallel to wall 0.05H
Passive Rotation about base >0.1H
Clay Active Parallel to wall 0.004H
Active Rotation about base 0.004H
Passive -
Effects of surcharges
Load imposed on the soil behind the wall should be allowed for in design.
Uniform surcharge loads may be converted to an equivalent height of fill and the earth
pressures calculated for the correspondingly greater height. For example, the buildings with
shallow foundation may be taken as a uniform surcharge of 10kPa per storey. (Figure 1.3)
For example, the standard loading for highway structures in Hong Kong are expressed in
terms of HA and HB loading as defined in BS5400: part 2: 1978. In the absence of more
exact calculations, the nominal load due to live load surcharge may be taken from Table 2.
Table 2:- Suggested surcharge loads to be used in the Design of Retaining
Structures
-
8/12/2019 The Constructor Notes
38/65
Road Class Types of Live loading Equivalent Surcharge
Urban Trunk
Rural trunk
(road likely to be regularly
used by heavy industrial
traffic)
HA +45 units of HB 20kPa
Primary Distributor
Rural main road
HA + 37.5 units of HB 15kPa
Footpath, isolated from
roads, play areas
5kPa
.
Figure 3: Surcharge load cases
-
8/12/2019 The Constructor Notes
39/65
Effect of water
The presence of water behind a wall has a marked effect on the pressures applied to the
wall. When the water intersect the walls, a hydrostatic pressure will exert against the wall,
together with uplift pressures along the base of the wall. Even when there is no water in
direct contact with the wall, such as when adequate drainage is provided, there is anincreased pressure on the wall due to the increase earth pressure. The effect of water
behind the wall is significant; the total force may be more than double that applied for dry
backfill. Many recorded wall failures can be attributed to the presence of water.
The height to which water can rise in the backfill, and the volume of flow, are both of prime
concern. To determine these the ground water conditions must be established. These may
be best derived form the observation of groundwater conditions prior construction using
piezometers. Notwithstanding the results of groundwater monitoring, the groundwater level
assumed for design should be not lower than one-third of the retained height.
The effect of leakage from services can be significant. There is evidence from field
measurements and failures in Hong Kong that this leakage contributes substantially to both
perched and main groundwater tables. Where inadequate drainage is provided behind a
retaining structure, there may be a damming effect which would result in raising
groundwater levels locally and in the general areas. Such a rise may adversely affect
thestability of slopes and retaining walls. Effective drainage measures should always be
provided in such cases.
Stability of Retaining walls
The stability of a free standing retaining structure and the wall contained by it is determined
by computing factors of safety (or stability factors), which may be defined in general terms
as:
Fs= Moments or forces aiding stability / moments or forces causing instability
Factors of safety should be calculated for the following separate modes of failure and should
apply to the 1 in 10 year groundwater condition:
(a) sliding of the wall outwards from the retaining soil,
(b) overturning of the retaining wall about its toe,
(c) foundation bearing failure, and
(d) larger scale slope or other failure in the surrounding soil.
http://theconstructor.org/geotechnical/stability-of-slopes/2632/http://theconstructor.org/geotechnical/stability-of-slopes/2632/ -
8/12/2019 The Constructor Notes
40/65
The forces that produce overturning and sliding also produce the foundation bearing
pressures and, therefore, (a) and (b) above are inter-related with (c) in most soils.
In cases where the foundation material is soil, overturning stability is usually satisfied if
bearing criteria are satisfied. However, overturning stability may be critical for strongfoundation materials such as rock and so on.
In general, to limit settlement and tilting of walls on soil materials, the resultant of the
loading on the base should be within the middle third. For rock foundation material, the
resultant should be within the middle half of the base.
When calculating overall stability of a wall, the lateral such pressure is calculated to the
bottom of the blinding layer, or in the case of a base with a key, to the bottom of the key
where the actual failure mechanism extends to that point.
Concrete framing system
There are many different reinforced concrete floor system, both cast in place and precast.
The cast-in-place systems are generally of one of the following types:
(a) One-way solid slab and beam
(b) Two-way solid slab and beam
(c) One-way concrete joist construction
(d) Two-way flat slab or flat plate without beams
(e) Two-way joist construction, called waffle construction.
