TEAM KRYLOV THE 2015 FOREIGN DIRECT …...International Investment Law (Oxford University Press,...
Transcript of TEAM KRYLOV THE 2015 FOREIGN DIRECT …...International Investment Law (Oxford University Press,...
!
TEAM KRYLOV
THE 2015 FOREIGN DIRECT INVESTMENT
INTERNATIONAL ARBITRATION MOOT
ARBITRATION PURSUANT TO THE RULES OF ARBITRATION OF THE
LONDON COURT OF INTERNATIONAL ARBITRATION
IN THE PROCEEDING BETWEEN
VASIUKI LLC
(Claimant)
v.
THE REPUBLIC OF BARANCASIA
(Respondent)
MEMORIAL FOR THE CLAIMANT
19 SEPTEMBER 2015
MEMORIAL FOR THE CLAIMANT
i
TABLE OF CONTENT
TABLE OF CONTENT ............................................................................................................ i LIST OF AUTHORITIES ...................................................................................................... iii LIST OF LEGAL SOURCES ............................................................................................... vii LIST OF ABBREVIATIONS ................................................................................................ xi STATEMENT OF FACTS ...................................................................................................... 1 SUMMARY OF ARGUMENTS ............................................................................................. 4 ARGUMENTS ......................................................................................................................... 6 ARGUMENTS ON JURISDICTION AND ADMISSIBILITY ........................................... 6 I. THE TRIBUNAL HAS JURISDICTION OVER THE PRESENT DISPUTE .................................. 6
A. The Tribunal Has Jurisdiction Ratione Materiae Under the CB-BIT ..................... 6 B. The Tribunal Has Jurisdiction Ratione Temporis as the CB-BIT Remains Valid
Despite Respondent’s Proposed Termination of the CB-BIT .................................. 8 1. Respondent’s proposed termination of the CB-BIT as of June 2008 was invalid
according to Article 54 VCLT ................................................................................. 8 a. Respondent’s unilateral termination of the CB-BIT was inconsistent with
Article 54(a) VCLT vis-à-vis Article 13(2) CB-BIT ........................................... 9 b. Absent Cogitatia’s consent, Respondent’s termination of the CB-BIT was
unlawful pursuant to Article 54(b) VCLT ........................................................ 10 2. Alternatively, Respondent’s EU accession did not render the CB-BIT obsolete
pursuant to Article 59 VCLT ................................................................................. 11 a. The CB-BIT and EU law do not cover the same subject matter ...................... 12 b. In any event, the CB-BIT and EU law can apply simultaneously .................... 14
3. Additionally, the CB-BIT remains applicable in accordance with Article 30(3) VCLT ..................................................................................................................... 15
4. As a matter of procedure, the termination of the CB-BIT was not effective as of 30 June 2008 ............................................................................................................... 16
II. CLAIMANT’S CLAIMS ARE ADMISSIBLE AS CJEU DOES NOT HAVE INTERPRETIVE
MONOPOLY OVER THE PRESENT CASE ............................................................................ 18 ARGUMENTS ON MERITS ................................................................................................ 19 III. RESPONDENT’S ADMINISTRATIVE AND REGULATORY MEASURES IN RESPECT OF THE
LRE BREACHED THE SUBSTANTIVE PROVISIONS OF THE CB-BIT ................................. 19 A. Respondent’s Measures Violated FET Standard of Article 2(2) CB-BIT ............ 19
1. Respondent’s premature revocation of the feed-in tariff violated Claimant’s legitimate expectations of regulatory stability ....................................................... 20
2. Respondent’s denial of Claimant’s license for Alfa and its blanket draconian tariff reduction were arbitrary ......................................................................................... 23
3. Respondent failed to accord Claimant due process when amending the LRE ...... 24 4. Respondent’s tariff reduction was discriminatory against Beta ............................ 25
B. Respondent’s Premature Revocation of the Feed-in Tariff Constituted Indirect Expropriation in Violation of Article 5 CB-BIT ..................................................... 26 1. The effects of the LRE Amendment amount to indirect expropriation ............... 27
MEMORIAL FOR THE CLAIMANT
ii
2. Furthermore, Respondent’s tariff reduction was unlawful as no compensation was paid .............................................................................................................. 28
3. In any event, Respondent’s premature revocation of benefits falls beyond the “police powers” exception .................................................................................. 28
IV. RESPONDENT’S MEASURES ARE NOT EXEMPTED UNDER EITHER THE CB-BIT OR
CUSTOMARY INTERNATIONAL LAW ................................................................................. 30 A. Respondent’s Measures Are Not Exempted Under CB-BIT ................................. 30
1. Article 11 CB-BIT is not a self-judging clause absent an expressed provision ..... 30 2. Article 11 CB-BIT does not apply to Respondent’s domestic situation ................ 31
B. Respondent’s Measures Are Not Exempted Under Customary International Law.. ............................................................................................................................ 32
ARGUMENTS ON REMEDIES ........................................................................................... 34 V. RESPONDENT CAN BE ORDERED TO PERFORM RESTITUTION ........................................ 34
A. The Tribunal Can Order Specific Performance Pursuant to LCIA Rules and ARSIWA ..................................................................................................................... 34
B. Order of Specific Performance Is Enforceable as It Does Not Violate Respondent’s Sovereignty ......................................................................................... 35
VI. CLAIMANT’S BASIS FOR CLAIMING AND QUANTIFYING DAMAGES IS APPROPRIATE ... 37 A. Claimant Is Entitled to Full Reparation Given the Causal Link Between
Respondent’s Unlawful Acts and Claimant’s Damages ......................................... 37 1. There is sufficient certainty that Respondent’s unlawful acts caused Claimant’s
lost net income ....................................................................................................... 37 2. Respondent’s unlawful acts have also resulted in Claimant’s lost future net
income. ................................................................................................................... 38 a. Claimant had engaged in Solar PV projects and would have engaged in
further developments but for Respondent’s unlawful acts ............................... 38 b. Claimant would probably earn higher net income arising from its existing and
planned Solar PV operations but for Respondent’s unlawful acts .................. 39 B. Further, Claimant’s Quantification of Damages Is Proper ................................... 40
1. Preliminarily, the differential method with the discounted cash flow valuation is appropriate to quantify Claimant’s damages ......................................................... 40
2. Subsequently, damages awarded should be discounted at Claimant’s WACC to reflect its NPV ........................................................................................................ 41
3. Accordingly, Claimant has properly quantified each head of damages ................. 41 C. Damages Awarded to Claimant Should Carry Compound Interest Rate at The
Rate of Claimant’s WACC ........................................................................................ 42 D. The Cost of Arbitration Born by Claimant Should Be Proportional to the Success
or Failure of Its Claims Pursuant to Article 28(4) LCIA Rules ............................ 43 PRAYERS FOR RELIEF ..................................................................................................... 44
MEMORIAL FOR THE CLAIMANT
iii
LIST OF AUTHORITIES
BOOKS Bonnitcha Jonathan Bonnitcha, Substantive Protection under Investment Treaties: A
Legal and Economic Analysis, (Cambridge University Press, 2014). Cardwell Paul James Cardwell, EU External Relations Law and Policy in the Post-
Lisbon Era, (TMC Asser Press, 2011). Cheng Bin Cheng, General Principles of Law as Applied by International Courts
and Tribunals, (Cambridge University Press, 2006). Crawford James Crawford, The International Law Commission’s Articles on State
Responsibility: Introduction, Text and Commentaries (Cambridge University Press, 2002).
Dolzer & Schreuer R. Dolzer and Christoph H. Schreuer, Principle of International
Investment Law, (2008). Dolzer & Stevens R. Dolzer and M. Stevens, Bilateral Investment Treaties, (New York:
Kluwer Law International, 1995). Dörr Oliver Dörr et al., The Vienna Convention on the Law of Treaties: A
Commentary, (Springer, 2012). Douglas Zachary Douglas, The International Law of Investment Claims,
(Cambridge University Press, 2012). Dugan Christopher Dugan, Investor-State Arbitration, (Oxford University Press,
2008). Kantor Mark Kantor, Valuation for Arbitration: Compensation Standard,
Valuation Methods and Expert Evidence, (New York: Kluwer Law International, 2008).
Newcombe & Paradell Andrew Newcombe and Lluís Paradell, Law and Practice of Investment
Treaties: Standards of Treatment, (New York: Kluwer Law International, 2009)
Marboe Irmgard Marboe, Calculation of Compensation and Damages in
International Investment Law (Oxford University Press, 2009). McLachlan Campbell McLachlan et al., International Investment Arbitration:
Substantive Principles (Oxford University Press, 2007). !
MEMORIAL FOR THE CLAIMANT
iv
Oppenheim Lassa Oppenheim, International Law: A Treatise, Vol. I, (Longmans, Green & Co, 1912).
!Redfern 1 Alan Redfern et al., Law and Practice of International Commercial
Arbitration, 4th Ed., (Sweet & Maxwell, 2004). Redfern 2 Alan Redfern et al., Redfern & Hunter on International Arbitration,
(Oxford University Press: 5th Edition, 2009). Reinisch August Reinisch, Standards of Investment Protection, (Oxford University
Press, 2008). Ripinsky and Williams Sergey Ripinsky and Kevin Williams, Damages in International Law,
(BIICL 2009). Vandevelde Kenneth J. Vandevelde, United States Investment Treaties: Policy and
Practice, (Boston: Kluwer Law and Taxation, 1992). Villiger Mark E. Villiger, Commentary on the 1969 Vienna Convention on the Law
of Treaties, (Martinus Nijhoff, 2009). Vinuales Jorge E. Vinuales, Foreign Investment and the Environment in
International Law, (Cambridge University Press, 2015). Wälde & Sabahi Thomas W Wälde and Borzu Sabahi, Compensation, Damages, and
Valuation, in The Oxford Handbook of International Investment Law, (Oxford University Press, 2009).
ARTICLES Bjorklund Andrea K. Bjorklund, Reconciling State Sovereignty and Investor
Protection in Denial of Justice Claims, 45 VA. J. INT’L LAW 816-818 (2005).
Boute Anatole Baute, Challenging the Re-regulation of Liberalized Electricity
Prices Under Investment Arbitration, ENERGY L.J. 497-439. (2011). D’Amato Anthony D’Amato, Consent, Estoppel, and Reasonableness Three
Challenges to Universal International Law, 10 VIRGINIA J. OF INT’L LAW. 1-31 (1969).
Dimopoulos 1 Angelos Dimopoulos, The Treaty of Lisbon: Half Way Toward a Common
Investment Policy, 21 EUR. J. OF INT’L L. 1049 (2010). Dimopoulos 2 Angelos Dimopoulos, The Validity and Applicability of International
Investment Agreements Between EU Member States Under EU and International Law, 48 COMMON MKT. L. REV. 63, 64 (2011).
MEMORIAL FOR THE CLAIMANT
v
Malik Mahnaz Malik, Best Practices Series Bulletin #3 - Fair and Equitable Treatment, International Institute for Sustainable Development, Feb. 10, 2009.
Mann & Moltke Howard Mann & Konrad von Moltke, Protecting Investor Rights and the
Public Goods: Assessing NAFTA’s Chapter 11, International Institute for Sustainable Development, June 18, 2002.
Nathanson Rachel A. Nathanson, The Revocation of Clean-Energy Investment
Economic-Support Systems as Indirect Expropriation Post-Nykomb: A Spanish Case Analysis, 98 IOWA L. REV. 863 (2013).
Schill & Briese Stephan Schill and Robyn Briese, “If the State Considers”: Self-Judging
Clauses in International Dispute Settlement, MAX PLANCK YEARBOOK OF
U.N LAW, VOL. 13 (2009). Schreuer Christoph H. Schreuer, Fair and Equitable Treatment in Arbitral Practice,
6. J. WORLD INV. & TRADE 357 (2005). Shan & Zhang Wenhua Shan & Sheng Zhang, The Treaty of Lisbon: Half Way toward a
Common Investment Policy, 21 EUR. J. OF INT’L L. 1049 (2010). Stephens-Chu Gisele Stephens-Chu, Is it Always All About the Money? The
Appropriateness of Non-Pecuniary Remedies in Investment Treaty Arbitration, 51 OXFORD INT’L L.J. 30(4) (2014).
Olivet Cecilia Olivet, A test for European solidarity: The case of intra-EU
Bilateral Investment Treaties, Transnational Institute, January, 2013. Wehland Hanno Wehland, Intra-EU Investment Agreements and Arbitration: Is
European Community Law an Obstacle?, CAMBRIDGE INT’L L.J. (2009). White William Burke White, The Argentine Financial Crisis: State Liability
under BITs and the Legitimacy of the ICSID System, University of Pennsylvania, Inst. for Law & Econ Research Paper No. 08-01 (2008).
