System Reliability Procurement: Non-wires Alternatives in Rhode Island Tim Roughan National Grid.
-
Upload
jayson-randall -
Category
Documents
-
view
212 -
download
0
Transcript of System Reliability Procurement: Non-wires Alternatives in Rhode Island Tim Roughan National Grid.
System Reliability Procurement: Non-wires Alternatives in Rhode Island
Tim Roughan
National Grid
2
Origins – RI Legislation
Least Cost Procurement Law - 2006
Intended to:
Increase stability through resource diversification
Integrate renewables
Reduce cost of energy
Increase accountability in planning and administration
Required the development of Standards for Energy Efficiency and System Reliability Procurements
Basis for 3-year EE plans
Approved in 2009
Updated in 2011
3
Origins – RI Legislation
Despite approval of proposed SRP Plan in 2009, no SRP funding
Some EE budget money set aside for SRP analysis tool development
Internal guidelines for NWA consideration developed in 2010/2011
EE/SRP Standards updated in 2011
More detail in SRP section on funding, BC analysis and reporting
Incorporated project eligibility criteria from internal guidelines
Established annual reporting
First SRP Report was approved and funded in 2012
4
Our Internal Process
Internal Principles Document
Cross-functional agreement on NWA process
Approved in February 2011
2 Review Cycles (below)
If NWA options are available, wires and NWAs are considered together
Initial Review: Engineering
•Review capital project needs to determine potential for NWA•Viable needs must:•Have >$1M wires option budget•Be unrelated to asset condition•Have >= 3 year lead time•Be <20% of total area’s load
Secondary Review: Customer
Org.•Review shortlist from T&D for quantitative NWA potential•Review should include assessment of:•Customer base•Load drivers•Available technologies
5
Identified Need
Two Feeders out of Tiverton
substation serving Tiverton &
Little Compton
Forecasted to be overloaded
starting in 2014
Potential for ~5,600 affected
Customers: 80% Residential,
20% C&I
Wires solution – substation
upgrade – will cost $2.9
million in 2014
Non-wires Goal: provide load
relief starting in 2014, up to
1MW by 2017
6
Pilot Design – A Collaborative Approach
Project plan includes SRP and EE components
New technology, enhanced incentives, marketing and evaluation through SRP funding
Measures delivered through EnergyWise, the RI single family, residential audit program
Demand response events conducted through SRP funding
Benefit/cost analysis uses the Total Resource Cost model
Uses same avoided costs as the statewide programs
Added benefits associated with the DR events
Regional T&D deferral benefit is replaced with specific locational T&D deferral benefit as calculated as a revenue requirement for deferral years 2014 through 2017
Associated benefits/costs of the leveraged EE components included in BC but not claimed by SRP
Pilot must be cost effective over full six-year life, not in each year
2012 Components
• Wi-fi Thermostats for Central AC Units
• Higher Frequency of EE Audits
• DR Lighting Ballast (Commercial Only)
2013 Enhancements
• Wi-fi Thermostats and Smart Plugs for Window AC Units
• Energy Star Window AC Purchase Rebate
• AC Unit Recycle Rebate
• Increased, Direct Marketing
• Community Event7
Technologies and Methods
Preliminary Results to Date
Year ParticipantsThermostats Installed
Window AC Control Plugs Installed
Estimated kWh Savings
Estimated kW Savings
Anticipated DR Savings (kW)
Total Estimated kW
2012 29 35 0 3,640 8.1 44 52.1
2013 45 57 45 18,744 28.8 75 113.8
Total 74 92 45 22,384 36.9 119 155.9
8
150kW load reduction needed in 2014.
This does not include savings from measures installed as a result of home
energy audits completed in the area
180 customers in 2012
83 customers so far in 2013
Evaluation of pilot program will determine amount of resulting savings that are
attributable to the pilot
Thank You!