Each system has its distinct advantages and limitations, depending on the spacing of
supports, magnitude of loads, required fire rating, and cost of the construction. The floor
plan of the building and the propose for which the building is to be used determine loading
conditions and the layout of supports. Whenever possible, columns should be aligned in
rows and spaced at regular intervals in order to simplify and lower the cost of the building
construction.
One-way joist construction
Figure 2.1shows a partial framing plan and some details for a type of construction that
utilize a series of very closely spaced beams and a relatively thin solid slab. This system is
http://theconstructor.org/concrete/concrete-framing-system/487/http://theconstructor.org/concrete/concrete-framing-system/487/http://theconstructor.org/concrete/concrete-framing-system/487/ -
8/12/2019 The Constructor Notes
41/65
generally the lightest (in dead weight) of any type of flat-spanning, poured-in-place
concrete construction and is structurally well suited to the light loads and medium spans of
office buildings and commercial retail buildings.
Figure 2.1:- Typical Concrete One-way joist construction
Waffle construction
Waffle construction consists of two-way spanning joists that are formed in a manner similar
to that for one-way spanning joists. The most widely used type of waffle construction is the
waffle flat slab, in which solid portions around column supports are produced by omitting
the void-making forms. An example of a portion of such a system is shown in Figure 2.2.
However, at points of discontinuity in the plan, such as at large openings or at edges of the
building- it is usually necessary to form beams. These beam may be produced at projections
below the waffle, as shown in Figure 2.2.
-
8/12/2019 The Constructor Notes
42/65
Figure 2.2:- Typical concrete waffle construction
On the other hand, if beam are provided on all of the column lines, as shown in Figure 2.3,
the construction is analogous to the two-way solid slab with edge supports. With this
system, the solid portions around the column are not required, since the waffle itself does
not achieve the transfer of high shear or development of the high negative moment at the
column.
As with the one-way joist construction, fire ratings are low for ordinary waffle construction.
The system is best suited for situations involving relatively light loads, medium to long
spans, approximately square column bays and a reasonable number of multiple bays in each
direction.
-
8/12/2019 The Constructor Notes
43/65
Figure 2.3:- Waffle construction with column-line beams within the waffle depth
Two-way solid slabs
If reinforced in both directions, the solid concrete slab may span two ways as well as one.
The widest use of such a slab is in flat slab or flat plate construction. In flat slab
constriction, beams are used only at points of discontinuity, with the typical system
consisting only of the slab and the strengthening elements used at column supports. Typical
details for a flat slab system are shown in Figure 2.4. Drop panels consisting of thickened
portions square in plan are used to give additional resistance to high shear and negative
moment that develops at the column supports. Enlarged portions are also sometimes
provided at the tops of the columns to further reduce the stresses in the slab.
-
8/12/2019 The Constructor Notes
44/65
Figure 2.4:- Concrete flat slab construction with drop panels and column caps
Two-way slab construction consists of multiple bays of solid two-way-spanning slabs with
edges supports consisting of bearing wall of concrete. Typical details for such a system are
shown in Figure 2.5.
-
8/12/2019 The Constructor Notes
45/65
Figure 2.5:- Two-way spanning concrete slab construction with edge supports
Two way-solid slab constructions is generally favored over waffle construction where higher
fire rating is required for the unprotected structure or where spans are short and loadings
high. As with all types of two-way spanning system, they function most efficiently where the
spans in each direction are approximately the same.
Composite construction: concrete plus structural steel
Figure 2.6shows a section detail of a type of construction generally referred to as
composite construction. This consists of a poured concrete spanning supported by structural
steel beams, the two being made to interact by the use of shear developers welded to the
top of the beams and embedded in the cast slab. The concrete slab may be formed by use
of plywood sheets, resulting in the details as shown in Figure 2.6. however, a more popular
form of construction is that in which a formed steel deck is used in the usual manner,
welded to the top of the beams. The shear developers are than site-welded through the
deck to the top of the beam. The steel deck may function essentially only to form the
concrete, or may itself develop a composite action with the poured slab.
