Svp field training report final

51
1 | Page FIELD TRAINING REPORT Submitted to Department of Civil Engineering By PARAB SHUBHAM VILAS 1202016 Under The Guidance Of PROF. Y.M.PATIL Under The Supervision Of ER. PATIL KAILAS R. Rajarambapu Institute of Technology, Rajaramnagar (An Autonomous Institute) Affiliated to Shivaji University Kolhapur 2014-15

Transcript of Svp field training report final

Page 1: Svp field training report final

1 | P a g e

FIELD TRAINING REPORT

Submitted to

Department of Civil Engineering

By

PARAB SHUBHAM VILAS

1202016

Under The Guidance Of

PROF. Y.M.PATIL

Under The Supervision Of

ER. PATIL KAILAS R.

Rajarambapu Institute of Technology, Rajaramnagar

(An Autonomous Institute)

Affiliated to Shivaji University Kolhapur

2014-15

Page 2: Svp field training report final

2 | P a g e

Preliminary Information:

a. General information of the candidate

1. Name- Parab shubham vilas

2. Enrollment No. : 1202016

3. Contact Address-At/Post- Islampur

Tal.Walwa Dist.Sangli

4. Email ID: [email protected]

5. Mobile No-9420728101

b. Name and address of the Company.

Omkar construction Pvt.Ltd bhugaon, Pune.

3 Amey Apartments, Pooja Park Society,

Prabhat Road, Kothrud, Pune-4110038, MH (India)

c. Period of Field Training:

01 Dec to 21Dec, 2014

TotalDays : 21

d. Contact officer in the above organization:

Name: Mr.S.A.Wable & Mr.K.R.Patil

Designation: D.C.E.( RIT Diploma Alumni-Batch 1989)

Phone number: 020-32422346

E-mail address: [email protected]

Page 3: Svp field training report final

3 | P a g e

CERTIFICATE

This is to certify that the Field Training undergone in the Omkar Constructions Pvt.

Ltd..iscarried out by Mr. PARAB SHUBHAM VILAS under my guidance. The report is

submitted towards the partial fulfillment of Third year, full time Under Graduate Programme in

Civil Engineering.

Date:

Name & Sign of Guide Name & Sign of Supervisor

Page 4: Svp field training report final

4 | P a g e

ACKNOWLEDGEMENT

I wish to express sincere thanks and gratitude to the DR.H.S.JADHAV(H.O.D.

Department of civil engineering) and PROF. Y.M.PATIL (Department of Civil Engineering,

Rajarambapu Institute of Technology, Rajaramnagar) for the whole hearted encouragement,

advice and timely guidance in completing this field training work.

I have to record my deep sense of indebtedness to Mr.K. R. Patil, (Omkar

Constructions pvt.ltd.)for providing us the facilities and instruments and for their stimulating

guidance and continuous encouragement.

I also like to thank my family for supporting me through this field training activity. It is

my pleasure to thank Dr. S.S.Kulkarni (Director R.I.T) and Prof.D.B.Kulkarni (Field training

in charge) for giving me this opportunity.

It is necessary here to acknowledge the valuable support and suggestions provided by

Mr. Rohit Jadhav, (Site Engineer,Omkar const. pvt lim.)in carrying out training work.

PARAB SHUBHAM VILAS

(Roll No.: -1202016)

Page 5: Svp field training report final

5 | P a g e

INDEX

Sr.No.

Page No.

1.

Project details

6

2.

Site layout and drawings

8

3.

Works on site

11

4.

Daily schedule

23

5.

Material rate and labour cost

27

6.

Field tests

28

7.

Equipments and safety

32

8.

Management work

42

9.

Interaction with project head

46

10.

conclusion

48

Page 6: Svp field training report final

6 | P a g e

Chapter 1

Project details

Name of the project: Crystal tower

Client: Paranjape schemes pvt.ltd.

Contractor: Omkar constructions pvt.Ltd.

Consultant:

1.Architectural consultant- Mr. A B Waidya

2.R.C.C. consultant- Mr. S.W. Mone

3.Legal consultant- Adv. H.P.Koparde

Estimated Cost: 18.5crore

Duration of Project:2.5 years

Project commencement Year: 2013

1.1. Project Brief

General Description and Scope of the Project

GENERAL DESCRIPTION:

This project is situated in Baner, Pune which is very near to the commercial zone,

schools, colleges, hospitals, bus stand etc. The site is situated in nature‟s beauty i.e it

has fresh air and is pollution free.

