Swachh Bharat Missionswachhbharaturban.gov.in/writereaddata/Presentation_CM_Meeting_Ma… · •...
Transcript of Swachh Bharat Missionswachhbharaturban.gov.in/writereaddata/Presentation_CM_Meeting_Ma… · •...
• Household toilets for 1.04 crore urban households
• Construct 2.56 lakh public toilets
• Construct 2.52 lakh community toilet seats
• Scientific disposal of Solid Waste in all Urban bodies
• Total cost: Rs.62,009 crore
Household Toilets
> Beneficiaries: Any household that,
a) Does not have a toilet OR
b) Has an insanitary toilet- • Discharging directly to drains or other water-body • Pit Larine can be updated by adding twin pit
system
> Centre Contribution - 4,000/- per Toilet
> State Contribution – at least 1,333/- per Toilet
> No Restriction on Land and Location
4
Sanitation Technologies besides Conventional Septic Tank (IS-2470)
Twin Pit Latrines DRDO- Bio-digester
Enhanced Slope (26-28o) P-Trap (12-20 mm water seal) Conventional- 50 mm
Low water Use Innovations
Reed Bed
Pre Fabricated Structures
Reference Case - Individual Toilet Construction
5
• Centralised Construction Model
• Govt to Build
• Beneficiary to contribute-
Rs 2000 in Municipal Corporation,
Rs 1500 in Municipality
Rs 1000 in Town Panchayat
• Total construction Cost/ unit- Rs. 18000-20,000.
• Govt. of India contribution:- Rs.4,000
• Balance amount Rs.12,000-15000 will be borne by
the State
Chhattisgarh
6
• Partially Centralised Construction Model
• Govt to Build only the Substructure
(Septic Tank etc.)
• Beneficiary has to construct the
superstructure on their own.
Bhopal
Reference Case - Individual Toilet Construction
7
• A scheme by an NGO in which IHHL constructed on cost-sharing basis.
• 30% of the cost to be borne by the household and the rest by NGO from various
sources including Government contribution
Pune
Reference Case - Individual Toilet Construction
8
• A public outreach and education campaign to
promote the concept of sanitary toilets was
conducted.
• A financial model of toilet construction
promoted on a cost-sharing basis.
• As per this 20 % of the toilet cost would be
paid by the beneficiaries and 80 % by Railtel
Corp as part of its CSR activities.
Gurgaon (CSR)
Reference Case - Individual Toilet Construction
• “Anusandhan Vihar”,- modern, sophisticated residential complex of 56 Type V & 56 Type IV accommodations in a G+7 configuration in DRDO Estate, Timarpur, Delhi.
• Wastewater treatment is based on DRDO Bio-digester technology
Delhi
Reference Case - Individual Toilet Construction (Biodigester)
10
Community & Public Toilets – Key Facts
Image Source: trade india
Construction Cost per Toilet Seat ~ Rs 65,000
Existing, Combines & Joint toilets are also eligible
Funds - 53.33% contribution from GoI/ State • 40% VGF/ Grant by Centre
• Minimum 25% (~13.33%) of Centre’s contribution by State
• Assistance for Preparation of DPR- by GoI - Rest 650 per
seat
Opportunity to leverage PPP, User Charges, etc.
11 Biogas generation at Sulabh Toilet Complex, Shirdi
Air-Conditioned PT Complex, Lucknow
Innovative Sanitation Technologies for Public and Community Toilets
NDMC Model – PPP, no cost to Govt; Cross Subsidisation
CTs Constructed and being maintained on PPP basis by private agencies in Jhuggi-Jhonpri (JJ) Clusters.
Toilets also provided in up-scale colonies for use of Domestic helps/ Maid/ Taxi Drivers/ Hawkers/ Beggars/ Auto Rickshaws.
Sometimes, it is financially difficult for agencies to run these toilets successfully and hygienically on PPP basis, where these have no potential for advertisement.