MISCELLANEOUS EEC 1 Council Regulation No 2913/92 of 12 October 1992 establishing the
Community Customs Code, Official Journal L 302, 19/10/1992. EEC 2 Council Directive No. 88/361 of 24 June 1988 for the implementation of
Article 67 of the 1988 Treaty OJ L 178/5. Expert Opinion of José E. Alvarez, Sempra Int’l v. Republic of Argentina, ICSID Case No. of José E. Alvarez ABR/02/16 and ARB/03/02, (Opinion of José Alvarez).
MEMORIAL FOR THE CLAIMANT
vi
DECC DECC, “Government response to the consultation on proposals for the levels of banded support under the Renewables Obligation for the period 2013-17 and the Renewables Obligation Order 2012”.
OECD: Indirect Expro. OECD, “Indirect Expropriation and the Right to Regulate in International
Investment Law”, OECD WORKING PAPERS ON INTERNATIONAL
INVESTMENT, Number 2004/04, September 2004. UNCTAD ICSID Dispute Settlement: 2.5 Requirement Rationae Materiae. UNCTAD: FET “Fair and Equitable Treatment, A Sequel (United Nations Conference on
Trade and Development, UNCTAD Series on International Investment Agreements II)” United Nations: Conference on Trade and Development, 2012.
MEMORIAL FOR THE CLAIMANT
vii
LIST OF LEGAL SOURCES
ARBITRAL DECISIONS ICSID AES AES Summit Generation Limited and AES-Tisza Erömü Kft. v. Republic of
Hungary, ICSID Case No. ARB/07/22, Award (23 September 2020). CMS, Award CMS Gas Transmission Company v. Argentine Republic, ICSID Case No.
ARB/01/8, Award (12 May 2005). CMS, Jurisdiction CMS Gas Transmission Company v. Argentine Republic, ICSID Case No.
ARB/01/8, Decision on Objection to Jurisdiction (17 July 2003). Corn Products Corn Products v. United Mexican States, ICSID Case No. ARB
(AF)/04/01, Decision on Responsibility (15 January 2008). Continental Continental Casualty Company v. The Argentine Republic, ICSID Case
No. ARB/03/9, Award (5 September 2008). EDF EDF International S.A., SAUR International S.A. and León
Participaciones Argentinas S.A. v. Argentine Republic, ICSID Case No. ARB/03/23, Award (11 June 2012).
Enron, Award Enron Corporation and Ponderosa Assets, L.P. v. Argentine Republic,
ICSID Case No. ARB/01/3, Award (22 May 2007). Generation Ukraine Generation Ukraine Inc. v. Ukraine, ICSID Case No. ARB/00/9, Award
(16 September 2003). LG&E, Award LG&E Energy Corp., LG&E Capital Corp., and LG&E International, Inc.
v. Argentine Republic, ICSID Case No. ARB/02/1, Award (25 July 2007). LG&E, Liability LG&E Energy Corp., LG&E Capital Corp., and LG&E International, Inc.
v. Argentine Republic, ICSID Case No. ARB/02/1, Decision on Liability (3 October 2006).
Metalclad Metalclad Corporation v. The United Mexican States, ICSID Case No.
ARB(AF)/97/1, Award (30 August 2000). Micula, Award Ion Micula, Viorel Micula, S.C. European Food S.A., S.C. Starmill S.R.L.,
and S.C. Multipack S.R.L. v. Romania, ICSID Case No. ARB/05/20, Award (11 December 2013).
MEMORIAL FOR THE CLAIMANT
viii
Micula, Jurisdiction Ion Micula, Viorel Micula, S.C. European Food S.A., S.C. Starmill S.R.L., and S.C. Multipack S.R.L. v. Romania, ICSID Case No. ARB/05/20, Decision on Jurisdiction and Admissibility (24 September 2008).
MTD MTD Equity Sdn. Bhd. and MTD Chile S.A. v. Republic of Chile, ICSID
Case No. ARB/017, Award (25 May 2004). Occidental Occidental Petroleum Corporation and Occidental Exploration and
Production Company v. The Republic of Ecuador, ICSID Case No. ARB/06/11, Decision on Provisional Measures (17 August 2007).
Parkerings Parkerings-Compagniet AS v. Republic of Lithuania, ICSID Case No.
ARB/05/8, Award (11 September 2007). Perenco, Jurisdiction Perenco Ecuador Limited v. The Republic of Ecuador, ICSID Case No.
ARB/08/6, Decision on Remaining Issues of Jurisdiction and Liability (12 September 2014).
Sempra Sempra Energy International v. Argentine Republic, ICSID Case No.
ARB/02/16, Award (28 September 2007). Tecmed Técnicas Medioambientales Tecmed, S.A. v. The United Mexican States,
ICSID Case No. ARB(AF)/00/2, Award (29 May 2003). Vivendi, Award Compañiá de Aguas del Aconquija S.A. and Vivendi Universal S.A. v.
Argentine Republic, ICSID Case No. ARB/97/3, Award (20 August 2007). Vivendi, Annulment Compañiá de Aguas del Aconquija S.A. and Vivendi Universal S.A. v.
Argentine Republic, ICSID Case No. ARB/97/3, Decision on Annulment (10 August 2010).
Waste Management II Waste Management, Inc. v. United Mexican States (“Number 2”), ICSID
Case No. ARB/01/3, Award (22 May 2007). UNCITRAL Bau Walter Bau v. The Kingdom of Thailand, UNCITRAL, Awards (1 July
2009). Binder Binder v. Czech Republic, UNCITRAL, Award on Jurisdiction (6 June
2007). Canfor Corp Canfor Corp v. United States of America, UNCITRAL, Decision on
Preliminary Question (6 June 2006). CME CME Czech Republic B.V. v. Czech Republic, UNCITRAL, Final Award
(13 September 2001).
MEMORIAL FOR THE CLAIMANT
ix
Eureko Eureko B.V. v. The Slovak Republic, UNCITRAL, Award in Jurisdiction, Arbitrability and Suspension (26 October 2010).
Glamis Gold Glamis Gold Ltd v. United States of America, UNCITRAL, Awards (8
June 2009). Methanex Methanex Corporation v. United States of America, UNCITRAL, Final
Award on Jurisdiction and Merits (3 August 2005). Pope & Talbot Pope & Talbot Inc. v. Government of Canada, UNCITRAL, Award in
Respect of Damages (31 August 2000). Saluka Saluka Investment B.V. v. The Czech Republic, UNCITRAL, Partial Award
(17 March 2006). S.D. Myers S.D. Myers, Inc v. Government of Canada, UNCITRAL, Partial Award (13
November 2002). SCC Al-Bahloul Mohammad Ammar Al-Bahloul v. The Republic of Tajikistan, SCC Case
No. V (064/2008), Final Award (8 June 2010). Eastern Sugar Eastern Sugar B.V. v. The Czech Republic, SCC Case No. 088/2004,
Partial Award (27 March 2007). Nykomb Nykomb Synergetics Technology Holding AB v. The Republic of Latvia,
SCC, Arbitral Award (16 December 2003). INTERNATIONAL COURT CASES Chorźow Case Concerning the Factory at Chorźow (Germany v. Poland), [1927]
PCIJ (Ser. A) No. 9. ELSI Elettronica Sicula S.p.A (ELSI) (United States v. Italy), [1989] ICJ. Gulf of Maine Case Concerning Delimitation of the Maritime Boundary in the Gulf of
Maine Area (Canada v. United States), [1984] ICJ. Gabčikovo-Nagymaros Case Concerning Gabčíkovo-Nagymaros Project (Hungary v. Slovakia),
[1997] ICJ Rep 7. EUROPEAN COURT CASES Eco Swiss Eco Swiss China Time Ltd v. Benetton International NV [1999] ECR
13055.
MEMORIAL FOR THE CLAIMANT
x
Nordsee Nordsee Deutsche Hochseefischerei GmbH v. Reederei Mond Hochseefischerei Nordstern AG & Co. KG and Reederei Friedrich Busse Hochseefischerei Nordstern AG & Co. KG [1982] ECR 1095.
STATE COURTS Parson Parsons Whittemore Overseas Co Inc v. Société Générale de l’Industrie du
Papier (RAKTA), U.S Court of Appeals for the Second Circuit - 508 F.2d 969 (2d Cir. 1974), December 23, 1974.
Texaco Texaco Overseas Petroleum Company and California Asiatic Oil
Company v. Government of the Libyan Arab Republic, YCA, Award on the Merits (19 January 1977).
TREATIES US-Argentina BIT Treaty Concerning the Encouragement and Reciprocal Protection of
Investment, United States-Argentina, 14 November 1991. US-Czech Republic BIT Treaty Concerning the Encouragement and Reciprocal Protection of
Investment, United States-Czech Republic, 27 August 1993. VCLT 1969 Vienna Convention on the Law of Treaties, 1155 UNTS 331 (entered
into force 27 January 1980). MISCELLANEOUS ARSIWA Commentary International Law Commission, Articles on Responsibility of States for
Internationally Wrongful Acts, with Commentaries, 2001. NY Convention The New York Convention on the Recognition and Enforcement of
Foreign Arbitral Awards, 1958. LCIA Rules The London Court of International Arbitration Rules, 1 October 2014. TFEU European Union, Treaty on the Functioning of the European Union, 26
October 2012.
MEMORIAL FOR THE CLAIMANT
xi
LIST OF ABBREVIATIONS
¶/¶¶ Paragraph(s)
ARSIWA Articles on Responsibility of States for Internationally Wrongful Acts
BEA Barancasia Energy Authority
CB-BIT Cogitatia-Barancasia Bilateral Investment Treaty
CCP Common Commercial Policy
CJEU Court of Justice of the European Union
COE Cost of Equity
EU European Union
EC European Commission
Facts Uncontested Facts
FET Fair and Equitable Treatment
ICJ International Court of Justice
ICSID International Centre for Settlement of Investment Disputes
ILC International Law Commission
LCIA London Court of International Arbitration
LRE Barancasia Law on Renewable Energy
LRE Amendment Law on the Amendment of Article 4 of the LRE
NPV Net Present Value
NPM Non-Precluded Measures
p. / pp. Page / Pages
PCA Permanent Court of Arbitration
PCIJ Permanent Court of International Justice
PO Procedural Order
Regulation Barancasia Regulation on the Support of Photovoltaic Sector
SCC Stockholm Chamber of Commerce
TFEU Treaty on the Functioning of the European Union
UNCITRAL United Nations Commission on International Trade Law
VCLT 1969 Vienna Convention on the Law of Treaties
WACC Weighted Average Capital Cost
MEMORIAL FOR THE CLAIMANT
1
STATEMENT OF FACTS
THE COGITATIA-BARANCASIA BIT
1.! In 1998, the Republic of Barancasia [“Barancasia” or “Respondent”] and the Federal
Republic of Cogitatia [“Cogitatia”] concluded the Cogitatia-Barancasia Agreement for
the Promotion and Reciprocal Protection of Investments [“CB-BIT”], which entered into
force on 1 August 2002.
CLAIMANT’S BUSINESS IN BARANCASIA
2.! In 2002, Vasiuki LLC [“Claimant”] was incorporated under the laws of Cogitatia.
Claimant initially engaged in small-scale fossil fuel and wind turbine installations in
several regions, including Cogitatia and Barancasia. In 2006, Claimant began to expand
through various “green power” subsidies offered by governments to promote the
development of renewable energy sources.
COGITATIA AND BARANCASIA’S ACCESSION TO EU
3.! On 1 May 2004, Cogitatia and Barancasia acceded to the European Union [“EU”].
Barancasia’s government subsequently reviewed its intra-EU BITs and claimed that they
had become obsolete. It proceeded to announce its intention to terminate all intra-EU
BITs and on 29 June 2007, sent a notification to Cogitatia outlining its intention to
terminate the CB-BIT by 30 June 2008. On 28 September 2007, Cogitatia confirmed
receipt of Barancasia’s notification, but did not otherwise reply.
BARANCASIA’S LAW ON RENEWABLE ENERGY
4.! In May 2010, Barancasia adopted the Law on Renewable Energy [“LRE”]. The LRE
provides that renewable energy production would be encouraged until the share of
electricity generated from renewable sources amounts to no less than 20 percent in
comparison to Barancasia’s gross consumption of energy. Such was to be done by fixing
feed-in tariffs given to investors that have received a license from the Barancasian
Energy Authority [“BEA”]. The LRE also provides that the feed-in tariff announced and
applicable at the time of the issuance of a license would apply for twelve years. On 1 July
2010, the BEA publicly announced that the feed-in tariff would be 0.44 EUR/kWh.
MEMORIAL FOR THE CLAIMANT
2
CLAIMANT’S REQUESTS FOR LICENSE
5.! Upon announcement of the feed-in tariff, Claimant applied for licenses for its first
photovoltaic [“PV”] project Alfa, launched in 2009, as well as its second project Beta.
