P. 1 of 18 Physical Development Half-yearly Progress Report For the Period Ended 31 December 2019 This half-yearly report covers the progress of Capital, Alterations, Additions, Repairs and Improvements (AA&I) as well as major renovation, spatial reorganization and fitting out projects delivered by the Campus Development Office (CDO) from July to December 2019. Capital Projects Under Construction and Funding Applications (Appendix A and B) Under the UGC-funded Hostel Development Plan to construct six new hostels to mitigate the shortfall in hostel bed places in the past years, foundation works of the new hostel for New Asia College was in progress during the report period. Consultants were also engaged to commence the detailed design of two new hostels for United College and Shaw College respectively. The other three hostels for Chung Chi College, Wu Yee Sun College and Postgraduate Students were scheduled in future phases of development. 2. In parallel with the UGC-funded projects, foundation work was also in progress for the donation-funded Chung Chi Student Development Complex and consultant was engaged to embark the detailed design of a donation-funded annex for the Art Museum of the University, namely the Lo Kwee-Seong Pavilion. 3. In spite of the social unrest and disturbances during the report period, e.g. road blockages, impact on mass transit services and situations on the campus ground etc., only marginal impact was registered in the abovementioned works as the site operations were mainly foundation works with limited machinery and labour content only. 4. During the report period, significant progress was also registered in UGC funding applications with the submission of four new capital project proposals in September 2019; following the Government’s announcement in the 2019-20 Budget to set aside a dedicated provision of HK$16 billion to cater for the expansion and improvements of the local institutes and universities. 5. These submissions included the Technical Feasibility Studies (TFS) and Project Definition Statements (PDS) for: (a) Proposed Engineering Building at Central Campus; (b) Innovation and Sustainability Building at Station Road; (c) Centralised General Research Laboratory Complex (Block 3) in Area 39; and (d) Teaching Building Adjacent to Art Museum. Funding approval to commence the detailed design would be pending the selection of the projects to Category B- status by the Capital Works Resources Allocation Exercise (CWRAE) in September 2020 the earliest after departmental approval of the submissions. 6. Regarding the Centralized General Research Laboratory Complex (Block 2) in Area 39 which was upgraded to Category B+ in 2019 CWRAE; detailed design and preparation for calling the superstructure and foundation tender were in full swing. The project was scheduled for tabling in upcoming LegCo committee meetings in 2019/2020 legislative session, to seek funding approval for the construction works. Land formation was also embarked by Civil Engineering and Development Department targeted for site handover to CUHK in mid-2020 to commence the construction. 香 港 中 文 大 學 校 園 發 展 處 THE CHINESE UNIVERSITY OF HONG KONG Campus Development Office

Transcript of THE CHINESE UNIVERSITY OF HONG KONG Campus ...P. 3 of 18 Green Building & Architectural Design...

Page 1: THE CHINESE UNIVERSITY OF HONG KONG Campus ...P. 3 of 18 Green Building & Architectural Design Awards 2019 The Chinese University of Hong Kong 香港中文大學 Green Building Leadership

P. 1 of 18

Physical Development – Half-yearly Progress Report

For the Period Ended 31 December 2019

This half-yearly report covers the progress of Capital, Alterations, Additions, Repairs and Improvements

(AA&I) as well as major renovation, spatial reorganization and fitting out projects delivered by the

Campus Development Office (CDO) from July to December 2019.

Capital Projects Under Construction and Funding Applications (Appendix A and B)

Under the UGC-funded Hostel Development Plan to construct six new hostels to mitigate the

shortfall in hostel bed places in the past years, foundation works of the new hostel for New Asia College

was in progress during the report period. Consultants were also engaged to commence the detailed design

of two new hostels for United College and Shaw College respectively. The other three hostels for Chung

Chi College, Wu Yee Sun College and Postgraduate Students were scheduled in future phases of

development.

2. In parallel with the UGC-funded projects, foundation work was also in progress for the

donation-funded Chung Chi Student Development Complex and consultant was engaged to embark the

detailed design of a donation-funded annex for the Art Museum of the University, namely the

Lo Kwee-Seong Pavilion.

3. In spite of the social unrest and disturbances during the report period, e.g. road blockages, impact on

mass transit services and situations on the campus ground etc., only marginal impact was registered in the

abovementioned works as the site operations were mainly foundation works with limited machinery and

labour content only.

4. During the report period, significant progress was also registered in UGC funding applications with

the submission of four new capital project proposals in September 2019; following the Government’s

announcement in the 2019-20 Budget to set aside a dedicated provision of HK$16 billion to cater for the

expansion and improvements of the local institutes and universities.

5. These submissions included the Technical Feasibility Studies (TFS) and Project Definition

Statements (PDS) for: (a) Proposed Engineering Building at Central Campus; (b) Innovation and

Sustainability Building at Station Road; (c) Centralised General Research Laboratory Complex (Block 3)

in Area 39; and (d) Teaching Building Adjacent to Art Museum. Funding approval to commence the

detailed design would be pending the selection of the projects to Category B- status by the Capital Works

Resources Allocation Exercise (CWRAE) in September 2020 the earliest after departmental approval of

the submissions.

6. Regarding the Centralized General Research Laboratory Complex (Block 2) in Area 39 which was

upgraded to Category B+ in 2019 CWRAE; detailed design and preparation for calling the superstructure

and foundation tender were in full swing. The project was scheduled for tabling in upcoming LegCo

committee meetings in 2019/2020 legislative session, to seek funding approval for the construction

works. Land formation was also embarked by Civil Engineering and Development Department targeted

for site handover to CUHK in mid-2020 to commence the construction.

香 港 中 文 大 學

校 園 發 展 處

THE CHINESE UNIVERSITY OF HONG KONG

Campus Development Office

Page 2: THE CHINESE UNIVERSITY OF HONG KONG Campus ...P. 3 of 18 Green Building & Architectural Design Awards 2019 The Chinese University of Hong Kong 香港中文大學 Green Building Leadership

P. 2 of 18

7. Regarding the Food & Health Bureau (FHB)-funded capital project of Proposed Teaching-Research

Complex in Area 39 for Faculty of Medicine, Category B- status was already granted by CWRAE to

apply for the detailed design funding. However, the process was impacted by the disturbances to the

LegCo Complex during the social unrest; the LegCo meetings have to be rescheduled to 2020 after

completion of the reinstatement works.

8. Progressive liaisons were also conducted with FHB regarding site and funding allocations to provide

CUHK with the needed facilities and new buildings in association with the Redevelopment of the Prince

of Wales Hospital (PWH) which was underway. FHB has also clarified that these provisions on CUHK

and PWH campuses to support the needy expansion of medical education, research and nurse training

would not be accountable under the UGC space inventory.

AA&I, Renovation and Minor Works Projects (Appendix C, D and E)

Funded by the Food & Health Bureau (FHB), urgent renovations works for the Choh-Ming Li Basic

Medical Sciences Building was delivered swiftly by the Campus Development Office during the report

period to facilitate the intake of increased number of medical and nursing students in the academic year

2019-20. In parallel, the UGC-funded AA&I projects e.g. Sports Centre Annex, alteration and addition

works to existing laboratory buildings were in steady progress together with various universal access and

slope enhancement works etc.

2. Regarding the assets enhancement works for the aged facilities, privately-funded renovations were

being carried out to various I-Houses, University lodges of Chiangs Building and Chan Kwan Tung

Inter-University Hall. Detailed Design was also in full swing to facilitate the conversion of the

Inter-University Hall near MTR Station into an InnoHub for knowledge transfer and incubation.

