SYSTEM RESTORATION PLAN
Transcript of SYSTEM RESTORATION PLAN
SYSTEM
RESTORATION PLAN
AORC-CIGRE Technical Meeting
2nd-4th May 2012
AORC-CIGRE Technical Meeting 2nd-4th May 2012
SYSTEM RESTORATION PLAN
1. Introduction
2. System Restoration Plan
2. Operating Procedure
3. Example of Manjung Island Restoration Plan
4. Initiatives to Prevent System Collapse
INTRODUCTION
AORC-CIGRE Technical Meeting 2nd-4th May 2012
INTRODUCTION
AORC-CIGRE Technical Meeting 2nd-4th May 2012
INTRODUCTION
• When the system frequency drops to 49.3Hz, the first
stage of Underfrequency Load Shedding (UFLS) is
initiated.
• When all the 13 UFLS stages (49.3Hz till 48.1Hz) have
been exhausted and the system frequency is still falling,
• And if any other manual load shedding actions taken are
unable to arrest frequency decay - SYSTEM COLLAPSE is inevitable.
AORC-CIGRE Technical Meeting 2nd-4th May 2012
INTRODUCTION
• When the system has collapsed, the operators need to take
steps to restore back the system from BLACKOUT
condition.
• To facilitate this end- A System Restoration Plan is
needed.
• With such a plan the operators and all other parties
involved can restore back the system systematically.
• The parties include the TNB and IPPs.
MAJOR GENERATING STATIONS IN PENINSULAR MALAYSIA
6
TNB - EGAT HVDC Interconnection
TNB - SINGAPORE Interconnection
Kuah
Melaka
Seremban
Georgetown
Kota Bharu
Kuala Terengganu
Ipoh
Kuantan
Shah Alam
Alor Setar
Kangar
JOHOR
PAHANG
MELAKA
NEGERI SEMBILAN
SELANGOR
PERAK
KEDAH
PULAU PINANG
KELANTAN
TERENGGANU
PERLIS
WILAYAH PERSEKUTUAN
LANGKAWI
MELAKA
BERSIA
KENERING
TEMENGOR
KENYIR
SG PIAH UPPER
SG PIAH LOWER
JOR
WOH
ODAK
CHENDEROH
PERGAU
MAIN GRID IN
PENINSULAR MALAYSIA
N
Legend
Hydro Power Station
Thermal Power Station
State Capital
Existing Planned
500kV Overhead Line
275kV Overhead Line
275kV Cable
Johor Bahru
PRAI
GELUGOR
SEGARI
CONNAUGHT
BRIDGE
SERDANG
KAPAR
POWERTEK
PD
POWER
GENTING
SANYEN
PORT
DICKSON
YTL
PASIR
GUDANG
PAKA
YTL
Ayer Tawar
Batu Gajah Papan
Kuala Kangsar
Bukit Tambun Junjung
Bukit Tengah
Gurun
Bedong
Kota Setar
Chuping
Bukit Tarek
KL (N) KL (E)
Hicom G
KL (S)
Salak Tinggi
Melaka
Kg Awah
Scudai
Telok Kalong
Tanah Merah
JANAMANJUNG
Major TNB Substation
YAN
Yong Peng (N)
Bukit Batu
Sedili
Lenggeng
Yong Peng (E)
300kV HVDC Line
Gurun
Bkt Keteri
Chuping
Kangar
Telok
Apau
Kuala
Perlis
Kota Setar
Kulim
Telok
Ewa
Sadao
Pattani
Songkhla
Khlong
Ngae
Bedong
PERLIS Yala 2
Hat Yai 2
Satun
Yala 1
KEDAH
Plentong Substation
Kg Senibong
230kV, 2 x 500MVA Cables
Senoko Power Station
SINGAPORE
JOHOR
Hat Yai 1
Existing HVDC / HVAC
Interconnections in Malaysia
TNB-EGAT HVDC
INTERCONNECTION
TNB- SINGAPORE
INTERCONNECTION
7
SYSTEM HIGHLIGHTS
Installed
Capacity
21,817 MW
Maximum Demand
(As per April 2012)
15,476 MW
SYSTEM
RESTORATION PLAN
AORC-CIGRE Technical Meeting 2nd-4th May 2012
AORC-CIGRE Technical Meeting 2nd-4th May 2012
SYSTEM RESTORATION PLAN
• The strategy for speedy restoration is to divide the network
into 7 electrical sub-systems or “Electrical Islands” .
• Islands are powered up “independently” and “in parallel” to
hasten restoration time.
• Failure to start-up or stabilise a single Island will not
jeopardise the overall restoration process.
• Obtain supply source from neighbour utilities/island if
possible.
• Combine / parallel islands until Main Grid reestablished.
AORC-CIGRE Technical Meeting 2nd-4th May 2012
SYSTEM RESTORATION PLAN
The 7 ‘Electrical Islands’:
1. Prai Island
2. Manjung Island
3. Port Klang Island
4. Serdang Island
5. Tuanku Jaafar Island
6. Pasir Gudang Island
7. Paka Island
INTRODUCTION
AORC-CIGRE Technical Meeting 2nd-4th May 2012
OPERATING
PROCEDURE
AORC-CIGRE Technical Meeting 2nd-4th May 2012
OPERATING PROCEDURE
• Immediately after a system collapse, the Control Manager at
NLDC will be busy assessing the state of the system.
• Power stations will be executing emergency procedures to
ensure the safe shutdown of generating units and maintain
station auxiliary supply.
• Defined areas of control and operation is necessary to allow
delegation of authority and responsibilities without affecting
safe operations of the system equipment.
