STAFF RE PO RT - AC Transit Clipper 2.pdfSRI 7-265 Attachment I Agenda Item 4a Bay Area Metro Center...
Transcript of STAFF RE PO RT - AC Transit Clipper 2.pdfSRI 7-265 Attachment I Agenda Item 4a Bay Area Metro Center...
Report No:Meeting Date
SR 17-265
October 25, 2017
Alameda-Contra Costa Transit District
STAFF RE PO RTTO:
FROM:
SUBJECT
AC Transit Board of Directors
Michael A. Hursh, General Manager
Clipper Next Generation (C2) Status Update
BRIEFING ITEM
RECOMMENDED ACTION(S)
Consider receiving a semi-annualstatus update on the next generation of Clipper(C2)
BACKGROUND/RATIONALE
Since the last status update on the Clipper C2 project in April 2017, significant progress hasmade in the C2 System Integrator solicitation process. Metropolitan Transportation
Commission (MTC) released the C2 System Integrator Request for Proposals (RFP) on itswebsite on September 13, 20].7. The issuance of a 626-page RFP document is a majormilestone, AC Transit technical staff contributes significantly in the system specificationdevelopment and technicalarchitecture review of the next generation system.
Attachment I shows the MTC Memorandum dated September 13, 2017 on Next-GenerationClippers (C2) System Integrator Request for Proposal (RFP) to the Clipper Executive Board(CEB). All prospective vendors must go through MTC based on the RFP. Prospective proposers
are instructed not to contact any MTC, transit operator commissioner, board member, andexecutive staff during the evaluation process. The restriction is interpreted broadly to ensurethat MTC and transit operators avoid the perception of unfair influence during the procurementnrnrpc<
Attachment 2 shows a Power Point presentation on the Clipper C2 solicitation activities and theassociated timelines.
Attachment 3 is an MTC September 2017 Monthly Clipper Program Management Report
As of late last year, it became apparent that the C2 system would likely not be fullyimp[emented before the C[contract expires in November 20].9. According]y, based on the CEBdirection, MTC has negotiated a contract amendment with Cubic Corp, which they wouldcontinue the current Clipper system operation for a minimum of two years plus three optionalyears
The next major task for the System Integrator RFP proposal review team is to carefully assessindustry responses to the RFP and score them accordingly. AC Transit Staff heavily involves inthe RFP development process and provides the technical and operational expertise to theselection team. Based on the MTC estimated project procurement timelines; the final vendorselection completes by the end of 2018 and notice to proceed approval by the Commission isestimate to occur in March 2019.
1 of 29
Report No. 17-265Page 2 of 2
BUDGETARY/FISCAL IMPACT:
There is no budgetary or fiscalimpact associated with this report
ADVANTAGES/DISADVANTAGES:
This report is being prepared to inform the Board of Directors about the Clipper C2 planningand procurement process and to serve as the basis for discussion
ALTERNATIVES ANALYSIS:
None. The District, along with other regional transit agencies, is committed to the Clippertransit fare payment card.
PRIOR RELEVANT BOARD ACTION/POLICIES:
Staff Report 17-111-- Clipper Next Generation(C2) Status Update
ATTACHMENTS
1. Next Generation Clipper (C2) System Integrator Request for Proposal Release2. Next Generation Clipper(C2) Power Point presentation3. Monthly Clipper Program Management Report of September 2017 by MTC
Approved by: Ahsan Baig, Chief Information Officer
Prepared by: Ahsan Bang, Chief Information Officer
2 of 29
SRI 7-265 Attachment IAgenda Item 4aBay Area Metro Center
375 Beale StreetSan Francisco. CA 941 05
TEL 41 5.778.6700
WEB www.mtc.ca.govCLIPPER
TO
FR:
Clippers Executive Board DATE: September 13, 2017
Carol Kuester
Next-Generation Clioper® (C2) System Integrator Request for Proposal (RFP) Release
This memorandum is to inform Board members that the C2 System Integrator RFP was released onSeptember 1 3, 20 17 on the M.!.f.niglZ$!!g, and notifications of issuance were sent to vendorsregistered with MTC. Release of this 626 page document represents a milestone that is theculmination of a collaborative effort by the region. Clippers staff would like to express gratitude toBoard members and transit agency staff who have dedicated time and resources to reaching thispoint in the C2 process.
