I-35 Reconstruction Project
TEXAS DEPARTMENT OF TRANSPORTATION
Updates to I-35 Central Texas Expansion Project Jacob Chau, WAC, Director of Transportation Operations Robert Brydia, TTI, Senior Research Scientist
I-35 Reconstruction Project
Presentation Outline
Construction Status ITS Infrastructure Updates
Alignment of WAC under FTW
Traveler Information Initiatives
2
I-35 Reconstruction Project
Corridor Overview
3
I-35 Reconstruction Project
Construction – North of Waco
4
~33 miles
3 lanes complete each direction – June 2015
Punch list items
Turned over to maintenance contractor
ITS infrastructure being moved to permanent condition
I-35 Reconstruction Project
North of Waco – Before and After
5
From this…. To this….
I-35 Reconstruction Project
Construction – South of Waco
6
+40 miles
Projects 1B, 1C, 2B, 3A1, 3A2, 3B
Significant milestones to meet
Sections complete 2016 - 2018
ITS infrastructure being moved to permanent condition as sections are complete.
I-35 Reconstruction Project
ITS Infrastructure – Bluetooth
43 sites on I-35 throughout WAC Meets FTW, DAL, AUS
infrastructure Several thousand matches per
day at most sites
Used for: – Travel times – Incident analysis – Daily operations report – Corridor delay
4 year data archive
7
I-35 Reconstruction Project
ITS Infrastructure – Wavetronix
19 sites on I-35 Bi-directional counts and
classifications
Used for: – Lane closure impact assessment – Projections of least impact – End-of-queue analysis
4 year data archive
8
I-35 Reconstruction Project
ITS Infrastructure – CCTV
18 CCTV on I-35 – 17 PTZ
Combination of CCTV / VIVIDS on alternate routes
Used for: – Traveler information – Real-time map – Support for incident management
50 total camera views now available in Lonestar
9
I-35 Reconstruction Project
ITS Infrastructure – Transition to Permanent
10
Move from this…. To this….
I-35 Reconstruction Project
ITS Infrastructure – Alternate Routes
Alternate Routes – 56 sites on key alternate routes
• Bluetooth • CCTV (PTZ and VIVIDS intercepts)
Used for: – Comparative travel times
• Loop 363-Temple / Loop 340-Waco – Traffic conditions during incidents – Real-time map
Status: – 37 sites installed / 19 remaining
11
I-35 Reconstruction Project
ITS Infrastructure – Integration to Lonestar
Operations Focus – Complete Lonestar integration 2011 – WAC supported by special TRF implementation
– Lonestar enhancements • WAC PCMS needs • WAC field infrastructure
– C2C travel time message injection from TTI • Data processed by TTI
2015 – WAC moved to FTW – CCTV integration – Naming conventions and statewide website enhancements – Coming soon Lonestar produced travel times
12
I-35 Reconstruction Project
Initiatives – Traveler Information
What are traffic conditions like now? What will traffic conditions be like on any portion of my drive? Where might I be delayed by work zone lane closures?
13
DELAYS CURRENT TRAVEL TIMES
INCIDENTS LANE CLOSURES
FORECASTED TRAVEL TIMES
DETOUR ROUTES
CURRENT SPEEDS
SNAPSHOTS
I-35 Reconstruction Project
Initiatives – Travel Times North of Waco
Use permanent DMS infrastructure in completed sections
Utilize PCMS elsewhere
Travel times computed by Lonestar
Bluetooth sensors feed both TTI and FTW
End of October, 2015
14
I-35 Reconstruction Project
Initiatives – Construction Delay Forecast Signs
System predicts short-term delays due to construction
Requires real-time data from – End-of-queue – Bluetooth – Wavetronix
Algorithm varies greatly when lane closure timeframes vary from scheduled times
Implementation cancelled
15
I-35 Reconstruction Project
Initiatives – Comparative Travel Times
Supports alternate routes around Temple and Waco
Initially conceived as PCMS basis, now permanent installations
Utilizes Bluetooth infrastructure
Building software
Doing field site investigation and deployment
Solar powered
January, 2016
16
I-35 Reconstruction Project
Initiatives – Current Delay
Supports on-going construction between Belton and Waco
Utilizes Bluetooth infrastructure
Correlates to delay on real-time map
Doing field site investigation and deployment
Solar powered
January, 2016
17
I-35 Reconstruction Project
Initiatives – End-of-queue warning systems
More than 300 deployment nights Specialty deployments
– DPS investigations – Semi-permanent locations – Waco 6-bridge package
TxDOT pioneered approach / Several states now following and looking at alternative contracting
Key is assessment / business rules
18-41% reduction in crashes over what would have occurred if EOQ systems not in place
18
I-35 Reconstruction Project
Initiatives – Incident Messaging
Added alternate/detour routes – Alternate – suggested – Detour – mandated – Determined by TxDOT based on field conditions
Routes suggested automatically by system Routes plot on real-time map Pre-set text based driving directions New icons Downloadable graphics Works on both smartphones and desktops
19
I-35 Reconstruction Project
Initiatives – Traveler Information Outreach
Lane closure email notices – Over 4,000 subscribers
Incident messaging – Nearly 2,400 subscribers
Real-time map – Corridor delay – Detour routes – Alternate route conditions
Twitter feeds – 6.2M impressions – Two new feeds coming
• Lane closures • Incidents
20
0500
10001500200025003000350040004500M
arch
Apr
ilM
ayJu
neJu
lyA
ugus
tS
epte
mbe
rO
ctob
erN
ovem
ber
Dec
embe
rJa
nuar
yFe
brua
ryM
arch
Apr
ilM
ayJu
neJu
lyA
ugus
tS
epte
mbe
rO
ctob
erN
ovem
ber
Dec
embe
rJa
nuar
yFe
brua
ryM
arch
Apr
ilM
ayJu
neJu
lyA
ugus
tS
epte
mbe
rO
ctob
erN
ovem
ber
Dec
embe
rJa
nuar
yFe
brua
ryM
arch
Apr
ilM
ayJu
neJu
lyA
ugus
tS
epte
mbe
rO
ctob
erN
ovem
ber
2012 2013 2014 2015
Daily 7-Day High Impact Total
I-35 Reconstruction Project
Questions?