TDC2/TCC2 Réunion de chantier 3 08.11.2013 In sharepoint: workspace/tcc2wg/LS1%20worksite%20meeting
TDC2-TCC2 consolidation status report to EATM
description
Transcript of TDC2-TCC2 consolidation status report to EATM
TDC2-TCC2 consolidationstatus report to EATM
10.12.2013In sharepoint:
https://espace.cern.ch/sba-workspace/tcc2wg/LS1%20worksite%20meeting/
2013 planning
Activities Duration Group Nov'13 Dec'13 4 11 18 25 2 9 16 23
TCSC removal 1w EN-HE,STI
TT20 QNL magnet exchange 1w EN-HE
Splitter removal 3w EN-HE
MDLV removal 1w EN-HE
Contingency 1w
Goal end 2013: 6 hot items out of the way.
Removal of hot items• Removal of hot items from the worksites:– TCSC removed first and brought to B.955– 3 splitter2 magnets and 2 MDLV removed and stored
in TDC2
3 splitter2 magnets2 MDLV magnets
Removal of hot items
Splitters in W49
MDLV in W50
Dose planning
4-Nov
17-Nov
30-Nov
13-Dec
26-Dec
8-Jan
21-Jan3-Fe
b
16-Feb
1-Mar
14-Mar
27-Mar
9-Apr
22-Apr
5-May
18-May
31-May
13-Jun
26-Jun
9-Jul
22-Jul
4-Aug
17-Aug
30-Aug
12-Sep
25-Sep
0
10000
20000
30000
40000
50000
60000
70000
80000
90000
Dose breakdown by week
Dose/week (uSv)Cumulative dose (uSv)Achieved (uSv)
Dos
e (u
Sv)
1900 uSv achieved / 11500 uSv estimated
2014 Planning
Worksite Operation Worksite Op.
Activities Duration Jan'14 Feb'14 March 14 April 14 May 14 June 14 July 14 Aug' 14 Sep' 14 Oct' 14 Nov' 14 Dec' 14 Jan' 15 Feb' 15 March 15 April 15 May 15 June 156 13 20 27 3 10 17 24 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 1 8 15 22 29
Civil engineering 8w
Cooling and ventilationChilled water 12w
Demin. Water 5w
AHU control upgrade 12w AHU control upgradeHandling 2w
Electricity NA NA physics LAB Ion Run NALV 10w start Closure upCabling 14+12w Cabling phase 1 up Cabling phase 2 (if needed)
Magnets 12w
Vacuum 8w
Secondary beam lines 8 w
Collimators and targets 2w
Cleaning 4w
safety systems 6w