Study Report USOF Mobile

20
Page 1 of 20 EXTRACTS OF Report of the Committee on CDOT Report for USOF Scheme for provision of Mobile Communication Services in uncovered villages 5. Benchmarking issue: The committee has following suggestions for benchmarking issues: C-DoT has done all the cost estimation for bench marking purpose based upon GSM technology, however the TSPs can use any technology. (i) Power : a) Use of Renewable Energy Technology (RET) Solar will be mandatory at all locations. b) 2 days back-up for Cat-A and Cat-B and 24 hours for Cat - C. c) DG sets and SMPS have not been included for benchmarking purpose in all categories. d) The above requirements are for bench-marking purpose. Service Provider shall comply to TRAI uptime requirements by using additional power arrangements, if required. e) The committee noted that minimum power requirement for one carrier CDMA site with Omni antenna will be 400 watts (Approximately). (ii) Backhaul : C-DoT had not taken into account provision of using satellite backhaul in the absence of terrain based information. Initial estimation suggest that 25% of sites in Arunachal Pradesh/ Andaman & Nicobar Islands, 10% in Himachal Pradesh/ Jammu & Kashmir, 5 % in Maharashtra and 2% of sites in other states can be considered using VSATs. However C-DoT may further fine tune the estimation. C-DoT has proposed integrated microwave backhaul for category A1, A2 & B.. It is not mandatory for TSP to buy BTS equipment with integrated backhaul as separate links can be installed depending upon requirement. It is also important to note that despite passage of about 17 years from the advent of mobile services in the country, over 50,000 villages remained uncovered. Therefore, it is expected that in many cases more hops of microwave link may be required or satellite link (VSAT) may be needed or long OFC links may be needed to connect to the BSC of TSP. USOFA has to decide how bench marking is to be done in such cases i.e. whether

Transcript of Study Report USOF Mobile

Page 1: Study Report USOF Mobile

Page 1 of 20

EXTRACTS OF Report of the Committee on

CDOT Report for USOF Scheme for provision of Mobile Communication

Services in uncovered villages

5. Benchmarking issue:

The committee has following suggestions for benchmarking issues:

C-DoT has done all the cost estimation for bench marking purpose based

upon GSM technology, however the TSPs can use any technology.

(i) Power :

a) Use of Renewable Energy Technology (RET) Solar will be

mandatory at all locations.

b) 2 days back-up for Cat-A and Cat-B and 24 hours for Cat - C.

c) DG sets and SMPS have not been included for benchmarking

purpose in all categories.

d) The above requirements are for bench-marking purpose. Service

Provider shall comply to TRAI uptime requirements by using

additional power arrangements, if required.

e) The committee noted that minimum power requirement for one

carrier CDMA site with Omni antenna will be 400 watts

(Approximately).

(ii) Backhaul :

C-DoT had not taken into account provision of using satellite backhaul in

the absence of terrain based information. Initial estimation suggest that

25% of sites in Arunachal Pradesh/ Andaman & Nicobar Islands, 10% in

Himachal Pradesh/ Jammu & Kashmir, 5 % in Maharashtra and 2% of

sites in other states can be considered using VSATs. However C-DoT may

further fine tune the estimation.

C-DoT has proposed integrated microwave backhaul for category A1, A2

& B.. It is not mandatory for TSP to buy BTS equipment with integrated

backhaul as separate links can be installed depending upon requirement.

It is also important to note that despite passage of about 17 years from the

advent of mobile services in the country, over 50,000 villages remained

uncovered. Therefore, it is expected that in many cases more hops of

microwave link may be required or satellite link (VSAT) may be needed or

long OFC links may be needed to connect to the BSC of TSP. USOFA has

to decide how bench marking is to be done in such cases i.e. whether

Page 2: Study Report USOF Mobile

Page 2 of 20

single end cost of m/w link, VSAT link or OFC terminal is to be considered

or any other alternative is to be considered.

If VSAT link is used for backhaul, the link capacity will depend upon the

BTS configuration as detailed below-

BTS Category Backhaul Link Capacity Satellite Link Capacity

A 256 Kbps 128 Kbps

B 384Kbps 192 Kbps

C 768 Kbps 384 Kbps

These backhaul satellite link capacities are based on GSM technology

which can be used for benchmarking purpose.

