Status of the LARP Phase II Secondary Collimator Prototype

18
Status of the LARP Phase II Secondary Collimator Prototype 30 September 2013 LHC Collimation WG Meeting Tom Markiewicz/SLAC BNL - FNAL- LBNL - SLAC US LHC Accelerator Research Program 6 September 2013

description

US LHC Accelerator Research Program. BNL - FNAL- LBNL - SLAC. Status of the LARP Phase II Secondary Collimator Prototype. 30 September 2013 LHC Collimation WG Meeting Tom Markiewicz/SLAC. 6 September 2013. Collimator Assembled 13-Mar-11 Mechanical & Resistance Tests Good. - PowerPoint PPT Presentation

Transcript of Status of the LARP Phase II Secondary Collimator Prototype

Page 1: Status of the LARP Phase II Secondary Collimator Prototype

Status of the LARPPhase II Secondary Collimator Prototype

30 September 2013LHC Collimation WG Meeting

Tom Markiewicz/SLAC

BNL - FNAL- LBNL - SLACUS LHC Accelerator Research Program

6 September 2013

Page 2: Status of the LARP Phase II Secondary Collimator Prototype

Collimator Assembled 13-Mar-11Mechanical & Resistance Tests Good

LHC Collimation WG Mtg - 30 Sept 2013 LARP RC Status - T. MarkiewiczSlide n° 2 / 18

Page 3: Status of the LARP Phase II Secondary Collimator Prototype

Collimator Assembled 18-Sept-13Mechanical & Resistance Tests Good

LHC Collimation WG Mtg - 30 Sept 2013 LARP RC Status - T. MarkiewiczSlide n° 3 / 18

Page 4: Status of the LARP Phase II Secondary Collimator Prototype

• Continuous 15m copper tube wrapped on copper mandrel• Tube enters from far end of mandrel then begins spiral to provide

~1m free length that can twist to allow rotation• 25mm thick Glidcop “jaw” brazed to mandrel

• 20 “20mm wide facets” 25um flat are the collimating surfaces• Molybdenum shaft with 2mm “heat expansion gap” from mandrel

• Mandrel held at midpoint only by a brazed Glidcop “hub”

Jaw Designed to Minimize Thermal Distortion1 hour beam→12kW with 10 second transients x5→60kW

LHC Collimation WG Mtg - 30 Sept 2013 LARP RC Status - T. MarkiewiczSlide n° 4 / 18

Page 5: Status of the LARP Phase II Secondary Collimator Prototype

New Bearing Restraint

LHC Collimation WG Mtg - 30 Sept 2013 LARP RC Status - T. Markiewicz

“Naked” Hub Screwed to Axle Bearing on Hub Spacer Ring & Bearing in Housing

Bearing Restraint Ring, Bearing in Housing & Clip Oversize Outer Housing w/ Flats that prevent rotation in jaw supports

Slide n° 5 / 18

Page 6: Status of the LARP Phase II Secondary Collimator Prototype

New RF Bearing Assembly

LHC Collimation WG Mtg - 30 Sept 2013 LARP RC Status - T. Markiewicz

Ceramic bearing in race & the 2 rings that capture it

Assembled bearing package that will hold the RF Foil

Trapped bearing in ring that is fixed to the collimator jaw

Attaching outer ring to collimator Closeup of ridge where bearing rolls

Before outer ring screwed on

Slide n° 6 / 18

Page 7: Status of the LARP Phase II Secondary Collimator Prototype

Final RF Bearing Installed

LHC Collimation WG Mtg - 30 Sept 2013 LARP RC Status - T. MarkiewiczSlide n° 7 / 18

Page 8: Status of the LARP Phase II Secondary Collimator Prototype

BeCu Foils, Rhodium plate “wipers”, Clamps to keep RF Bearing Package

from Dragging

LHC Collimation WG Mtg - 30 Sept 2013 LARP RC Status - T. Markiewicz

Foils, wipers & clamps Thermistor/Foil/Wiper Holder

Holder w/Wiper/Foil Attached

Beam-side View View Behind Foil w/ Clamp ATtached

Slide n° 8 / 18

Page 9: Status of the LARP Phase II Secondary Collimator Prototype

Welding Flanges Attached to Tank Cover and Baseplate

LHC Collimation WG Mtg - 30 Sept 2013 LARP RC Status - T. MarkiewiczSlide n° 9 / 18