3. With the funding support to establish six research centres for the Health@InnoHK and

AIR@InnoHK in Hong Kong Science & Technology Park (HKSTP) under the HK$10 billion Innovation

Funding Scheme initiated by the HKSAR Government, users’ engagement and fitting out works design

were also coordinated progressively with the project consultants; works will be tendered and carried out

in phases to tally with the operational schedules of the six InnoCentres and space availability in HKSTP.

Preliminary Master Plan Concept for Redevelopment of Existing Public Transport Interchange

near MTR University Station

In response to an earlier conversation between the Government and the University Management, a

Preliminary Master Plan Concept was also compiled to explore the potential redevelopment of the

existing Public Transport Interchange near the MTR University Station and the adjacent areas to cater for

CUHK and CUHK Medical Center’s future expansions and long range developments in the vicinity.

Project Portfolio

The updated portfolio of active projects under planning, funding applications, detailed design and

construction are summarized as follows; the monthly and cumulative totals for consultancies services and

works in progress are listed overleaf for reference:

i) UGC-funded capital projects under detailed design and construction amounted to HK$2,600mil;

ii) Donation-funded capital projects amounted to HK$850mil;

iii) The budget estimates for new capital projects under planning and applications for UGC / FHB funding

amounted to HK$11,600mil.

Page 3: THE CHINESE UNIVERSITY OF HONG KONG Campus ...P. 3 of 18 Green Building & Architectural Design Awards 2019 The Chinese University of Hong Kong 香港中文大學 Green Building Leadership

P. 3 of 18

Green Building & Architectural Design Awards 2019

The Chinese University of Hong Kong 香港中文大學

Green Building Leadership Category (Government, Institutions & NGOs) - PIONEER AWARD

綠建領導類別 - 先鋒大獎 (政府機構,公用機構及非政府組織)

CUHK is the first and only University in Hong Kong receiving this prestige award; putting CUHK in the GBA Green Building Leadership

hall of fame together with other top notch companies / organizations e.g. Henderson Land Development Company Limited, New World

Development Limited, Swire Properties Limited, The Hong Kong Housing Authority etc.

Jockey Club Postgraduate Halls 2&3, CUHK 賽馬會研究生宿舍二座及三座

GREEN BUILDING AWARD 2019: FINALIST

(New Buildings Category: Completed Projects – Residential Building)

THE HONG KONG INSTITUTE OF ARCHITECTS ANNUAL AWARDS 2018/19: FINALIST

(Residential Building)

Chung Chi Student Development Complex 崇基學生活動中心

GREEN BUILDING AWARD 2019: FINALIST

(New Buildings Category: Projects Under Construction and /or Design - Institutional Building)

WORLD ARCHITECTURE FESTIVAL 2019: SHORTLISTED

(Future Project: Education)

CUHK Medical Centre 香港中文大學醫院

GREEN BUILDING AWARD 2019: FINALIST

(New Buildings Category: Projects Under Construction and / or Design – Commercial Building)

Page 4: THE CHINESE UNIVERSITY OF HONG KONG Campus ...P. 3 of 18 Green Building & Architectural Design Awards 2019 The Chinese University of Hong Kong 香港中文大學 Green Building Leadership

P. 4 of 18

Physical Development – Half-yearly Progress Report

For the Period Ended 31 December 2019

Description 2019

Cumulative Total for the Fiscal Year(s)

July August September 2019-20 2018-19/2017-18

Expenditures on Capital and AA&I Works, inclusive of hostel development and private funds

$15.811m $24.056m $24.297m $88.317m $210.932m/$138.018m

Expenditures on Minor Works (supported by Minor Works vote and others)

$15.692m $14.207m $15.757 $80.971m $69.046m/$83.319m

Description 2019

Cumulative Total for the Fiscal Year(s)

October November December 2019-20 2018-19/2017-18

Expenditures on Capital and AA&I Works, inclusive of hostel development and private funds

$22.246m $10.286m $34.719m $155.568m $247.102m/$228.762m

Expenditures on Minor Works (supported by Minor Works vote and others)

$20.979m $16.539m $17.253m $135.742m $111.639m/$110.927m

Note: Fiscal year - 1st April 2019 to 31st March 2020

Report Period - 1st July 2019 to 31st December 2019

Page 5: THE CHINESE UNIVERSITY OF HONG KONG Campus ...P. 3 of 18 Green Building & Architectural Design Awards 2019 The Chinese University of Hong Kong 香港中文大學 Green Building Leadership

P. 5 of 18

Physical Development – Half-yearly Progress Report

For the Period Ended 31 December 2019

Section Content Page

I. MAJOR CAPITAL PROGRAMME ON UGC FUNDING 7 - 9 1. Jockey Club Postgraduate Halls 2 & 3

(previously named 2x338-place Student Hostels (Block A3 & A4) on Northern Campus)

2. New Student Hostels under Hostel Development Fund (HDF)

(a) 300-place Student Hostel at New Asia Campus

(b) 250-place Student Hostel at United Campus

(c) 300-place Student Hostel at Shaw Campus

(d) 300-place Student Hostel at Chung Chi Campus

(e) 250-place Student Hostel at Wu Yee Sun Campus

(f) 394-place Student Hostel in Area 39

3. Centralised General Research Lab Complex (Block 2) in Area 39

4. Final Accounts of 3+3+4 Capital and New College Projects

II. AA&I WORKS ON UGC BLOCK ALLOCATION 10 - 12 A. 2019-2020 Block Allocation

1. Space Addition and Reorganization at G/F of Lady Shaw Building for Office / Teaching Laboratory

2. Infrastructure and Safety Enhancement Works -

(a) Stabilisation Works for Slope Behind University Residence No. 16 & 17

(b) Construction of New Dangerous Goods Stores for Compressed Gases on Campus

3. Repairing Works for Two Slopes with Potential Danger B. 2018-2019 Block Allocation

1. Upgrading of Information Technology Infrastructure for Next Generation Campus Network

2. Provisions of New Laboratory Space –

(a) Spatial Reorganisation of 5/F Mong Man Wai Building and Lady Shaw Building

(b) Extension on 2/F of Ho Sin-Hang Engineering Building

3. Spatial Re-organization and Improvement Works for Dissecting Laboratories on LG/F of Choh-Ming Li

Basic Medical Sciences Building

C. 2017-2018 Block Allocation

1. Extension on roof of Mong Man Wai Building and 1/F of William M.W. Mong Engineering Building for

new laboratory space

2. Extension of University Sports Centre

III. OTHER CAPITAL PROJECTS AND AA&I WORKS 13 - 14 1. Teaching-Research Complex in Area 39 2. Redevelopment of Prince of Wales Hospital and Associated University Facilities in Prince of Wales Hospital by

Hospital Authority

3. Chung Chi Student Development Complex 4. Lo Kwee Seong Pavilion of the Art Museum 5. Renovation of Facilities in Choh-Ming Li Basic Medical Science Building (Remaining Works) 6. Six InnoCentres at the Hong Kong Science and Technology Park

7. Other Minor Projects Being or Having Been Put Forth to the UGC for AA&I Funding Consideration

IV. MINOR WORKS 15 - 18

Appendix – Selected Projects Images

i – xv

Page 6: THE CHINESE UNIVERSITY OF HONG KONG Campus ...P. 3 of 18 Green Building & Architectural Design Awards 2019 The Chinese University of Hong Kong 香港中文大學 Green Building Leadership