On 25 August 2010, the BEA only granted Claimant a license for Beta, claiming that the
feed-in tariff would only apply to new projects, and not existing ones like Alfa. This
condition itself was not stipulated in the LRE.
THE NEW COST OF MANUFACTURE
6.! In 2011, a groundbreaking technology made solar panels substantially cheaper to
manufacture, thereby reducing the costs of PV development. The decrease of
development costs enabled investors to garner more profit under the 0.44EUR/kWh tariff
provided by the Barancasian government. Subsequently, the BEA received over 7,000
new applications for licenses to develop PV plants, with Claimant launching twelve more
PV projects.
THE NEW COST’S IMPACT ON BARANCASIA
7.! In media interviews in early 2012, the Barancasian government claimed that the LRE was
a mistake as the 0.44EUR/kWh tariff applicable for twelve years enabled investors to
garner more profit. The government concluded that it could no longer accommodate such
tariff, given that it would require Barancasia to divert some of its state revenues to
finance the tariffs and to possibly exceed its EU-mandated borrowing limits for the
relevant years. The BEA proceeded to grant the licenses to as many as 6,000 of the new
applicants nonetheless.
BARANCASIA’S REDUCTION OF THE FEED-IN TARIFF
8.! In November 2012, the Barancasian Parliamentary Energy Committee conducted private
hearings with specially invited representatives of the renewable energy industry and
certain stakeholders, excluding inter alia Claimant, who was not made known of such.
On 3 January 2013, Barancasia adopted an Amendment to the LRE, which entered into
force on 5 January 2013 with retroactive effect as of 1 January 2013, requiring the feed-in
tariffs to be adjusted annually according to the costs of the best available technology. The
BEA also announced that the new feed-in tariff would be 0.15EUR/kWh, likewise
applicable from 1 January 2013. By that time, Claimant had already made considerable
investments for its twelve new PV projects, e.g. buying equipment to be shipped on 31
MEMORIAL FOR THE CLAIMANT
3
January 2013. As a result of the Amendment, Claimant also encountered difficulties with
its financing of its projects.
REFERRAL TO ARBITRATION
9.! Upon failure to negotiate, Claimant submitted a request for arbitration to the London
Court of International Arbitration [“LCIA” or “the Tribunal”] dated 2 November 2014,
alleging violations of the CB-BIT’s standards of protection and requesting for remedies
for the considerable losses incurred from such violations.
MEMORIAL FOR THE CLAIMANT
4
SUMMARY OF ARGUMENTS
I. JURISDICTION AND ADMISSIBILITY
THE TRIBUNAL HAS JURISDICTION AND CLAIMANT’S CLAIMS ARE ADMISSIBLE
10.! The Tribunal has jurisdiction to hear the present case. Claimant’s business in the
renewable energy sector in Barancasia qualifies as an investment protected under the CB-
BIT, which was valid at the time of Respondent’s substantive violations thereof. The CB-
BIT was not terminated despite Respondent’s proposed termination as of June 2008 and
it was neither rendered wholly obsolete nor its provisions inapplicable following
Cogitatia and Barancasia’s accession to EU in 2004. Respondent also failed to fulfill the
procedural requirements of termination under VCLT (Section I). Moreover, Claimant’s
claims are admissible as the present case is not subject to the interpretative monopoly of
Court of Justice of the European Union [“CJEU”] (Section II).
II. MERITS
RESPONDENT’S BREACH OF THE SUBSTANTIVE PROVISIONS OF THE CB-BIT
11.! Respondent violated Article 2(2) CB-BIT by failing to accord Claimant fair and equitable
treatment [“FET”] through its denial of Claimant’s license for Alfa, its retroactive
application of the LRE Amendment, and its premature revocation of the licensed benefits
under the LRE that fundamentally altered the pricing regime set to attract PV
investments. Consequently, Respondent undermined Claimant’s legitimate expectation
that it would be entitled to the 0.44EUR/kWh for twelve years, arbitrarily denied Alfa’s
license, disregarded due process of law, and discriminated against Beta when it applied
blanket tariff reduction. Furthermore, Respondent indirectly expropriated Claimant’s
investment in violation of Article 5 CB-BIT when it deprived Claimant of its economic
benefit from the licensed tariff without compensation, unjustified by the “police powers”
exception (Section III).
NON-EXEMPTION OF RESPONDENT’S ACTIONS
12.! Respondent’s actions are not exempted under either the CB-BIT or the customary defense
of necessity pursuant to Article 25 ARSIWA. Respondent’s LRE Amendment was not
MEMORIAL FOR THE CLAIMANT
5
necessary to meet its economic and renewable energy objectives and to adhere to its EU
obligations. Furthermore, Respondent’s measures are not exempted under customary
international law since Respondent contributed to the situation of necessity and
Respondent’s LRE Amendment was not the “only way to safeguard its essential security
interest.” Thus, Respondent is obliged to compensate Claimant for losses it has suffered
due to Respondent’s breach of the CB-BIT.
III. REMEDIES
CLAIMANT’S ENTITLEMENT TO RESTITUTION FOR THE PRE-2013 FEED-IN TARIFF
13.! The Tribunal may and should order Respondent to continue paying the pre-2013
0.44EUR/kWh feed-in tariff to Claimant since it has the power to do so pursuant to 2014
LCIA Rules and Article 35 ARSIWA. Furthermore, the order would be enforceable since
Respondent is a party to the New York Convention and it has waived its right to
sovereign immunity by entering into the CB-BIT (Section IV).
CLAIMANT’S ENTITLEMENT TO COMPENSATION FOR LOSSES CAUSED BY RESPONDENT
14.! Alternatively, Claimant is entitled to compensation for the losses that it incurred as a
result of Respondent’s unlawful acts. Claimant suffered reduced its income due to
Respondent’s denial of Claimant’s license for Alfa and feed-in tariff reduction, which
affected Beta, the twelve projects, and the other future developments. The method of
valuation used by Claimant to quantify its damages is the Discounted Cash Flow
[“DCF”] method, applying Claimant’s Weighted Average Capital Cost [“WACC”]
rather than Cost of Equity [“COE”] as the Claimant financed its operations through both
debt and equity. In any event, Respondent should compensate Claimant for its out-of-
pocket expenses (Section V).
MEMORIAL FOR THE CLAIMANT
6
ARGUMENTS
ARGUMENTS ON JURISDICTION AND ADMISSIBILITY
I. THE TRIBUNAL HAS JURISDICTION OVER THE PRESENT DISPUTE
15.! Article 23(1) LCIA Rules provides that the Tribunal may determine its own jurisdiction
and authority over a dispute, which includes adjudication on the continuing validity,
effectiveness and scope of the Arbitration Agreement. In a BIT setting, an Arbitration
Agreement consists of the host State’s standing offer to arbitrate, presently embodied
under Article 8 CB-BIT,1 and the investor’s consent to arbitrate by submitting the case.2
16.! Upon Respondent’s rejection of Claimant’s offer to negotiate on 20 April 2014, 3
Claimant, as a Cogitatian investor owning Alfa,4 Beta5 and twelve other PV projects in
Barancasia,6 has properly invoked Article 8(2) CB-BIT as the arbitration clause. Bearing
the burden of proof,7 Claimant submits that the Tribunal retains the jurisdiction vested
by Article 8 CB-BIT since it has both jurisdiction [A] ratione materiae and [B] ratione
temporis.
A.! The Tribunal Has Jurisdiction Ratione Materiae Under the CB-BIT
17.! The Tribunal has jurisdiction over disputes within the protection of the CB-BIT. 8
Claimant’s claims concerning the feed-in tariffs fall within the protection of Article 8
CB-BIT as the Arbitration clause, which provides that the Tribunal has jurisdiction
over:
“any dispute which may arise between an investor of one Contracting Party and the other Contracting Party in connection with an investment in the territory of that other Contracting Party shall be settled, if possible, by negotiations between the parties to the dispute.”
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!1 CB-BIT, Article 8(2)(d). 2 Redfern 1, p.66. 3 Request for Arbitration, p.3; CB-BIT, Article 8(2). 4 Facts, ¶12. 5 Facts, ¶23. 6 Facts, ¶27. 7 Canfor Corp, ¶176. 8 Generation Ukraine, ¶8.10.
MEMORIAL FOR THE CLAIMANT
7
18.! In this vein, Claimant primarily relies on Article 1(e) CB-BIT, which defines
investments as “rights conferred by laws or under contract and any licenses and permits
pursuant to laws…to search for, extract, cultivate or exploit natural resources.” Based on
the ordinary meaning of the foregoing text,9 the rights of a qualifying renewable energy
operator to a PV license and to receive the announced feed-in tariff for twelve years are
investments as they are evidently conferred by law pursuant to Articles 3, 4, and 5 LRE.
19.! Even if the right to receive the feed-in tariff does not constitute an investment per se,
Article 8(1) CB-BIT does not require that the subject of the dispute be an investment.
The broad language of Article 8(1) CB-BIT entails a lower threshold conferring the
Tribunal’s jurisdiction ratione materiae inasmuch as there is (i) an investment and (ii) a
dispute between Claimant and Respondent that is (iii) “in connection with” Claimant’s
investment, all of which are fulfilled in this case.
20.! First, Article 1(a) CB-BIT includes “immovable and movable properties” as investments
protected under the CB-BIT. Claimant’s business undoubtedly encompasses a wide
range of immovable properties in Barancasia within the terms of Article 1(a) CB-BIT,
spanning from the small-scale fossil fuel to the renewable energy facilities, such as gas
and wind turbine installations, solar panels as well as land plots.10
21.! Second, a dispute occurs when there is disagreement on law and fact11 between the
Parties. There is a disagreement on law between Claimant and Respondent when the
BEA denied Claimant’s license for Alfa alleging that only new projects could obtain
license, 12 despite such limitation being absent in the LRE. 13 Additionally, factual
disagreement exists following Respondent’s arbitrary change of its renewable energy
laws,14 which effectively destroyed Claimant’s PV investments in Barancasia, infra.15
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!9 VCLT, Article 31. 10 Facts, ¶¶3,4,13,33,36. 11 UNCTAD, p.9. 12 Facts, ¶22. 13 LRE, Article 5. 14 Facts, ¶¶34,35. 15 Section III of this Memorial.
MEMORIAL FOR THE CLAIMANT
8
22.! Third, there is a nexus between the dispute and Claimant’s investments.16 The CB-BIT
attaches the phrase “in connection with the investment” to “any dispute,”17 requiring a
legally significant connection between the dispute and the investments. 18 Such
connection is established when Respondent’s measure in changing its renewable energy
framework effectively destroyed Claimant’s PV business in Barancasia and violated
Respondent’s obligations under the CB-BIT owed to Claimant as regards FET and
indirect expropriation.
23.! As a dispute concerning investments is established, the Tribunal retains its jurisdiction
ratione materiae over the case.
B.! The Tribunal Has Jurisdiction Ratione Temporis as the CB-BIT Remains Valid
Despite Respondent’s Proposed Termination of the CB-BIT
24.! Aside from the Tribunal’s jurisdiction ratione materiae, it also has jurisdiction ratione
temporis, which requires the obligation to be in force against the host State at the time
the breach occurs. 19 As the legal instrument regulating Respondent’s rights and
obligations, the CB-BIT must exist when Respondent violates Claimant’s rights under
the CB-BIT.
25.! Notwithstanding Respondent’s proposal of its termination, the CB-BIT remains valid, as
[1] it has not been terminated pursuant to VCLT. 20 Alternatively, Respondent’s
accession to EU [2] did not render the CB-BIT obsolete or [3] its provisions
inapplicable. Further, [4] Respondent did not fulfill procedural rules under VCLT.
1.! Respondent’s proposed termination of the CB-BIT as of June 2008 was invalid
according to Article 54 VCLT
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!16 Douglas, p.242, ¶463. 17 CB-BIT, Article 8(1). 18 Methanex, ¶147. 19 Douglas, p.329. 20 VCLT, Article 42(2).
MEMORIAL FOR THE CLAIMANT
9
26.! Although termination is recognized as an inherent right of every party to a treaty,21
VCLT limits its invocation to certain grounds, inter alia Article 54 VCLT, in that treaty
termination may take place “(a) in conformity with the provisions of the treaty or (b) at
any time by consent of all the parties after consultation with other contracting States.”
Presently, the CB-BIT has not been terminated since Respondent’s proposed
termination thereof by June 2008 did not comply with [a] Article 54(a) VCLT vis-à-vis
Article 13(2) CB-BIT, nor [b] Article 54(b) VCLT.
a.! Respondent’s unilateral termination of the CB-BIT was inconsistent with
Article 54(a) VCLT vis-à-vis Article 13(2) CB-BIT
27.! Article 13(2) CB-BIT provides that:
“This Agreement shall remain in force for a period of ten years. Thereafter, it shall remain in force until the expiration of a twelve month period from the date either Contracting Party notifies the other in writing of its intention to terminate the Agreement.”