(iii) Towers :

C-DOT has not specified any standards for Towers. It is recommended

tower design should be based on TEC GRs or as per design approved

from an organization like Structural Engineering Research Centre (SERC)/

TEC/ IITs for structural fitness, safety, load bearing capacity, ability to

withstand wind speed etc.

6. Recommendations: Salient features of various Network Elements being

recommended are as below. TEC GRs may be used for reference purposes if

any key technical functional requirements as below are not adequate:

6.1 Infrastructure Recommendations against Category A, B & C along with

Benchmark Costing Calculations at State Level

Table A: Category ‘A’ Infrastructure Recommendation

For the purposes of arriving at the benchmark, Category ‘A’ Equipment is

taken as based on GSM Base Stations

BTS to be equipped up to 2TRXs for GSM with Omni Antenna. It may be

further classified into Category ‘A1’ and Category ‘A2’. For CDMA equivalent

is single carrier BTS with Omni antennae.

In Category ‘A’, 50% Category A1 and 50% Category ‘A2’ may be assumed

Category ‘A1’ and Category ‘A2’ to have Ground Based Tower with a height

20 meter.

Page 3: Study Report USOF Mobile

Page 3 of 20

Category ‘A1’ transmit power of 2W and Category ‘A2’ transmit power of 5

watts at the antenna port subject to adherence to the latest EMF Radiation

norms of DOT with coverage radius of 1 and 2 Kms respectively.

To operate on non-conventional energy sources i.e. solar power

To provide voice communication, SMS and additionally support data

communication service with data rates of 100 to 128 kbps capability.

It must adhere to license conditions including the latest EMF Radiation norms

of DOT.

Table B: Category ‘B’ Infrastructure Recommendation

For the purposes of arriving at the benchmark, Category ‘B’ Equipment is

taken as based on GSM Base Stations

It may support 2TRX Omni for GSM or CDMA with 1 carrier Omni.

It may be mounted on a tower of up to 30 meters height and may transmit

upto 10 watts Power at the antenna port subject to adherence to the latest

EMF Radiation norms of DOT for coverage radius above 2 KMs and up to 4

Km respectively.

Should operate on non-conventional energy source i.e. solar.

It shall support voice communication, SMS and additionally support data

communication rates of 100 to 128 kbps capability.

It may use sectoral antennae depending on location of equipment and

distribution of population around it.

It must adhere to license condition including the latest EMF Radiation norms

of DoT

Table C: Category ‘C’ Infrastructure Recommendation

For the purposes of arriving at the benchmark, Category ‘C’ Equipment may

be taken as based on GSM Base Stations

It may support 2+2+2 configuration (GSM) or equivalent CDMA configuration

one carrier three sector(1C3S).

Page 4: Study Report USOF Mobile

Page 4 of 20

To have a Ground Based tower of 40 meters and transmit up to 20 watts

Power at the antenna port subject to adherence to the latest EMF Radiation

norms of DOT for coverage distances beyond a radius of 4- 6 Kms.

Should operate on non-conventional energy sources i.e. solar.

It must adhere to license condition including the latest EMF Radiation norms

of DoT

It shall support voice communication, SMS and additionally support data

communication rates of 100 to 128 kbps capability.

6.2 C-DoT report has provided the distribution of villages based on population as below:

SN Size of village population % of villages

1 Up to 1000 50%

2 Between 1000 - 2500 37%

3 Above 2500 13%

Based on the above population criteria, C-DoT was requested to carry out

state-wise analysis again to determine the tentative number of Category ‘A’,

Category ‘B’ or Category ‘C’ type of BTS. The state-wise categorization based on

the population criteria is given in Annexure B. However, the actual categorization

of the type of infrastructure required at a particular location will be governed by

many other factors such as area spread of a village/cluster of villages, the

population spread, terrain conditions and the availability of ancillary infrastructure

such as power, backhaul etc. Therefore, the population-based categorization is

just indicative in nature and actual deployment of sites from among the

categories worked out above will be subject to variation according to the actual

field conditions.

It is noted by the committee that TSPs have roll out obligations in respect of BHQ

and rural areas. Committee felt it necessary to point out that a condition may

perhaps required to be incorporated in the tender/contract that the BTS installed

under this scheme will not be counted towards roll out obligations under license.