-
8/12/2019 The Constructor Notes
46/65
Figure 2.6:- Steel frame with poured-in-place concrete slab
THERMAL CRACKING OF CONCRETE AND PREVENTION
Thermal Cracking of Concrete and Prevention
Temperature difference within a concrete structure may be caused by portions of the
structure losing heat of hydration at different rates or by the weather conditions cooling or
heating one portion of the structure to a different degree or at a different rate than another
portion of the structure.
These temperature differences result in differential volume change, leading to cracks. This is
normally associated with mass concrete including large and thicker sections ( 500mm) of
column, piers, beams, footings and slabs. Temperature differential due to changes in the
ambient temperature can affect any structure.
-
8/12/2019 The Constructor Notes
47/65
The temperature gradient may be caused by either the centre of the concrete heating up
more than the outside due to the liberation of heat during cement hydration or more rapid
cooling of the exterior relative to the interior. Both cases result in tensile stresses on the
exterior and, if the tensile strength is exceeded, cracking will occur. The tensile stresses are
proportional to the temperature differential, the coefficient of thermal expansion, theeffective modulus of elasticity (which is reduced by creep), and the degree of restraint. The
more massive is the structure, the greater is the potential for temperature differential and
restraint.Hardened concrete has a coefficient of thermal expansion that may range from 4
to 910-6 per deg. F. When one portion of a structure is subjected to a temperature
induced volume change, the potential for thermally induced cracking exists. Special
consideration should be given to the design ofstructures in which some portions are
exposed to temperature changes, while other portions of the structure are either partially or
completely protected. A drop in temperature may result in cracking in the exposed element,
while increases in temperature may cause cracking in the protected portion of the structure.Preventive Measures:
Reducing maximum internal temperature. Delaying the onset of cooling. Controlling the rate at which the concrete cools by insulating the exposed concrete
surface during first 5 days. This could be done by 50mm thick thermocol sheets encased
with polythene sheet laid over concrete surfaces already covered with hessian cloth and
water sprinkler keeping the hessian wet. The temperature gradient between core of
concrete and the surfaces should not be allowed to be more than 150C.
Increasing the tensile strength of concrete. Reducing the concrete temperature at placement up to say 32 0 C. Using low heat of hydration cement or using fly ash replacement of part of cement. Keeping steel formwork warm by air heating during winter. Use of thermally insulating material as formwork. Keeping insulating formwork for longer duration. Low grade of cement, OPC 33 grade is the best. Cement with high C2S content.Repairs: Sealing and grouting ofconcrete cracks.
Concrete Crazing:Crazing is the development of a network of fine random cracks or fissures on the surface
ofconcrete caused by shrinkage of the surface layer.
http://theconstructor.org/concrete/special-concrete/hardened-concrete1/http://theconstructor.org/structures/http://theconstructor.org/concrete/crack/http://theconstructor.org/practical-guide/material-testing/concrete-material-testing/http://theconstructor.org/practical-guide/material-testing/concrete-material-testing/http://theconstructor.org/concrete/crack/http://theconstructor.org/structures/http://theconstructor.org/concrete/special-concrete/hardened-concrete1/ -
8/12/2019 The Constructor Notes
48/65
These cracks are rarely more than 3mm deep, and are more noticeable on over floated or
steel-troweled surfaces. The irregular hexagonal areas enclosed by the cracks are typically
no more than 40mm wide and may be as small as 10mm in unusual instances (Fig. 1(a) &
(b)).
Generally, craze cracks develop at an early age and are apparent the day after placement or
at least by the end of the first weak. Often they are not readily visible until the surface has
been wetted and it is beginning to dry.
They do not affect the structural integrity ofconcrete and rarely do they affect durability.