P. 6 of 18

Physical Development – Half-yearly Progress Report

For the Period Ended 31 December 2019

Key Legend:

P: Project: M: Amount of Contract/Sub-contract:

AP Authorized Person $A Air-conditioning Installation

PA Project Architect/Architectural Consultant $AV Audio-visual System

PB Building Services Consultant $C Construction Works

PD Project Designer $E Electrical Installation

PG Geotechnical Consultant $F Fire Services Installation

PLA Landscape Architect $F&E Major Equipment Installation

PM Project Manager $FO Fitting-out Works

PQ Quantity Surveyor/Building Surveyor $L Lifts Installation

PS Structural Consultant $LF Laboratory Furniture Installation

TBA To be Appointed $M Building Construction / Main Contract Works

$R Foundation / Sub-structure

$S Site Investigation/Slopes/External Works

$T Telephone System

C: Contract/Sub-contract:

CA Air-conditioning Installation

CAV Audio-visual System

CD&B Design & Build D: Date:

CE Electrical Installation D/AIP Date accorded AIP

CF Fire Services Installation D/C Date for Commencement

CF&E Furniture & Equipment Installation DC/E Date for Completion with Anticipated EOT

CFO Fitting-out Works D/FA Date accorded Full Approval

CL Lifts Installation D/PC Date of Practical Completion

CLF Laboratory Furniture Installation D/TC Date for Targeted Completion

CM Building Main Contractor

CR Substructural

CS Site Investigation/Slopes/External Works

CT Telephone System

GI Ground Investigation

TS Topographic Survey

Page 7: THE CHINESE UNIVERSITY OF HONG KONG Campus ...P. 3 of 18 Green Building & Architectural Design Awards 2019 The Chinese University of Hong Kong 香港中文大學 Green Building Leadership

P. 7 of 18

Physical Development – Half-yearly Progress Report

For the Period Ended 31 December 2019

I. Major Capital Programme on UGC Funding:

Project Title

Percentage

of Works

Completed

Description

Dec

I. 1. Jockey Club Postgraduate Halls 2 & 3

(previously named 2x338-place Student Hostels

(Block A3 & A4) on Northern Campus)

PM – Holman Chong

AP/PA – Andrew Lee King Fun & Associates Architects Ltd.

PS/PG – Meinhardt (C&S) Ltd.

PLA – ACLA Ltd.

PB – Parsons Brinckerhoff (Asia) Ltd.

PQ – Rider Levett Bucknall Ltd.

CM – Chinney Construction Co. Ltd.

D/FA – July 2015

D/C – November 2016 (CM)

D/TC – 4th Quarter 2018

(a) Outline Proposal / Schematic Design 100% Occupation Permit for the hostel blocks was issued by

Buildings Department in November 2018.

Hostel blocks had been completed and handed over to user in

December 2018. Fitting-out works for Amenity Hall and

statutory inspections for Sports Court were completed in June

2019.

Defects rectification were in progress. Ad hoc site meetings

were conducted to review the status of defect rectification.

Materials and documents for BEAM Plus Final Assessment

submission had been made in December 2019.

Preparation of final accounts were in progress for the Main

Contract and direct contracts for FF&E.

Opening Ceremony with donor was held in October 2019.

(b) Detailed Design 100%

(c) Tendering 100%

(d)

(e)

Foundation Works

Site Works

100%

100%

Page 8: THE CHINESE UNIVERSITY OF HONG KONG Campus ...P. 3 of 18 Green Building & Architectural Design Awards 2019 The Chinese University of Hong Kong 香港中文大學 Green Building Leadership

P. 8 of 18

Physical Development – Half-yearly Progress Report

For the Period Ended 31 December 2019

I. Major Capital Programme on UGC Funding (cont’d):

Project Title

Percentage

of Works

Completed

Description

Dec

I. 2. New Student Hostels under Hostel Development Fund

(HDF)

(a) 300-place Student Hostel at New Asia Campus

(Project Estimate : HK$269.2Mil)

PM – Stephen Leung

PA – Spence Robinson Ltd.

PQ – K.C. Tang Consultants Ltd.

CM – Build King Construction Ltd.

D/C – 17 Jun 2019 (CM)

D/PC – 2nd Quarter 2022

D/TC – 3rd Quarter 2022

(i) Hoarding Work

(ii) Site Formation Work

(iii) Foundation Work

100%

16%

0%

Main Contract was awarded in June 2019. Hoarding work

was completed in Oct 2019. Section 1 Works including Site

Formation and Foundation Works are in progress. Section 2

on Superstructure Works will be commenced tentatively in

August 2020.

(b) 250-place Student Hostel at United Campus

(Project Estimate : HK$224.3Mil)

PM – Thomas Yuen / Hocky Lam AP – LWK & Partners (HK) Ltd. PA – Ida & Billy Architects Ltd. PS/PG – Arthur Yung and Associates Co. Ltd. PB – Far East Consulting Engineers Ltd. PLA – LWK & Partners (HK) Ltd. PQ – Beria Consultant Ltd.

D/FA – December 2018

D/C – 1st Quarter 2021

D/TC – 3rd Quarter 2023

(i) Consultancy appointment

(ii) Outline Proposal / Schematic Design

(iii) Statutory Submission

100%

70%

10%

The Lead Architectural Consultancy Service was awarded in

May 2019 for commencement of design, and the Quantity

Surveying Consultancy Service was awarded in July 2019.

Design workshops with the College were held in September

and October 2019 to explore design possibilities and options.

Building Committee Meetings were held in September and

November 2019 to review and discuss the project design,

budget, programme and proposal for adjustments / addition

parameters.

College consultation was scheduled to be held in 1st Quarter

2020. General building plan was under preparation and

scheduled to be submitted to Buildings Department for

approval in 1st Quarter 2020.

(c) 300-place Student Hostel at Shaw Campus

(Project Estimate : HK$269.2Mil)

PM – Patrick Chan / German Cheung

PA – WCWP International Ltd.

PQ – Rider Levett Bucknall Ltd.

D/FA – December 2018

D/C – 2nd Quarter 2021

D/TC – 2nd Quarter 2024

(i) Consultancy appointment

(ii) Outline Proposal / Schematic Design

100%

50%

The Lead Architectural Consultancy Service was awarded in

October 2019 for commencement of schematic design.

(d) 300-place Student Hostel at Chung Chi

Campus (Project Estimate : HK$269.2Mil)

(e) 250-place Student Hostel at Wu Yee Sun

Campus (Project Estimate : HK$224.3Mil)

Undergoing planning and preliminary design

(f) 394-place Student Hostel in Area 39

(Project Estimate : HK$353.5Mil)

Page 9: THE CHINESE UNIVERSITY OF HONG KONG Campus ...P. 3 of 18 Green Building & Architectural Design Awards 2019 The Chinese University of Hong Kong 香港中文大學 Green Building Leadership

P. 9 of 18

Physical Development – Half-yearly Progress Report

For the Period Ended 31 December 2019

I. Major Capital Programme on UGC Funding (cont’d):

Project Title

Percentage

of Works

Completed

Description

Dec

I. 3. Centralized General Research Laboratories Complex

(Block 2) in Area 39

(Project Estimate : HK$1,400Mil)

PM – S.C. Li / Thomas Yuen AP/PA – Andrew Lee King Fun & Associates Architects Ltd. PS/PG – Meinhardt (C&S) Ltd. PLA – Urbis Ltd. PB – WSP Hong Kong Ltd. PQ – Rider Levett Bucknall Ltd.