Site Visits and Pre-Proposal Conference
Proposer visits at selected operator sites will take place from October 1 8 to 20 and are being plannedby MTC and transit operator staff. These sites will include the BART Test Lab, Caltrain SanFrancisco Station, a VTA light rail station, Embarcadero Station, the San Francisco Ferry Building,and bus yards at SFMTA, AC Transit, and VTA. A Proposers' conference is scheduled after the sitevisits on October 20th at the Bay Area Metro Center at 375 Beale Street.
Communication with Prospective Vendors
During this RFP process, all contact with prospective vendors must be through one MTC point ofcontact. Prospective proposers will be instructed not to contact or lobby any MTC or transit operatorcommissioner, board member, executive, or staff regarding the RFP or the subject matter of the RIFPduring the evaluation process. This restriction is interpreted broadly to ensure that MTC and transitoperators avoid even the perception of unfair influence during the bidding process. Theconsequences to a proposer of attempting to influence the procurement are severe, resulting in thedisqualification of the proposer from participating in the RFP. Please direct any questions aboutcommunication with vendors to Denise Rodrigues at !!ff}(Iriaues(a bavareametro.gov .
We will continue to provide the Clipper® Executive Board with updates on key developments in thisprocurement process.
arol Kuester
J:\COMMITTE\Clipper Executive Board\CEB2017\09.CEB.Sept 2017\4aC2 RFP Release.v4.docx
3 of 29
SR 17-265 Attachment 2
CLIPPER. Clipper 2 UpdateAC Transit Board MeetingOctober 25, 20 ] 7
l
We want a singlefare payment
system!
CLIPPER
l
4 of 29
SR 17-265 Attachment 2
I millionUnique Cards Used
47%Ma rket Sha re
780,000Average Weekday Ridership
$50 millionMonthly Transit
Operator Revenue
97% of customersare satisfied 3
"'h:~".
2
5 of 29
SR 17-265 Attachment 2
BUY YOUR CLIPPER CARD HERE!Use on most Bay Area public transit.
Fast convenient and pnloaded.
3
6 of 29
SR 17-265 Attachment 2
b H aHH to Bu +n Isdn b: b' +8 pi$Bct l+n bo.banishIndustry Review RFP for Clippers Regional Fae Payment System ('C21 System INegratar
s=:"u lg$-=DnaHn Ttelle9udul 7nl9patB411CofTln++l $tTq.n Odin dPe !BOaatrlrB@n#l.. lu ba.H n hdbny Rpi+tFOrg!n Bean qx Piopou HH b ' N liu GtryFZH aope4 C'QI Regd+ Mrs{ Fae PBlt11011 cleo'n IrleDH piqHl=
n fait vn peraoplrenega ra:enallrl ' 61nnfalSy RlrngU'
What's inn
Help us decideTAKE THE NEW SURVEY!
futureofclipper.com
Extensive outreach to industry and public on C2CLIPPER
4
7 of 29
SR 17-265 Attachment 2
DesignPa rtner
pdernize
iyments
MobileConne
CLIPPER
)sponsible for what? MTCContractingVendor managementAccountingCustomer education
Transit AgenciesFare policynspection and enforcementDevice maintenance
System IntegratorFare collection/processingOperationsSecurityDistributionCustomer serviceAccount managementSupport other vendors
CLIPPER.
5
8 of 29
SR 17-265 Attachment 2
Procurement Timeline
\
Jan 201 8LSept 2017 HProposalRFP DeadlineReleased
\
Best and P'
Final Offer
Mar 201 9CommissionApprovesAward
Notice toProceed
9 of 29
September 201 7
I able ot contents
Projects and Progress
System Performance
System ImplementationValue Distribution
Customer Education
financial Information
Contractor Performance
l
3
8
11
14
15
17SRI 7-265 Attachment 3
SR 17-265Attachment 3
10 of 29
Clippers Update October 1 1, 201 7
Projects and Progress happy to support the launch in a variety of ways,including 34 outreach events in 10 days where wegave away 2,125 adult Clipper cards, distributed441 senior cards and provided assistance to morethan 6,000 SMART customers. We havecontinued to coordinate on customer service
issues and are also supporting connecting busagencies, who are experiencing an increaseddemand for senior cards. We've also directed
Cubic to develop some new reports to helpSMART better monitor and manage Clipper farecollection on the new service.
A Message from Carol KuesterDirector, MTC Electronic PaymentsOne big piece of news was release of the requestfor proposals (RFP) for the Clipper NextGeneration System Integrator in mid September.The deadline for proposals is in mid-January, sowe wil! have our work cut out for us to conduct allMe tasks related to selection of a contractor. If
you or anyone at your agency receives questionsabout the RFP, please refer them to MTCContracts Officer Denise Rodriguez [email protected].