However crazed surfaces can be unsightly. Crazing in concrete usually occurs because of
wrongconstruction practices like:
Poor or inadequate curing. Intermittent wet curing and drying. Excessive floating Excessive laitance on surface. Finishing with float when bleed water is on the surface. Sprinkling cement on the surface to dry up the bleed water. Over vibration loading extra bleed & laitance on surface.Preventive Measure for Concrete Crazing: Proper and early start of curing. Use of curing compound on the surface. Never sprinkle dry cement or a mixture of cement and fine sand on the surface of the
plastic concrete.
http://theconstructor.org/practical-guide/work-procedure/concrete-work-procedure/http://theconstructor.org/constrution/http://theconstructor.org/constrution/http://theconstructor.org/practical-guide/work-procedure/concrete-work-procedure/ -
8/12/2019 The Constructor Notes
49/65
SOIL TESTS REQUIRED FOR DEEP
FOUNDATIONS
Deep foundations are those where the depth of foundation is generally greater than two
times of width of footing (D = 2B). Deep foundations are required due to variousreasons.Read hereabout why deep foundations are required and types of deep
foundations.
The soil tests required for deep foundations are:1. While the composition and depth of the bearing layer for shallow foundations may vary
from one site to another, most pile foundations in a locally encounter similar deposits. Since
pile capacity based onsoil parameters is not as reliable from load tests, as a first step it is
essential to obtain full information on the type, size, length and capacity of piles (including
details of load settlement graph) generally adopted in the locality. Correlation of soil
characteristics (from soil investigation reports) and corresponding load tests (from actualprojects constructed) is essential to decide the type of soil tests to be preformed and to
make a reasonable recommendation for the type, size, length and capacity of piles since
most formulae are empirical.
2. If information about piles in the localityare not available or reliable, it may be
necessary to drive a test pile and correlate with soil data.
3. Standard penetration test (SPT)to determine the cohesion (and consequently the
adhesion) to determine the angle of friction (and consequently the angle of friction between
soil and the pile and also the point of resistance) for each soil stratum of cohesion less soil
of soil.
4.Static cone penetration test (CPT)to determine the cohesion (and subsequently the
adhesion) for soft cohesive soils and to check with SPT result for fine to medium sands.
http://theconstructor.org/geotechnical/types-of-deep-foundation/7252/http://theconstructor.org/geotechnical/types-of-deep-foundation/7252/http://theconstructor.org/geotechnical/types-of-deep-foundation/7252/http://theconstructor.org/practical-guide/material-testing/soil/http://theconstructor.org/practical-guide/material-testing/soil/http://theconstructor.org/geotechnical/types-of-deep-foundation/7252/ -
8/12/2019 The Constructor Notes
50/65
Hence for strata encountering both cohesive and cohesion less soils, both SPT and CPT tests
are required.
5. Vane shear testfor impervious clayey soils.
6. Un-drained triaxial shear strengthof undisturbed soil samples (obtained with thin
walled tube samplers) to determine cohesion (c) and angle of internal friction ( ) for clayeysoils (since graphs for correlations were developed based on un-drained shear parameter).
In case of driven piles proposed for stiff clays, it is necessary to check with the c and
from remoulded samples also. Drained shear strength parameters are also determined to
represent in-situ condition of soil at end ofconstruction phase.
7. Self boring pressure meter testto determine modulus of sub-grade reaction for
horizontal deflection for granular soils, very stiff cohesive soils, soft rock and weathered or
jointed rock.
8. Ground water condition and permeability of soilinfluence the choice of pile type to
be recommended. Hence the level at which water in the bore hole remains are noted in thebore logs. Since permeability of clay is very low, it takes several days for water in the drill
hole to rise upto ground water table.
Ground water samples need to be testedto consider the possible chemical effects
onconcrete and the reinforcement. Result of the cone penetration test for the same soil
show substantial scatter. Hence, they need to be checked with supplementary information
from other exploration methods.
Pressure metersare used to estimate the in-situ modulus of elasticity for soil in lateral
direction. Unless the soil is isotropic, the same value cannot be adopted for the vertical
direction.
Composition and Types of SoilsSoil grains consists of inert rock materials (cobble, gravel, sand and silt) often combined
with significant amounts of clay (say more than 5%). While inert silt grains may be angular
or rounded (thus contributing to greater or less angle of internal friction), particles of clay
are small platelets with negative charges on both faces which attract the positively charged
ends of water molecules. Thus bond is responsible for the cohesion ends of water molecules.
This bond is responsible for the cohesion C of clay.
