Status of the LARPPhase II Secondary Collimator Prototype
14 October 2013LHC Collimation WG Meeting
Tom Markiewicz/SLAC
BNL - FNAL- LBNL - SLACUS LHC Accelerator Research Program
6 September 2013
![Page 2: Status of the LARP Phase II Secondary Collimator Prototype](https://reader035.fdocuments.us/reader035/viewer/2022062501/5681668d550346895dda5ad1/html5/thumbnails/2.jpg)
Collimator Assembled 13-Mar-11Mechanical & Resistance Tests Good
LHC Collimation WG Mtg - 14 Oct 2013 LARP RC Status - T. MarkiewiczSlide n° 2 / 20
![Page 3: Status of the LARP Phase II Secondary Collimator Prototype](https://reader035.fdocuments.us/reader035/viewer/2022062501/5681668d550346895dda5ad1/html5/thumbnails/3.jpg)
Collimator Assembled 18-Sept-13Mechanical & Resistance Tests Good
LHC Collimation WG Mtg - 14 Oct 2013 LARP RC Status - T. MarkiewiczSlide n° 3 / 20
![Page 4: Status of the LARP Phase II Secondary Collimator Prototype](https://reader035.fdocuments.us/reader035/viewer/2022062501/5681668d550346895dda5ad1/html5/thumbnails/4.jpg)
• Continuous 15m copper tube wrapped on copper mandrel• Tube enters from far end of mandrel then begins spiral to provide
~1m free length that can twist to allow rotation• 25mm thick Glidcop “jaw” brazed to mandrel
• 20 “20mm wide facets” 25um flat are the collimating surfaces• Molybdenum shaft with 2mm “heat expansion gap” from mandrel
• Mandrel held at midpoint only by a brazed Glidcop “hub”
Jaw Designed to Minimize Thermal Distortion1 hour beam→12kW with 10 second transients x5→60kW
LHC Collimation WG Mtg - 14 Oct 2013 LARP RC Status - T. MarkiewiczSlide n° 4 / 20
![Page 5: Status of the LARP Phase II Secondary Collimator Prototype](https://reader035.fdocuments.us/reader035/viewer/2022062501/5681668d550346895dda5ad1/html5/thumbnails/5.jpg)
New Bearing Restraint
LHC Collimation WG Mtg - 14 Oct 2013 LARP RC Status - T. Markiewicz
“Naked” Hub Screwed to Axle Bearing on Hub Spacer Ring & Bearing in Housing
Bearing Restraint Ring, Bearing in Housing & Clip Oversize Outer Housing w/ Flats that prevent rotation in jaw supports
Slide n° 5 / 20
![Page 6: Status of the LARP Phase II Secondary Collimator Prototype](https://reader035.fdocuments.us/reader035/viewer/2022062501/5681668d550346895dda5ad1/html5/thumbnails/6.jpg)
New RF Bearing Assembly
LHC Collimation WG Mtg - 14 Oct 2013 LARP RC Status - T. Markiewicz
Ceramic bearing in race & the 2 rings that capture it
Assembled bearing package that will hold the RF Foil
Trapped bearing in ring that is fixed to the collimator jaw
Attaching outer ring to collimator Close-up of ridge where bearing rolls
Before outer ring screwed on
Slide n° 6 / 20
![Page 7: Status of the LARP Phase II Secondary Collimator Prototype](https://reader035.fdocuments.us/reader035/viewer/2022062501/5681668d550346895dda5ad1/html5/thumbnails/7.jpg)
Final RF Bearing Installed
LHC Collimation WG Mtg - 14 Oct 2013 LARP RC Status - T. MarkiewiczSlide n° 7 / 20
![Page 8: Status of the LARP Phase II Secondary Collimator Prototype](https://reader035.fdocuments.us/reader035/viewer/2022062501/5681668d550346895dda5ad1/html5/thumbnails/8.jpg)
BeCu Foils, Rhodium plate “wipers”, Clamps to keep RF Bearing Package
from Dragging
LHC Collimation WG Mtg - 14 Oct 2013 LARP RC Status - T. Markiewicz
Foils, wipers & clamps Thermistor/Foil/Wiper Holder
Holder w/Wiper/Foil Attached
Beam-side View View Behind Foil w/ Clamp ATtached
Slide n° 8 / 20
![Page 9: Status of the LARP Phase II Secondary Collimator Prototype](https://reader035.fdocuments.us/reader035/viewer/2022062501/5681668d550346895dda5ad1/html5/thumbnails/9.jpg)
Welding Flanges Attached to Tank Cover and Baseplate
LHC Collimation WG Mtg - 14 Oct 2013 LARP RC Status - T. MarkiewiczSlide n° 9 / 20
![Page 10: Status of the LARP Phase II Secondary Collimator Prototype](https://reader035.fdocuments.us/reader035/viewer/2022062501/5681668d550346895dda5ad1/html5/thumbnails/10.jpg)
Dry Fit Cover to Baseplate & test Rotation w/Foils Attached
LHC Collimation WG Mtg - 14 Oct 2013 LARP RC Status - T. MarkiewiczSlide n° 10 / 20
![Page 11: Status of the LARP Phase II Secondary Collimator Prototype](https://reader035.fdocuments.us/reader035/viewer/2022062501/5681668d550346895dda5ad1/html5/thumbnails/11.jpg)
Resistivity Test: 1 mOhm/side
LHC Collimation WG Mtg - 14 Oct 2013 LARP RC Status - T. MarkiewiczSlide n° 11 / 20