D/FA – September 2017

D/C – July 2020

D/TC – December 2023

The project was upgraded to Cat. B+ in 2019 CWRAE.

Detailed design report and full set of tender document were

submitted to UGC / ArchSD for their vetting in September

and November 2019 respectively.

Detailed design was in full swing and regular design

workshops were held with the users to establish the detailed

laboratory requirements.

Tender for superstructure and foundation works was

scheduled to be issued in March 2020. PWSC and FC

meetings of the Legislative Council were scheduled in 2nd

Quarter 2020 for construction funding approval.

I. 4. Final Accounts of 3+3+4 Capital and New College

Projects

(a) Centralized General Research Laboratories

Complex (Block 1) in Area 39

Assessment of bills of variations and preparation of final

account of works contracts for project close out with the UGC

were in progress. The project final accounts are anticipated

to be completed progressively.

(b) 1,500-place Student Hostels

Site A: Morningside College & S.H. Ho College

Site B: Lee Woo Sing College

(c) Extension to Existing University Library 100%

(d) Student Amenity Centre

(e) An Integrated Teaching Building

(f) Two-Integrated Teaching Buildings

- Yasumoto International Academic Park (YIA)

- Wu Ho Man Yuen Building (WMY)

Page 10: THE CHINESE UNIVERSITY OF HONG KONG Campus ...P. 3 of 18 Green Building & Architectural Design Awards 2019 The Chinese University of Hong Kong 香港中文大學 Green Building Leadership

P. 10 of 18

Physical Development – Half-yearly Progress Report

For the Period Ended 31 December 2019

II. AA&I Works on UGC Block Allocation:

A. 2019-2020 Block Allocation

Project Title

Percentage

of Works

Completed

Description

Dec

II.A.1. Space Addition and Reorganisation at G/F of Lady

Shaw Building for Office/Teaching Laboratory

(Approved Project Estimate: HK$29.946Mil)

PM – Patrick Chan / German Cheung

D/FA – March 2019

D/C – 4th Quarter 2020

D/TC – 1st Quarter 2022

(a)

Structural Feasibility and Invitation of

Expression of Interest for Consultancies

Services

80%

Users’ allocation to be discussed to formulate the users’

requirements.

II.A.2. Infrastructure and Safety Enhancement Works

(Approved Project Estimate: HK$29.078Mil)

(a)

Stabilisation Works for Slope Behind University

Residence No. 16 & 17 (7NE – C/C65)

PM – Arthur Ma

PG – AECOM Asia Co. Ltd.

D/FA – August 2018

D/C – November 2019

D/TC – 3rd Quarter 2020

(i) Investigation / Site Survey

(ii) Detailed Design

(iii) Tendering

(iv) Stabilization Works

100%

100%

100%

15%

Design submission was approved by Buildings Department.

Contract for the slope stabilization works was awarded and

site works was commenced in November 2019.

(b)

Construction of New Dangerous Goods Stores

for Compressed Gases on Campus

PM – Hocky Lam

AP/PA –Singular Studio Ltd.

D/FA – March 2019

D/C – 3rd Quarter 2020

D/TC – 1st Quarter 2021

(i) Consultancy Services Appointment

(ii) Outline Proposal / Schematic Design

(iii) Statutory Submission

100%

100%

50%

The Lead Architectural Consultancy Services and the

Quantity Surveying Consultancy Service were awarded in

August 2019 for commencement of design. Regular meetings

with the users were held to establish the users’ requirement,

reviewing the conceptual design and design development.

General building plans and structural plans were submitted to

Buildings Department for approval in December 2019.

II.A.3. Repairing Works for Two Slopes with Potential

Danger

(Approved Project Estimate: HK$6.0Mil)

PM – Arthur Ma / Paul Seto

PG – Au Posford Consultants Ltd.

D/FA – 2nd Quarter 2020

D/C – 3rd Quarter 2020

D/TC – 1st Quarter 2021

(a)

(b)

(c)

(d)

(e)

Consultancy Services Appointment

Investigation / Site Survey

Design and Statutory Approval

Tendering

Stabilization Works

100%

20%

0%

0%

0%

Geotechnical consultant was appointed in December 2019 and

desk study / stability investigation began. Slope stabilization

design targeted to be submitted to Buildings Department for

approval in February 2020.

Page 11: THE CHINESE UNIVERSITY OF HONG KONG Campus ...P. 3 of 18 Green Building & Architectural Design Awards 2019 The Chinese University of Hong Kong 香港中文大學 Green Building Leadership

P. 11 of 18

Physical Development – Half-yearly Progress Report

For the Period Ended 31 December 2019

II. AA&I Works on UGC Block Allocation:

B. 2018-19 Block Allocation

Project Title

Percentage

of Works

Completed

Description

Dec

II.B.1. Upgrading of Information Technology Infrastructure

for Next Generation Campus Network

(Approved Project Estimate: HK$29.938Mil)

D/FA – March 2018

D/C – March 2019

D/TC – December 2020

(a)

(b)

(c)

(d)

Outline Proposal / Schematic Design

Detailed design

Tendering

Construction

100%

100%

100%

70%

Detailed design for the information technology infrastructure

was completed. Procurement of equipment was underway.

Site works commenced in January 2019 and to be completed

progressively.

II.B.2.

Provisions of New Laboratory Space

(Approved Project Estimate: HK$27.462Mil)

(a)

Spatial Reorganisation of 5/F Mong Man Wai

Building and Lady Shaw Building

PM – Mabel Lam

D/FA – May 2019

D/C – March 2020

D/TC – December 2020

(i) Outline Proposal / Schematic Design

(ii) Detailed Design

(iii) Tendering

(iv) Site Work

100%

100%

100%

50%

Construction works for the new office / workshop at Lady

Shaw Building were completed. The detailed design for the

laboratories on 5/F of Mong Man Wail Building was mostly

completed. General building plan submission was made.

Site work would commence in April 2020.

(b) Extension on 2/F of Ho Sin-Hang Engineering

Building

PM – Hocky Lam

AP/PA – Seniorman Design Ltd.

D/FA – March 2018

D/C – 1st Quarter 2020

D/TC – 3rd Quarter 2020

(i) Consultancy Appointment

(ii) Outline Proposal / Schematic Design

(iii) Statutory Submission

(iv) Detailed Design

(v) Tendering

100%

100%

100%

100%

80%

General building plans and structural plans submissions were

approved by Buildings Department. Regular design

workshops were held with the users to review and develop the

detailed designs and tender drawings. Tender for main contract

was issued in November 2019 and returned in December 2019.

Tender assessment was underway.

II.B.3. Spatial Re-organization and Improvement Works for

Dissecting Laboratories on LG/F of Choh-Ming Li

Basic Medical Sciences Building

(Approved Project Estimate: HK$29.986Mil)

PM – S.C. Li

D/FA – December 2018

D/C – March 2019

D/TC – August 2019

(a)

(b)

(c)

(d)

Outline Proposal / Schematic Design

Detailed design

Tendering

Construction

100%

100%

100%

100%

Detailed design was completed. Main Contract was awarded

in February 2019. The works were completed in August

2019 and handovered to users to meet the new academic term

of September 2019.