28.! Interpreted in its ordinary meaning,22 Article 13(2) CB-BIT only permits one way to
terminate the CB-BIT, i.e. unilateral termination after the initial ten years period has
elapsed. By using the term ‘thereafter’, Cogitatia and Respondent effectively limited
their inherent right to terminate the CB-BIT only after its initial period. This is
corroborated by VCLT’s travaux préparatoires, which noted that when parties have
specified the treaty’s validity period, they link the power of denunciation specifically to
the treaty’s expiry date.23
29.! Since the CB-BIT only entered into force on 1 August 2002,24 the invocation of its
termination via the sending of notification is only available after 1 August 2012. Thus,
Respondent’s proposed termination by June 200825 was invalid as it was invoked in
June 2007.26 If the Tribunal were to accept Respondent’s invocation, it would certainly
run counter to the terms of the provision, thus the principle of pacta sunt servanda.27
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!21 Oppenheim, p.571. 22 VCLT, Article 31. 23 UN Doc. A/CN.4/156, p.63, ¶9. 24 PO2, ¶1. 25 Annex No. 7.1. 26 Facts, ¶9. 27 VCLT, Article 26.
MEMORIAL FOR THE CLAIMANT
10
30.! Nevertheless, even if notification could be made within the CB-BIT’s initial validity
period, the termination should only take effect in August 2012. In that case, Claimant’s
existing and future investments28 remain protected under the CB-BIT by virtue of the
‘survival clause’ embodied under Article 13(3) CB-BIT, extending protection beyond
termination of the CB-BIT.
b.! Absent Cogitatia’s consent, Respondent’s termination of the CB-BIT was
unlawful pursuant to Article 54(b) VCLT
31.! As Respondent’s invocation of unilateral termination fails, Article 54(b) VCLT provides
that only way the CB-BIT may be terminated is through (i) consultations resulting in (ii)
mutual consent to terminate,29 both of which are lacking in the present case.
32.! First, Respondent did not conduct consultations to obtain consent.30 Article 54(b) VCLT
expressly provides that to terminate a treaty, there must be “consent following
consultations.” To this end, although Respondent’s Resolution31 noted that meetings
would be conducted to discuss termination of intra-EU BITs, there is no evidence that
such meetings did in fact take place. Even if they did, the fact that the Resolution allows
Respondent to carry out the termination notwithstanding the results of such meetings,
i.e. notwithstanding mutual consent, is in itself contradictory to Article 54(b) VCLT.
33.! Second, even if prior consultations are not required in treaty termination, Cogitatia
never consented to terminate the CB-BIT. Irrespective of its form, consent must be
established beyond doubt. 32 While VCLT allows parties to express objection to
terminate within three months, 33 Cogitatia’s receipt of Respondent’s notification to
invoke termination 34 and subsequent silence 35 nevertheless fall short of ‘tacit
acquiescence’36 for Respondent to carry on with the termination.37
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!28 CB-BIT, Article 12. 29 Dörr, Article 54, ¶8, p.948. 30 Dörr, Article 54, ¶¶44,45, p.960. 31 Annex No. 6. 32 Dörr, Article 54, ¶38, p.958. 33 Villiger, Article 65, ¶15, p.808. 34 Facts, ¶10. 35 Facts, ¶¶24,31. 36 Villiger, Article 65, ¶15, p.809.
MEMORIAL FOR THE CLAIMANT
11
34.! Cogitatia’s confirmation of receipt of Respondent’s notification on 28 September 200738
does not constitute acquiescence. In Gulf of Maine, the U.S. acted similarly when it
confirmed receipt of Canada’s proposals for an equidistance method yet subsequently
remained silent, for an even longer period of three years. Nevertheless, the ICJ ruled that
such absence of protest is not ipso facto consent and to regard it as so is “overstepping
the conditions required for invoking acquiescence.”39 The rationale underpinning such is
that governments are not obliged to raise protests against other governments,
particularly when the latter issue questionable unilateral declarations,40 as is the case at
hand.
35.! In fact, Respondent’s attempts to confirm the termination after its proposed termination
by June 2008 41 evinced its own hesitation on whether it had obtained Cogitatia’s
consent to terminate the CB-BIT. Had Respondent undoubtedly believed there was
mutual consent to terminate, particularly given its subsequent unilateral removal of the
CB-BIT from its Ministry of Finance website in 2008,42 it would not have continued to
reach Cogitatia for confirmation. Since Respondent’s act as the acknowledging party
should objectively be assessed to avoid Cogitatia’s subjective view on the termination,43
its hesitation is thus decisive to negate the termination’s effect.
36.! Having established that Cogitatia did not validly acquiesce to the termination of the CB-
BIT, the present case no longer constitutes a termination issue and Claimant is therefore
entitled to invoke responsibility from Barancasia due to its substantive violations of the
CB-BIT,44 infra.45
2. Alternatively, Respondent’s EU accession did not render the CB-BIT obsolete
pursuant to Article 59 VCLT
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!37 Villiger, Article 65, ¶16, p.809. 38 Annex No. 7.2. 39 Gulf of Maine, ¶142. 40 D’Amato, p.18. 41 Annex No. 7.1. 42 Facts, ¶11. 43 Dörr, Article 45, ¶17, p.772. 44 ARSIWA, Article 45. 45 Section III of this Memorial.
MEMORIAL FOR THE CLAIMANT
12
37.! In the alternative, Cogitatia and Respondent’s accession to EU in 200446 did not render
the CB-BIT obsolete pursuant to Article 59 VCLT. Although the accession
consequently bound both Parties to EU law,47 rendering EU law e.g. TFEU, as the later
treaty while intra-EU BITs prior to the accession as the earlier treaty, such does not
automatically terminate the CB-BIT.
38.! To invoke obsolescence under Article 59 VCLT, Respondent must prove two-leveled
tests:48 the objective test of whether the two treaties relate to the same subject matter,
and the subjective test of whether both Parties intended to terminate the CB-BIT or
whether the two treaties are “so far incompatible that they cannot be applied at the same
time.” Such approach has been adopted in Eastern Sugar,49 Binder50 and Eureko,51
where the tribunals unanimously ruled on the continuing validity of respective intra-EU
BITs.
39.! Claimant asserts that the CB-BIT is not obsolete, as [a] both treaties do not cover the
same subject matter and [b] they are not incompatible with each other.
a.! The CB-BIT and EU law do not cover the same subject matter
40.! Two treaties cover the same subject matter when a later treaty covers a certain subject
matter that an earlier treaty covers, but also encompasses one or more further matters.52
As Claimant’s claim was filed in 2014,53 assessment of sameness must be made in the
context of TFEU. After its entry into force in 2009, Article 207 vis-à-vis Article 3 TFEU
grants EU exclusive competence over FDI under the ambit of CCP.54 However, as CCP
was introduced in the context of EU’s external action concerning common customs
tariff and generalized tariff preferences,55 it excludes FDI within intra-EU setting, as is
our case.
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!46 Facts, ¶5. 47 VCLT, Article 5. 48 Dörr, Article 59, ¶10, p.1014. 49 Eastern Sugar, ¶¶158-172. 50 Binder, ¶¶19,45,64. 51 Eureko, ¶242. 52 Dörr, Article 59, ¶11, p.1014. 53 Request for Arbitration, p.2. 54 TFEU, Article 3(e). 55 EEC 1, p.1-50.
MEMORIAL FOR THE CLAIMANT
13
41.! As the subject matter of the dispute, FDI regulated under both treaties differ
significantly in terms of the scope of investment and standards of protection, 56
particularly regarding the issue of renewable energy in this case. In fact, it is sufficient
that one claim made by Claimant does not lie within the scope of EU law’s protection to
conclude difference in subject matter.57 Presently, the CB-BIT and EU law do not cover
the same subject matter concerning the (i) scope of investment, (ii) standards of
protection and (iii) expropriation.
42.! As regards covered investments, notwithstanding its non-exhaustive nature, Article
64(2) TFEU solely covers ‘direct investments’, including real estate, securities, and
financial instruments. The emphasis on a ‘direct link’ between the investor and the
investment is understood to exclude indirect or portfolio investments outside FDI
covered under EU’s CCP.58 Conversely, Article 1 CB-BIT covers broader scope of
protection to include indirect investments, such as intellectual property rights under
Article 1(1)(d) CB-BIT.
43.! As regards standards of protection, the extent and scope of protection of both treaties
are different. As for the extent of protection, EU law embodied under Article 206 TFEU
only provides guarantee for ‘investment liberalization’ or ‘market access’, but does not
extend ‘investment protection’. 59 In contrast, Article 2 CB-BIT extends continuous
protection over investments, covering both pre- and post- establishment thereof,60 in
order to create favorable conditions for investors.
44.! As for the scope of protection, EU’s principle of non-discrimination in treatment
between Member States61 does not equate to the FET protection in the CB-BIT.62 While
assessment of the EU principle of non-discrimination is confined to the investor’s
nationality,63 the FET standard encompasses a broader assessment of an investor’s other
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!56 Eureko, ¶246. 57 Eureko, ¶259. 58 Shan & Zhang, p.1059. 59 Shan & Zhang, p.1061. 60 CB-BIT, Article 2(2). 61 TFEU, Article 18. 62 CB-BIT, Articles 2(2). 63 Eureko, ¶258.
MEMORIAL FOR THE CLAIMANT
14
distinguishing characteristics.64 Additionally, the Eureko tribunal upheld that the FET
standard entails protection of investors’ legitimate expectation, arbitrariness and
procedural fairness that remain outside the scope of EU law.65
45.! As regards expropriation, EU freedom of establishment under Article 345 TFEU is not
equivalent to protection against expropriation. This is due to the controversy of whether
EU has the power to take positive action and determine the conditions for lawful
expropriation,66 unlike the CB-BIT.
46.! Ultimately, even if solar energy is a ‘Community good’ belonging to Member States
collectively, Article 4 TFEU provides that EU only has shared competence over energy.
Under Article 2(2) TFEU and the subsidiarity principle, EU shall only exercise its
shared competence insofar as Member States cannot sufficiently do so. Here,
Respondent has evidently exercised its shared competence in its renewable energy
framework by enacting the LRE and subsequently, albeit unilaterally, changing its
provisions. Thus precisely the investment in dispute concerning Claimant’s protection
following Respondent’s change of its renewable energy framework falls outside EU’s
exclusive competence.67
b.! In any event, the CB-BIT and EU law can apply simultaneously
47.! Even if the two treaties cover the same subject matter, the earlier treaty would only
become obsolete if (i) there is mutual intention to terminate the treaty or (ii) the
provisions of the later treaty are “so far incompatible with those of the earlier one that
the two treaties are not capable of being applied at the same time.”68
48.! First, while Respondent’s intention to terminate the CB-BIT was well established,
Cogitatia did not share it. In Eastern Sugar, the tribunal ruled that implicit intention to
terminate could only be found if both Parties have removed intra-EU BITs from their
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!64 S.D. Myers, ¶259. 65 Eureko, ¶250. 66 Dimopoulos 1, p.112. 67 Cardwell, p.406. 68 Dörr, Article 59, ¶20, p.1017.
MEMORIAL FOR THE CLAIMANT
15
respective sites.69 Notwithstanding Respondent’s removal of BITs, nothing factually
indicates that Cogitatia has done the same.
49.! Second, there is no true incompatibility70 between the CB-BIT and EU law to the extent
that they cannot apply simultaneously. Compliance with the CB-BIT does not inherently
undermine the idea underlying the EU, which is to establish a single common market
where stakeholders from Member States would face the same opportunities and
obstacles.71 In fact, the Eureko tribunal has ruled that intra-EU BITs should not be
regarded to breach EU’s principle of non-discrimination under Article 18 TFEU72 solely
because they provide additional rights and obligations to investors of the Parties.
50.! Instead, most Member States prefer to maintain existing intra-EU agreements, shown by
the current validity of as many as over 190 intra-EU BITs. Netherlands, as seen in
Eureko,73 alongside Belgium, Germany and UK have been the most outspoken Member
States against EC’s proposal to phase out intra-EU BITs.74 Despite the pending EC
infringement proceedings against five Member States concerning intra-EU BITs, they
do not affect the present case, particularly given that there has not been an EC
intervention75 and the Tribunal’s power to assess the present dispute is limited to claims
brought by Claimant.
51.! As such, the CB-BIT remains valid despite Respondent’s accession to EU.
3.! Additionally, the CB-BIT remains applicable in accordance with Article 30(3)
VCLT
52.! Article 30(3) VCLT provides that absent conflict of law clause under the lex posterior
rule, an earlier treaty remains applicable to the extent that its provisions are compatible
with those of the later treaty governing the same subject matter.76 Despite subscription
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!69 Eastern Sugar, ¶155; Eureko, ¶100. 70 Eureko, ¶241. 71 Dimopoulos 2, p.63. 72 Eureko, ¶263. 73 Eureko, ¶161. 74 Olivet, p.5. 75 PO2, ¶4. 76 Dörr, Article 30, ¶22, p.514.
