Study report on the TDC2/TCC2 Cabling and Low Voltage activities Ivan Moya Martinez– EN/EL/CF –...

26
Study report on the TDC2/TCC2 Cabling and Low Voltage activities Ivan Moya Martinez– EN/EL/CF – WP 31st Meeting 2014.04.08

Transcript of Study report on the TDC2/TCC2 Cabling and Low Voltage activities Ivan Moya Martinez– EN/EL/CF –...

Page 1: Study report on the TDC2/TCC2 Cabling and Low Voltage activities Ivan Moya Martinez– EN/EL/CF – WP 31st Meeting 2014.04.08.

Study report on the TDC2/TCC2 Cabling and Low Voltage

activities

Ivan Moya Martinez– EN/EL/CF – WP 31st Meeting 2014.04.08

Page 2: Study report on the TDC2/TCC2 Cabling and Low Voltage activities Ivan Moya Martinez– EN/EL/CF – WP 31st Meeting 2014.04.08.

Summary• Replacement of cable trays– Cable trays– DC Cables– Control cables

• New cables installation requests + reinstallation of temporary cables

• Redo joints magnets cables TCC2• Consolidation of existing cables• Low Voltage refurbishment activity

Ivan Moya Martinez– EN/EL/CF – WP 31st Meeting 2014.04.08

Page 3: Study report on the TDC2/TCC2 Cabling and Low Voltage activities Ivan Moya Martinez– EN/EL/CF – WP 31st Meeting 2014.04.08.

Replacement of cable trays (I)

Ivan Moya Martinez– EN/EL/CF – WP 31st Meeting 2014.04.08

Re-routing zone (40m approx.)

Page 4: Study report on the TDC2/TCC2 Cabling and Low Voltage activities Ivan Moya Martinez– EN/EL/CF – WP 31st Meeting 2014.04.08.

Replacement of cable trays (II)

DC cables in one cable tray (0D115+0D116+0D516)Control cables in one cable tray with separator (0D110+0D114)Maintains some of the old cable trays & re-use some parts of the old cable trays.

Ivan Moya Martinez– EN/EL/CF – WP 31st Meeting 2014.04.08

Page 5: Study report on the TDC2/TCC2 Cabling and Low Voltage activities Ivan Moya Martinez– EN/EL/CF – WP 31st Meeting 2014.04.08.

Replacement of cable trays: 0D516 & 0D514 (III)

• Cables in cable tray 0D516 already identified (DC cables) 8 cables

• Cables in cable tray 0D514 already identified (Control cables) 17 cables

Ivan Moya Martinez– EN/EL/CF – WP 31st Meeting 2014.04.08

Page 6: Study report on the TDC2/TCC2 Cabling and Low Voltage activities Ivan Moya Martinez– EN/EL/CF – WP 31st Meeting 2014.04.08.

Replacement of cable trays: DC Cables (I)

Start point

Number of affected cables:a) 56 in cable traysb) 14 on the floor (+8 no accessible)

Number of joints and lugsa) Lugs : 14*2+38 =66

1) 14 short cables (link between magnets)2) 38 arrivals

b) Joints : 38+36=741) 36 for magnets in “forbidden zone”2) 38 the rest of the zone

Type of cables:a) PZK1 (1x1x240 AL ) ”ANTIRAD”b) PZK2 (2x1x240 AL ) ”ANTIRAD”c) PZM3 (3x1x400 AL) ”ANTIRAD”d) PZM4 (4x1x400 AL) ”ANTIRAD”

Ivan Moya Martinez– EN/EL/CF – WP 31st Meeting 2014.04.08

x4x4x4

x4

x2x4

x4

Cable tray 0D116 + 0D516

Forbidden zone

x4x2

x2x2

x6x4x4x8

x2

Cable tray 0D115

Page 7: Study report on the TDC2/TCC2 Cabling and Low Voltage activities Ivan Moya Martinez– EN/EL/CF – WP 31st Meeting 2014.04.08.

Replacement of cable trays: DC Cables (II)

Old cables PZK1 (1x1x240 AL ), PZK2 (2x1x240 AL ), PZM3 (3x1x400 AL) PZM4 (4x1x400 AL) – “ANTIRAD”IS23

New cables ZCR1 (1x240 AL CL.2 0.6/1kV) ZCT1 (1x400 AL CL.2 0.6/1kV)Technical appendix 362 rev. 11.5 (01.12.2004)

EDMS Id: 1213585 provided by Yann Pira

““

““

*

**

*

**

Page 8: Study report on the TDC2/TCC2 Cabling and Low Voltage activities Ivan Moya Martinez– EN/EL/CF – WP 31st Meeting 2014.04.08.