In the meantime, we continue to seek feedback
from customers and stakeholders. We began adual survey of C]ipper customers as we]] as transitriders who choose not to use Clipper; the formeris a biennial survey to monitor how we're doing,and the latter is to glean better understanding ofthe barriers to Clipper use. We anticipate both ofthese surveys wiH inform current operations asweU as C2 development plans. We aresupplementing these survey's with stakeholderinterviews in the 6lelds of accessibility and socialservices as weU as employers who utilize varioustransit beneHlt programs.
We are keeping other expansion programsmoving, including the BART extension stations,the SFMTA Central Subway, AC Transit's BusRapid Transit (BR'l) service and the TransbayTerminal Transit Center. We also are glad to seeanother long-awaited project driver consoleintegration for AC Transit -- near completion, withinstallation complete and sofnvare scheduled fordep[oyment in early 201 8. This work wi]] benefitother transit agencies that want similar integrationwhen funding is available.
Speaking of integration, we are thrilled that BARTstarted to retrofit at least one ticket machine in
every station to dispense adult Clipper cards, so allBART riders wiU now have easier access to
Clipper. They plan to complete this integrationproject by late November. Combining in-stationcard access with the 50-cent per-ride surcharge onpaper tickets going into effect January 1, weexpect to welcome many more BART riders to theranks of Clipper customers. We're coordinatingclosely with BART staff on a number of outreachevents to ensure that the card fee is not a barrier
to adopting Clipper, while at the same timeexpanding our program for community-basedprograms serving low income individuals.
You might notice that transaction volumesincreased significandy in August (see Table I).While we at:tribute part of this increase to the endof summer and return to regu]ar travel patterns,we also have various institutional programsincluding college-based passes like the new GatorPass -- to thank for this resurgence in Clipper use.
If you have any other questions, please contactyour Clipper liaison here at MTC. You can alsoreach me at 41 5.778.5253 or
ckuester(@bayareamtro.gov.
BE READY TORIDE SMART!We can help you get an adult or $eQiu' Clipper card Bild add value.
SONORA COUNTY NRPORT STAND Sat\Kday. Sept 2
SANA ROSA NORTH STATION
Sami Rosa DowawH STATION Sep r2ROHHERT PARK STITIOh SunaaK Seplembn 3
CQTATI NATION September 3
DOWNTOWN gAnOH Septemba ' 3
STHIONATO 9 a
ON STAnch
CIRC CEnER SmnOI Sep r2N R#AEL STATIDH 9Septefv6er 2
In other news, August saw the culmination ofmany expansion and enhancement pro)ects, notleast of which was the launch of SMART's fare
service with half-price fares. After Labor Day,SMART fares increased to fuU price. We were
l
SRI 7-265 Attachment 311 of 29
October 1 1 , 201 7
Table 1: Summary of System Usage
Transaction Volume
AverageWeekday BI H 783,66011 741,395Ridership '
fee-Generating ll 22,030,10711 20,228,348Transactions'
UniqueCardsUsed ll 1,004,613i 945,849
ActiveCardAccounts ll 2,003,71011 1,954,365
Settled Transit IH $49,921,703 ll $46,194,479Operator Revenue
Autoload Activity
Percent of RegisteredCards with Autoload
Call Volume
Customer Service
Representative (CSRICalls
CS Calls per UniqueCard Used
Website Traffic
Unique Visitors --Standard
Unique Visitors --Mobile
Website Visits --Standard
Website Visits - Mobile
Website Visits perUnique Card Used
Notes on System Usage:Transaction volumes increased, xx'high is typical of the August-September dme frame, likely boosted by the number ofinstitutional pass programs at colleges and universities (such as the new Gator Pass). August was the first month withmore than I million unique cards used and more than 2 million active card accounts.
I Includes average daily number of boardings, including transfers but excluding some Caltrain monthly pass trips(Caltrain only requires monthly passcustomers to tag their cards once at the beginning of each month)2 Includes single-tag fare payments, BART and Caltrain exits, Golden Gate Transit entries, add-value transactions, opt-out purse refunds and pass use,including institutional passes. Docs not include transfers or transactions where fee value is SO(e.g., issuance of free cards, zero value tags in dual-tagsl'stems, etc.).