Page 7: Svp field training report final

7 | P a g e

SCOPE OF THE PROJECT:

It is a residential project aimed at affordable housing with all faciltites like

wide internal roads, garden, jogging track, internal security with CCTV cameras and

security guard, large parking space, ampitheatre, purified drinking water supply with

solar water heating system, invertor backup system and Ganesh temple.

This project targets to provide residence for about 1,000 people.

Training Site Details:

Address:

Total Plot Area = 25690.38sq.m.

Total Carpet Area = 2122.13sq.m.

No. of buildings =3

Total flats=144

Training In charge: Mr. Rohit Jadhav

Location: Banerphata, Pune

Organization structure is as given below:-

1) Chairman:- Mr.A.A.Wable & Mr.K.R.Patil

2) Vice-Chairman:- Mr.S.A.Wable

3) M.D.:- Mr. Shrinivas Wable

4) Manager:- Mr.A.S.Gaikwad

5) Site Engineer:-Mr.Rohitjadhav

6) Supervisor:-Mr.SudhakarAade

7)LaborIn charge :-Mr.G. L. Mahamun

Page 8: Svp field training report final

8 | P a g e

Site Layout

Page 9: Svp field training report final

9 | P a g e

Location Map

Proposed Building

Page 10: Svp field training report final

10 | P a g e

Floor Plan

Typical 3BHK Flat

Page 11: Svp field training report final

11 | P a g e

Chapter 2

Works On Site

Footing-

Footing is important part of foundation. To provide a level or uniform platform for

structure footing is provided. Footing spread out the weight of the structure so the soil can carry

the load spread out within the footing itself at about 45 degree angle and then spread out in the

soil. They are typically made of concrete with rebar reinforcement that has been poured into an

excavated trench. The choice of suitable type of footing depends on the depth at which the bearing strata

lies, the soil condition and the type of superstructure Raft footing is used on site by investigating nature of soil and bearing capacity of soil. As

the loading on footing is very large so that the thickness of the raft 0.6m is taken with

reinforcement fitting.After excavating surface is compacted and PCC is provided with

waterproofing. Over the PCC, raft is provided. Column footing is used to transfer the load of the

column to the raft.

Information of site-

Size of the raft footing- 21 X 35m

no of column footing-

Thickness of footing-0.6m

Concrete used- M25 (cement-50kg, metal-150kg, crushed sand-96kg, admixture-

500ml, water- 21lit

Procedure for the raft footing-

1. The bed is compacted and sprinkled over with water.

2. Then the whole area is dug out to the specified depth and 30 cm more wide than the area

to be covered.

3. a layer PCC concrete is laid to a suitable thickness to act as a bottom cover.

4. After this, the reinforcement is laid. The reinforcement consists of closely spaced bars

placed at right angles to one another.

5. Then the M20 cement concrete is laid and compacted to the required thickness.

6. The concrete slab so laid is then properly cured

7. When loads are excessive, thick concrete beams running under the columns can also be

constructed.

Suitability-

This type of foundation is useful for public buildings, office buildings, school buildings,

residential quarters etc. where the ground conditions are very poor and bearing powerof the

soil is so low that individual spread footing cannot be provided.

Page 12: Svp field training report final

12 | P a g e

Page 13: Svp field training report final

13 | P a g e

Column

A reinforced concrete column is a structural members designed to carry compressive

loads, composed of concrete with an embedded steel frame to provide reinforcement. For design

purposes, the columns are separated into two categories: short columns and slender columns.

A column may be classified based on different criteria such as:

1. Based on shape

Rectangle

Square

Circular

Polygon

2. Based on slenderness ratio

Short column, ? ? 12

Long column, ? > 12

3. Based on type of loading

Axially loaded column

A column subjected to axial load and uniaxial bending

A column subjected to axial load and biaxial bending

Constructing RCC (Reinforced Cement Concrete) Column involves following four stages of

works -

1. Column layout work

2. Column reinforcement work

3. Column formwork, and

4. Pouring concrete into column.

Column layout work

In this stage of works the location of columns are determined practically in field. It is

done by laying rope according to grids shown in the drawing and then mark the location of

columns related to rope.

Page 14: Svp field training report final

14 | P a g e

Page 15: Svp field training report final

15 | P a g e

Retaining wall

Retaining wall is structure used to maintain ground surface at different elevations on

either side of it. Retaining wall provides lateral support to vertical slopes of soil. They retain soil

which will otherwise collapse in to more natural shapes. The retained soil is referred as backfill.