Page 10: Status of the LARP Phase II Secondary Collimator Prototype

Dry Fit Cover to Baseplate & test Rotation w/Foils Attached

LHC Collimation WG Mtg - 30 Sept 2013 LARP RC Status - T. MarkiewiczSlide n° 10 / 18

Page 11: Status of the LARP Phase II Secondary Collimator Prototype

Resistivity Test: 1 mOhm/side

LHC Collimation WG Mtg - 30 Sept 2013 LARP RC Status - T. MarkiewiczSlide n° 11 / 18

Page 12: Status of the LARP Phase II Secondary Collimator Prototype

Jaw Alignment & CMM

LHC Collimation WG Mtg - 30 Sept 2013 LARP RC Status - T. MarkiewiczSlide n° 12 / 18

Page 13: Status of the LARP Phase II Secondary Collimator Prototype

Final Adjustment of Actuator & Drive Wheel (relative to Inner Limit Switch)

LHC Collimation WG Mtg - 30 Sept 2013 LARP RC Status - T. Markiewicz

Remember to play movie

Slide n° 13 / 18

Page 14: Status of the LARP Phase II Secondary Collimator Prototype

Leak Test Cooling Tubes (most recent)Pressure & Leak Rate

LHC Collimation WG Mtg - 30 Sept 2013 LARP RC Status - T. Markiewicz

Left Jaw (AC) Right Jaw (BD)

Slide n° 14 / 18

Page 15: Status of the LARP Phase II Secondary Collimator Prototype

Prep & “CuSil” the Cooling Tube to the Bellows Feedthrough

LHC Collimation WG Mtg - 30 Sept 2013 LARP RC Status - T. MarkiewiczSlide n° 15 / 18

Page 16: Status of the LARP Phase II Secondary Collimator Prototype

Need Today to Remove Spring to CuSil the Remaining Two Tubes

LHC Collimation WG Mtg - 30 Sept 2013 LARP RC Status - T. MarkiewiczSlide n° 16 / 18

Page 17: Status of the LARP Phase II Secondary Collimator Prototype

Work List

After that, wind 2nd mandrel, then …………..Prep with strips & braze coils and inner hub/shafts to mandrels (2 of 2 done)Machine assembly round & concentric to axis at diameter to accept Glidcop jawsMachine & Cu plate Glidcop jawsPrep and braze jaws to mandrels (2nd done 8-Apr-13)

Machine facets, end features (2nd done 28-May-13)

Install RF bearing housingInstall shaft support bearings and rotation drivesTest prior to installation in vacuum systemPrep existing vacuum base plate to receive new collimatorsMount, align & testDecide details of how vacuum cover will be attached to vacuum base plate &

machine appropriatelyMate cover & baseplateTest rotation after welding, pre and post vacuumVacuum bakeoutTest after bakeoutShip

Begin 3-June-2-13

SLA

CS

LAC

?

LHC Collimation WG Mtg - 30 Sept 2013 LARP RC Status - T. MarkiewiczSlide n° 17 / 18

Page 18: Status of the LARP Phase II Secondary Collimator Prototype

At SLAC• After CuSil test for tube integrity• Clamp vacuum cover in place, attach foils & test rotate 1 facet• Weld cover, vacuum test all welds & CuSil joints• Final full facet test rotation in vacuum• Solder metric water fittings, pressure test then dry & leak test tubes again• Immobilize jaws & ship (in 2 weeks time?)At CERN• Decide whether to open vacuum seal or not• Off beam tests:

• Function, metrology, impedance, vacuum• Bakeout (???)

• SPS tests (???)• Hi Rad Mat Tests & Subsequent Analysis

Suggested Plan That Needs More Discussion

LHC Collimation WG Mtg - 30 Sept 2013 LARP RC Status - T. MarkiewiczSlide n° 18 / 18