MEMORIAL FOR THE CLAIMANT
16
to EU law upon accession to the EU,77 Claimant submits that the Tribunal retains
jurisdiction since Article 8 CB-BIT remains applicable, absent incompatibility with EU
law.
53.! As endorsed in Eastern Sugar and Eureko, although EU law does not provide for a
possibility for an investor to directly sue a host State,78 it does not render the arbitration
clauses in both cases incompatible. In fact, EU itself recognizes investor-State dispute
settlement given its signatory to the Energy Charter Treaty, which provides for such
mechanism under Article 26 Energy Charter Treaty. Accordingly, the Tribunal retains
jurisdiction absent true incompatibility between ISDS mechanism and the EU regime.
4.! As a matter of procedure, the termination of the CB-BIT was not effective as of 30
June 2008
54.! Having established substantive termination grounds, Respondent’s purported
termination was not effective by June 2008, as the termination of the CB-BIT is
conditional upon observance of procedural rules,79 which Respondent failed to observe.
As parties to VCLT,80 invocation of the CB-BIT’s termination by either Cogitatia or
Barancasia must observe the procedural rules under Articles 65-68 VCLT,81 read in
light of one another.82
55.! Presently, Respondent’s notification does not fulfill such procedural obligation.
According to Article 65(1) vis-à-vis Article 67 VCLT, notification to terminate a treaty
must (i) be written,83 (ii) signed by the State’s representative84 and (iii) contain the
reasons therefor.85 Article 65(2) VCLT states that upon such notification to invoke
termination and absent objection within three-months, the party making the notification
may then carry out “in the manner provided in Article 67 the measure proposed,”
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!77 VCLT, Article 15. 78 Eastern Sugar, ¶180; Eureko, ¶274. 79 UN Doc. A/CONF.39/II/Add.1-2, p.79. 80 PO2, ¶5. 81 Dörr, Article 65, ¶1, p.1131. 82 Dörr, Article 65, ¶6, p.1133. 83 VCLT, Article 67(1). 84 Villiger, Article 67, ¶5, p.841. 85 Villiger, Article 65, ¶13, p.808.
MEMORIAL FOR THE CLAIMANT
17
thereby entailing a second diplomatic notification to effect termination that must also be
(i) written and (ii) signed.
56.! Although Respondent’s notification to invoke the CB-BIT’s termination was written and
signed by its Prime Minister, it does not provide the reason for such measure, falling
short of the third element. However, even if the Tribunal found that the attachment of
Respondent’s Resolution suffices,86 Respondent did not provide a second notification to
effect termination and merely removed the intra-EU BITs from its website,87 thereby
failing to comply with the second notice requirement under Article 67 VCLT. Absent
such second notification, the termination has no effect, as Cogitatia has not accepted the
termination explicitly or tacitly, 88 supra.89
57.! Therefore, the CB-BIT remains valid, legitimately conferring jurisdiction upon this
Tribunal over this case.
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!86 Annex No. 6. 87 Facts, ¶11. 88 Dörr, Article 67, ¶15, p.1171. 89 Section I.B.1.b of this Memorial.
MEMORIAL FOR THE CLAIMANT
18
II. CLAIMANT’S CLAIMS ARE ADMISSIBLE AS CJEU DOES NOT HAVE INTERPRETIVE
MONOPOLY OVER THE PRESENT CASE
58.! Having established the Tribunal’s jurisdiction, Claimant’s claims are also admissible.
Although CJEU is the judicial body under EU regime,90 it does not have exclusive right
to interpret the questions of EU law in the present dispute. Article 267 TFEU stipulates
that CJEU’s right to provide preliminary rulings is limited to cases submitted by a
“court or tribunal of a Member State.”
59.! Indisputably, this Tribunal does not constitute a tribunal of a Member State since LCIA
arbitration is consensual under well-established rules, in a neutral place and with a
neutral authority.91 In fact, CJEU’s precedence confirms that the court has constantly
denied commercial arbitral tribunals’ access to the preliminary reference procedure.92
Although factually different, the strict application of Article 267 TFEU is likewise
upheld in Nordsee, where CJEU also declined to give preliminary ruling as the case was
submitted by an international arbitral tribunal.93
60.! In conclusion, as the CB-BIT remains valid and applicable, it serves as legitimate basis
of Claimant’s claims and simultaneously confers protection of Claimant’s investments.
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!90 Wehland, p.318. 91 Eureko, ¶264. 92 Eco Swiss, p.I-3055. 93 Nordsee, p.1095.
MEMORIAL FOR THE CLAIMANT
19
ARGUMENTS ON MERITS
!III. RESPONDENT’S ADMINISTRATIVE AND REGULATORY MEASURES IN RESPECT OF THE
LRE BREACHED THE SUBSTANTIVE PROVISIONS OF THE CB-BIT
61.! Absent choice of law clause in the CB-BIT,94 Article 22(3) LCIA Rules allows the
Tribunal to apply laws or rules of law it considers appropriate to resolve specific issues
and claims raised by the Parties, e.g. the CB-BIT, Respondent’s domestic law, relevant
rules of international law, and EU law.95
62.! To this end, Claimant’s arguments on merits hinge on three actions done by
Respondent, first, its denial of Claimant’s license for Alfa under the LRE,96 second, its
premature revocation of the initial fixed feed-in tariff, 97 and third, its retroactive
application of the LRE Amendment.98 Such acts effectively constitute [A] a violation of
the FET standard and [B] unlawful indirect expropriation, which have severely
constrained Claimant’s PV business in Barancasia.
A.! Respondent’s Measures Violated FET Standard of Article 2(2) CB-BIT
63.! Respondent breached its obligation under Article 2(2) CB-BIT by failing to accord
Claimant “FET at all times in its territory.” As the Article makes no reference to the
minimum standard of treatment or customary international law, 99 the present FET
provision is thus autonomous100 and must be interpreted in accordance with “its ordinary
meaning to be given to the terms of the treaty in their context and in the light of its
object and purpose.”101
64.! The term ‘fair’ and ‘equitable’ requires the host State to act in a manner that is ‘just’,
‘even-handed’, and ‘unbiased’.102 However, as this plain meaning does not provide
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!94 Annex No. 1; Micula, Award, ¶287. 95 Micula, Award, ¶287; Newcombe & Paradell, p.62. 96 Facts, ¶22. 97 Facts, ¶¶34,35. 98 PO3, ¶9. 99 Schreuer , p.360; Dolzer & Stevens, p.60. 100 Reinisch, p.111. 101 VCLT, Article 31(1); Tecmed, ¶155. 102 MTD, ¶113.
MEMORIAL FOR THE CLAIMANT
20
much assistance, the determination of FET must be studied through case laws. 103
Although there is no doctrine of binding precedent in international investment law,
decisions of past tribunals serve as persuasive and valuable guidance for subsequent
tribunals.104
65.! Past tribunals have interpreted FET clauses to require host States to conduct several
measures, e.g. to provide a stable and predictable legal and business framework for
investors’ business,105 to accord due process and transparency,106 and to refrain from
engaging in arbitrary and discriminatory acts.107
66.! Even if Article 2(2) CB-BIT is subject to the customary minimum standard of
treatment,108 the Tribunal is not barred from applying the aforementioned measures on a
case-by-case basis since the substantive factors of FET in both regimes may be the
same.109 Thus, Claimant submits that Respondent’s actions breached the FET standard
since Respondent [1] violated Claimant’s legitimate expectations, [2] engaged in
arbitrary conduct, [3] failed to accord Claimant due process, and [4] discriminated
against Claimant.
1.! Respondent’s premature revocation of the feed-in tariff violated Claimant’s
legitimate expectations of regulatory stability
67.! Respondent undermined Claimant’s legitimate expectations of regulatory stability for
Beta and its twelve projects when it enacted the LRE Amendment in 2013, which
prematurely revoked the fixed 0.44EUR/kWh tariff applicable for twelve years,
resulting in a reduced tariff of 0.15EUR/kWh subject to annual review.110
68.! Adopted in Micula,111 Saluka,112 and Parkerings,113 violation of legitimate expectation
occurs when the host State reneges on assurances it had made to induce investments,
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!103 Micula, Award, 11 December 2013, ¶507. 104 Corn Products, ¶77; Metalclad, ¶108. 105 Enron, ¶260; Saluka, ¶303. 106 Tecmed, ¶154; ELSI, ¶128. 107 Waste Management II, ¶98. 108 Waste Management II, ¶98; Metalclad, ¶76. 109 UNCTAD: FET, pg.90. 110 Annex No. 4; Facts, ¶¶34,35. 111 Micula, Award, ¶668.
MEMORIAL FOR THE CLAIMANT
21
which were reasonably relied on by the investors in making their investments. Having
the burden of proof,114 Claimant submits that Respondent failed to provide a stable and
predictable legal framework for Claimant’s investments in Barancasia despite (i)
assurances made, which (ii) were relied by Claimant (iii) reasonably.
69.! First, despite absence of stabilization clause, Respondent gave Claimant assurance of
regulatory stability for Claimant’s investments when it enacted the LRE,115 set to attract
investors in Barancasia’s PV sector. It subsequently reinforced such assurance by
issuing Claimant’s licenses for Beta and the twelve projects.116 In Micula, the tribunal
held that having specifically enacted the EGO 24 law to attract investments in the
disfavored regions and granted PIC licenses, Romania had created an assurance that
crystallized Micula’s legitimate expectations, thus it must stand by its statement and
conduct.117
70.! Similarly, Respondent’s LRE and its subsequent granting of the licenses despite events
calling for a regulatory change in Respondent’s renewable energy scheme amount to an
assurance sufficient to crystallize Claimant’s legitimate expectations of regulatory
stability. Article 4 LRE was set to induce PV investors by expressly guaranteeing that
the tariff applicable at the time of the issuance of the license would apply for twelve
years. 118 The 0.44EUR/kWh tariff announced 119 thus became applicable for twelve
years, which Respondent affirmed by subsequently issuing licenses to Claimant’s
twelve projects without any reservation that they may be subject to change.120 This was
conducted even after Respondent admitted the unsustainability of its renewable energy
support scheme121 and promised to review its legislation122 due to the discovery of a
groundbreaking technology in 2011,123 which reduced investors’ PV production costs
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!112 Saluka, ¶302. 113 Parkerings, ¶331. 114 Glamis Gold, ¶601. 115 Facts, ¶14. 116 Facts, ¶¶23,33. 117 Micula, Award, ¶¶686,687. 118 LRE, Article 4. 119 Facts, ¶21; Priemo, ¶8. 120 Facts, ¶33. 121 Facts, ¶29. 122 Facts, ¶32. 123 Facts, ¶25.
MEMORIAL FOR THE CLAIMANT
22
and led to a “solar bubble.”124 Thus, the enactment of the unqualified provision in the
LRE and Respondent’s subsequent conduct amount to an assurance of regulatory
stability of the scheme.
71.! Second, Claimant undoubtedly relied on the LRE incentives and the assurance of the
tariff’s stability respectively when it invested in Beta and the twelve projects. In fact,
Claimant waited to have its license approved by Respondent before it began
construction of Beta in 2010125 and the twelve projects in 2012.126 Further, had it not
been for Respondent’s conduct affirming the scheme’s normal operation without any
reservations despite evident operational and financial drawbacks and challenges,
Claimant would not have invested in the scale and manner that it did.127
72.! Third, it was reasonable for Claimant to rely on the stability of the LRE because the
only condition that the LRE can be modified is when the 20% renewable energy
production target has been met,128 which has not yet been met.129
73.! Moreover, it was all the more reasonable for Claimant to rely on such assurance due to
the long-term nature of the investment and the goals of renewable energy of Respondent
and EU.130 The Perenco tribunal held that it was reasonable for Perenco to rely on
Ecuador’s Law 42, even when there was a surge in oil price, because it was set to
promote long-term investments for capital-intensive project that requires substantial
‘up-front costs’.131 Claimant reasonably relied on Respondent’s assurance in the LRE
precisely because it was set to promote “the reduction of dependence on fossil energy
sources and energy imports”132 and to meet its 2020 EU renewable energy target.133
74.! In conclusion, Respondent’s LRE Amendment clearly breached Claimant’s legitimate
expectations when investing its PV projects in Barancasia.
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!124 Facts, ¶28. 125 Facts, ¶23. 126 PO2, ¶9. 127 Micula, Award, ¶721. 128 LRE, Article 2. 129 PO2, ¶10. 130 Facts, ¶7. 131 Perenco, Jurisdiction, ¶564. 132 LRE, Article 1. 133 Facts, ¶7.