Retaining walls are usually built to hold back soil mass. However, retaining walls can

also be constructed for aesthetic landscaping purposes. Retaining walls are structures that are

constructed to retain soil or any such materials which are unable to stand vertically by

themselves. They are also provided to maintain the grounds at two different levels.

On site of crystal tower retaining wall is used to retain soil between two different levels

ground level basement level. This retaining wall is cast along boundary of site.M 25 grade

concrete is used with reinforcement of 8 mm tor steel bars. For water proofing purpose

“shahabadi” tiles are laid on one side of retaining wall.

Page 16: Svp field training report final

16 | P a g e

Slab and beam casting:-

Reinforcement

It shall be as per BBS(behavior based safety) prepared according to approved drawing. The R/F

shifting and binding shall be started as soon as shuttering is completed. R/F binding shall

continue as formwork and shuttering work is progresses.

Concreting

Construction joint

The construction joint shall be pre decided and fixed prior to start of the concreting. It is

planned to have two construction joints for main building as decided. In case of major break

down of the Batching plant, the additional Construction joint may be left. The location of the

construction joint shall be at the one-third span. Construction joint shall be straight and have

profile of „L‟ shape so that successive layer of concrete shall be perfectly bonded with previous

laid layer.

Preparation of construction joint shall include roughening, removing all laitance adhering to the

joint and application of thick slurry before start of the new concrete.

Production and placement of concrete.

Stock of material shall be sufficient to start the concrete. It shall be ensured by

stores/purchase dept that concreting is not stopped on account of materials.

All plant and machinery are checked and made in working conditions.

Concrete of grade M-25 shall be produced from our batching plant and directly pumped

to the location of concrete placement through the pipeline. The pouring sequence shall be from

grid A towards construction joint. Since the grade of concrete for column is M-40 and

surrounding concrete is M-25, sufficient offset around column shall be casted with M-40.The

offset dimensions shall be provided by PMC.

Proper walkways/platforms shall be arranged so that the supports of the pipeline and

manpower are not directly stand on reinforcement.

Page 17: Svp field training report final

17 | P a g e

Sufficient carpenters along with supervisor shall inspect the behavior of supports below the

slab during the casting. Extra Props shall be stocked below slab to provide additional supports in

case of any failure of supports.

Curing

The curing shall be started immediately after thumb set of the concrete laid. Hessian

clothe /Plastic shall be covered over the set concrete to reduce moisture evaporation from the

concrete during hardening and thus to minimize shrinkage crazy cracks. These cracks are

inheriting property of the concrete specially appears during casting of flat surfaces.

Final curing shall be done by ponding and stacking water for minimum period of 7 days

.

Page 18: Svp field training report final

18 | P a g e

Page 19: Svp field training report final

19 | P a g e

P.C.C.:- PCC-plain cement concrete of grades M10 or M15 is used as leveling course in the

foundation trenches to act as level platform for RCC footing for columns / masonry footing for

load bearing walls.it also serves as separating layer between natural soil and footing so that any

harmful chemical present in soil will not act on the footing .PCC has no structural importance.in

case of trances or pits excavated than the required depth ,the extra depth should be filled with

PCC of required grade at the expense of contractor to the required level to place the footing.

For P.C.C., At the site , they were used M10 Grade concrete and thickness of the

P.C.C. was 150mm.

INFORMATION OF SITE :-

Size of the PCC :- 21 x 35 sq.m.

Thickness of PCC:- 0.15 m

Concrete grade :- M10

Procedure for PCC.:-

i) Excavation levels and dimensions to be checked as per drawings.

ii) Remove all the loose earth from the pits.

iii) Do water sprinkling and ramming the cleaned surface of pit by mechanical

rammer.

iv) Do the shuttering by planks and runners wherever if necessary.

v) Mix the concrete with required proportion and water cement ratio by mechanical

mixer machine and place the same in to pits.

vi) Poured surface to be rammed and finished smoothly.

Page 20: Svp field training report final

20 | P a g e

Waterproofing:-

Water-proof or water-resistant describes objects relatively unaffected by water or

resisting the ingress of water under specified conditions. Such items may be used in wet

environments or under water to specified depths. Waterproofing describes making a structure

waterproof or water-resistant

"Water resistant" and "waterproof" often refer to penetration of water in its liquid state and

possibly under pressure, whereas damp proof refers to resistance to humidity or

dampness. Permeation of water through a material or structure.

Waterproofing is done by using rough Shahabad tile. Shown in fig.