Hence Cross-subsidised.
Reference Case – Public & Community Toilet Construction and O&M
Tiruchirappalli Model- SHG • Very high incidence of Open Defecation- frequent incidents of
Water borne diseases.
• NGO appealed to health as a motivator.
• Women's Self Help Groups (SHG) were formed in slums.
• NGO constructed toilets with the help of 42 Women’s SHGs
• For Maintenance –Women SHGs were involved after training.
• Management of 170 community toilets successfully taken over
by the Women’s SHGs with support from MC.
• Demonstrates women not only learned but are implementing
new skills acquired through participation and involvement.
• The incidence of diarrhoea among children fell from 73% to
10% and among adults from 10% to 2%.
Reference Case – Public & Community Toilet Construction and O&M
Solid Waste Management (SWM)
Source: driverlayer.com
Estimated Outlay- Rs. 36,828 Crore
Funds – • 20% VGF/ Grant by Centre
• Minimum contribution by State 75: 25
(~6.66%)
• GoI Assistance- upto Rs.240/ person
100% cost for preparing & approving the
DPR will be funded by GoI
Upto Rs.12/ person (model DPRs are available on MoUD site)
Recommended Waste Treatment Options by City classification
Population Waste Qty.
(TPD) Treatment Option
Estimated Cost (Rs. Crores)
excluding land cost
15,000 to
50,000 3-10
• Biomethanation
• Conventional Composting
• Vermi Composting
10-20 Lakhs/1TPD of
segregated wet waste
50,000 to
1,00,000 10-20
• Biomethanation
• Conventional Composting
• Vermi Composting
10 Lakhs/1TPD of segregated
wet waste
1,00,000 to
10,00,000 20-350
• Integrated Waste Processing
• Biomethanation
• Composting
• RDF
400 Lakhs/100 TPD
10,00,000 to
200,00,000 350-8000
• Integrated Waste Processing
• Biomethanation
• Composting
• RDF
• Waste to Energy
Case based
16
Incineration • Waste is delivered by waste collection vehicles to the waste
pit, then carried on a stoker (combustion system) through the combustion oven and transformed into ash.
• Ash is discharged while energy contained in exhaust gases from the combustion process is recovered as steam in the boiler and used to drive power generator turbines.
• Resulting electricity is also available for use outside the facility
Waste to Energy – Relevant Technologies
Gasification • Converts carbonaceous wastes into Carbon Monoxide,
Hydrogen and Carbon • Dioxide by reacting the material at high temperatures
(>700 °C), without combustion, with a controlled amount of oxygen.
• Resulting gas mixture is called syngas or producer gas and is itself a fuel.
17
Reference Cases - Municipal Solid Waste Incineration Plant
16 MW – OKHLA Technology - China (Hangzhou New Century Company Ltd)
12 MW – GHAZIPUR Technology- Germany (Martin GmbH) Plant cost Rs. 18 Crore/ MW
11.5 MW – Jabalpur (under Construction) Technology- Japan (Hitachi Zosen) Cost per MW- Rs 16 Cr
18
Advantage of Gasification • Syngas is potentially more efficient than direct
combustion of the original fuel because it can be combusted at higher temperatures or even in fuel cells.
• Syngas may be burned directly in gas engines, used to produce methanol and hydrogen, or converted into synthetic fuel.