Licensor / TERM Cells may also be kept informed.

Page 5: Study Report USOF Mobile

Page 5 of 20

6.3 Power Backup

The Load requirement after discussion with C-DoT for the various categories of

infrastructure is given in the table below:

Infrastructure

Category

Load of the BTS Miscellaneous

Load

Total Load

Category A1 100W 50W 150W

Category A2 150W 50W 200W

Category B 350W 50W 400W

Category C 800W 150W 950W

6.4 Battery

6.4.1 Category A1

150W is the load due to the equipment of one TSP

Days of autonomy assumed = 2 days

Battery Rating = (Load * Backup Time) / (Efficiency*De-rating Factor*Voltage)

(150W*24Hrs*2 Days)/ (0.95*0.80*24V) = 394.73 AH

Assuming that there will be some charging from Solar during cloudy days also,

the battery rating can be taken as 350 AH, i.e., two battery banks of 175 AH

each.

6.4.2 Category A2

200W is the load due to the equipment of one TSP

Days of autonomy assumed = 2 days

Battery Rating = (Load * Backup Time) / (Efficiency*De-rating Factor*Voltage)

(200W*24Hrs*2 Days)/ (0.95*0.80*24V) = 526.31 AH

Assuming that there will be some charging from Solar during cloudy days also,

the battery rating can be taken as 500 AH, i.e., two battery banks of 250 AH each

6.4.3 Category ‘B’

400W is the load due to the equipment of one TSP

Days of autonomy assumed = 2 days

Battery Rating = (Load * Backup Time) / (Efficiency*De-rating Factor*Voltage)

(400W*24Hrs*2 Days)/ (0.95*0.80*24V) = 1052.63 AH

Assuming that there will be some charging from Solar during cloudy days also,

the battery rating can be taken as 1000 AH, i.e., two battery banks of 500 AH

each

Page 6: Study Report USOF Mobile

Page 6 of 20

6.4.4 Category ‘C’

950W is the load due to the equipment of one TSP

Hours of autonomy assumed = 24 Hours

Battery Rating= (Load current * Backup Time)/(Efficiency*De-rating

Factor*Voltage) = (950*24Hrs) / (0.95*0.80*50)

= 600 AH

Assuming that there will be some charging from Solar panels during cloudy days

also, the battery rating can be taken as 600 AH, i.e., two battery banks of 300 AH

each. The 24 hours autonomy has been taken because the villages are remote

and at the same time battery capacity is to kept low for saving on CAPEX.

6.5 A set of two batteries banks with each bank conforming to the following

specifications:

Table Battery Backup Recommendations

a. Battery Capacity: Two sets of each capacity-

175 ampere hours for Category ‘A1’,

250 ampere hours for Category ‘A2’,

500 ampere hours for Category ‘B’ and

300 ampere hours for Category ‘C’ type of infrastructure

b. Type: Tubular Valve Regulated Lead Acid maintenance free battery.

c. Output Voltage: -48V for Category C/-24V for Category A & B

d. The two batteries may be connected in the load sharing mode

Page 7: Study Report USOF Mobile

Page 7 of 20

6.6 Solar Panels for supporting the BTS load:

For Category ‘A1’ equipment Solar power system of 1658Wp is recommended.

For Category ‘A2’ equipment Solar power system of 2340Wp is recommended.

For Category ‘B’ equipment Solar power system of 4680Wp is recommended.

For Category ‘C’ equipment Solar power system of 6340Wp is recommended.

6.7Diesel Generator:

No Diesel Generator is recommended for all categories of BTS. Therefore cost of

DG set has not been taken for benchmarking.

6.8 SMPS:

SMPS has not been considered for benchmarking as all types of BTS will run on solar energy.

6.9 Antenna Technology Options:

An Individual Tri Sectored Cross Polarized Single Band Antenna or Omni-

directional antenna as per categorization of BTS is recommended.

The gain should be better than 9 dBi for the Omni directional antenna and 17 dBi

with 90° beam width for the sectoral antenna.

6.10Backhaul technology proposed as below:

a. Other wireless technologies like Wi-Max may also be used for backhauling.

For rugged terrains where laying OFC and getting LoS for the microwave

maybe a problem, satellite backhaul maybe used.

b. 2% of sites can be considered on VSAT backhaul with the exception of

Arunachal Pradesh & Andaman & Nicobar Islands with 25% sites; J&K & HP

with 10% of sites and Maharashtra with 5% sites being on VSAT in line with

TRAI Recommendation for Arunachal Pradesh.