Page 21: Svp field training report final

21 | P a g e

Expansion joints:-

An expansion joint or movement joint is an assembly designed to safely absorb the heat-

induced expansion and contraction of construction materials, to absorb vibration, to hold parts

together, or to allow movement due to ground settlement or earthquakes. They are commonly

found between sections of buildings, bridges, sidewalks, railway tracks, piping systems, ships,

and other structures.

Building faces, concrete slabs, and pipelines expand and contract due to warming and cooling

from seasonal variation, or due to other heat sources. Before expansion joint gaps were built into

these structures, they would crack under the stress induced.

Page 22: Svp field training report final

22 | P a g e

Shuttering

Timber is the most common Formwork is an ancillary construction, used as a mould for a

structure. Into this mould, fresh concrete is placed only to harden subsequently. The construction

of formwork takes time and involves expenditure upto 20 to 25% of the cost of the structure or

even more. Design of these temporary structures are made to economic expenditure. The

operation of removing the formwork is known as stripping. Stripped formwork can be reused.

Reusable forms are known as panel forms and non-usable are called stationary forms.

material used for formwork. The disadvantage with timber formwork is that it will warp,

swell and shrink. Application of water impermeable cost to the surface of wood mitigates these

defects.

At our site following types of shuttering is used

Plywood shuttering

Steel shuttering

Mivan shuttering

Mivan shuttering:

Mivan is aluminum formwork system.mivan technology is suitable for constructing large

number of houses in short span of time using room size forms to construct walls and slabs in one

continuous pour on concrete .mivan technology facilitate fast construction, strict quality control,

exact dimensions ,we can form any size as per requirements.mivan panels are costly than

plywood panels ,labour charge is also comparatively more.

Page 23: Svp field training report final

23 | P a g e

Chapter 3

Daily schedule

Field Training Details:-

Sr No

Day & date

Description of work at training site

Materials used and Quality

control of work

1 Monday

1/12/2014

Casting of P.C.C. of G building M10 Grade of concrete

Waterproofing work (Above the P.C.C.)

G building

a)Rough Shahbadi tiles

b)Cement c)Water

Formwork for foundation G building

2 Tuesday

2/12/2014

Casting of P.C.C.G building

M10 Grade of concrete

Waterproofing work (Above the P.C.C.)

G building

a)Rough Shahbadi tiles

b)Cement c)Water

Formwork for foundation G building

3

Wednesday

3/12/2014

Casting of Raft , Foundation G building

M25 Grade of concrete

by RMC

Checking of reinforcement of slab

H building

4 Thursday

4/12/2014

Casting of P.C.C. G building M10 Grade of concrete

Page 24: Svp field training report final

24 | P a g e

Sr No

Day & date

Description of work at training site Materials used at site and

Quality control of work

Waterproofing work (Above the P.C.C.)

G building

a)Rough Shahbadi tiles

b)Cement c)Water

Formwork for foundation G building

5 Friday

5/12/2014

Casting of starters of columns G building

M30 Grade concrete

Casting Retaining wall G building M25 Grade concrete

Checking slab reinforcement H building

6 Saturday

6/12/2014

Casting of slab

M25 Grade concrete

Casting Retaining wall G building

M25 Grade concrete

Formwork for foundation G building

7 Sunday

7/12/2014

8 Monday

8/12/2014

De-shuttering of slab on lateral side

H building

Casting of Raft , foundation G building

M25 Grade of concrete by RMC

Formwork for Retaining wall G building

9 Tuesday

9/12/2014

Casting of P.C. G building M10 Grade of concrete

Waterproofing work (Above the P.C.C.)

G building

a)Rough m,Shahbadi tiles

b)Cement c)Water

Page 25: Svp field training report final

25 | P a g e

Sr No

Day & date

Description of work at training site

Materials used at site and

Quality control of work

Formwork for foundation G building

10 Wednesday 10/12/2014 Casting Retaining wall G building M25 Grade of concrete

Casting of P.C.C. G building

M10 Grade of concrete

Waterproofing work (Above the P.C.C.) G building a)Rough Shahbadi tiles

b)Cement c)Water

11 Thursday

11/12/2014

Formwork for slab of H building

Casting of starters of columns G building M30 Grade concrete

Casting Retaining wall G building

M25 Grade concrete

12 Friday

12/12/2014

Casting of Column up to plinth level G

building

M30 Grade concrete

Formwork for slab of H building

Casting Retaining wall G building

M25 Grade concrete

13 Saturday

13/12/2014

Casting of Column up to plinth level G

building

M30 Grade concrete

Casting of P.C.C. G building M10 Grade of concrete

Waterproofing work (Above the P.C.C.)