![Page 12: Status of the LARP Phase II Secondary Collimator Prototype](https://reader035.fdocuments.us/reader035/viewer/2022062501/5681668d550346895dda5ad1/html5/thumbnails/12.jpg)
Jaw Alignment & CMM
LHC Collimation WG Mtg - 14 Oct 2013 LARP RC Status - T. MarkiewiczSlide n° 12 / 20
![Page 13: Status of the LARP Phase II Secondary Collimator Prototype](https://reader035.fdocuments.us/reader035/viewer/2022062501/5681668d550346895dda5ad1/html5/thumbnails/13.jpg)
Final Adjustment of Actuator & Drive Wheel (relative to Inner Limit Switch)
LHC Collimation WG Mtg - 14 Oct 2013 LARP RC Status - T. Markiewicz
Remember to play movie
Slide n° 13 / 20
![Page 14: Status of the LARP Phase II Secondary Collimator Prototype](https://reader035.fdocuments.us/reader035/viewer/2022062501/5681668d550346895dda5ad1/html5/thumbnails/14.jpg)
Leak Test Cooling Tubes (most recent)Pressure & Leak Rate
LHC Collimation WG Mtg - 14 Oct 2013 LARP RC Status - T. Markiewicz
Left Jaw (AC) Right Jaw (BD)
Slide n° 14 / 20
![Page 15: Status of the LARP Phase II Secondary Collimator Prototype](https://reader035.fdocuments.us/reader035/viewer/2022062501/5681668d550346895dda5ad1/html5/thumbnails/15.jpg)
Prep & “CuSil” the Cooling Tube to the Bellows Feedthrough
LHC Collimation WG Mtg - 14 Oct 2013 LARP RC Status - T. Markiewicz
BeforeSlide n° 15 / 20
![Page 16: Status of the LARP Phase II Secondary Collimator Prototype](https://reader035.fdocuments.us/reader035/viewer/2022062501/5681668d550346895dda5ad1/html5/thumbnails/16.jpg)
On 30 Sept Remove Return Spring to CuSil the Remaining Two Tubes
LHC Collimation WG Mtg - 14 Oct 2013 LARP RC Status - T. Markiewicz
Before After
Leak Check Tubes Again
Slide n° 16 / 20
![Page 17: Status of the LARP Phase II Secondary Collimator Prototype](https://reader035.fdocuments.us/reader035/viewer/2022062501/5681668d550346895dda5ad1/html5/thumbnails/17.jpg)
Install Tank Cover, Install Thermistor Feedthrough Flanges, Simulate Weld with Vise Grips and
Test Rotation Drive (1 OCT)
LHC Collimation WG Mtg - 14 Oct 2013 LARP RC Status - T. MarkiewiczSlide n° 17 / 20
![Page 18: Status of the LARP Phase II Secondary Collimator Prototype](https://reader035.fdocuments.us/reader035/viewer/2022062501/5681668d550346895dda5ad1/html5/thumbnails/18.jpg)
Design, Fab, Install, Adjust & Test Flexure to Set Actuator Height
(can always be accessed through flange openings and adjusted if needed)
LHC Collimation WG Mtg - 14 Oct 2013 LARP RC Status - T. MarkiewiczSlide n° 18 / 20
![Page 19: Status of the LARP Phase II Secondary Collimator Prototype](https://reader035.fdocuments.us/reader035/viewer/2022062501/5681668d550346895dda5ad1/html5/thumbnails/19.jpg)
Work List
After that, wind 2nd mandrel, then …………..Prep with strips & braze coils and inner hub/shafts to mandrels (2 of 2 done)Machine assembly round & concentric to axis at diameter to accept Glidcop jawsMachine & Cu plate Glidcop jawsPrep and braze jaws to mandrels (2nd done 8-Apr-13)
Machine facets, end features (2nd done 28-May-13)
Install RF bearing housingInstall shaft support bearings and rotation drivesTest prior to installation in vacuum systemPrep existing vacuum base plate to receive new collimatorsMount, align & testDecide details of how vacuum cover will be attached to vacuum base plate &
machine appropriatelyMate cover & baseplateTest rotation after welding, pre and post vacuumVacuum bakeoutTest after bakeoutShip
Begin 3-June-2-13
SLA
CS
LAC
?
LHC Collimation WG Mtg - 14 Oct 2013 LARP RC Status - T. MarkiewiczSlide n° 19 / 20
![Page 20: Status of the LARP Phase II Secondary Collimator Prototype](https://reader035.fdocuments.us/reader035/viewer/2022062501/5681668d550346895dda5ad1/html5/thumbnails/20.jpg)
At SLAC• Clamp vacuum cover in place, attach foils & test rotate 1 facet• Weld cover, vacuum test all welds & CuSil joints• Final full facet test rotation in vacuum• Solder metric water fittings, pressure test then dry & leak test tubes again• Immobilize jaws & ship (in 2 weeks time?)At CERN• Decide whether to open vacuum seal or not• Off beam tests:
• Function, metrology, impedance, vacuum• Bakeout (???)
• SPS tests (???)• Hi Rad Mat Tests & Subsequent Analysis
Suggested Plan That Needs More Discussion
LHC Collimation WG Mtg - 14 Oct 2013 LARP RC Status - T. MarkiewiczSlide n° 20 / 20