MEMORIAL FOR THE CLAIMANT
23
2.! Respondent’s denial of Claimant’s license for Alfa and its blanket draconian tariff
reduction were arbitrary
75.! A long array of tribunals has defined ‘arbitrariness’ as acts done with disregard for the
rule of law, affecting foreign investors “without engaging in a rational decision-making
process.” 134 The tribunals in Lauder 135 and CMS 136 have elaborated this notion,
describing arbitrary measures as actions that “depend on individual discretion and not
upon reason or fact.” Respondent engaged in the arbitrary manner when it (i) denied
Alfa’s license without rational justification, (ii) affected existing projects, and (iii)
retroactively applied the LRE Amendment.
76.! Respondent treated Claimant arbitrarily when it denied Claimant’s license for Alfa
solely because Alfa was an existing investment.137 The purpose of the LRE was to
incentivize renewable energy investments, thus it is to be interpreted liberally in that if
existing projects are connected to the national grid and generate electricity, such projects
that are being developed must be issued a license and entitled to the feed-in tariff.138 In
fact, Alfa’s improvement in capacity at a rate of 2.2% per year sufficiently fulfills such
criteria,139 considering that continued use of solar panels typically lead to a decrease in
generating capacity over time. As both Respondent140 and its expert141 failed to refer to
any basis in the LRE or alternatively, interpreted the LRE contrary to its object and
purpose, the denial of license is thus an arbitrary, ultra vires act.
77.! Such arbitrariness is further buttressed by Respondent’s lack of transparency in refusing
to disclose any criteria in the approval procedure, citing “confidentiality obligations.”142
Thus, Respondent’s denial of Claimant’s license for Alfa was conducted in disregard of
the rule of law and without rational justification.
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!134 LG&E, Liability, ¶¶158,162. 135 Lauder, ¶221. 136 CMS, Award, ¶291. 137 Facts, ¶22; Kovič, ¶6. 138 LRE, Article 5; Regulation, Article 3. 139 Kovič, ¶6. 140 Facts, ¶22. 141 Priemo, ¶7. 142 PO2, ¶16.
MEMORIAL FOR THE CLAIMANT
24
78.! Moreover, Respondent has treated Claimant arbitrarily when the LRE Amendment
affected existing investments incompatible with the new groundbreaking technology,
such as Beta.143 Respondent amended the LRE so as to prevent unfair windfall profits to
investors that benefitted from the “best available technology.”144 However, Respondent
applied the LRE Amendment even to existing investments that did not benefit from the
new technology,145 when it could have done so by grandfathering existing licensed
projects146 or by applying the LRE Amendment strictly to new applicants that benefit
from the new technology.
79.! Additionally, retroactive changes to support schemes are evidently arbitrary even when
it is only for a short period. 147 Retroactive changes run counter to the CB-BIT’s
objective to “create and maintain favorable conditions” for investments of investors of
either Contracting Parties, 148 consistent with the EU prohibition on retroactive scheme
changes as “investors’ legitimate expectations concerning the returns on existing
investments must be respected.”149 The retroactive application of the Amendment was
based on preference since denying Claimant benefits it was initially entitled to from 1
January 2013,150 four days before the LRE Amendment entered into force,151 did not
even address windfall profits.
80.! As Respondent’s measures were merely based on individual discretion and founded
neither on reason, fact nor the rule of law, Respondent has treated Claimant arbitrarily.
3.! Respondent failed to accord Claimant due process when amending the LRE
81.! In a FET context, an investor may be deprived of due process by the host State not only
with respect to denial of justice, but also as regards procedural fairness in legislative or
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!143 PO2, ¶30. 144 Problem, p.34 145 Facts, ¶35. 146 DECC, pg. 90. 147 Matter of Replan Dev. V. Department of Hous. Preserv. & Dev. Of City of N.Y., Court of Appeals of the State of New York, November 19, 1987. 148 Annex No. 1, pg. 24. 149 Memo/13/948, Memo on the Communication on “Delivering the internal electricity market. Making the most of public intervention”, 5 November 2013. 150 Facts, 35. 151 PO3, ¶9.
MEMORIAL FOR THE CLAIMANT
25
executive actions.152 In Waste Management, the tribunal found that a violation of due
process involves “a complete lack of transparency and candor in an administrative
process,”153 which entails host States’ failure to accord transparency through public
hearings,154 especially in case of regulatory changes affecting investors’ investment.155
82.! A State that fails to inform an investor of possible changes to its relevant laws would
perpetrate unfairness, material to the investor’s ability to operate its investments.156
Despite being a concerned stakeholder of the PV sector in Barancasia,157 Claimant was
not accorded the opportunity to be heard as there was not only lack of notice of the
hearings, but the hearings were conducted privately,158 in which only “specially invited”
representatives of industry and certain stakeholder groups were called to provide
testimony.159 Therefore, Respondent’s measure violated Claimant’s right of due process
since the private nature of such hearings rendered them wholly opaque and lacking
adequate justification and consultations with relevant affected stakeholders, including
Claimant.160
4.! Respondent’s tariff reduction was discriminatory against Beta
83.! Under international investment law, discrimination is generally established when
investments of comparable characteristics and subject to the same laws and regulations
are accorded differential treatment without reasonable justification.161 In Nykomb, the
tribunal found a breach of discrimination when Latvia refused to pay the agreed price
when it had in fact paid the higher price to two other electricity generation companies.162
Applying the same logic as regards reverse discrimination, according similar treatment
to investments of different character also amounts to a breach of non-discrimination
principle.
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!152 Dolzer & Schreuer, pp.142,162; Vinuales, p.356; Schreuer, p.381. 153 Waste Management II, ¶98. 154 Malik, p.13. 155 Dugan, p.520. 156 Bonnitcha, p.205. 157 Facts, ¶4. 158 PO3, ¶6. 159 Facts, ¶34. 160 PO2, ¶15. 161 Saluka, ¶313. 162 Nykomb, p.99.
MEMORIAL FOR THE CLAIMANT
26
84.! As the LRE Amendment affected all existing investments, including Beta that used an
older, more expensive technology, it consequently deprived Claimant of the 8% return
on investment for Beta.163 Even if such treatment is a permissible discrimination, it was
done without rational justification since calculation of profitability and computation of
return on investment are different determinations. As Respondent could have limited the
application of the Amendment to new investments, Respondent treated Claimant in a
discriminatory manner.
B.! Respondent’s Premature Revocation of the Feed-in Tariff Constituted Indirect
Expropriation in Violation of Article 5 CB-BIT
85.! Respondent’s premature revocation of the initial benefits conferred on Beta and the
twelve projects constituted indirect expropriation violating Article 5 CB-BIT. Absent
elaboration on elements to find expropriation in the CB-BIT, recourse to decisions of
past tribunals is necessary, given its valuable and persuasive authority to answer
questions of principles.164
86.! Expropriation formally means “a forcible taking by the government of tangible or
intangible property owned by private persons by means of administrative or legislative
to that effect.”165 Unlike direct expropriation, indirect expropriation is defined as the
taking or deprivation of the property of foreign investors by a host state, which may
occur even when the legal title remains with the owners and the property is not
seized, 166 justifiable only by virtue of legitimate police powers. 167 As practiced in
Tecmed168 and LG&E,169 the tribunals found that “measures having effect equivalent to
expropriation” are sufficient to qualify as ‘indirect expropriation’.
87.! Presently, the effects of the LRE Amendment170 that dismantled the initial renewable
energy support scheme171 on which Claimant pivoted its PV investments172 [1] amount
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!163 PO2, ¶27. 164 Metalclad, ¶108. 165 Tecmed, ¶113. 166 S.D. Myers, ¶283; McLachlan, ¶¶290-98. 167 Saluka, ¶255. 168 Tecmed, ¶114. 169 LG&E, Liability, ¶185. 170 Annex No. 4. 171 Facts, ¶29.
MEMORIAL FOR THE CLAIMANT
27
to indirect expropriation in violation of Article 5 CB-BIT that [2] is unlawful and [3]
falls outside the scope of the “police powers” exception.
1.! The effects of the LRE Amendment amount to indirect expropriation
88.! Indirect expropriation occurs when host States’ measures (i) substantially affect
investors’ investments, (ii) deprive investor of the economic benefits of its investments,
and (iii) interfere with investors’ reasonable investment-backed expectations. 173
Presently, Respondent’s denial of license and its premature revocation of the licensed
benefits constitute indirect expropriation since all three elements are met.
89.! First, the substantial effect of an expropriatory act must be irreversible and permanent to
qualify as indirect expropriation. 174 As the PV industry was set to encourage the
innovation of technology, the PV production costs will gradually fall instead of increase.
Due to such fall, the effects of Respondent’s LRE Amendment are irreversible and
permanent since Claimant would no longer be qualified to receive the higher
0.44EUR/kWh tariff even if the new tariff will be reviewed annually.175 This all the
more affects Beta, which was not built using the new and much cheaper technology.176
90.! Second, Respondent’s measure significantly deprived Claimant of “the reasonably-to-
be-expected economic benefit of the property.”177 As an electricity producing company,
Claimant makes investment decisions based on long-term forecasts of risks and
returns,178 which Respondent has disrupted through the draconian tariff reduction that
deprived Claimant of its projected revenue sufficient to recoup capital in making PV
installations. While the rate of return remains 8%,179 the real and effective return is
much less as the assumptions used to calculate it are based on the new technology and
not on the old technology, which incurred greater costs of PV investment, thus the high
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!172 Facts, ¶¶23,27. 173 LG&E, Liability, ¶190; Metalclad, ¶103. 174 Tecmed, ¶116. 175 LRE Amendment, Article 4. 176 PO2, ¶30. 177 Metalclad, ¶103. 178 Boute, p.503. 179 Facts, ¶27.
MEMORIAL FOR THE CLAIMANT
28
feed-in tariff. This is clearly evident when Claimant encountered financial difficulties in
financing its projects as a result of the disproportionate LRE Amendment.180
91.! Third, as discussed supra,181 Claimant expected that the investments in Respondent’s
PV sector to last for a long term and it took this into account to estimate the time and
business required to recover such investment and obtain the expected return upon
making its application.182 Thus, Respondent’s expropriatory curtailment of investment
rights evidently interfered with Claimant’s expectations when investing in Beta and the
twelve projects.
2.! Furthermore, Respondent’s tariff reduction was unlawful as no compensation was
paid
92.! Article 5 CB-BIT lays down four cumulative elements to determine whether an
expropriation is legitimate, namely (i) public purpose, (ii) due process of law, (iii) non-
discrimination, and (iv) payment of prompt, adequate and effective compensation. Here,
there is no indication that compensation has ever been paid to Claimant, subsequently
rendering the indirect expropriation unlawful.
3.! In any event, Respondent’s premature revocation of benefits falls beyond the
“police powers” exception
93.! Respondent is not exempted from compensating Claimant since its measures do not fall
within the “police powers” exception.183 The “police powers” exception exists in a very
limited ambit,184 strictly covering bona fide measures with a non-discriminatory manner
necessary for the maintenance of public order, e.g. environmental concerns.185 Such
threshold demands high compatibility in that general public interest must be served for
the maintenance of public order.
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!180 PO3, ¶20. 181 Section III.A.1 of this Memorial. 182 Tecmed, ¶117. 183 Methanex, Part IV, Ch. D, p.7, ¶15; OECD: Indirect Expro., p.18. 184 Tecmed, ¶115. 185 Mann & Moltke, p.15.
MEMORIAL FOR THE CLAIMANT
29
94.! However, Respondent’s draconian tariff reduction did not satisfy such threshold, as its
political and economic situation at the time was stable. While there were teacher strikes,
there was no violence involved.186 Further, Respondent’s Prime Minister confirmed that
its economy is developing given that its FDI policy was “a tremendous success,”187
despite its economic concern of exceeding EU borrowing limit and 15% diversion of
state revenues.188 Thus, Respondent cannot hide behind the pretext of protecting public
order against the backdrop of the allegedly ‘unstable’ Barancasian economy.
95.! Additionally, the reduction destroyed investors’ confidence in Respondent’s PV sector,
thus discouraging low-carbon investments,189 precisely contrary to the LRE’s aim to
protect the environment.190 Moreover, as established supra,191 Respondent’s measures
discriminated Claimant’s Beta.
96.! Consequently, Respondent must still compensate Claimant as its measures fall beyond
the “police powers” exception.
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!186 PO2, ¶17. 187 Annex No. 8, p.40. 188 Facts, ¶¶29,30. 189 Nathanson, p.902. 190 LRE, Article 1. 191 Section III.A.4 of this Memorial.
MEMORIAL FOR THE CLAIMANT
30
IV. RESPONDENT’S MEASURES ARE NOT EXEMPTED UNDER EITHER THE CB-BIT OR
CUSTOMARY INTERNATIONAL LAW
97.! Respondent’s administrative and regulatory measures violating the substantive
provisions of the CB-BIT cannot be exempted under [A] Article 11 CB-BIT as an NPM
clause nor [B] the customary necessity defense under Article 25 ARSIWA.