G building

a)Rough Shahbadi tiles

b)Cement c)Water

14 Sunday

14/12/2014

15 Monday

15/12/2014

Casting of Raft , Foundation G building M25 Grade of concrete by RMC

Fitting of steel reinforcement of slab

Casting Retaining wall G building M25 Grade concrete

16 Tuesday

16/12/2014

Casting of P.C.C. G building M10 Grade of concrete

Page 26: Svp field training report final

26 | P a g e

Waterproofing work (Above the P.C.C.)

G building

a)Rough Shahbadi tiles

b)Cement c)Water

Casting of Column up to plinth level G

building

M30 Grade concrete

17 Wednesday

17/12/2014

Casting of Column up to plinth level G

building

M30 Grade concrete

Casting of P.C.C. G building M10 Grade of concrete

Waterproofing work (Above the P.C.C.) G building

a)Rough Shahbadi tiles

b)Cement c)Water

Fitting of steel reinforcement of slab

18 Thursday

18/12/2014

Casting of Raft , Foundation G building

M25 Grade of concrete by RMC

Fitting of steel reinforcement of slab

\Casting Retaining wall G building

M25 Grade concrete

19 Friday

19/12/2014

Casting of starters of columns G building

M30 Grade concrete

Casting Retaining wall G building M25 Grade concrete

Fitting of steel reinforcement of slab

20 Saturday

20/12/2014

Casting of Raft , Foundation

G building

M25 Grade of concrete by RMC

Casting Retaining wall G building

M25 Grade concrete

Fitting of steel reinforcement of slab

Page 27: Svp field training report final

27 | P a g e

Raw Material Rate

Sr.No Description of material Unit Rate per unit

1

Cement

Per Bag

250 /-

2

Crushed sand

Brass

1500 /-

3

Natural sand

Brass

4500 /-

4

Aggregate

Brass

2000 /-

5

Steel

Ton

56000 /-

Labour Rate for items

Sr.No Description Rate per unit

1 Shuttering Contractor Rs-38 (Built up)

2 Bar Bender Rs-15 (per Sq.Ft)

3 Labour Contractor (Brickwork , Plastering) RS-80 ( per Sq.Ft)

4 Tile fitting RS-25 ( per Sq.Ft)

5 Electrition RS-80 ( per Sq.Ft)

6 Plumbing RS-2000 ( per unit)

7 Painter Work RS-15 ( per Sq.Ft)

8 P-O-P Work RS-60 ( per Sq.Ft)

9 Fabricator RS-10 ( per Sq.Ft)

Page 28: Svp field training report final

28 | P a g e

Field Tests

Tests on concrete:

1) Slump cone test:-

The concrete slump test is an empirical test that measures the workability of

fresh concrete. It is a term which describes the state of fresh concrete. It refers to the ease with

which the concrete flows. It is used to indicate the degree of wetness. The test is popular due to

the simplicity of apparatus used and simple procedure.

Principle:-The slump test result is a slump of the behavior of a compacted inverted cone of

concrete under the action of gravity. It measures the consistency or the wetness of concrete.

Procedure:-The test is carried out using a mould known as a slump cone or Abrams cone. The

cone is placed on a hard non-absorbent surface. This cone is filled with fresh concrete in three

stages, each time it is tamped using a rod of standard dimensions. At the end of the third stage,

concrete is struck off flush to the top of the mould. The mould is carefully lifted vertically

upwards, so as not to disturb the concrete cone. Concrete subsides. This subsidence is termed as

slump, and is measured in to the nearest 5 mm.

Observations:-slump cone : 80 mm.

Conclusion:- slump cone is below 90mm therefore concrete is consistent.

Page 29: Svp field training report final

29 | P a g e

2) Cube testing:

Out of many test applied to the concrete, this is the most important which gives an idea about all

the characteristics of concrete. By this single test one judge that whether Concreting has been

done properly or not. For cube test specimens cubes of 15 cm x 15cm x 15 cm are commonly

used.

This concrete is poured in the mould and tempered properly so as not to have any voids. After 24

hours these moulds are removed and test specimens are put in water for curing. The top surface

of this specimen should be made even and smooth. This is done by putting cement paste and

spreading smoothly on whole area of specimen.