Replacement of cable trays: 0D110 Control Cables (I)

• Cables in cable tray 110 : identification in progress.– Some cables are old. – Difficult to follow in the cable trays.– No info of the use.

• Cables:– C4E75: LEP TDM project, is it still alive?– NE4?:– CB50: routing not according to thecâblothèque.– NE48?

Ivan Moya Martinez– EN/EL/CF – WP 31st Meeting 2014.04.08

Page 9: Study report on the TDC2/TCC2 Cabling and Low Voltage activities Ivan Moya Martinez– EN/EL/CF – WP 31st Meeting 2014.04.08.

Replacement of cable trays: 0D114 Control Cables (II)

• Cables in cable tray 114 : identification in progress.

Ivan Moya Martinez– EN/EL/CF – WP 31st Meeting 2014.04.08

Page 10: Study report on the TDC2/TCC2 Cabling and Low Voltage activities Ivan Moya Martinez– EN/EL/CF – WP 31st Meeting 2014.04.08.

Replacement of cable trays: 0D117 Control Cables (III)

• Cables in cable tray 117 : identification in progress.– Difficult to follow in the cable trays.– Cables at the end of forbidden zone. (Pump system (CV), radiation

monitor, emergency lights, plugs, lighting system…)– Cables entering in the ventilation pit?

Ivan Moya Martinez– EN/EL/CF – WP 31st Meeting 2014.04.08

Red door

Page 11: Study report on the TDC2/TCC2 Cabling and Low Voltage activities Ivan Moya Martinez– EN/EL/CF – WP 31st Meeting 2014.04.08.

Replacement of cable trays: Control Cables Summary (IV)

• 34 cables to re-install• Total cable length = 3701 m• 6 cables in the “forbidden zone”• Users:

– Vacuum: 1 cables– RP: 1 cables– BMP detectors: 18 cables– Intercom:3 cables– Magnets: 3 cables– Telephone (sec.+normal+alarm): 3 cables– Others : 5

• BT cables not included: lighting, security lighting, AUG, pumps (CV), plugs, …• Remaining work:

– 4 cables in cable tray 0D110– 7 cables in cable tray 0D114– Re-check cable passing to TT20/end TDC2.

Ivan Moya Martinez– EN/EL/CF – WP 31st Meeting 2014.04.08

Page 12: Study report on the TDC2/TCC2 Cabling and Low Voltage activities Ivan Moya Martinez– EN/EL/CF – WP 31st Meeting 2014.04.08.

New cables installation requests + temporal cable

• 18 cables to install• Total cable length = 2985 m• 4 cables in the “forbidden zone”• Users:– Vacuum: 15 cables– RP: 2 cables– ABM detectors: 1 cable

Ivan Moya Martinez– EN/EL/CF – WP 31st Meeting 2014.04.08

Page 13: Study report on the TDC2/TCC2 Cabling and Low Voltage activities Ivan Moya Martinez– EN/EL/CF – WP 31st Meeting 2014.04.08.

Cable consolidation (I)• Near the splitter 2:

– 50 or 60 new cables to pull.• No possibility to redo

connectors – They will be replaced in LS2

• Best solution: wait to LS2

Ivan Moya Martinez– EN/EL/CF – WP 31st Meeting 2014.04.08

• Home made box (vacuum)– Redo the box in a proper place.– Home made cables to reinstall and

to be included in the câblothèque.( 4 short cables)

– In LS2, new cables can be installed from surface.

Page 14: Study report on the TDC2/TCC2 Cabling and Low Voltage activities Ivan Moya Martinez– EN/EL/CF – WP 31st Meeting 2014.04.08.

Cable consolidation (II)• 3 cables pulled by user up to BTV925

– Are they needed?– New cables to re-install porperly?

Ivan Moya Martinez– EN/EL/CF – WP 31st Meeting 2014.04.08

Page 15: Study report on the TDC2/TCC2 Cabling and Low Voltage activities Ivan Moya Martinez– EN/EL/CF – WP 31st Meeting 2014.04.08.

Cable consolidation (III)• Cable to remove:

– MDFP230707: 6 cables– MDFP230710: 6 cables– Easy access– Removal up to TA801 (to

be re-used in the future if it is needed)

– No interference with other cables.

Ivan Moya Martinez– EN/EL/CF – WP 31st Meeting 2014.04.08

Page 16: Study report on the TDC2/TCC2 Cabling and Low Voltage activities Ivan Moya Martinez– EN/EL/CF – WP 31st Meeting 2014.04.08.