Page 8: Study Report USOF Mobile

Page 8 of 20

c. The percentages for VSAT at state/Circle level as indicated in para 3.1(ii) of

this report can be reconfirmed from CDOT prior to benchmarking by USOF.

7. The CAPEX calculations done by C-DoT for Category A1, A2, B and C are

available in Annexure C1, C2, C3 and C4 respectively. The total CAPEX are

given in Annexure D.

8. Other Observations:

(i) The committee noted that the existing TSPs hold spectrum in 800 MHz,

800/1800 MHz and 900/1800 MHz bands. Many of the Circle (Non-Metro)

licenses will come up for renewal in 2015, 2016/2017 before the expiry of

the contract period with USOF. The band in which the spectrum is

available with the TSP after renewal will depend on the spectrum acquired

by it in auction. There is a possibility that such band is different than the

band used for deployment of USO funded sites. To ensure continued

coverage, a suitable condition may have to be incorporated in the tender

which should also indicate that cost of change of equipment /spectrum,

etc., if any, will have to be borne by the TSP. Further, suitable provision

may also be made for inspection of sites by DOT/ USOF in case frequency

band is changed.

(ii) C-DOT has done all coverage calculations based on use of 900 MHz

band. However, the committee noted that the same coverage

requirements arrived at by C-DOT will be met even if the 1800 MHz band

is used, with the same tower height and radiated power as there is margin

available w.r.t. the coverage designed by C-DoT..

(iii) Based on the Recommendations of the Committee contained in Section 3,

4, 5 and 6 as above, C-DoT was requested to rework the estimated cost

which now comes out Rs.3611 Crores (approx.). The committee has not

gone into details of cost specifics provided by C-DoT and the figures given

above have been used for comparison purpose. The Report includes

optimization of network elements including energy efficiency and solution

are given at State Levels instead of calculated/ designed at national level.

The Recommendations have taken note of TRAI Recommendations as at

Annex A w.r.t. improving telecom services in NE states and investment

plan dated 26/09/2013.

(iv) USOF may examine the applicability of PMA related Gazette Notifications

for this project.

Page 9: Study Report USOF Mobile

Page 9 of 20

(v) For the purpose of arriving at the benchmark, the equipment is taken as

based on GSM BTS. Recently, BSNL has floated tenders for a USOF

Project for Solar based low power BTS solution for LWE areas using TEC

GR (Cat 1). USOF administration may take into account tender results/

response also.

(vi) TSPs must keep provision for at least 2 mobile handset chargers in each

BTS site for enabling the customers to charge their handsets as availability

of grid supply is poor in these areas.

(vii) TSPs must ensure battery backup of 48 hours in category ‘A’ & ‘B’

and 24 hours in category ‘C’ even if different capacity equipment is

installed by them.

Page 10: Study Report USOF Mobile

Page 10 of 20

ANNEXURE - A Chapter XII:- Summary of TRAI Recommendations

12.1 The Authority recommends that USOF should ensure compliance to stringent timelines and in-built penalty clauses in USO funded projects. In NOFN project, USOF/BBNL should build-in severe penalty clauses for delays in its agreements with the agencies implementing the project. At the same time, USOF/BBNL should also incentivize executing agencies in case the work is completed before the stipulated timeframe. The USOF/BBNL needs to urgently re-assess the capabilities of Railtel to carry out the project and review its decision regarding the executing agency, if necessary. (Para 1.20) 12.2 The Authority recommends that, in the first phase, 2G mobile coverage should be extended to all remaining BHQs, towns and such villages which have a population of more than 250 in the NE Region. The State-wise list of all such villages, is placed at Annexure-V. It is further recommended that after execution of the first phase, the actual number of uncovered villages should be assessed and the remaining uncovered villages should be taken up subsequently. (Para 2.30) 12.3 The Authority recommends that the overall investment requirement for the suggested comprehensive plan for covering the telecom infrastructure gaps in the North East Region states would be approximately Rs 2918 Crores. (Para 2.59) 12.4 The Authority recommends that in case a service provider covers at least 80% of the habitations having population above 250 (as per 2011 Census) in the Assam and North East LSAs, a discount of 2% of AGR in the license fee should be given to such a service provider. (Para 11.6) 12.5 The Authority recommends that PGCIL and BSNL should lease their dark fibre in the NER to other TSPs who are interested in taking fibre on lease. These PSUs ought to re-engineer their internal processes so as to quickly respond to the demands raised by other service providers and should be able to provide the requested bandwidth/ fibre on lease within two months of the raising of demand. PGCIL should immediately reduce its bandwidth leasing charges in the NER to make them comparable to those charged in other parts of the country. (Para 11.8) 12.6 The Authority recommends that bandwidth charges for providing satellite connectivity to TSPs in the NER should be subsidized through USO funds. The amount of subsidy should be restricted to 75% of the total bandwidth cost; the remaining 25% of the bandwidth cost should be borne by the TSPs. The subsidy should be limited to 1 Mbps bandwidth for connecting remote BTSs to the BSC. In case of District Headquarters which have to rely on satellite connectivity for media redundancy purposes, the subsidy amount for the bandwidth should be restricted to the bandwidth proposed for such District Headquarters in these recommendations. (Para 11.10)