l0.4%28,262 28,737 1.7% 25.611
l
2
5.7% EI 794,451
8.9% ll 22,307,704
s.29 ll 950,453
2.5s ll i,825,293
8.1a%a ll $48,740,858
.1.4%
.1.2%
5.7%
%
2.4%
30% 30% 31%
0.03 0.03 0.03
150,8S2
89,101
218,028
152,558
0.37
33,3S0
76,374
189,717
128,507
0.34
t3.lsll 166,065
16.79 ll 80,622
14.9% ll 237,967
18.7%ll 135,140
0.39
.9.2%
l0.5%
.8.4%
SRI 7-265 Attachment 312 of 29
October 1 1 , 201 7
System Performance
Figure 1 : Transactions3
25,ooo,ooo
z3,ooo,ooo
21/000/000zo-milliontransactionbenchmark
z9.ooo.ooo
i7.ooo,ooo
z5,ooo,oooAua-aK Nov-zK Feb-z6 May-z6 Aug-z6 Nov-a6 Feb-a7 May-a7 Aug-a7
Figure 2: Number of Active Cards4 in Circulation per Month
= Unregistered Cards= Registered Cards
Reg. Active Cards as a % ofTotaIActive Cards
2/5oo,ooo 100%
a>
<0a
.QE3Z
2.000,00075% g
aJ
aJa£aJ
aJa.
z,5oo,ooo5o%
25%
I,ooo,ooo
5oo,ooo
0 In:n:n:n.n:n:n:n:n:nlB:n.n;n:n:rtx:n:xtxtxtxtrtxfxJ 0%Aug-z5 Dec-a5 Apr-i6 Aug-z6 Dec-z6 Apr-a7 Aug-a7
Month Ending
3 ''Clipper Total" is fare-paJ'ment and add-value transactions that count toward the 20 million-transaction contract benchmark. Sudden fluctuationsmay be attributable to the number of days in a given month.4 Active cards are those that have been used at least once within the last 12 months.
3
SRI 7-265 Attachment 313 of 29
October 1 1 , 201 7
Table 2: Monthly Market Penetration Rates
Clipper Market Penetration Rate
AC Transit
BARTs
Caitrain7
Golden Gate Ferry
Golden Gate Transit
Muni
SamTrans
San Francisco Bay FerryVTA
Napa Solano Groupe
City Coach
FAST
SoITrans
VINE
East Bay Groupe
County Connection
Tri Delta Transit
WestCAT
Wheels
Sonoma/IOI GroupPetaluma Transit
Santa Rosa CityBus
Sonoma Co. Transit
Union City Transit
1,950,264
6,504,643
953,998
249,036
199,824
8,548,560
374,710
144,190
1,410,974
42.3%
6S.9%
63.2%
88.S%
44.3%
42.3%
30.6%
44.7%
43.1%
42.3%
67.4%
56.4%
90.9%
48.5%
44.6%
37.6%
51.8%
43.8%
4S.0%
67.0%
55.7%
92.1%
49.2%
43.6%
38.7%
54.4%
44.8%
41 285
282
205
016
782
404
844
266
469
825
121
923
452
746
799
13
l
19
18
2
21
19
16
34
16
3
3
3
2
19
3%
2%
1%
4%
5%
5%
7%
9%
8%
9%
2%
7%
5%
7%
3%
12
l
19
16
3
21
18
17
34
17
3
3
3
3
19
9%
o%
3%
6%
1%
3%
9%
5%
o%
o%
2%
4%
2%
3%
7%
12
0
17
16
2
20
18
17
35
14
3
2
3
3
0
1%
8%
9%
4%
9%
7%
8%
7%
1%
8%
2%
7%
2%
5%
o%
16
22
2
154
58
34
39
21
10
6
2
4
Figure 3: Unique Cards Usedt
1,100,000
I,ooo,ooo
9oo,ooo
8oo,ooo
7oo,ooo
6oo,ooo
5oo,oooAug
z,oo4,q
t5 Nov-z5 Feb-z6 May-a6 Aug-x6 Nov-a6 Feb-a7 May-a7 Aug-z7
5 MTC uses the National Transit Database(NTD) to calculate most market penetration rates. NTD typically has a npo month delay before ridershipdata are available.
6 Calculation of BART montHy market penetration is calculated using monthly ' BART total exits by ticket q'pe, which is equivalent to number oflinked trips per month.7 Calculation of Caltrain market penetration assumes that monthly pass holders board Caltrain 1 .75 times a dal ' per weekday. Caltrain sold 1 5,105calendar passes during the July 2017 pass vending window8 Total for this operator group includes fare payment not allocated to a specific operator.9 Unique Clipper cards used in a speciGlc month
4
SRI 7-265 Attachment 3
14 of 29
Cli p©F® Update October 1 1, 201 7
Figure 4: Average Weekday Ridership S FMTA, BART, AC Transit and VTA
e''aL®0mLaQ.Q.
