Status of MDI+BDS Cost Estimate Lau Gatignon. Summary ItemkCHFComments 4 QD0 magnets1340But...

16
Status of MDI+BDS Cost Estimate Lau Gatignon

Transcript of Status of MDI+BDS Cost Estimate Lau Gatignon. Summary ItemkCHFComments 4 QD0 magnets1340But...

Status of MDI+BDS Cost Estimate

Lau Gatignon

SummaryItem kCHF Comments

4 QD0 magnets 1340 But replaceable item!

IP feedback system 610 Preliminary

Pre-alignment system (BDS+MDI) 15500

Stabilization 750

Pre-isolation (2 systems) 500 CE uncertainties significant

Post-collision line magnets 12200

Post-collision line vacuum 3200

2 Main beam dumps > 50000 ? Real work yet ?to be startedDecommissioning to be added?

2 Tune-up beam dumps, if needed > 50000 ? See above

BDS magnets ? Last on the list

BDS vacuum ?

BDS collimators, instrumentation, … ?

Total so far 34100 Excl. dump and missing items

This is a first report. Your feedback is essential! Thank you!

QD0 magnetsPBS Item 4.2.2.5 (QD0⁺/QD0⁻)

Item (needed per magnet) Cost Comments

Permendur sectors (27) 33 kCHF 100 mm each; manuf. by electro-erosion

PM blocks (108) 137 kCHF 2 single-block (with different magnetization direction) glued per each PM block

“C” beams (2) 30 kCHF “C” precision: 20 μm on the 2.7 m

Coils (4 + 1 spare) 100 kCHF

Lateral plates (2) + Ancillary (coils supports) + Assembly

25 kCHF Plates precision: 20 μm on the 2.7 m

Ancillary (control/safety + cabling) 10 kCHF

Total /magnet 335 kCHF

Total (4 magnets) 1340 kCHF

M.Modena

IP feedback system

Item Cost [kCHF]

2 Kickers 2002 BPMs 1002 Amplifiers 1002 BPM processors 402 Feedback boards 40Cables 10External power, control,monitoring

120

Total 610

P.Burrows

Pre-alignment system MDIItem Cost [kCHF]Pre-alignment systemCam-movers, WPS, inclinometer, stretching device, etc

820

Monitoring of QD015 Rasnik systems, cabling, DAQ

100

Link left/rightOpen WPS sensors, hydraulic networks, HLS sensors, cabling, etc

375

Total 1300

Note: coherent with LHC (4.5 MCHF for 4 experiments)

H.Mainaud

Pre-alignment system BDSItem Cost [kCHF]GeodesyReference networks

363

PrealignmentCAM movers, sensors (WPS, HLS, inclinometer), metrological plates,Installation and pre-positioning, etc

13770

As built measurementsIncluding analysis and modeling

25

Total 14200

CAM movers: same as in main linacWPS: not same as for main linac (optical sensors with learning curve factor),

but prototype cost divided by 3 (for the moment).

Note:

H.Mainaud

StabilisationPreliminary estimates from A.Jeremie exist (for 2 QD0):

Item kEuro Comments

Foot/support 2 Elastomere included

Actuators (piezos + electronics) 53 Incl. electronics

Absolute sensors 84

Capacitive sensors 120

Tilt-meter 3.4 Optional

DAQ + Computer 15

Pulse (.e. DAQ cost) 80

Filter 160

Total 550 Preliminary!

A.Jeremie

A very rough cost estimate of the pre-isolator:

two 110 tons masses, 20 air-springs, leveling system position controls,

~ 500 kCHf.

But large uncertainties on civil engineering costsThis does not includes R&D and prototypes.

Post-collision line magnetsE.Gschwendtner,

M.Modena

Post-collision line vacuum

for one side, thus (30% less for 2nd one) 3.2 MCHF

E.Gschwendtner,R.Veness

Main beam dumpsNo estimate has been made yet. But work starting in EN/STI groupBut an old ILC estimate (R.Appleby, GDE @ Bangalore, 2006) raises some questions

Not yet studied:

BDS&MDI magnets, rectifiers and their various services BDS collimators, optional muon sweepers MDI vacuum Support structures for QD0 Push-pull platforms + infrastructure …..

Independent estimates to come from other groups:

Civil engineering and services (form CE working group) Detectors (from PH-LCD) ….

Some questions and remarks:

One is very happy that we have made good progress in the cost estimates,even though we are not yet at the end.

For the moment spares, CERN manpower, operational and R&D costsmust not be included. However, tooling for installation must be.

Steiner Stapnes will want to discuss with some of us how to make surethat all is correctly counted, but not twice, in particular also concerning the detectors

The CES working group should do the costing for the cavern and services, but we shallmontor that everything is included.

Elimination cost must be calculated in cases where it is important (dumps!), but will most likely not be quoted at the CDR stage

We must make progress with the estimates for the BDS Philippe Lebrun and the management will see how the cost estimates for the beam

dumps can be speeded up The number of magnets for the post collision lines slide is not consistent with the

final conclusion. Should they be made super conducting to reduce power consumption?

Next steps:

Regular follow-up of progress in Cost and Schedule Working Group meetings

Internal Review of the overall CLIC Cost Estimates on 9th of December

External Cost Review Committee on 5 and 6 April 2011

Internal Review of CLIC CDR Value EstimateGuidelines for contents of presentations

• Presentations are made by PBS domain/subdomain coordinators, i.e. they follow the PBS description of the project

• Only material costs will be addressed for the time being• Each presentation will be 20 min + 10 min questions• Each presentation should contain

– Brief description of the PBS domain/subdomain– PBS level(s) at which the elementary costs were input– Value estimate methodology: analytical/scaling

• Scaling variables and laws• Possible application of learning curves (learning coefficients)• Consistency with general schedule

– Justification of elementary/unit costs, references, benchmarking• Publications• Earlier projects (CERN or elsewhere)• Industrial cost studies• When applicable, consistency check with ILC RDR

– Summary tables of material value at 3 TeV and 500 GeV• Installation through industrial contracts is part of material cost

– Uncertainties: technical, commercial– Potential for further cost reduction/mitigation

To b

e disc

ussed