Page 11: Study Report USOF Mobile

Page 11 of 20

12.7 The Authority recommends that issues for allocation of spot frequencies for Microwave backhaul and clearance for setting up VSAT connectivity and BTS may be addressed on a priority basis by the WPC for the NER States and reasonable time frames (not exceeding two months) should be fixed for allocation of frequencies and providing spectrum-related clearances. (Para 11.11) 12.8 For the purpose of establishing connectivity within their respective service areas, the TSPs of North East LSA may be allowed to install microwave repeaters in Assam LSA and vice-versa. This will, however, be subject to non-interference from the other point-to-point links. (Para 11.12) 12.9 The Authority recommends that the TSPs having spectrum in the NER region should enter into Inter and Intra-Circle roaming agreements amongst themselves within a period of 6 months for all the BTSs along the National Highways that pass through NER states. In case they fail to do so, they should be so mandated by the DoT. (Para 11.13) 12.10 The Authority recommends that the Government should mandate all agencies viz. National Highways Authority of India(NHAI), Border Road Organisation(BRO), State Public Works Departments(PWD) etc involved in construction of National and State Highways to provide for infrastructure utility ducts along the Highways which can be used by companies providing utility services like telecom, power etc. for laying cables. (Para 11.14) 12.11 DoT should take up the issue of providing subsidy for installation of solar power units at telecom towers (BTS and repeater) with the Ministry of New and Renewable Energy (MNRE). (Para 11.16) 12.12 The Authority recommends that the DoT should immediately take up this issue with Ministry of Home Affairs and DoNER to either obtain exemption for the movement of equipment and pre-identified personnel related to telecom services from the compliances of NOCs and road permits OR for establishing a streamlined system whereby a single common permit/NOC is required for the entire North East region. An option to be explored is that MHA initiate a centralized clearing system where clearances can be obtained from the concerned State Governments and given to the TSPs. (Para 11.20) 12.13 The Authority recommends that the State Governments of the NER may: a. Address the issues raised by the TSPs on priority so that they are encouraged to roll-out services faster in the region; b. Provide land for erection of Ground Based Towers(GBT) and Govt buildings for erection of Roof Top Towers (RTT); c. Ensure availability of commercial power for BTSs on priority;

Page 12: Study Report USOF Mobile

Page 12 of 20

d. Facilitate availability of sufficient diesel supply to the TSPs particularly during bandhs/strikes; e. Ensure that wherever BTSs are running on DG sets they are able to run round-the-clock so that the people get uninterrupted telecom connectivity; f. Set up a single-window clearance system for all telecom related clearances/NOCs like pollution/noise control certificate, environment clearance, site acquisitions, commercial power supply etc; g. Rescind the levy of taxes/charges on the use of DGs by TSPs; h. Facilitate optical fiber cable (OFC) laying in their States by allowing pulling of OFC on Transmission towers/poles of State Electricity Boards; and, i. Nominate a senior officer to coordinate with the TSPs for handling of any issue concerning telecom services in the States.(Para 11.22)