SFMTA BART ACTransit ''aN4oo,ooo
3oo,ooo
\J 200.000a'0Laa :'','.'
0b
gb
88
b
£b
/b
/ #F
£# g /
d#8 f
Week Ending
Figure 5: Average Weekday Ridership SamTrans, CaltrainloGolden Gate Bus/Ferry and San Francisco Bay Ferry
SamTrans Caltrain
--Golden Gate Transit --Golden Gate Ferry
£E0maQ.Q.
a
a>
<
20,000ncisco Ba
z5,ooo
lO,ooo
5,ooo
0b
gb
8# / /
/
b
/ £F
£# g J8 £
8 fWeek Ending
ride of the month to load their passes10 Spikes in Caltrain boardings at the beginning of the month are due to Caltrain monthly pass holders' only needing to tag on and off during their first
5
SRI 7-265 Attachment 315 of 29
October 1 1 2017
Figure 6: Average Weekday Ridership FAST, VINE, SoITrans, City Coach
FAST 'VINE SoITra ns City Coach
1, 200
C
E0m
aQ.Q.
®a&
9oo
6oo
3oo
0b
?b
d#
b
£b
/b
/ £F
}g f #d g
8 fWeek Ending
Figure 7: Average Weekday Ridership East Bay and Union City Transit
County Connection lta Tra nsit WestCAT
Wheels --U don CityTransit
C
E0m
aQ.Q.
a
a>
<
3,ooo
2.5oo
2.000
z, 5oo
I,ooo
5oo
0
Fb8
# F b
/b
/ £f
g# F #d #
8 fWeek Ending
6
SRI 7-265 Attachment 316 of 29
C October 2017
figure Average Weekday Ridership - Sonoma/1 01 :orridor
PetalumaTra nsit 'Santa Rose CityBus 'Sonoma CountyTra nsit
e4oo
E0m
35o
300
a)
Q.
z5o
200
aJ
ga)2 100
Week Ending
SRI 7-265 Attachment 317 of 29
October 1 1 , 201 7
System Implementation
Table 3: Expansion and Enhancement Highlights
Description/Completion Date Status
SMART Implementation of Clipper on Cubic is creating a set of new ridership reports for SMARTSonoma-Marin Area RaiITransit that willbe deployed this month. Acceptance testing for(SMART)(Completed) the SMART system is underway and should be complete
by the end of the calendar year.
VTA Card Reader and Driver Console Installation of Clipper card readers and driver consoles onReplacement(2017) the existing \nA bus fleet is complete. Availability testing
Ticket Machine Retrofit(2018) is also complete. The next step is decommissioning theold wireless communications equipment at three VTA busmaintenance facilities. Cubic willinstallthe same Clipperequipment on 22 new VTA buses scheduled for deliverylater this yea r.MTC issued a new change notice to Cubic to furnish thecontractor retrofitting VTA ticket machines with 175 cardreader devices to vend Clipper cards.
BART Extension stations(phases) andhandheld card reader (HCR)replacement (2017)
Coordination for new AT&T T-l connections and theinstallation of HCR4 devices by Cubic at the next fourBART expansion stations is progressing in parallelwithMTC's overallupgrade of the Clipper communicationsnetwork. BART plans to begin service to two stations onits eBART line and to extend the Warm Springs/Fremontline south to two additionalstations in 2018.
Cubic has replaced about half of BART's older HCR3devices with new HCR4 devices for use by BART stationagents. Cubic willcomplete remaining installations thisfa I Ia
Regional Network Modernization
(Ongoing)AT&T is replacing older frame relay circuits with T-llinesat 121sites owned by the seven largest Clipper operatorsEach site has five phases:(1) site preparation,(2) AT&Tupgrades,(3) Cubic upgrades,(4) cutover from the old tonew circuits, and(5) decommissioning of the old circuits.AC Transit, Golden Gate Transit, VTA and SFMTA arecomplete. Cubic has completed work at llCaltrain sites.Most site preparation and AT&T work is complete for fiveSamTrans sites and 22 BART sites.
SRI 7-265 Attachment 318 of 29
October 1 1 , 201 7
Description/Completion Date Status
SFMTA Implementation of Clipper onthe Central Subway (2019)
Redeployment of ticketmachines to new TransbayTransit Center (March 2018)
Cubic and MTC attended a progress meeting with the
CentralSubway implementation team and toured theconstruction progress at the first of three stations on thenew MuniMetro line. Cubic willbegin furnishing materialfor SFMTA contractors to complete site work for Clipperequipment. The CentralSubway is slated to open to thepublic in late 2019.