Page 12: THE CHINESE UNIVERSITY OF HONG KONG Campus ...P. 3 of 18 Green Building & Architectural Design Awards 2019 The Chinese University of Hong Kong 香港中文大學 Green Building Leadership

P. 12 of 18

Physical Development – Half-yearly Progress Report

For the Period Ended 31 December 2019

II. AA&I Works on UGC Block Allocation:

C. 2017-18 Block Allocation

Project Title

Percentage

of Works

Completed

Description

Dec

II.C.1. Provision of New Laboratory Space

(Approved Project Estimate : HK$29.811Mil) (a) Extension on roof of Mong Man Wai Building

for New laboratory space

PM – Thomas Yuen / Hocky Lam AP/PA – Cheung Kong-Yeung Architects Ltd. CM – Goldfield N&W Construction Co. Ltd D/FA – March 2017 D/C – November 2019 D/TC – 3rd Quarter 2020

(i) Consultancy Appointment

(ii) Outline Proposal / Schematic Design

(iii) Statutory Submission

(iv) Detailed Design

(v) Tendering

(vi) Construction

100% 100% 100% 100% 100% 5%

Tender assessment was completed and Main Contract was

awarded in October 2019. Consent application to Buildings

Department for commencement of work was submitted in

November 2019 and scheduled to commence works in

January 2020.

(b) Extension on 1/F of William M.W. Mong

Engineering Building for new laboratory space

PM – Thomas Yuen/ Hocky Lam

AP/PA – Cheung Kong-Yeung Architects Ltd.

CM – Goldfield N&W Construction Co. Ltd

D/FA – March 2017

D/C – November 2019

D/TC – 2nd Quarter 2020

(i) Consultancy Appointment

(ii) Outline Proposal / Schematic Design

(iii) Statutory Submission

(iv) Detailed Design

(v) Tendering

(vi) Construction

100%

100%

100%

100%

100%

5%

Tender assessment was completed and Main Contract was

awarded in October 2019. Consent application to Buildings

Department was submitted in November 2019 and scheduled

to commence work in January 2020.

II.C.2. Extension of University Sports Centre

(Approved Project Estimate: HK$29.951Mil)

PM – Thomas Yuen AP/PA – Meta 4 Design Forum Ltd. CM – Chiu Lee Construction Co. Ltd. D/FA – March 2017 D/C – April 2019 D/TC – 1st Quarter 2021

(a)

(b)

(c)

(d)

(e)

Consultancy Appointment

Outline Proposal / Schematic Design

Statutory Submission

Detailed Design

Tendering

100% 100% 100% 100% 100%

Construction works was commenced in August 2019. Site

formation, foundation and drainage diversion works were in

progress.

(f) Construction

20%

Page 13: THE CHINESE UNIVERSITY OF HONG KONG Campus ...P. 3 of 18 Green Building & Architectural Design Awards 2019 The Chinese University of Hong Kong 香港中文大學 Green Building Leadership

P. 13 of 18

Physical Development – Half-yearly Progress Report

For the Period Ended 31 December 2019

III. Other Capital Projects and Major Alterations, Additions and Improvement (AA&I) Works:

(on private funds or seeking UGC’s support)

Project Title

Percentage

of Works

Completed

Description

Dec

III. 1. Teaching–Research Complex in Area 39 Building Committee was formed and its 1st meeting was held

in December 2019. A first draft of the tender document for

the consultancy was also prepared and issued to ASD for

comment in November 2019. Invitation for Expression of

Interest in the Lead Architectural and Associated Consultancy

was issued in December 2019.

III. 2. Redevelopment of Prince of Wales Hospital (PWH)

and the associated University Facilities in Prince of

Wales Hospital by Hospital Authority (HA)

Schedule of Accommodation for University space in PWH

was worked out by Faculty of Medicine and submitted to HA

for their incorporation. Scheme layout plans on the

reprovisioned space at existing HA premises from the project

consultants of HA was commented by the University for HA’s

consideration. In addition, scheme design proposals for the

Faculty’s proposed new developments in / or adjoining to the

PWH Campus was under study for FHB’s and HA’s

consideration.

III. 3.

Chung Chi Student Development Complex at Chung

Chi College

(Project Estimate : HK$250Mil)

PM – Patrick Chan / German Cheung

PA – Leigh & Orange Ltd.

PQ – KC Tang Consultants Ltd.

D/FA – 1st Quarter 2019

D/C – March 2019

D/TC – 3rd Quarter 2021

(a) Feasibility Study 100% Site works commenced in March 2019 and in steady progress.

The target completion date is scheduled in 3rd Quarter 2021.

(b) Consultancy Appointment 100%

(c) Detailed Design 100%

(d) Site Work (Section 1) 63%

III. 4.

Art Museum - Lo Kwee-Seong Pavilion

(Project Estimate : HK$150Mil)

PM – Stephen Leung

PA – Rocco Design Architects Associates Ltd.

PQ – Turner and Townsend Ltd.

D/FA – 1st Quarter 2020

D/C – September 2019

D/TC – 3rd Quarter 2023

(a) Feasibility Study 100% Lead Consultancy was awarded in September 2019 and in

Schematic Design stage. (b) Consultancy Appointment 100%

(c) Detailed Design 20%

(d) Site Work 0%

III. 5.

Renovation of Facilities in Choh-Ming Li Basic

Medical Sciences Building (Remaining Works)

(Project Estimate : HK$57.2Mil)

PM – Mabel Lam

PA – Seniorman Design Ltd.

PQ – TLS & Associates Ltd.

D/FA – March 2019

D/C – May 2020

D/TC – December 2021

(a) Feasibility Study 100% Detailed design was completed. The draft tender documents

and PWSC Paper have been submitted to FHB / ArchSD for

their comment. It was tentatively scheduled for construction

funding approval at PWSC and FC meetings of the Legislative

Council in 2nd Quarter 2020.

(b) Consultancy Appointment 100%

(c) Detailed Design 70%

(d) Tender Documentation 0%

Page 14: THE CHINESE UNIVERSITY OF HONG KONG Campus ...P. 3 of 18 Green Building & Architectural Design Awards 2019 The Chinese University of Hong Kong 香港中文大學 Green Building Leadership

P. 14 of 18

Physical Development – Half-yearly Progress Report

For the Period Ended 31 December 2019

III. Other Capital Projects and Major Alterations, Additions and Improvement (AA&I) Works: (cont’d)

(on private funds or seeking UGC’s support)

Project Title

Percentage

of Works

Completed

Description

Dec

III. 6.

Six InnoCentres at the Hong Kong Science and

Technology Park

(Project Estimate : HK$150Mil)

PM – Mabel Lam

PA – Tony Ip Green Architects Ltd.

PQ – Turner & Townsend Ltd.

D/FA – September 2019

D/C – May 2020

D/TC – December 2020

(a) Feasibility Study 100% With the funding support to establish six research centres for

Health@InnoHK and AIR@InnoHK in Hong Kong Science

and Technology Park (HKSTP) under the HK$10 billion

Innovation Funding Scheme initiated by the HKSAR

Government, users’ engagement and fitting out works design

were also coordinated progressively with the project

consultants; works will be tendered and carried out in phases

to tally with the operational schedules of the six InnoCentres

and space availability in HKSTP.

General building plans submission to Buildings Department

were made. Detailed design for the six InnoCentres were

mostly completed and will be tendered out in packages

progressively. Site works for two centres under first package

will commence in May 2020. Overall completion of all

centres will be by end December 2020.