These specimens are tested by compression testing machine after 7 days curing or 28 days

curing. Load should be applied gradually at the rate of 140 kg/cm2 per minute till the Specimens

fails. Load at the failure divided by area of specimen gives the compressive strength of concrete.

Tests on materials used:-

A) Sand and aggregate:-

1) Sieve analysis:-

A sieve analysis is a practice or procedure used to assess the particle size

distribution (also called gradation) of a granular material. The size distribution is often of critical

importance to the way the material performs in use.

Procedure:-

A gradation test is performed on a sample of aggregate in a laboratory. A typical sieve

analysis involves a nested column of sieves with wire mesh.

A representative weighed sample is poured into the top sieve which has the largest

screen openings. Each lower sieve in the column has smaller openings than the one

above. At the base is a round pan, called the receiver.

The column is typically placed in a mechanical shaker. The shaker shakes the column,

usually for some fixed amount of time. After the shaking is complete the material on

each sieve is weighed. The weight of the sample of each sieve is then divided by the

total weight to give a percentage retained on each sieve.

A suitable sieve size for the aggregate should be selected and placed in order of

decreasing size, from top to bottom, in a mechanical sieve shaker. A pan should be

Page 30: Svp field training report final

30 | P a g e

placed underneath the nest of sieves to collect the aggregate that passes through the

smallest. The entire nest is then agitated, and the material whose diameter is smaller than

the mesh opening pass through the sieves. After the aggregate reaches the pan, the

amount of material retained in each sieve is then weighed.

3) Moisture content.

B) Tests on steel:-

1) Tensile test:-

The specimen is subjected to tensile load and extension is noted against the

load within the elastic limit. Loads at, Yield point, Breaking point and Ultimate point are noted.

With these, stress-strain graph is plotted and following results are calculated.

Modulus of Elasticity = Stress (within the elastic limit)/Strain.

Yield stress = (Load at yield point /original c/s area)

Ultimate stress = (Ultimate Load/ original c/s area.)

2) Bend test:-

The ASTM E-290 standard covers bend testing of bars primary for evaluation of

their ductility. Specifications such as size and type, radius of bending, angle of bend, number and

size of visible cracks if any, are reported. The standard demanded that after testing the convex

surface of the bend specimen shall be examined with the unaided eye to identify cracks or other

open defects.

3) Rebend test:-

Reinforcing steel specifications often require a rebend test. This is a

measure of the strain age embrittlement of the bars. After bending through a specified angle

around a specified mandrel diameter, samples are aged in an air oven, and then rebent through a

smaller specified angle. Samples must show no signs of cracking in order to pass this test.

C) Tests on water:-

1) pHof water.

2) Hardness of water.

Page 31: Svp field training report final

31 | P a g e

Page 32: Svp field training report final

32 | P a g e

Chapter 4

Equipments & safety Machines

It is common fact we find wide variety of construction on every construction site. Which

makes the job easy, safe and quicker. Depending on application construction machines are

classified into different types which are

1. Earth moving instrument

2. Construction vehicles

3. Material handling instrument

4. Construction instrument

Following machines are mainly used on site for construction purpose:

Weigh batcher:

Weigh Batcher is used in various industrial applications and is accessed at affordable

prices in the market. These are appreciated for their efficient working ability and long working

life. Weigh batcher is machine used in construction industry to weigh exact quantity of sand

,cement ,aggregates to form concrete.Concrete weigh batcher (double hopper) is an effective

device extensively used for weighing production of controlled concrete.it is suitable to produce

M20,M25,M30 concrete. If lesser quantity of concrete is required then instead of RMC weigh

batcher is used.

Weigh batcher is generally placed on flat surface otherwise we have to level it with level

tube.by adjusting the weights on scale we can measure exact quantity of material to be used

.Then this mixed is send to concrete mixer.

Suitable design for M 15, M 25 & M 30 are provided with:

Type: Scale Type

Size: 2.2 x 1.05 x 1.8 meters

Capacity: 500 Kg (250 Kg Each)

Mechanism: Lever Type

Operation:

Capacity of the hopper - 250 / 500 kg each

Page 33: Svp field training report final

33 | P a g e

Level the machine properly on platform

Clean the machine regularly to get the proper weights of sand & aggregate

Put the required weights in to the pan (100 kg, 50 kg & 20kg) As per weight required for

odd calibration, adjust the weight on the scale given. (10 mm = 1000 gm)

Unload the material directly in the mixer hopper, outlet given on rear side.

Water dispenser:

Water dispenser is machine used to add exact amount of water in to mix of

cement ,aggregates, sand etc.For specific concrete grade amount of warter is fixed so we

can digitaly adjust the water and flow of water in to concrete mixer.