SFMTA issued a purchase order to Cubic to relocate fourunderutilized ticket machines from Muni Metro stations
to the new Transbay Transit Center when it opens nextspring. The city is completing work to enable Cubic toinstallequipment next spring.
MTC and Cubic provided materialto AC Transit's BRTcontractor in advance of site preparations for Clipper cardreader installation. MTC willissue a notice to proceed toCubic next May to commence work on the installation ofthe Clipper devices, which willsupport the plannedopening of the BRT line in 2019.
Driver console integration installation is complete. Cubicwilldeploy software early in 2018.
Cubic willdecommission four AVMs at the TemporaryTransbay Terminalafter operations are shifted to thepermanent terminalnext spring
AC Transit Implementation of Clipper onnew Bus Rapid Transit (BRT)service (2018-19)
Driver Console Integration(early 2018)
Decommissioning Add ValueMachines (AVMs) fromTemporary Transbay Termina(2018)
Golden Gate Business rules simplificationTransit (July 2018)
Golden Gate Transit is adjusting transfer rules to coincidewith its next major fare change in 2018. MTC willroute achange order pending execution of a funding agreement.
In-PersonCustomerService
Centers
In-person customer servicecenter enhancements
(complete)
MTC is routing a contract change order to complete theFaneuilin-person customer service center at The Hub @375 Beale and the Embarcadero BART/Munistation.Faneuil, which operates these two centers, can now issuereplacement cards at The Hub.
SRI 7-265 Attachment 319 of 29
Cljppere Update October 1 1 , 201 7
Table 4: Software Release HighlightsDescription
Completed e
e
Fare/policy changes: Caltrain, SMART and Sonoma County Transit fare changes, disableCaltrain 8-ride sales; Sonoma County Transit route fare credit; East Bay youth agechangeOther: BART ticket machine test configuration data, display of Gator Pass and BARThigher education products on Golden Gate Ferry and SFMTA ticket machines, SMARTwebsite deployment for fullfare, elimination of Park with Clipper, Golden Gate Ferrylimited-use ticket balance inquiry, device availability update, SFMTA upload/downloadmanagement
October e
eFare/policy changes: Caltrain fare changesOther: Changes to SMART microsite, enhancements to ticket office terminals, updateto retailmap on Clipper website
November 8 Fare/policy changes: Caltrain fare changes, disable use of Caltrain 8-ridee Other: AC Transit route changes
January > Other: AC Transit route changes, deployment of driver console integration software
TBD e Fare/policy changes: BART, SFMTA and VTA fare and product changes; VTA newtransfers
e Other: BART higher education product display and cash balance on Add Fare machines;migration of Clipper Direct to JavaServer Faces(JSF), Clipper globalcalendar extension
Note: Schedule is as of September 28, 201 7; completed deployment as of October 4. Fare changes mayappear multiple times if Cubic needs to issue multiple software releases to implement a specific change. Forexample, Cubic may need to post a notice about a change, make the change to pricing for Clipper Direct onemonth later and then make the change in aU other sales channels one month after that. Each change is notedseparately.