AORC-CIGRE Technical Meeting 2nd-4th May 2012
OPERATING PROCEDURE
• Preferably to energise 132KV line.
• All open strategy (Transmission & Distribution)
• Black Start Generator energise dead bus.
• Stabilisation of generators by small incremental loads.
• The generators will then be synchronised to other stable generators through Transmission grid in their island.
• Finally when the islands are stable they will be reconnected back to each other and eventually form back the grid system.
AORC-CIGRE Technical Meeting 2nd-4th May 2012
OPERATING PROCEDURE
PRAI
island
MANJUNG
island
PAKA
island PKLG
island
SRDG
island
TJPS
island
PGPS
island PGL
HVAC
EGAT
HVAC/HVDC
AORC-CIGRE Technical Meeting 2nd-4th May 2012
OPERATING PROCEDURE
Crisis Communication Flowchart:
AORC-CIGRE Technical Meeting 2nd-4th May 2012
OPERATING PROCEDURE
Operation Rooms Activation:
Monitor TNB Restoration Operation National
Operation Room
VVIP Room
Strategic
Operation Room
Media Room
TNB higher management strategies plan
after national blackout
Briefing & press statement
Briefing to ministers, board of directors etc
INTRODUCTION
AORC-CIGRE Technical Meeting 2nd-4th May 2012
EXAMPLE OF
MANJUNG ISLAND
RESTORATION PLAN
AORC-CIGRE Technical Meeting 2nd-4th May 2012
OPERATING PROCEDURE
1. Island peak load: 911 MW
2. Trough load: 598 MW
3. Critical Substations
• 500kV Air Tawar & Janamanjung
• 275kV Papan, Kuala Kangsar, Bukit Tengah & Segari
4. Power Stations Generation Capacity:
• Janamanjung Power Station: 2,100MW
• Segari Power Station: 1,350MW
• GB3 Power Station: 655MW
• Cameron Highlands Power Station: 250MW
INTRODUCTION
AORC-CIGRE Technical Meeting 2nd-4th May 2012
SCENARIO 1:
CAMERON HIGHLANDS
POWER STATION SETS
AVAILABLE FIRST
1
2
3
4 5
6
7
INTRODUCTION
AORC-CIGRE Technical Meeting 2nd-4th May 2012
SCENARIO 2:
SEGARI POWER STATION
SETS AVAILABLE
FIRST
1
2 3
4
5
6
7 8
AORC-CIGRE Technical Meeting 2nd-4th May 2012
SCENARIO 3:
JANAMANJUNG
POWER STATION
TRIP TO HOUSE LOAD
1
3 4
5
6
7
8 9
2
AORC-CIGRE Technical Meeting 2nd-4th May 2012
INITIATIVES
TO
PREVENT SYSTEM
COLLAPSE
AORC-CIGRE Technical Meeting 2nd-4th May 2012
INITIATIVES TO PREVENT SYSTEM COLLAPSE
1. Security-Checked Switching
• All supervisory switching are preceded by automatic system
security check by the EMS.
• System operators will be alarmed if a switching cause an
overload condition or creates a harmful N-1 contingency.
2. Availability & Reliability of State Estimator (SE)
• Important for the continuous monitoring of the security of
the grid system.
AORC-CIGRE Technical Meeting 2nd-4th May 2012
INITIATIVES TO PREVENT SYSTEM COLLAPSE
3. Real Time Short Circuit (RTSCT) Analysis.
• RTSCT provides the real-time short circuit current
calculations flowing through all circuit breakers & isolators
in the system.
• System operators are now aware of any possible danger as a
result of a fault in the system.
• Preventive actions can be taken to prevent any violations of
short circuit CB ratings.
AORC-CIGRE Technical Meeting 2nd-4th May 2012
INITIATIVES TO PREVENT SYSTEM COLLAPSE
4. Islanding Detection System.
• Automatic display electrical island when they formed.
5. Real Time Contingency Analysis (RTCA)
• To help control engineers to identify the next worst case
contingency.
• Perform all N-1 and selected N-2 contingencies every 5
minutes.
6. Power Flow (PWFLOW)
• To enable control engineers to conduct real time power
flow studies.
AORC-CIGRE Technical Meeting 2nd-4th May 2012
INITIATIVES TO PREVENT SYSTEM COLLAPSE
7. Dispatcher Training Simulator (DTS)
• Fully utilise the DTS facility since it was introduced in
1997.
• Real events initialise from the real-time can be regenerated
& experienced by the system operators.
8. Improve SCADA display
• System operators have overall system & regional
overview.
9. Full redundancy on communication network to ensure
reliable data transfer.
AORC-CIGRE Technical Meeting 2nd-4th May 2012
INITIATIVES TO PREVENT SYSTEM COLLAPSE
10. Efficient Emergency Outage Management.
• Control Engineers to perform Load Flow Analysis before implementing outage.
11. Disturbance Recorder.
• Install at critical and strategic substations.
• Help control room operator to make decision for faster restoration.
12. Corporate Emergency Response Plan (CERP)
• Developed for the organization to response to an emergency situation.
• Aim to enable a prompt, coordinated and effective response to an emergency situation.
• Corporate level drill at least once a year.
AORC-CIGRE Technical Meeting 2nd-4th May 2012
SYSTEM MINUTES HISTORY
Transmission System Minutes
7.32
9.34
6.56
1.02 0.854 0.76261.013
0
2
4
6
8
10
FY05/06 FY06/07 FY07/08 FY08/09 FY09/10 FY10/11 FY11/12
Financial Year
Min
ute
s
AORC-CIGRE Technical Meeting 2nd-4th May 2012
THANK YOU