(b) Consultancy Appointment 100%

(c) Detailed Design 60%

III. 7. Other Minor Projects Being or Having Been Put

Forth to the UGC for AA&I Funding Consideration

Projects submitted to UGC for consideration in June

2019 under 2020/2021 Block Allocation

(1)

Spatial re-organization and Improvement Works

a) Music Department at Hui Yeung Shing Building

b) Faculty of Education at Ho Tim Building

(Estimated Cost: HK$29.8 Mil)

(2) Upgrading and Addition of Sports Facilities at Outdoor

Areas for Active Campus Project

(Estimated Cost: HK$28.8 Mil)

(3) Accessibility Improvement Works for Barrier Free Access

a) Replacement of Lift at Chan Chun Ha Hall

b) New Lifts at Adam Schall Residence

c) Improvement Works to Lift Lobby and Upgrading

Existing Lift at Elisabeth Luce Moore Library

d) Installation of Automatic Doors to Toilets and

Automatic Swing Gates in Libraries

e) Addition of Lift from International House I/II to

LG2/4 of Lee Woo Sing College

(Estimate Cost: HK$29.7 Mil)

(4) Stabilization of Slopes – Phase 15

(Estimated Cost: HK$29.2 Mil)

(5) Safety Enhancement Works – Construction Pedestrian

Footbridge between Basic Medical Sciences Building

and Mong Man Wai Building to Enhance the Pedestrian

Safety

(Estimated Cost: HK$27.28 Mil)

The outcome will be known in March 2020.

Page 15: THE CHINESE UNIVERSITY OF HONG KONG Campus ...P. 3 of 18 Green Building & Architectural Design Awards 2019 The Chinese University of Hong Kong 香港中文大學 Green Building Leadership

P. 15 of 18

Physical Development – Half-yearly Progress Report

For the Period Ended 31 December 2019 IV. Minor Works:

(July 2019 - Dec 2019)

A. The following minor works have been completed during the period of report: (Project Cost: HK$121 Mil)

(1) Fitting Out Works at LG12C at University Administration Building

(2) Fitting Out Works of Makerspace (phase 2) at LG/F University Library

(3) Fitting Out Works of Microfilm Room at G/F University Library

(4) Renovation Works of Laboratory at Room 258 at University Science Centre for Department of Chemistry

(5) Alteration and addition works for green roof at 3/F podium Choh-Ming Li Basic Medical Sciences

Building

(6) Alteration and addition works for converting language laboratories into multi-purpose classrooms at Lee

Shau Kee Building for Registry

(7) Application for Extension of Temporary Occupation Permit & Temporary Building Permit of temporary

structure at Nissen Hut and Chien Mu Library

(8) Fitting Out Works at 2/F of Elisabeth Luce Moore Library

(9) Upgrading Works at Central Data Centre at Wu Ho Man Yuen Building for High Performance

Computing System

(10) Alteration and addition work for new passenger lift at G/F to LG4/F of Lee Woo Sing College

(11) Renovation Works for Faculty of Medicine at Prince of Wales Hospital:

(a) Lui Che Woo Clinical Sciences Building

Room 124010, 10/F for Li Ka Shing Institute of Health Sciences

(b) Li Ka Shing Specialist Clinics, North Wing

Surgical Skill Lab, 3/F for CUHK Jockey Club Minimally Invasive Surgical Skills Centre

(Phase 1)

(12) Renovation Works for Faculty of Medicine at Tai Po Hospital:

(a) Multicentre

Room GB6, G/F Multicentre for Department of Psychiatry

(13) GIS based Slope Information System and Engineer Inspection for Maintenance – Reports of Engineer

Inspection and Maintenance Manual for 75 features were completed. Inspection Reports for 23 new

features were submitted to GEO and pending for registration. The GIS based Slope Information System

is in progress.

Page 16: THE CHINESE UNIVERSITY OF HONG KONG Campus ...P. 3 of 18 Green Building & Architectural Design Awards 2019 The Chinese University of Hong Kong 香港中文大學 Green Building Leadership

P. 16 of 18

Physical Development – Half-yearly Progress Report

For the Period Ended 31 December 2019

IV. Minor Works: (July 2019 - Dec 2019)

B. The following minor works are at different stages of construction or implementation: (Project Cost: HK$51 Mil)

(1) Alteration and addition works for Chan Kwan Tung Inter-University Hall (January 2020) & Chiang’s

Building (July 2020)

(2) Spatial Re-organisation of 10/F and 11/F of William M. W. Mong Engineering Building for Department of

Biomedical Engineering – (June 2020)

(3) Alteration and Major Renovations to convert Inter-University Hall into an InnoHub – (Phase 1: April 2020 /

Phase 2: July 2020)

(4) Renovation Works for Faculty of Medicine at Prince of Wales Hospital:

(a) Lui Che Woo Clinical Sciences Building

Room 34141, 1/F for Department of Chemical Pathology – (June 2020)

Room 74002, 5/F for Department of Orthopaedics & Traumatology (May 2020)

(b) Li Ka Shing Specialist Clinics, North Wing

Surgical Skill Lab, 3/F for CUHK Jockey Club Minimally Invasive Surgical Skills Centre

(Phase 2) – (July 2020)

(c) Special Block E & F

Office 2 & 3, 1/F Block F for Department of Obstetrics and Gynaecology – (July 2020)

(d) CUHK Li Ka Shing Medical Sciences Building

10/F (ROOMS 1016A to 1016D) for Li Ka Shing Institute of Health Sciences (April 2020)

11/F (ROOM 1107) for Li Ka Shing Institute of Health Sciences – (May 2020)

Orthopaedic Learning Centre, 1/F for Department of Orthopaedics and Traumatology –

(May 2020)

(e) The Sir Yue-Kong Pao Centre for Cancer and The Lady Pao Children’s Cancer Centre

CC4, LG/F for Department of Imaging & International Radiology (March 2020)

Entrance Lobby, LG/F for Faculty and Planning Office (March 2020)

Remarks: ( ) denotes scheduled completion date

Page 17: THE CHINESE UNIVERSITY OF HONG KONG Campus ...P. 3 of 18 Green Building & Architectural Design Awards 2019 The Chinese University of Hong Kong 香港中文大學 Green Building Leadership

P. 17 of 18

Physical Development – Half-yearly Progress Report

For the Period Ended 31 December 2019

IV. Minor Works: (July 2019 - Dec 2019)

(C) The following minor works are at different stages of feasibility studies, design or tender:

(1) Proposed extension of existing Fitness Room at C.W. Chu College – Schematic design was completed and pending confirmation of funding.

(2) Proposed PET/MRI laboratory at Shanghai Fraternity Association Research Services Centre – Schematic

design in progress.

(3) Hong Kong Institute of Biotechnology

(a) Proposed GMP Laboratories on G/F – Schematic design in progress.

(b) Renovation Works of Clean Room Laboratories on 2/F – Detailed design was completed and

preparation of tender document was underway.

(4) Proposed Electronic Microscope Laboratory at LG/F University Science Centre – Schematic design in

progress.

(5) Fitting Out Works of LG/F (Rooms LG1 & LG2) East Wing of Art Museum – Schematic design in progress.

(6) Fitting Out Works of Laboratory 3 & 5 on 8/F Mong Man Wai Building – Detailed design in progress.

(7) Renovation Works of PV panel, metal shelter and climbing wall at University Sports Centre annex –

Detailed design in progress.