10
SRI 7-265 Attachment 320 of 29
Value Distribution
October 1 1, 201 7
Figure 8: Clipper Sales by Channel
-'e"-Autoload and Remote Add Value '-'e'-Ticket Machin
"'e"- Reta ilers -'e''Ticket OfficesS3o,ooo,ooo
S25,ooo,ooo
$20,000,000
$l5,ooo,ooo
$10,000,000
$5,ooo,ooo
$o
Aug-z5 Nov-a5 Feb-z6 May-z6 Aug-z6 Nov-a6 Feb-a7 May-a7 Aug-z7
Figure 9: Cash and Product Sales per Month
H Prod uct Sales H Cash Value
$ 23ia87i56
'a $4o£0
g $3'aD
? $:'0n
$10
$oAug-a5 Dec-i5 Apr-z6 Aug-z6 Dec-z6 Apr-a7 Aug-a7
11
SRI 7-265 Attachment 321 of 29
October 1 1, 201 7
Table 5: Adult Pass Sales
%
Changefrom July
2017
%
Changefrom
August2016
# passesloaded
throughAutoload
% passesloaded
throughAutoload
August2017
July2017
August2016
Monthly Pass Sales
Caltrain Monthly
SamTrans Local Monthly
SamTrans Local/SF Monthly
SFMTA Muni Only MonthlySFMTA Muni "A" Fast
Monthly
VTA Standard Monthly
VTA Express MonthlySubtotal
15,129
2,512183
49,845
19,955
14,478
2,549
184
49,295
19,961
4.5%
.1.5%
.0.5%
1.1%
o.o%
14,884
2,675
219
52,473
24,788
1.6%
.6.1%
.16.4%
.5.0%
.19.5%
3,361178
13
9,518
4,020
22.2%
7.1%
7.1%
19.1%
20.2%
Other Pass Sales
5,579196
93,399
5,526185
92,178
t.o%ll 6,449
s.9%ll 222
1.3% FI lo1,710
.13.5%
.11.7%
.8.2%
275
21
17,386
4.9%
l0.7%
18.6%
].OI Corridor/Sonoma
Petaluma Transit 31-day
Santa Rosa CltyBus 31-day
Sonoma County Transit 31day
AC Transit Local 31-day
AC Transit Transbay 31-day
3,047
1,159
36,004
70,592
2,892
1,143
31,519
61,000
5.4%
1.4%
14.2%
IS.7%
3,417
1,236
36,400
70,218
.l0.8%
.6.2%
.1.1%
o.s%
397
343
33,765
61,922
13.0%
29.6%
93.8%
87.7%
7,003
268
6,841
273
2.4%
.1.8%
7,620
284
.8.1%
.5.6%
.3.2%
.5.6%
.11.6%
2,558
67
33
4
29
l196
36.5%
25.0%
BART HVD 45/48
BART HVD 60/64
Caltrain 8-Ride
East Bay Transit Group
East Bay Regional AdultLocal 31-day
East Bay Regional AdultExpress 31-day
Tri Delta Adult 31-day
WestCAT Adult 31-day
Wheels Adult 31-day
Napa Solano Group
FAST 31-day
VINE 31-day
SoITrans 31-day
City Coach 31-day
Union City Transit 31-daySubtotal
TOTAL
149
17
99
3
567
151
17
101
4
442
-1.3%
o.o%
-2.0%
.25.0%
28.3%
154
18
112
0
387
22.2%
23.5%
29.3%
33.3%
34.6%46.5%
14411 llill 29.7%lj i31EI 9.99EI 51 35.4%
24
80
281
38
25
3
17
5
11
075
047
5
68
234
24
26
413
9
5
319
892
380
17
20
58
-3
.25
30
.44
120
8
5
o%
6%
1%
3%
8%
o%
8%
4%
o%
o%
4%
12
79
165
0
15
0
7
8
0
287
417
100.0%
1.3%
70.3%
5
36
91
13
8
0
7
l0
116,642397
20
45
32
34
61
041
20
0
55
13
8%
o%
4%
2%
2%
o%
2%
o%
o%
o%
o%
66.7%
142.9%
-37.5%
212
3
196
2
221
3
.4.2%
.l0.8%
12
SRI 7-265 Attachment 322 of 29
October 1 1, 201 7
Figure 10: Order Value and Unique Patrons by Employer Program per Month= Clipper Direct muter Check Direct
= Other Third Party nique Patrons
$8,ooo,ooo 1 1 8o,ooo
$7/ooo,ooo
$6.ooo,ooo
7o,ooo
6o,oooa3
>a
''a
0
$5,ooo,ooo 5o,ooo
4o,ooo
3o,ooo
20,000
£0
Q.aJ3
eD
$4,ooo,ooo
S3,ooo,ooo
S2.000,000
$l,ooo,ooo lO,ooo
$ol
D<
d>
0Z aJ
l
E<>
0Z
h
E
0H
D<
Month
Table 6: Clipper Retail Sales, August 201 7
ii
Cash Sales
Pass Sales
Total SalesCards Sold
Includes $90,939 in card sales fees
$3,968,562
$3,715,072$7,774,574
30,313
7%
.11%
.3%
3%
Table 7: Clipper Retail Locations and Sales by County, August 201 7
Alameda
Contra CostaMarin
NapaSan FranciscoSan MateoSanta ClaraSolano
SonomaTotalTotal sales numbers
60
34
14
3
97
$1,003
$71
$7
$4,714
$650
$886
$41
$7,774
in August.