Page 13: Study Report USOF Mobile

Page 13 of 20

Annexure B: BTS TOWERS in each State Category Wise

State No. of Proposed

BTS

Villages Getting Covered

by Proposed

BTSs

Population House hold

Covered by BTS Towers

No. of Towers of Cat

'A' (Pop< 1000)

No. of Towers of Cat

'B'(Pop>= 1000 & Pop< 2500)

No. of Towers of Cat

'C' (Pop>= 2500)

% Pop. covered

by Categor

y 'A'

% Pop. covere

d by Category 'B'

% Pop. covered by Category 'C'

ANDAMAN & NICOBAR ISLANDS

95 175 19397 3911 93 2 0 97.9% 2.1% 0.0%

Andhra Pradesh 540 1139 778223 173527 233 230 77 43.1% 42.6% 14.3%

Arunachal Pradesh

1062 1894 303683 57564 1017 42 3 95.8% 4.0% 0.3%

Assam 247 349 298186 52876 139 79 29 56.3% 32.0% 11.7%

BIHAR 105 265 157882 26648 52 38 15 49.5% 36.2% 14.3%

CHHATTISGARH 2210 4829 2696020 538524 1103 878 229 49.9% 39.7% 10.4%

Dadra & Nagar Haveli

2 2 3961 788 1 0 1 50.0% 0.0% 50.0%

GOA 16 21 9612 2007 15 1 0 93.8% 6.3% 0.0%

GUJRAT 923 1792 1299194 239180 359 455 109 38.9% 49.3% 11.8%

HARYANA 19 28 12284 7851 9 3 7 47.4% 15.8% 36.8%

HIMACHAL PRADESH

381 1556 261820 48258 294 79 8 77.2% 20.7% 2.1%

JAMMU & KASHMIR

200 434 442295 68117 54 84 62 27.0% 42.0% 31.0%

JHARKHAND 983 4752 1966288 369561 286 417 280 29.1% 42.4% 28.5%

KARNATAKA 527 938 691105 135978 279 208 40 52.9% 39.5% 7.6%

MADHYA PRADESH

722 1647 884159 159678 347 314 61 48.1% 43.5% 8.4%

MAHARASHTRA 1913 4805 2913861 583156 788 819 306 41.2% 42.8% 16.0%

MANIPUR 319 498 257182 41570 240 67 12 75.2% 21.0% 3.8%

MEGHALAYA 602 2662 727880 131974 331 227 44 55.0% 37.7% 7.3%

MIZORAM 305 386 224345 42490 240 60 5 78.7% 19.7% 1.6%

NAGALAND 225 362 349650 54214 105 81 39 46.7% 36.0% 17.3%

ODISHA 1347 6245 2092738 465508 526 568 253 39.0% 42.2% 18.8%

PUNJAB 38 80 44118 7646 18 18 2 47.4% 47.4% 5.3%

RAJASTHAN 1678 3133 1962087 327791 863 685 130 51.4% 40.8% 7.7%

SIKKIM 10 11 4403 834 10 0 0 100.0% 0.0% 0.0%

TAMIL NADU 54 78 106209 26444 32 12 10 59.3% 22.2% 18.5%

TRIPURA 90 171 232842 46032 13 34 43 14.4% 37.8% 47.8%

UTTAR PRADESH

780 1774 1506094 237370 308 295 177 39.5% 37.8% 22.7%

Uttrakhand 373 1401 376635 72045 227 122 24 60.9% 32.7% 6.4%

WESTBENGAL 305 884 641593 123598 107 107 91 35.1% 35.1% 29.8%

Total 16071 42311 21263746 4045140 8089 5925 2057 50.3% 36.9% 12.8%

Page 14: Study Report USOF Mobile

Page 14 of 20

Annexure C 1 CATEGORY A1 CAPEX in Rs. for each BTS Tower given by C-DoT

Category A1 Infrastructure Components' Cost Details

Component Description Unit Cost (in INR) 2 TRX 2W with omni-directional antenna and

integrated backhaul

100000

Battery Bank of 2 battery of 175AH each 200000 Solar pannel (1638Wp) along with CCU 165800 Ground Based 20M 550000 SMPS 2+1 modules (25A) 0 TOTAL COST 1015800 Land & Fencing 200000 10 % Installation Charges 101580 CAPEX for one site including Installation Charges 1317380