(8) Proposed Renovation Works at 1/F Tin Ka Ping Building

(a) Phase 1: Expansion of HK Literature - Appointment of Consultant

(b) Phase 2: New Space for Contemporary Chinese Literature – Funding Application

(9) Proposed Renovation Works at Choh-Ming Li Basic Medical Sciences Building - Detailed design was

completed and pending confirmation of funding.

(10) Renovation Works for Faculty of Medicine at Prince of Wales Hospital:

(a) Lui Che Woo Clinical Sciences Building

Room 104023A, 8/F for Clinical Research Management Office – Tender was issued, pending

HA’s approval.

Seminar Room & CSLC Office, 2/F for Faculty and Planning Office – Tender was issued,

pending HA’s approval.

Rooms 64002, 64042, 64043 & 64048, 4/F for Department of Surgery – Tender was issued,

pending HA’s approval.

Rooms 74043 to 74046, 5/F for Department of Orthopaedics & Traumatology – Tender was

issued, pending HA’s approval.

Rooms 114038 & 114041, 9/F for Department of Medicine and Therapeutics – Tender was

issued, pending HA’s approval.

Rooms 24151A, 24156A & 24160A, G/F for Department of Surgery. – Tender was issued,

pending HA’s approval.

Rooms 84026 to 84031, 6/F for Department of Otorhinolaryngology, Head and Neck Surgery –

(Pending by HA/User)

(b) The Sir Yue-Kong Pao Centre for Cancer and The Lady Pao Children’s Cancer Centre

Room 424A, 4/F for Department of Surgery – Tender was issued, pending for HA’s approval.

3/F (Room 306A) & 4/F (424B & 428) for Department of Surgery – Tender was issued, pending

for HA’s approval.

Page 18: THE CHINESE UNIVERSITY OF HONG KONG Campus ...P. 3 of 18 Green Building & Architectural Design Awards 2019 The Chinese University of Hong Kong 香港中文大學 Green Building Leadership
Page 19: THE CHINESE UNIVERSITY OF HONG KONG Campus ...P. 3 of 18 Green Building & Architectural Design Awards 2019 The Chinese University of Hong Kong 香港中文大學 Green Building Leadership

Programme – Capital Projects

Programme – AA&I Projects

- i -

CDO - Dec 2019

CDO - Dec 2019

Note: Programmes will be adjusted from time to time to suit actual progress and/ or rescheduling arrangements

Page 20: THE CHINESE UNIVERSITY OF HONG KONG Campus ...P. 3 of 18 Green Building & Architectural Design Awards 2019 The Chinese University of Hong Kong 香港中文大學 Green Building Leadership

Appendix A- Capital Projects

Jockey Club Postgraduate Halls 2 & 3 on Northern Campus

Two multi-storey hostel blocks with a total of 676 student hostel places, including accommodation for wardens,tutors and attendants; common and supporting facilities

CFA : 15,980 sqm

Project cost : HK$675.2 mil

Status : Occupation Permit for Hostel Blocks was issued by BuildingsDepartment in November 2018. Fitting-out for Amenity Hall andstatutory inspections for Sports Court completed in June 2019.

Completion : 4th Quarter 2018 for main hostel blocks

Physical Development –

Half-yearly Progress Report

Period ended 31 December 2019

Proposed Centralized General Research Laboratory Complex Block 2 in Area 39 (Expanded and relocated version )

Proposed Lab Block 2Revised TFS

approved

Block 1 Block 3

& 4

Teaching-

Research

ComplexP G

HallsC W Chu

College

A multi-storey research laboratory building in Area 39, including research laboratories, seminar rooms, offices, DG stores, car parking facilities

CFA : 23,674 sqm

Preliminary Estimate : HK$1,400 mil @4th Quarter 2019

Status : The project was upgraded to Cat. B+ in 2019 CWRAE. Building Committee Meetings were held to explore the design concepts and formulate the user’s requirements.

Detailed design was in progress. The detailed design report and tender document were

submitted to UGC/ ArchSD for vetting.

Completion : 2023 - 2024

Block 2

- ii -

Page 21: THE CHINESE UNIVERSITY OF HONG KONG Campus ...P. 3 of 18 Green Building & Architectural Design Awards 2019 The Chinese University of Hong Kong 香港中文大學 Green Building Leadership

New Student Hostels under Hostel Development Fund (HDF) - 300-place Student Hostel, New Asia Campus

Appendix A- Capital Projects

New Student Hostels under Hostel Development Fund (HDF) - 250-place Student Hostel, United Campus

Multi-storey 300-place student hostel on New Asia Campus with multi-purpose hall and related facilities

CFA : 5,920 sqm

Project Cost : HK$269 mil

Status : Phase 1 of Main Contract Works including hoarding, site formation and foundation work were commenced in June 2019. Site formation work was mostly completed andfoundation work is in progress.

Completion : 3rd Quarter 2022

Multi-storey 250-place hostel with accommodation for wardens, tutors and supporting facilities

CFA : 5,100 sqm

Preliminary Estimate : HK$232 mil @ 3rd Quarter 2019

Status : Consultant was appointed to commence Detailed Design in May 2019. Building Committee Meetings and design workshops were held to explore the design concepts and formulate the user’s requirements.

Completion : 3rd Quarter 2023- iii -

Page 22: THE CHINESE UNIVERSITY OF HONG KONG Campus ...P. 3 of 18 Green Building & Architectural Design Awards 2019 The Chinese University of Hong Kong 香港中文大學 Green Building Leadership

New Student Hostels under Hostel Development Fund (HDF) - 300-place Student Hostel, Shaw Campus

Appendix A- Capital Projects

Multi-storey 300-place hostel with accommodation for wardens, tutors and supporting facilities

CFA : 5,800 sqm

Preliminary Estimate : HK$293mil @ 3rd Quarter 2018

Status : Building Committee was formed; consultant was appointed to commence DetailedDesign in Oct 2019.

Completion : 2nd Quarter 2024

- iv -

Page 23: THE CHINESE UNIVERSITY OF HONG KONG Campus ...P. 3 of 18 Green Building & Architectural Design Awards 2019 The Chinese University of Hong Kong 香港中文大學 Green Building Leadership

Appendix A– Capital Projects

Government Funding by Food & Health Bureau

Re-provision and expansion of CUHK facilities in Prince of Wales Hospital Redevelopment by Hospital Authority / Food & Health Bureau

Faculty of Medicine Teaching & Research Complex in Area 39

- v -

Area 39 Master Development Plan

Page 24: THE CHINESE UNIVERSITY OF HONG KONG Campus ...P. 3 of 18 Green Building & Architectural Design Awards 2019 The Chinese University of Hong Kong 香港中文大學 Green Building Leadership

Appendix B – Capital Projects

Private Funding

Redevelopment of Art Museum Annex

Redevelopment of existing Art Museum Annex to extension of gallery space with Exhibition Area, Café, Artist Studio, workshop and supporting facilities

CFA : 4,780 sqm

Project Cost : HK$150 mil

Status : The Lead Consultancy Contract was awarded to Rocco Design Architects Associates Ltd in Sep 2019 for commencement of Schematic Design

Completion : 3rd Quarter 2023

Proposed Lab Block 2Revised TFS

approved

- vi -

Proposed Lab Block 2Revised TFS

approved

Chung Chi Student Development Complex

Chung Chi Student Development Complex includes upper block as “Multi-functional Building” with staff quarters and a mini-theatre and the lower block as “Student Development Centre” with activity rooms and CC student union offices. A footbridge will link the two blocks with direct access from roof of Pommerenke Student Centre.