• Plants under Construction at Chennai, Pune and Kohlapur
• Conversion from 70 tonnes of waste to 1 MW of power
• Plant Cost for 1.0 MW- Rs.16 to 18 Crore
Reference Case - Municipal Solid Waste Gasification Plant
19
• 100 MT of mix waste produce 16 MT of compost
• Suited for above 50 MT/d mixed or segregated waste
• Land required for 100 MT/d plant is 1.5 Ha
• Cost of Integrated Compost & RDF 100 MT/d plant varying from
Rs. 6 to 8 Crore
• Cost of civil structure - 55% | Cost of machineries - 45%
• Tipping fee model most preferred with Rs. 600/MT
• Over 280 compost plants setup in country
• 2500 MT/d compost plant in Hyderabad is largest in the Country
Models A. Processing & Disposal
Tipping Fee Model (Indore, Hyderabad and most of Cities)
Royalty Model (Jaipur)
B. Integrated Waste Management Model (Allahabad, Kanpur)
Integrated Compost and RDF Technology
Current Interventions by MoUD
Waste to Compost
• Ministry is working with M/o Chemicals & Fertilizers on Compost Marketing
Obligation to extend Subsidy on sale of Compost along with Chemical Fertilizers
(Rs 1500/- per MT)
Waste to Energy
• M/o Power is amending Electricity Act-2003, wherein a provision is included to
mandatorily purchase all power generated from municipal waste by State
DISCOMS.
• Ministry is pursuing with CERC to determine the Generic Tariff for Solid Waste-
to-Energy
Waste to Resources
• BIS is developing standards for use of processed C&D waste as aggregate in
construction
21
Soft Components
IEC & PA Campaigns
Rs 1463 Cr to be provided by GoI to States over mission period for Information, Education and Communication & Public Awareness Campaigns
Rs 731.5 Cr may be expended at state level while Rs 731.5 Cr is to be further released to ULBs for their own IEC & PA activities. Additional Rs 292.6 Cr will be available with the Centre for national level campaigns.
Capacity Building and Administrative Expenses
Rs 366 Cr will be released to States over mission period Rs 188 Cr may retained at state level for capacity building Rs 188 Cr is to be released to ULBs for their own Capacity Building and office
expenses May be used for training and exposure visits. Rs 244 Cr will be available with the Centre for national level workshops and training
22
ICT and IEC Initiatives undertaken for Swachh Bharat
Hello Tune subscription on Airtel Animations/ Videos on YouTube
List of Empanelled Agencies- http://swachhbharaturban.gov.in/writereaddata/List_of_SWM_Empanelled_Agencies.pdf
Model RFPs-http://swachhbharaturban.gov.in/Model_RFPs.aspx?id=12e756d6932678afcc13d16e10bcfbc0
Swachh Bharat Mission: Funds Released & Progress so far…
Current Status # State/UT Total (Rs. In crore)
1 Andhra Pradesh 40.00
2 Arunachal Pradesh 9.36
3 Assam 0.23
4 Bihar 37.72
5 Chhattisgarh 30.79
6 Delhi 7.53
7 Goa 3.17
8 Gujarat 57.30
9 Haryana 17.92
10 Himachal Pradesh 6.02
11 Jammu & Kashmir 14.75
12 Jharkhand 15.27
13 Karnataka 80.01
14 Kerala 19.18
15 Madhya Pradesh 88.64
16 Maharashtra 135.00
17 Manipur 11.21
18 Meghalaya 4.05
19 Mizoram 9.79
20 Nagaland 10.52
21 Odisha 1.43
22 Puducherry 1.95
23 Punjab 41.40
24 Rajasthan 60.73
25 Sikkim 3.09
26 Tamil Nadu 118.46
27 Telangana 28.95
28 Uttar Pradesh 86.07
29 Uttarakhand 5.94
30 West Bengal 64.01
Total 1010.49
Target upto 31st March
2016
Constructed
upto March 2015
Constructed in
April 2015
25 lakh 2.7 lakhs 1.18 lakhs
Target up to March 2016 Constructed in upto April 2015
1 lakh 1,222
Target up to March 2016 Achievement upto April
2015
Achievement of 100% collection
and transportation- 1000 cities 329
Achievement of 100% processing &
disposal- 100 cities
Model RFP for selecting
partner has been shared with
States
Individual Household Toilets
Public & Community Toilets
Solid Waste Management
Thanks! Praveen Prakash
Joint Secretary & Mission Director (SBM)
Ministry of Urban Development (MoUD)
(+91) 90131 33636