Temp Supply New Working Instruction

2
I. Steps involved in effecting new temporary service connection ( Supply for Construction of Building) and subsequent Tariff Conversion. 1. The application for "Supply for Construction of building" can be registered through application tracking module under "temporary Service" Option in AE user. 2. During Registration process, the following fields should be selected in addition to the already available fields . a. Type of Temporary supply --> Supply for Construction of Building (or) Additional Construction exceeding 2000 sq.ft b. Whether undertaking obtained from consumer --> YES c. Permanent Tariff After Construction --> As per the Tariff mentioned in the Undertaking. 3. After completion of Registration , Registration fee may be collected. 4. Necessary sanction may be obtained from the authorities as per the power of sanction. 5. During Sanction Entry in the application module, the Miscellaneous charges applicable to the permanent tariff mentioned in the undertaking will be raised and the same can be collected. 6. After collection of all the charges, service number will be assigned in the "000" distribution through priority register. 7. Assessment: For CT Services - Monthly For Non - CT - Bimonthly. For example if the date of service connection is 10.10.2013, then the billing cycle is Even Cycle . Already assessed cases, the next billing month will be two months from the latest assessment month. For example, if the latest assessment date is 15-09- 2013, then next assessment Month will be 11/2013.

description

Temporary Supply

Transcript of Temp Supply New Working Instruction

I. Steps involved in effecting new temporary service connection ( Supply for Construction of Building) and subsequent Tariff Conversion.

1. The application for "Supply for Construction of building" can be registered through application tracking module under "temporary Service" Option in AE user.2. During Registration process, the following fields should be selected in addition to the already available fields .

a. Type of Temporary supply --> Supply for Construction of Building (or) Additional Construction exceeding 2000 sq.ft

b. Whether undertaking obtained from consumer --> YES

c. Permanent Tariff After Construction --> As per the Tariff mentioned in the Undertaking.

3. After completion of Registration , Registration fee may be collected.4. Necessary sanction may be obtained from the authorities as per the power of sanction.

5. During Sanction Entry in the application module, the Miscellaneous charges applicable to the permanent tariff mentioned in the undertaking will be raised and the same can be collected.

6. After collection of all the charges, service number will be assigned in the "000" distribution through priority register.7. Assessment: For CT Services - Monthly For Non - CT - Bimonthly.

For example if the date of service connection is 10.10.2013, then the billing cycle is Even Cycle .

Already assessed cases, the next billing month will be two months from the

latest assessment month.

For example, if the latest assessment date is 15-09-2013, then next assessment Month will be 11/2013.8. After completion of construction activities, the tariff for the service can be changed to the permanent tariff mentioned in the undertaking by using the "Tariff Conversion-2013" link provided in the AEE user. During the above conversion process, new service number will be assigned as per the distribution code selection and testing fee of Rs.75.00 will be raised as misc slip.9. The existing LM51 services used for construction activities can be converted into

LM61 using the "Tariff Conversion-2013" link already provided in AE user.10. The copy of the Undertaking Format is available in the application tracking module and Tariff Conversion Module.