CFA : 4,420 sqm

Project Estimate : HK$250 mil @ 3rd Quarter 2018

Status : Site works commenced in Mar 2019. Site foundation & formation works in progress.

Completion : 3rd Quarter 2021

Page 25: THE CHINESE UNIVERSITY OF HONG KONG Campus ...P. 3 of 18 Green Building & Architectural Design Awards 2019 The Chinese University of Hong Kong 香港中文大學 Green Building Leadership

Extension of University Sports Centre

Appendix C- Selected AA&I Projects

A new extension block of single floor fitness centre next to the existing University Sports Centre with roof garden on top.

CFA : 445 sqm

Project Cost : HK$35 mil

Status : Construction works commenced in August 2019. Site formation, foundation and drainage diversion works in progress.

Completion : 1st Quarter 2021

- vii -

Page 26: THE CHINESE UNIVERSITY OF HONG KONG Campus ...P. 3 of 18 Green Building & Architectural Design Awards 2019 The Chinese University of Hong Kong 香港中文大學 Green Building Leadership

Provision of New Laboratory Space on Roof Extension of Mong Man Wai Building

Roof top extension to provide new wet / teaching laboratories for research activities

CFA : 640 sqm

Project Cost : HK$20 mil

Status : under construction Completion : 3rd Quarter 2020

Provision of New Laboratory Space at 1/F of William M W Mong Engineering Building

Extension on existing 1/F flat roof to provide new teaching laboratories for research activities

CFA : 190 sqm

Project Cost : HK$10 mil

Status : under construction.Completion : 2nd Quarter 2020

Appendix C- Selected AA&I Projects

- viii -

Page 27: THE CHINESE UNIVERSITY OF HONG KONG Campus ...P. 3 of 18 Green Building & Architectural Design Awards 2019 The Chinese University of Hong Kong 香港中文大學 Green Building Leadership

Appendix C- Selected AA&I Projects

Construction of New Dangerous Goods Stores for Compressed Gases on Campus

Construction of New Dangerous Goods Stores for Compressed Gases on Campus

CFA : 155 sqm

Project Cost : HK$ 8.89 mil

Status : Detailed design in progressCompletion : 1st Quarter 2021

Proposed New Dangerous

Goods Store

Section

Construction of an extension at the open courtyard at G/F of Lady Shaw Building for office use

CFA : 795 sqm

Project Estimate : HK$30 mil @ 4th Quarter 2018

Status : Expression of interest for Consultancy under invitation

Completion : 1st Quarter 2022

Space Addition and Reorganisation at G/F of Lady Shaw Building for Office/Teaching Laboratory

- ix -

Page 28: THE CHINESE UNIVERSITY OF HONG KONG Campus ...P. 3 of 18 Green Building & Architectural Design Awards 2019 The Chinese University of Hong Kong 香港中文大學 Green Building Leadership

Appendix C- Selected AA&I Projects - Infrastructure Enhancements

Traffic Improvement Work near Central Avenue

Construction of new staircase with flatter gradient to provide pedestrian friendly linkage between Clinic Road and Central Avenue connecting the shuttle lifts at Pentecostal Mission Hall Complex and Mong Man Wai Building, forming a walking route linking the lower and upper level of the campus.

Project cost : HK$9.44mil

Completion : Dec 2019

Slope Improvement Work

Slope stabilization works for Feature no. 7NE-C/C65 at the south of University Residence No.17

Project Cost : HK$11 mil

Completion : 3rd Quarter 2020

- x -

Page 29: THE CHINESE UNIVERSITY OF HONG KONG Campus ...P. 3 of 18 Green Building & Architectural Design Awards 2019 The Chinese University of Hong Kong 香港中文大學 Green Building Leadership

Appendix D–Asset Enhancement Projects

Renovation Works for Chan Kwan Tung Inter-University Hall and Chiang’s Building

Chan Kwan Tung Building Inter-University HallCFA : 1,113 sqmProject Cost : HK$ 24 milCompleted : under constructionCompletion : 1st Quarter 2020

Chiang’s BuildingCFA : 2,345 sqmProject Cost : HK$ 55 milStatus : under constructionCompletion : 3rd Quarter 2020

Renovation Works of Chan Kwan Tung Inter-University Hall and Chiang’s Building

Chiang’s Building sample flat interior

- xi -

Page 30: THE CHINESE UNIVERSITY OF HONG KONG Campus ...P. 3 of 18 Green Building & Architectural Design Awards 2019 The Chinese University of Hong Kong 香港中文大學 Green Building Leadership

Appendix E- Selected Minor Works Projects

Additional Lift at Lee Woo Sing College

Installation of new glazed passage lift from G/F to LG3/F at canteen area.

Status : Lift shaft and lift car installation completed and under statutory inspections.

Project Cost : HK$7.44 mil

Commencement : December 2018

Completion : 1st Quarter 2020

Renovation Works to International House 1 & 2

Renovation of House 1 & 2 in phases including student bedrooms, pantries and common areas.

Project Cost : HK$ 30 milCompletion : July 2019

- xii -

Page 31: THE CHINESE UNIVERSITY OF HONG KONG Campus ...P. 3 of 18 Green Building & Architectural Design Awards 2019 The Chinese University of Hong Kong 香港中文大學 Green Building Leadership

Enhancement of Study Spaces to existing library at 2/F

CFA : 1,100 sqm

Project Cost : HK$5.5mil

Completion : August 2019

Fitting Out Works at 2/F Elisabeth Luce Moore Library, Chung Chi College

Appendix E– Selected Minor Works Projects

Conversion of existing reading and bookshelving areas into MakerSpace.

CFA : 1,000sqm

Project Cost : HK$6mil

Completion : August 2019

Fitting Out Works of MakerSpace at University Library

- xiii -

Page 32: THE CHINESE UNIVERSITY OF HONG KONG Campus ...P. 3 of 18 Green Building & Architectural Design Awards 2019 The Chinese University of Hong Kong 香港中文大學 Green Building Leadership

Appendix E- Selected Minor Works Projects

Renovation of Inno Hub at Inter-University Hall

Renovation of Inter-University Hall from LG/F to 5/F for InnoHub (renamed as Innoport) to house Pi Centre, EPIN Office for ORKTS including the facilities for café, offices, exhibition area, co-working space, workshop and warden flat etc.

Status : Construction in progress

Project Cost : HK$15 mil

Commencement : October 2019

Completion : Phase 1 – April 2020

: Phase 2 – July 2020 - xiv -

Page 33: THE CHINESE UNIVERSITY OF HONG KONG Campus ...P. 3 of 18 Green Building & Architectural Design Awards 2019 The Chinese University of Hong Kong 香港中文大學 Green Building Leadership

The Sir Yue-Kong Pao Centre for Cancer, Prince of Wales Hospital

Renovation Works for The Sir Yue-Kong Pao Centre for Cancer, Prince of Wales Hospital

CFA : 146 sqm

Project Cost : HK$ 2M

Status : Work in progress

Completion : 1st Quarter 2020

Appendix E- Selected Minor Works Projects

Major Renovation of 10/F and 11/F William M W Mong Engineering Building

Spatial Reorganization of 10/F and 11/F William M W Mong Engineering Building for Faculty of Engineering

CFA : 2,000 sqm

Project Cost : HK$23 mil

Completion : Substantial completion in December 2019

- xv -