Silt or sand with appreciable amounts of clay (say more than 15%) behaves like clayey soil
since the permeability of clay is of the order of 10-7cm/s compared to 10cm/s for sand. This
capacity of the clay to hold the water molecules for long even when the pressure is applied
on the soil, greatly influences its behaviour, i.e. shear strength, compressibility and
permeability.
http://theconstructor.org/constrution/http://theconstructor.org/practical-guide/material-testing/concrete-material-testing/http://theconstructor.org/practical-guide/material-testing/soil/http://theconstructor.org/practical-guide/material-testing/soil/http://theconstructor.org/practical-guide/material-testing/concrete-material-testing/http://theconstructor.org/constrution/ -
8/12/2019 The Constructor Notes
51/65
Simple and Quick Methods of Field Identification of Soils:1. Fine sand is differentiated from siltby placing a spoonful of soil in a glass of jar or
test tube, mixing with water and shaking it to a suspension. Sand settles first, followed by
silt which may take about five minutes. This test may also be sued for clay which takes
more than 10 minutes to start settling. The percentages of clay, silt and sand are assessed
by observing the depths of the sediments.
2. Silt is differentiated from clay as follows:
a) Clay lumps are more difficult to crush with fingers than silt. When moistened, the soil
lump surface texture is felt with the finger. If it is smooth, it is clay, if rough it is silt.
b) A ball of the soil is formed and shaken horizontally on the palm of the hand. If the
material becomes shiny from water coming to the surface, it is silt.
c) If soil containing appreciable percent of clay is cut with a knife, the cut surface appears
lustrous. In case of silt, the surface appears dull.
3) Field indication for the consistency of cohesive soils are as follows:
Stiff consistency: Cannot be moulded with the finger. Medium consistency: Can be moulded by the fingers on strong pressure. Readily
indented with thumb nail.
Soft consistency: Easily moulded with the fingers.4) Colour of the soil indicatesits origin and the condition under which it was deposited.
Sand and gravel deposits may contain lenses of silt, clay or even organic deposits. If so, the
presumptive bearing capacity is reduced.
-
8/12/2019 The Constructor Notes
52/65
Based on the field identification of the soil, the presumptive bearing capacity of the soil can
be guessed by referring to Table-2 of IS:1904 1986. The objectives of preliminary soil
investigations are to drawn up an appropriate program for detailed soil investigation and to
examine the sketch plans and preliminary drawings prepared by the Architect from the point
of suitability of the proposed structure.
TO DETERMINE THE PARTICLE SIZE DISTRIBUTION OF ASOIL BY SEIVING
Theory:
The soil is sieved through a set of sieves. The material retained on different sieves is
determined. The percentage of material retained on any sieve is given by
Where = mass of soil retained on sieve n
M= total mass of the sample.
The cumulative percentage of the material retained
Where , etc are the percentages retained on sieve 1, 2 etc which are coarser than
sieve n. The percentage finer than the sieve n
Equipment:
1. Set of fine sieves, 2mm, 1mm, 600micron, 425, 212, 150, and 75 micron.
2. Set of coarse sieves, 100mm, 80mm, 40mm, 10mm, and 4.75mm.
3. Weighing balance with accuracy of 0.1% of the mass of the sample.
4. Oven
5. Mechanical shaker
6. Trays
http://theconstructor.org/practical-guide/material-testing/soil/http://theconstructor.org/practical-guide/material-testing/soil/ -
8/12/2019 The Constructor Notes
53/65
7. Mortar with a rubber covered pestle.
8. Brushes
9. Riffler
Part-I: Coarse Sieve Analysis
Procedure:
1. Take the required quantity of the sample. Sieve it through a 4.75mm Is sieve. Take the
soil fraction retained on 4.75mm IS sieve for the coarse sieve analysis (Part-I) and that
passing through the sieve for the fine sieve analysis (Part-II).
2. Sieve the sample through the set of coarse sieves by hand. While sieving through each
sieve, the sieve should be agitated such that the sample rolls in irregular motion over the
sieve, the material retained on the sieve may be rubbed with the rubber pestle in the
mortar, if necessary. Care shall be taken so as not to break the individual particles. The
quantity of the material taken for sieving on each sieve shall be such that the maximum
mass of material retained on each sieve does