A.! Respondent’s Measures Are Not Exempted Under CB-BIT
98.! Respondent’s measures are not exempted under Article 11 CB-BIT, which provides:
“Nothing in this Agreement shall be construed to prevent either Contracting Party from taking measures to fulfill its obligations with respect to the maintenance of international peace or security.”
99.! Although Article 11 CB-BIT was intended to serve as a safeguard clause that
contemplates ‘non-precluded’ measures to which either Contracting Party can resort
to,192 it does not exempt Respondent’s measures since [1] the provision is not self-
judging, [2] nor does it cover Respondent’s domestic situation.
1.! Article 11 CB-BIT is not a self-judging clause absent an expressed provision
100.! Respondent cannot unilaterally determine whether its acts remain legitimate despite
deviating from its treaty obligations,193 as Article 11 CB-BIT is not self-judging. For
such Article to be self-judging, in which the State adopting the measures in question
may determine its application,194 the self-judging nature must be expressly stated and
not merely assumed.195 In CMS, the tribunal ruled that, “when States intend to create a
right to determine unilaterally the legitimacy of extraordinary measure importing non-
compliance with obligations in a treaty, they do so expressly.”196
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!192 Continental, ¶164; Vandevelde, p.220. 193 CMS, Award, ¶370. 194 CMS, Award, ¶366. 195 Expert Opinion of José E. Alvarez, ¶¶13-15; Schill & Briese, p.69; CMS, Award, ¶370; Sempra, ¶379. 196 CMS, Award, ¶339.
MEMORIAL FOR THE CLAIMANT
31
101.! However, Article 11 CB-BIT only speaks of ‘measures’, contrary to self-judging
clauses, which explicitly state “measures that [it] considers necessary.”197 Consequently,
absent such language, application of Article 11 CB-BIT is subject to judicial review.198
2.! Article 11 CB-BIT does not apply to Respondent’s domestic situation
102.! Furthermore, Respondent’s domestic situation falls beyond the scope of Article 11 CB-
BIT, as it does not amount to an event concerning ‘the maintenance of international
peace or security’. Unlike most NPM clauses that preclude acts done for ‘the
maintenance of public order’ 199 or the host State’s ‘own national interests’, 200 the
Contracting Parties have clearly limited the application of the Article strictly to
“measures to fulfill their obligations with respect to the maintenance of international
peace or security.”201
103.! The Sempra tribunal found the phrase ‘maintenance of international peace and security’
to strictly refer to State obligations under the United Nations Charter.202 The CMS
tribunal likewise noted that circumstances falling under such ambit of an NPM would
normally include military events.203 Conversely, nothing of such nature occurred that
threatened Respondent’s essential security interest, thus falling outside the scope of the
NPM clause.
104.! Even if Article 11 CB-BIT could apply to economic emergencies as an essential security
issue, Respondent’s mere financial restraints did not qualify as such. In Continental
Casualty, the tribunal established that financial restraints could only qualify as essential
security interest in circumstances entailing “poverty of more than half of the population,
immediate threats to the health of the most vulnerable members of the population, or
widespread unrest and disorders.”204 In fact, tribunals in CMS, Enron, and Sempra have
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!197 1998 US-Mozambique BIT, Article 14(1); GATT, Article XXI. 198 CMS, Award, ¶366. 199 US-Argentina BIT, Article 11. 200 US-Czech BIT, Article X. 201 CB-BIT, Article 11. 202 Sempra, ¶372. 203 CMS, Award, ¶¶359,373. 204 Continental, Award, ¶180.
MEMORIAL FOR THE CLAIMANT
32
rejected Argentina’s arguments on the same note rendering Argentina liable for its
breach of the US-Argentina BIT.205
105.! Conversely, Respondent has yet to divert its 15% state budget to finance solar feed-in
tariffs and to exceed its EU-mandated borrowing limit to affect its essential security
interests or to place it in a situation of necessity.206 In fact, even after knowing the
unsustainability of the scheme due to the groundbreaking technology, Respondent
nonetheless granted 6,000 licenses out of 7,000 applications. 207 Additionally, no
violence occurred during the national strikes in 2012.208 Moreover, Respondent was
undergoing an economic growth.209
106.! Consequently, Respondent’s actions to address its essential security concerns are not
exempted under Article 11 CB-BIT.
B.! Respondent’s Measures Are Not Exempted Under Customary International Law
107.! Respondent’s measures are not exempted under the customary international law, as it
failed to fulfill four cumulative elements of the defense of necessity under Article 25
ARSIWA. To be precluded from wrongfulness, a State must meet the high threshold of
the customary defense of necessity as the secondary rule of exception to liability210 so as
to prevent States from eluding compliance with international obligations.211
108.! To this end, Respondent fails to satisfy the cumulative elements as it (i) had in fact
contributed to the situation of necessity. 212 Even if the situation was caused by
exogenous factors, Respondent (ii) was not threatened by a grave and imminent peril to
the extent that (iii) its measure was the ‘only way’ to safeguard its essential interests.213
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!205 CMS, Award, ¶97; Enron, ¶77; Sempra, ¶326. 206 Facts, ¶¶29,30. 207 PO2, ¶13; PO3; ¶22. 208 PO2, ¶17. 209 Annex No. 8, p.40. 210 ARSIWA Commentary, ¶21. 211 Gabčíkovo-Nagymaros, ¶51; White, p.5. 212 ARSIWA Commentary, Article 25(2)(b); CMS, Award, ¶294; Sempra, ¶353. 213 Sempra, ¶353; Gabčíkovo-Nagymaros, ¶54.
MEMORIAL FOR THE CLAIMANT
33
109.! First, Respondent had contributed to the purported state of necessity, which may be “in
one way or another, intentionally or by negligence.”214 Respondent’s financial restraint
was caused by its injudicious economic policies and decisions. Despite knowing the
unsustainability of its renewable energy scheme due to the groundbreaking
technology, 215 Respondent nonetheless granted licenses to 6,000 applicants, 216
unnecessarily imposing great burden to it.
110.! Second, Respondent was evidently not exposed to any grave and imminent peril, as
there was no crisis.217 The threat to divert 15% of Respondent’s state revenue and to
exceed EU mandated borrowing limit,218 the public pressure in highlighting investors’
windfall profits after the groundbreaking technology,219 and orderly national teacher
strikes demanding salary increase and educational funding in Barancasia220 pale in
comparison to the Argentine crisis, where there was deep recession, deflation,
unemployment, and the urgency of enacting Emergency Law within a week.221
111.! Third, Respondent’s options to safeguard its interests were not limited to enacting the
Amendment that prematurely revoked the initial fixed tariff.222 This assessment does not
require a hindsight analysis of which way would have been more successful or less
costly,223 inasmuch as it can be proven that the host State had other options to take.224
Instead of amending the law with retroactive effect to all existing investments,
Respondent could have alleviated its financial difficulties through other means, e.g.
limiting the applicability of the Amendment to new investments, as the scheme was only
unsustainable in the future.225
112.! As such, Respondent’s actions are not exempted under Article 25 ARSIWA.
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!214 Report of the ILC, UN Doc. A/35/10 (1980); Cheng, p.73. 215 Facts, ¶¶25,29. 216 PO2, ¶13. 217 Enron, ¶306. 218 Facts, ¶¶29,30. 219 Facts, ¶¶28,32. 220 Facts, ¶32. 221 Continental, ¶180; LG&E, Liability, ¶¶234,240. 222 Annex No. 4, p.34. 223 CMS, Award, ¶323; Crawford, p.184. 224 CMS, Award, ¶324. 225 Facts, ¶29.
MEMORIAL FOR THE CLAIMANT
34
ARGUMENTS ON REMEDIES
!V. RESPONDENT CAN BE ORDERED TO PERFORM RESTITUTION
113.! As Respondent’s violation of the CB-BIT cannot be exempted, Claimant may therefore
request the Tribunal to order specific performance for Respondent to continue paying
the previous 0.44EUR/kWh feed-in tariff to Claimant.
114.! Under customary international law, an order of specific performance as a form of
restitution prevails over compensation, as the latter is only to be awarded insofar as
“damage is not yet made good by restitution.”226 In this vein, [A] the Tribunal has the
power to order specific performance pursuant to Article 22(1)(vii) LCIA Rules vis-à-vis
Article 35 ARSIWA, which [B] would not violate Respondent’s sovereignty, therefore
enforceable.
A.! The Tribunal Can Order Specific Performance Pursuant to LCIA Rules and
ARSIWA
115.! Absent a provision concerning remedies in the relevant BIT, arbitral tribunals generally
turn to the parties’ consent to the applicable rules of arbitration.227 In this regard, Article
22(1)(vii) LCIA Rules expressly confers this Tribunal the power “to order compliance
with any legal obligation…and specific performance of any agreement.”228 Such is
corroborated in Al Bahloul and Nykomb, in that tribunals may order for specific
performance pursuant to Article 35 ARSIWA, 229 which provides that parties must
comply with a tribunal’s order of specific performance for restitution inasmuch as it is
(i) materially possible and, (ii) proportionate to the benefit deriving from restitution
instead of compensation.230
116.! First, Claimant submits that ordering Respondent to continue paying the previous
0.44EUR/kWh feed-in tariff is materially possible. Under ARSIWA, mere legal or
practical difficulties such as administrative constraints do not constitute material !!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!226 ARSIWA Commentary, Article 36(1); Chorzow, p.47; Texaco, p.508; Occidental, ¶34. 227 Stephens-Chu, p.890. 228 LCIA Rules, Article 22.1(7). 229 Al Bahloul, ¶47; Nykomb, p.39. 230 Crawford, ¶143.
MEMORIAL FOR THE CLAIMANT
35
impossibility.231 Thus, while Respondent may argue that specific performance would
require it to exceed its EU-mandated borrowing limits for the relevant years, such
administrative constraint only constitutes legal or practical difficulty, falling short of the
standard of impossibility.
117.! Second, ordering Respondent to continue paying the previous 0.44EUR/kWh feed-in
tariff is proportionate to an order for compensation. The amount of money due to the
Claimant if the Respondent were to continue paying the previous 0.44EUR/kWh is
equivalent to the losses incurred by the Claimant as a result of the tariff reduction. The
order for specific performance would not bestow on Claimant more than what it was
originally entitled to.
118.! Thus, the Tribunal can order Respondent to continue paying the previous 0.44EUR/kWh
feed-in tariff to Claimant.
B.! Order of Specific Performance Is Enforceable as It Does Not Violate
Respondent’s Sovereignty
119.! Claimant’s request for specific performance is enforceable since (i) Respondent has
waived its sovereign immunity by entering into the CB-BIT and (ii) such order is
enforceable pursuant to Article 8(3) CB-BIT vis-à-vis the NY Convention.
120.! First, by entering into the CB-BIT, Respondent has waived its immunity from the
jurisdiction of national courts for proceedings concerned with the arbitral process.232
Thus, both Parties have already waived their sovereign immunity in respect of the LCIA
tribunal’s power to order for specific performance as provided by Article 22 LCIA
Rules.
121.! Second, the order for specific performance would be enforceable under Article 8(3) CB-
BIT since the arbitral award shall be “final and binding on both parties” and
enforceable. Similarly, a State bound by the NY Convention is obliged to respect the
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!231 Crawford, p.185. 232 Bjorklund, pp.816-818.
MEMORIAL FOR THE CLAIMANT
36
binding effect of arbitral awards,233 and both Cogitatia and Barancasia are parties to the
NY Convention.234
122.! Respondent might object to enforcement on the ground that under Article 8(3) CB-BIT,
arbitral awards are enforceable only if they are in accordance with the domestic
legislation. Similarly, under the NY Convention, an award cannot be enforced if it were
contrary to the “public policy” of that State.235 However, as the New York District Court
ruled, the public policy defense to enforcement should be narrowly construed, and
enforcement should only be denied when it “violates the Forum State’s most basic
notions of morality and justice.”236 In this case, ordering Respondent to continue paying
the previous feed-in tariff would not violate justice and morality since Respondent will
merely be paying what is due under the LRE to Claimant. Hence, Respondent cannot
invoke the public policy defense to enforcement.
123.! Therefore, the Tribunal should first consider ordering the Respondent to continue
paying the previous 0.44EUR/kWh feed-in tariff as a form of remedy.
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!233 Redfern 2, ¶11.53. 234 PO2, ¶6 235 NY Convention, Art V(2)(b) 236 Parsons, ¶973.
MEMORIAL FOR THE CLAIMANT
37
VI. CLAIMANT’S BASIS FOR CLAIMING AND QUANTIFYING DAMAGES IS APPROPRIATE
124.! Should the Tribunal find that an award for restitution is not possible, Claimant
alternatively requests for damages, which is Claimant’s loss of net income resulting
from Respondent’s denial of Claimant’s license for Alfa and its feed-in tariff reduction
that affected Beta, the twelve projects, and the remaining future developments.