Magnets cables joints

Ivan Moya Martinez– EN/EL/CF – WP 31st Meeting 2014.04.08

• From “Magnets” Draft EDMS 1260733

• 12 connections of as shown in the document (6 under MBN V071 and 6 under MBN 067) have been found.

• Solution:“Manchonnage”

Page 17: Study report on the TDC2/TCC2 Cabling and Low Voltage activities Ivan Moya Martinez– EN/EL/CF – WP 31st Meeting 2014.04.08.

Time Estimations

Page 18: Study report on the TDC2/TCC2 Cabling and Low Voltage activities Ivan Moya Martinez– EN/EL/CF – WP 31st Meeting 2014.04.08.

Low Voltage works

James Devine – EN/EL/BT – WP 31st Meeting 2014.04.08

• Scope: Replacement of all obsolete and non-compliant systems. – Lighting (Normal & Emergency)– Power distribution (Socket outlets)– Fixed appliances (Cranes, transport rails)– AUG buttons

• Reversed sequence of installation:– Install new– Remove old

Page 19: Study report on the TDC2/TCC2 Cabling and Low Voltage activities Ivan Moya Martinez– EN/EL/CF – WP 31st Meeting 2014.04.08.

Normal Lighting

James Devine – EN/EL/BT – WP 31st Meeting 2014.04.08

• Provide minimum 100 Lux illumination at floor level throughout TDC2/TCC2.

• 50% de-rating for radiation impact on luminaires.

• 58W T26 Fluorescent lighting within TDC2, long life tubes and ferromagnetic ballasts to resist radiation.

• 207W LED High-bay lighting within TCC2, power converters installed in CV Mezzanine to reduce radiation dose.

Page 20: Study report on the TDC2/TCC2 Cabling and Low Voltage activities Ivan Moya Martinez– EN/EL/CF – WP 31st Meeting 2014.04.08.

Emergency Lighting

James Devine – EN/EL/BT – WP 31st Meeting 2014.04.08

• Provide 1 Lux illumination along escape routes

• 50% de-rating for radiation.

• Comatelec LEDs within TDC2 and TCC2, custom radiation resistant design specific for CERN.

• Additional Thorlux LED fittings installed on TCC2 catwalk for illumination of beam line bridges.

Page 21: Study report on the TDC2/TCC2 Cabling and Low Voltage activities Ivan Moya Martinez– EN/EL/CF – WP 31st Meeting 2014.04.08.

Power Distribution

James Devine – EN/EL/BT – WP 31st Meeting 2014.04.08

• Install rationalized electrical distribution for socket outlets in vicinity of beam line

• Remove obsolete equipment and cables where possible.

• Agreement on positions with users required.

OLD

NEW

Page 22: Study report on the TDC2/TCC2 Cabling and Low Voltage activities Ivan Moya Martinez– EN/EL/CF – WP 31st Meeting 2014.04.08.

AUG buttons

James Devine – EN/EL/BT – WP 31st Meeting 2014.04.08

• Existing cabling + buttons are life expired.• Replacement with new cables and CERN

specific AUG button.• Rationalise AUG placement to minimise

dose (installation and operation).

OLD NEW

Page 23: Study report on the TDC2/TCC2 Cabling and Low Voltage activities Ivan Moya Martinez– EN/EL/CF – WP 31st Meeting 2014.04.08.

Sequence of works

James Devine – EN/EL/BT – WP 31st Meeting 2014.04.08

1. Pulling of new cables arriving to TT20/BA20/TDC2(4.5m)

2. Emergency Lighting Installation3. AUG Installation4. New Lighting & Power installation5. EL/CF cable tray removal/installation

activities6. Final removal of obsolete equipment

Page 24: Study report on the TDC2/TCC2 Cabling and Low Voltage activities Ivan Moya Martinez– EN/EL/CF – WP 31st Meeting 2014.04.08.

Conclusions• Identification must be finished.• The preparation of the work is quite advanced.• Procedure to work in safety condition must be

finished (grounding)• The work in the splitter zone implies high doses• New dose survey is needed for a better

calculation of the dose.• Some more work is required to reduce the total

dose.

Ivan Moya Martinez– EN/EL/CF – WP 31st Meeting 2014.04.08

Page 25: Study report on the TDC2/TCC2 Cabling and Low Voltage activities Ivan Moya Martinez– EN/EL/CF – WP 31st Meeting 2014.04.08.

Thanks!

Ivan Moya Martinez– EN/EL/CF – WP 31st Meeting 2014.04.08

Page 26: Study report on the TDC2/TCC2 Cabling and Low Voltage activities Ivan Moya Martinez– EN/EL/CF – WP 31st Meeting 2014.04.08.

WDP – DRAFT!!! Handle with precaution!!

RP Survey 31.1.14