Page 34: Svp field training report final

34 | P a g e

Cutter machine:

Cutter machine is used to cut the steel for reinforcement it is having rotating blade which

has to change after deterioration .it is portable machine so we an easily move it to any place .it

works on electric power. cutter machine is used also cut binding wires etc.

Page 35: Svp field training report final

35 | P a g e

Concrete mixer:

A concrete mixer (also commonly called a cement mixer) is a device that homogeneously

combines cement, aggregate such as sand or gravel, and water to form concrete. A typical

concrete mixer uses a revolving drum to mix the components. For smaller volume works

portable concrete mixers are often used so that the concrete can be made at the construction site,

giving the workers ample time to use the concrete before it hardens. An alternative to a machine

is mixing concrete by hand. This is usually done in a wheelbarrow; however, several companies

have recently begun to sell modified tarps for this purpose.

For smaller jobs, such as residential repairs, renovations, or hobbyist-scale projects, many

cubic yards of concrete are usually not required. Bagged cement is readily available in small-

batch sizes, and aggregate and water are easily obtained in small quantities for the small work

site. To service this small-batch concrete market, there are many types of small portable concrete

mixers available.

Page 36: Svp field training report final

36 | P a g e

Vibrator needle:

Since concrete contains particles of varying sizes, the most satisfactory compaction would

perhaps be obtained by using vibrators with different speeds of vibration. Polyfrequency vibrators used

for compacting concrete of stiff consistency are being developed. The vibrators for compacting concrete

are manufactured with frequencies of vibration from 2800 to 15000 rpm. The various types of vibrators

used are described below:

This is perhaps the most commonly used vibrator. It essentially consists of a steel tube

(with one end closed and rounded) having an eccentric vibrating element inside it. This steel tube

called poker is connected to an electric motor or a diesel engine through a flexible tube. They are

available in size varying from 40 to 100 mm diameter. The diameter of the poker is decided from

the consideration of the spacing between the reinforcing bars in the form-work.

The frequency of vibration varies up to 15000 rpm. However a range between 3000 to

6000 rpm is suggested as a desirable minimum with an acceleration of 4g to 10g.

The normal radius of action of an immersion vibrator is 0.50 to 1.0m. However, it would be

preferable to immerse the vibrator into concrete at intervals of not more than 600mm or 8 to 10

times the diameter of the poker.

The period of vibration required may be of the order of 30 seconds to 2 minute. The concrete

should be placed in layers not more than 600mm high.

Page 37: Svp field training report final

37 | P a g e

R.M.C. :

Ready-mix concrete is concrete that is manufactured in a factory or batching plant,

according to a set recipe, and then delivered to a work site, by truck mounted intransit machine.

This results in a precise mixture, allowing specialty to be developed and implemented on

construction sites.

Ready-mix concrete is sometimes preferred over on-site concrete mixing because of the

precision of the mixture and reduced work site confusion. However, using a pre-determined

concrete mixture reduces flexibility, both in the supply chain and in the actual components of the

concrete.

Ready-mix concrete is also referred as the customized concrete products for commercial

purpose. Ready-mix concrete, or RMC as it is popularly called, refers to concrete that is

specifically manufactured for delivery to the customer's construction site in a freshly mixed and

plastic or unhardened state. Concrete itself is a mixture of Portland cement, water and aggregates

comprising sand and gravel or crushed stone. In traditional work sites, each of these materials is

procured separately and mixed in specified proportions at site to make concrete. Read-mix

concrete is bought and sold by volume - usually expressed in cubic meters

Disadvantages of R.M.C.

The materials are batched at a central plant, and the mixing begins at that plant, so the

traveling time from the plant to the site is critical over longer distances. Some sites are

just too far away, though this is usually a commercial rather than a technical issue.

Generation of additional road traffic. Furthermore, access roads and site access have to be

able to carry the greater weight of the ready-mix truck plus load. (Green concrete is

approx. 2.5 tonne per m³.) This problem can be overcome by utilizing so-called 'minimix'

companies which use smaller 4m³ capacity mixers able to reach more-restricted sites.

Concrete's limited timespan between mixing and going-off means that ready-mix should

be placed within 210 minutes of batching at the plant Modern admixtures can modify that

timespan precisely, however, so the amount and type of admixture added to the mix is

very important.