OPTIONAL INFRASTRUCTURE

Component Description Cost in INR Diesel Generator Set (3KVA) 0 Satellite Backhaul 300000 25% Cases in

Arunachal & Andaman & Nicobar; 10 % HP & J&K, 5 % Maharashtra, 2% Other Cases

CAPEX for one site including Installation Charges + Optional items

1323380

CAPEX for one site including Installation Charges + Optional items for Arunachal Pradesh & Andaman & Nicobar Islands with 25% VSATs

1392380

CAPEX for one site including Installation Charges + Optional items for J&K & HP with 10% VSATs

1347380

CAPEX for one site including Installation Charges + Optional items for Maharashtra with 5 % VSATs

1332380

Page 15: Study Report USOF Mobile

Page 15 of 20

Annexure C 2

CATEGORY A2 & Average for Cat ‘A’ CAPEX in Rs. for each BTS Tower given by C-DoT

Category A2 Infrastructure Components' Cost Details Component Description Unit Cost (in INR) 2 TRX 5W with omni-directional antenna and integrated backhaul

100000

Battery Bank of 2 battery of 250AH each 285000 Solar pannel (2340Wp) along with CCU 234000 Ground Based 20M 550000 SMPS 3+1 modules (25A) 0 TOTAL COST 1169000 Land & Fencing 200000 10 % Installation Charges 116900 CAPEX for one site including Installation Charges 1485900 OPTIONAL INFRASTRUCTURE Component Description Cost in INR Diesel Generator Set (3.5KVA) 0 Satellite Backhaul 300000 25% Cases in Arunachal

& Andaman & Nicobar; 10 % HP & J&K, 5 % Maharashtra, 2% Other Cases

CAPEX for one A2 site including Installation Charges + Optional items

1491900

CAPEX for one A2 site including Installation Charges + Optional items for Arunachal Pradesh , Andaman & Nicobar with 25% VSATs

1560900

CAPEX for one A2 site including Installation Charges + Optional items for J&K & HP with 10% VSATs

1515900

CAPEX for one A2 site including Installation Charges + Optional items for Maharashtra with 5 % VSATs

1500900

With 50% of sites being Category A1 & A2 each

CAPEX for one 'A' site including Installation Charges + Optional items with 2% VSATs

1406540

Page 16: Study Report USOF Mobile

Page 16 of 20

CAPEX for one 'A' site including Installation Charges + Optional items for Arunachal Pradesh & Andaman & Nicobar with 25% VSATs

1475540

CAPEX for one A site including Installation Charges + Optional items for J&K & HP with 10% VSATs

1430540

CAPEX for one A site including Installation Charges + Optional items for Maharashtra with 5 % VSATs

1402860

Page 17: Study Report USOF Mobile

Page 17 of 20

Annexure C 3

CATEGORY B CAPEX in Rs. for each BTS Tower given by C-DoT

Category B Infrastructure Components' Cost Details

Component Description Unit Cost (in INR)

10W BTS with 2 TRX Omni) with integrated backhaul 350000

Battery Bank of 2 batteries of 500AH each 550000

Solar Panel (4680 Wp) 468000

Ground Based 30M 1000000

SMPS 5+1 modules (25A) 0

Total Cost 2368000

Land & Fencing 200000

10 % Installation Charges 236800

CAPEX for one site including Installation Charges 2804800

OPTIONAL INFRASTRUCTURE

Component Description Cost in INR

Diesel Generator Set (7KVA) 0 Satellite Backhaul 300000 25% Cases in

Arunachal & Andaman & Nicobar; 10 % HP & J&K, 5 % Maharashtra, 2% Other Cases

CAPEX for one site including Installation Charges + Optional items

2810800

CAPEX for one site including Installation Charges +

Optional items for Arunachal Pradesh & Andaman & Nicobar Islands with 25% VSATs

2879800

CAPEX for one site including Installation Charges + Optional items for J&K & HP with 10% VSATs

2834800

CAPEX for one site including Installation Charges + Optional items for Maharashtra with 5 % VSATs

2819800

Page 18: Study Report USOF Mobile

Page 18 of 20

Annexure C 4

Category C Infrastructure Components' Cost Details given by C-DoT

Category C Infrastructure Components' Cost Details

Component Description Unit Cost

GSM BTS Outdoor (2+2+2 configuration) along with antenna set and feeder cable 600000