125.!While the CB-BIT does not provide any standard of damages except for lawful
expropriation, 237 Claimant is nonetheless [A] entitled to full reparation pursuant to
Article 36 ARSIWA given the causal link between Respondent’s unlawful acts and
Claimant’s damages, which [B] it has properly quantified. Subsequently, [C] damages
awarded to Claimant should carry compound interest rate and [D] the cost of arbitration
born by the Claimant should be proportional to the success or failure of its claims.
A.! Claimant Is Entitled to Full Reparation Given the Causal Link Between
Respondent’s Unlawful Acts and Claimant’s Damages
126.! ARSIWA provides that a State is under the obligation to make full reparation only for
injury caused by its wrongful act.238 Past tribunals have concurred that such obligation
arises when there is a proximate causal link that is “not too remote” between the
damages and the State’s unlawful acts.239 The causal link is established when Claimant
would not have suffered damages but for Respondent’s unlawful acts.240 In this case,
there is sufficient certainty that Respondent’s unlawful acts have caused Claimant’s [1]
historical and [2] future profits.
1.! There is sufficient certainty that Respondent’s unlawful acts caused Claimant’s
lost net income
127.! Historical damages refer to accrued losses resulting from the alleged breach. 241 In
Micula, the claimants were entitled to such damage since they incurred loss of net
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!237 CB-BIT, Article 5 (1). 238 Crawford, p.492; ARSIWA Commentary, Article 31(10). 239 Micula, Award, ¶923; CME, ¶921. 240 Micula, Award, ¶917. 241 LG&E, Award, ¶¶50,51.
MEMORIAL FOR THE CLAIMANT
38
income immediately after Romania’s unlawful revocation of incentives.242 Similarly,
Claimant is entitled to Alfa’s reduced net income from that of August 2010 to that of the
date of the award since it resulted immediately from Respondent’s denial of Alfa’s
license, which disentitled Claimant from the 0.44 EUR/kWh tariff.
128.! Furthermore, Claimant is also entitled to loss of Beta’s net income since it would have
been higher had Respondent maintained the feed-in tariff guarantee rather than reducing
it from 0.44EUR/kWh to 0.15EUR/kWh, a reduction of nearly 65%. 243 This is
consistent with the tribunal’s finding in LG&E, where the claimant was entitled to
damages since it would have received higher level of dividends had the respondent
maintained “the basic guarantees” of the “gas regulatory framework.”244
2.! Respondent’s unlawful acts have also resulted in Claimant’s lost future net income
129.! The ILC Commentary to Article 36 ARSIWA held that damage for lost future net
income is only to be awarded when the anticipated income comprises of “legally
protected interests of sufficient certainty to be compensable.” 245 Such sufficient
certainty is established when the claimant would have continued or started to engage in
a profit-making activity but for the respondent’s unlawful acts. 246 The tribunal
elaborated in Micula that it is sufficient for the activity’s profitability to be probable.247
130.! In this case, [a] Claimant had engaged in Solar PV projects and, if not for Respondent’s
unlawful acts, would have engaged in further developments, [b] both of which probably
would earn higher net income arising therefrom.
a.! Claimant had engaged in Solar PV projects and would have engaged in
further developments but for Respondent’s unlawful acts
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!242 Micula, Award, ¶953. 243 Facts, ¶35 244 LG&E, Award, ¶48. 245 ARSIWA Commentary, Article 36(27); LG&E, Award, ¶51. 246 Micula, Award, ¶1009. 247 Micula, Award, ¶1009.
MEMORIAL FOR THE CLAIMANT
39
131.! Aside from existing Solar PV projects that Claimant had been engaged in such as Alfa
since 2010,248 Beta since 2011249 and the twelve projects since 2012,250 Claimant would
also have constructed the remaining future development but for the Respondent’s tariff
reduction.
132.! The tribunal in Micula ruled that in giving award for lost opportunity, it must first be
proven that there is “contemporaneous evidence” whether in the form of “feasibility
plan, budget, memos or correspondence” evincing claimant’s intention for its future
development.251 Presently, Claimant's business plan clearly indicates its plan to develop
sixty solar panel installations by the end of 2023 at the rate of building 6 projects every
year from 2014 until 2023.252 In fact, such intention was affirmed by its construction of
the initial 12 projects. Had the Respondent maintained the pre-2013 feed-in tariff rate,
Claimant would have continued to accomplish its business plan by 2023.
b.! Claimant would probably earn higher net income arising from its existing and
planned Solar PV operations but for Respondent’s unlawful acts
133.! The tribunal in Vivendi ruled that probable future profitability can be established by
presenting the projects’ “proven record of profitability.”253 With respect to Alfa, had it
been granted the license, it would have received more net income as it would be entitled
to the EUR0.44/kWh feed in tariff until 2023 when the license expires, instead of the
market rate of EUR0.19 to EUR 0.22.254 Furthermore, the record shows that Alfa’s
productivity has improved consistently at a rate of 2.2% year-on-year from 2010 to
2012.255 As for Beta, it had operated for two years with a track record of profitability
between 2011 and 2013 before Respondent reduced the feed-in tariff.256
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!248 Facts, ¶¶12,22. 249 Facts, ¶23 250 Facts, ¶36. 251 Micula, Award, ¶1073. 252 Kovič, ¶11; Kovič Annex 4. 253 Vivendi, Award, ¶8.3.4; Vivendi, Annulment, p.65. 254 Kovič, Annex 1(A). 255 Kovič, Annex 1(A). 256 Kovič, ¶8; Facts, ¶23.
MEMORIAL FOR THE CLAIMANT
40
134.! In the case of projects with no past track record, such as the twelve projects,257 the
tribunal in Vivendi ruled that profitability can still be proven through evidence of
expertise and record of profitability of other projects it had operated in “similar
circumstances.”258 Such evidence of profitability could be adduced by a “concession
that guaranteed a certain level of profits.”259 The profitability of the twelve projects is
probable given Claimant’s success in developing Alfa and Beta as well as the
subsequent tremendous know-how on the Solar PV sector it obtained. 260 Finally,
Respondent’s initial grant of license for EUR0.44/kWh feed-in tariff guarantees that
Claimant will have a certain level of profits.261
135.!Moreover, Claimant would further engage in future developments as set forth in its 2023
business plan despite the absence of construction and licensing,262 as it has legitimately
relied on Respondent’s grant of license for its initial twelve projects.
B.! Further, Claimant’s Quantification of Damages Is Proper
136.! Having established Claimant’s claim for damages, Claimant submits that its
quantification of damages [1] by using the differential method with the discounted cash
flow valuation is appropriate. Subsequently, [2] damages awarded should be discounted
at Claimant’s WACC to reflect its NPV. Finally, [3] Claimant properly quantified each
of its head of damages.
1.! Preliminarily, the differential method with the discounted cash flow valuation is
appropriate to quantify Claimant’s damages
137.! In various jurisprudences involving international law violations, tribunals have resorted
to the “differential method” to evaluate damages,263 which compares the claimant’s
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!257 PO2, ¶26. 258 Vivendi, Award, ¶8.3.4; Vivendi, Annulment, p.65. 259 Micula, Award, ¶1010. 260 Facts, ¶23. 261 Facts, ¶33. 262 Kovič, ¶11; Kovič Annex 4, p.1-2. 263 Marboe, p.3.122; Wälde & Sabahi, p.1057.
MEMORIAL FOR THE CLAIMANT
41
financial position in the actual situation to the hypothetical situation where the unlawful
act had not been committed by the State.264
138.! The “differential method” should also be applied vis-à-vis the DCF valuation, which is
the most well accepted method for valuations,265 whereby the present value of both
future expected and past net cash flows is calculated using the same discount rate to
avoid an “Invalid Round Trip.”266 Therefore, Claimant’s damages are to be quantified
by comparing its DCF in the actual situation to its DCF in the hypothetical situation
where Respondent had not committed the unlawful act.
2.! Subsequently, damages awarded should be discounted at Claimant’s WACC to
reflect its NPV
139.! All awards on lost past and future net income must be discounted at an appropriate rate
in order to calculate its NPV.267 The tribunal in CMS established that “analysts have
tended to favor” discounting such awards at claimant’s WACC rather than its COE,268
since WACC discount factor represents “the cost of raising funds from shareholders and
lenders in a company,”269 and “blends equity holders and lenders requirements.”270 In
contrast, COE discount factor only represents the “value of equity” and does not account
for the value of debt.271
140.! In this regard, the damages should be calculated using Claimant’s 8% WACC discount
rate,272 rather than its 12% COE discount rate,273 thus taking into account Claimant’s
financing of its projects, which was 50% by debt and 50% by equity.274
3.! Accordingly, Claimant has properly quantified each head of damages
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!264 Marboe, p.3.122. 265 Kantor, p.131. 266 Kantor, p.131. 267 Marboe, p.5.193. 268 CMS, Award, ¶430. 269 EDF, Award, ¶1285. 270 Bau, Award, ¶14.35. 271 CMS, Award, ¶215. 272 Kovič, ¶12; Priemo, ¶9. 273 Priemo, ¶9. 274 Annex No. 9.
MEMORIAL FOR THE CLAIMANT
42
141.! In sum, Claimant is entitled to EUR 2,437,217, which comprises Alfa (EUR 120,621),
Beta (EUR 123,261), the twelve projects (EUR 1,427,500) and the other future
developments (EUR 765,835).275
142.! Alternatively, should the Tribunal not award lost future income for the twelve projects
and the future developments, Respondent should at least be ordered to pay EUR
933,938 to Claimant, constituting Alfa (EUR 120,621), Beta (EUR 123,261), and the
twelve projects’ out-of-pocket-expenses (EUR 690,056).
143.! Even assuming that lost future income is not possible due to uncertainty of future
profitability, past tribunals concurred that damages for wasted out-of-pocket expenses
should be awarded.276 Such “out-of-pocket” expenses include costs of particular assets
contributed to the investment.277 Claimant is thus entitled to the EUR 690,056 out-of-
pocket expenses for the twelve projects,278 which includes the amount of money that
Claimant had spent on land, PV panels, deposit on remaining PV panels as well as labor,
and bank interest.279
144.! Additionally, Respondent may argue that Claimant is not entitled to the full amount of
damages because it failed to mitigate damages by continuing the construction of the
twelve projects even after the tariff reduction in 2013.280 The duty to mitigate damages
has been defined as the duty of the wronged party to mitigate its losses.281 However,
Claimant’s continued construction of the twelve projects cannot be construed as a
failure to mitigate damages since Respondent had given a legal permit for Claimant to
construct the twelve projects by granting licenses in 2012.282
C.! Damages Awarded to Claimant Should Carry Compound Interest Rate at The
Rate of Claimant’s WACC
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!275 Kovič, ¶¶7-11. 276 Pope & Talbot, ¶81; MTD, ¶253. 277 Ripinsky & Williams, p.294. 278 Kovič, ¶9. 279 Kovič, Annex 2. 280 PO2, ¶26. 281 Marboe, p.3.240. 282 Facts, ¶33.
MEMORIAL FOR THE CLAIMANT
43
145.! Past tribunals as recently affirmed by the tribunal in Micula, held that award of damage
should be given with compound interest,283 so as to restore Claimant to the position it
would have been had the breach not occurred. 284 Thus, the damages awarded to
Claimant should be given with compound interest, at the 8% rate of its WACC so as to
avoid an “Invalid Round Trip.”285
D.! The Cost of Arbitration Born by Claimant Should Be Proportional to the Success
or Failure of Its Claims Pursuant to Article 28(4) LCIA Rules
146.! Article 28(4) LCIA Rules stipulates that the tribunal’s decisions on both arbitration
costs and legal costs should reflect the parties’ relative success and failure in the
award.286 Hence, the cost of the arbitral proceedings that should be born by Claimant
should be proportional to the success or failure of its claims.
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!283 Micula, Award, ¶1266. 284 Micula, Award, ¶1265. 285 Kovič, ¶12. 286 LCIA Rules, Article 28(4).
MEMORIAL FOR THE CLAIMANT
44
PRAYERS FOR RELIEF
Claimant respectfully asks the Tribunal to find that:
I.! It has jurisdiction over the present dispute and Claimant’s claims are admissible;
II.! Respondent breached its substantive obligations stipulated under the CB-BIT;
III.! Respondent is not exempted under either the CB-BIT or the customary defense of
necessity;
IV.!Respondent should be ordered to do specific performance for restitution by continuing
to pay the pre-2013 0.44EUR/kWh feed-in tariff to Claimant;
V.! Alternatively, Respondent should pay EUR 2,437,217 as compensation to Claimant
because Claimant’s basis for claiming and quantifying compensation is appropriate.
TEAM KRYLOV
On behalf of Claimant
19 September 2015
!