Water pump

Grinder machine

Breaker

Lift and trolley

Wheel borrow

Drill machine

Page 38: Svp field training report final

38 | P a g e

Page 39: Svp field training report final

39 | P a g e

Equipments

Plumb bob:

Plastering tool:

Page 40: Svp field training report final

40 | P a g e

Scraper:

Circular sieve:

Page 41: Svp field training report final

41 | P a g e

Shikanja:

Span:

Page 42: Svp field training report final

42 | P a g e

SITE SAFETY

For achieving safety on the site no. of safety officers are appointed. A better safety

control measures are also adopted on site while construction.

Safety Equipments used on construction site:

a) Compulsory use of helmets on site.

b) Safety belts are used on site while working on height.

c) A horizontal barrigation is provided at building lift ducts, and on the other spot also

d) For safer working on site all construction equipments are regularly surveyed.

e) Safety is enforced by law on sate to each and every worker on site.

f) A trained operators are appointed at crane and other construction equipments.

g) Hand gloves are used as safety tool.

h) A safety sign boards are also provided on site with a much higher density.

i) Safety nets are used to held the materials that fall down during work.

j) Fire Extinguisher.

Page 43: Svp field training report final

43 | P a g e

Page 44: Svp field training report final

44 | P a g e

CHAPTER5

Management Work

Bar Chart:

Sr.No Activities Duration (weeks)

A. Excavation 2

B. P.C.C.+ Water 3

C. Raft + Column 8

D. Pardi 2

E. First Slab 5

F. Second Slab 5

G. Third Slab 4

Page 45: Svp field training report final

45 | P a g e

Details of Labour

Sr. No. Description Category Nos. Rates

1. Carpenter In charge 1 500

. Helper 9 250

Sutar 20 400

2. Fitter In charge 2 500

Helper 12 250

Foreman 3 450

3. Concreting Incharge 1 600

Helper 12 250

Foreman 6 500

4. Centering Incharge 1 700

Helper 10 300

Foreman 2 550

Page 46: Svp field training report final

46 | P a g e

Interview of Project Head:-

Interviewee: Mr. Kailas Ramchandra.Patil( Managing Director, Om constrution.)

Age-48 years

Education-diploma in 1989 from RIT

Home town- shirala, dist-sangli

Experience-25 years

Past project- 1st project-at rajarambapu factory

-at Pratibha construction

-Raj bank,

-ashti sugar nagar

-bhugaon project

Running project-Dmart at Mumbai and kalian

-Toyota show room at miraj

-Sadaphuli,baner

-Crystal towers, baner

What were the problems faced on the labourer’s front?

After starting the construction, the workers had carried out strikes in order to increase

their wages i.e when they were provided with insufficient wages. Due to this we

faced problems in calculating estimates and also the time duration of completion of

project was increased.

Were there any problems while acquiring the land for this project?

We did not face any problems from people from whom the land was bought but while

construction of compound walls began the neighbors used to threaten us in the name

of a court stay order and due to this we had to pay them some extra amount which

was an indirect loss for the company.

How is the experience of construction in this project?

The area for construction of this project is good and the location is also easily

accessible, also materials are available in abundance and due to this we did not face

any material shortage, transportation is also good in this area.

If we want to start our own company like yours what are your

suggestions for newcomers like us?

Honestly, I recommend a newcomer in this field to gain some hands on experience in

a company first and then after knowing how things work around here, that person can

start his own company. Starting a company without any job experience will most

probably lead to losses at first as the individual will have to adapt and learn the basics

of the game which will take some time.

Even Im an engineer and only technical knowledge is not enough for someone

to start his own company, an individual needs to learn many more things which are

only learnt by doing jobs as an employee in the industry.

Page 47: Svp field training report final

47 | P a g e

Page 48: Svp field training report final

48 | P a g e

CONCLUSION:

During Field training, I got lot of practical knowledge of various machines,

tools & various equipments and also taking various precautions during operating

them. I also gained the knowledge how to work efficiently with less effort and

proper care to avoid accident and develop worker relationship.

Regarding the quality of work I like to add that due to poor supervising

the concreting quality was little bad. Proportion of mixing of contents in aggregate

was not stable. In this high society building there is no bathroom in servant

room.

All these features of an organization has really added some good qualities in

me. Thus this vocational training was very helpful for my academic and future life.

Page 49: Svp field training report final

49 | P a g e

Appendix:-

SITE PHOTO GALLARY:-

Reinforcement: -

o Slab reinforcement: -

Page 50: Svp field training report final

50 | P a g e

Page 51: Svp field training report final

51 | P a g e