Backhaul Microwave Radio 450000

Battery Bank of 2 battery of 300 AH each 300000

SMPS 2+1 modules (50A) 0 Solar Panel (6340Wp) 634000 Diesel Generator Set 10KVA 0 Ground Based Tower 40M 1350000 Total Cost 3334000 Land & Fencing 200000 10 % Installation Charges 333400

CAPEX for one site including Installation Charges 3867400

OPTIONAL INFRASTRUCTURE Component Description Cost in INR

Satellite Backhaul 300000

25% Cases in Arunachal & Andaman & Nicobar; 10 % HP & J&K, 5 % Maharashtra, 2% Other Cases

CAPEX for one site including Installation Charges + Optional items

3873400

CAPEX for one site including

Installation Charges + Optional items for Arunachal Pradesh & Andaman & Nicobar Islands with 25% VSATs

3942400

CAPEX for one site including Installation Charges + Optional items for J&K & HP with 10% VSATs

3897400

CAPEX for one site including Installation Charges + Optional items for Maharashtra with 5 % VSATs

4140900

Page 19: Study Report USOF Mobile

Page 19 of 20

Annexure D Total CAPEX in Rs. for 16071 Category A, B & C BTS Sites

State No. of Proposed

BTS

No. of Towers of Cat

'A' (Pop< 1000)

No. of Towers of Cat

'B'(Pop>= 1000 & Pop< 2500)

No. of Towers of Cat

'C' (Pop>= 2500)

Category 'A' CAPEX (Rs.

Cr.)

Category 'B'

CAPEX (Rs. Cr)

Category 'C'

CAPEX (Rs. Cr.)

CAPEX Total

(Rs. Cr.)

A & N ISLANDS 95 93 2 0 13.7 0.6 0.0 14.3

Andhra Pradesh 540 233 230 77 32.8 64.6 29.8 127.3

Arunachal Pradesh

1062 1017 42 3 150.2 12.1 1.2 163.5

Assam 247 139 79 29 19.6 22.2 11.2 53.0

BIHAR 105 52 38 15 7.3 10.7 5.8 23.8

CHHATTISGARH 2210 1103 878 229 155.3 246.8 88.7 490.8

Dadra & Nagar Haveli

2 1 0 1 0.1 0.0 0.4 0.5

GOA 16 15 1 0 2.1 0.3 0.0 2.4

GUJRAT 923 359 455 109 50.5 127.9 42.2 220.6

HARYANA 19 9 3 7 1.3 0.8 2.7 4.8

H. P. 381 294 79 8 42.1 22.4 3.1 67.6

J & K 200 54 84 62 7.7 23.6 24.2 55.5

JHARKHAND 983 286 417 280 40.3 118.2 108.5 266.9

KARNATAKA 527 279 208 40 39.3 58.5 15.5 113.2

MADHYA PRADESH

722 347 314 61 48.8 88.3 23.6 160.7

MAHARASHTRA 1913 788 819 306 110.7 230.9 118.8 460.4

MANIPUR 319 240 67 12 33.8 18.8 4.6 57.3

MEGHALAYA 602 331 227 44 46.6 63.8 17.0 127.4

MIZORAM 305 240 60 5 33.8 16.9 1.9 52.6

NAGALAND 225 105 81 39 14.8 22.8 15.1 52.7

ODISHA 1347 526 568 253 74.0 159.7 98.0 331.7

PUNJAB 38 18 18 2 2.5 5.1 0.8 8.4

RAJASTHAN 1678 863 685 130 121.5 192.5 50.4 364.4

SIKKIM 10 10 0 0 1.4 0.0 0.0 1.4

TAMIL NADU 54 32 12 10 4.5 3.4 3.9 11.8

TRIPURA 90 13 34 43 1.8 9.6 16.7 28.0

UTTAR PRADESH

780 308 295 177 43.4 82.9 68.6 194.8

Uttrakhand 373 227 122 24 32.0 34.3 9.3 75.5

WESTBENGAL 305 107 107 91 15.1 30.1 35.2 80.4

Total 16071 8089 5925 2057 1146.9 1667.6 797.2 3611.7

Page 20: Study Report USOF Mobile

Page 20 of 20

Note: Annual OPEX and TAX components as applicable have not been taken into consideration and could be added as applicable separately.