335742
189
961
428
514
068
580
756
574
$16$7
$5
$2
$48
$20
$18
$n$3
$25
722875
085
654
602
329
460
511
480
324
32
48
7
12
307
totaling $90,939include card sales fees,
13
SRI 7-265 Attachment 323 of 29
October 1 1, 201 7
Customer Education
C2 Public Engagement: We are continuing analysis of the opt-in input survey while at the same timeconducting stakeholder research. We began administration of our cash customer survey and Clipper customersurvey in late September; interviews wiH continue through early November. Thanks to aU the transit operatorsfor their help conducting the surveys on their properties.
Other activities include:
e Coordinating with BART on their fare change communications campaign,e Improving opt-in options for registered Clipper cardholders,e Exploring website improvements;
e Developing a transit agency-accessible archive of past campaigns, and
e Testing campaign strategies for 6isca] year 2017-1 8.
See Table 8 for a schedule of activities
Table 8: Customer Education Activities, August 201 7-January 2018August September October November December January
e
=aJ>
'u
<
SMART iau nch SMART lau nch
Developmentof FY 20].7-18
campaign
a)
=
0
SMARToutreach
C2 survey
a nalysis
Sta keholderinterviews
Prepare C2reportCa
Ea
C
=
a.
Conduct cash
customer and
Clippercustomer
surveys
Pla nning forcash customer
and Clippercustomer
surveys
0e
E0U
=
}0a.
BART fa re
cha nge/ca rddispensing
Fare policychanges
Website
improvements
14
SRI 7-265 Attachment 3
24 of 29
October 1 1, 201 7
Financial Information
Figure 11: Revenue by Operator, August 201 7
,:,.7*.*57j'84.9 :ll-?'s"; l;.:.il:,,,,..':',:9' H SFMTA (Muni)
H BART
sgz6,335 l-:''. \~*~>\ I ..::.::::===.=i.....-- $6, a75 H Caltrain
S2,056,355 ---.:.l:n ll' .. E BACTransit
S2,544.284 .ii4f bL'i!® H b H Golden Gate Ferry[-] VTA
Golden Gate Tra nsit
SamTrans
$a6.z7o,725 H SF Bay Ferry
H Napa Solano
H East Bay
H SFMTA Parking
n Sonoma/zoz
H U don City
$ao,887,ao7
Table 9: Revenue by Operator Per Month, Previous Six Months
l$25,960,216 $23,741,909i $25,320,368 $25,021,185; $23,210,664
$10,664,574 $10,331,625 $10,299,964 $10,701,098@ $10,778,385
$4,248,5891: $4,23s,s6si $4,458,499 $4,144,057: $4,455,222
sz,449,4021 $2,184,348 $2,307,742W $2,226,950 $2,226,950
sl,so1,226E $1,518,9741 $1,610,910 st,884,28ql $2,029,888
H Lelilq I(eldBART
SFMTA (Munn
Caltrain
AC Transit
Golden Gate
ferryVTA
Golden Gate:Tra nsitSamTrans
SF Bay Ferry
Napa Solano
East Bay Group
Sonoma/IOI
SFMTA Parking
Union CityTotal MonthlyRevenue
$26,170,725
$10,887,107
$4,304,705
$2,544,284
$2,056,355
$928,613
$1,034,327
$921,192
$890,627
$965,243
$982,570
$830,518
$963,011
$922,813
$922,993
$916,335
$1,078,857
$517,224
$817,091
$151,886
$238,241
$4,738
$7,061
$o
$48,523,188
$507,363
$745,537
$129,649
$205,763
$9,079
$10,363
$3,406$45,435,398
$511,729
$848,623
$143,764
$235,475
$10,235
$12,750
$5,152$47,713,022
$430,246
$881,935
$139,115
$205,144
$9,448
$13,725
$S,079
$47,45S,800
$441,608
$843,951
$138,769
$193,964
$8,403
$11,185
$4,791$46,189,586
$484,930
$944,436
$159,003
$243,750
$10,290
$10,261
$6,175$49,817,214
15
SRI 7-265 Attachment 325 of 29
October 1 1, 201 7
Table 10: Bank Account Balances, Previous 12 Months
September 2016
October 2016
November 2016
December 2016
$52
$53
$53
$53
$54
$56
$57
$58
$58
$58
$60
$61
643,941
500,860
824,318
652,332
$784
$1,002
$1,229
$1,317
$1,565
$397
$615
$832
252
669
620
392
January 2017
February 2017
March 2017
April 2017
May 2017
June 2017
July 2017
August 2017
768,751;
958,432
889,590
20S,062
407,332
698,828
453,019
388,981
819
644
289
156
158
895
996
022
Table 1 1 : Refunds by Operator
Agency
101 Corridor Group
AC Tra nsit
BART
Caltrain
East Bay Group
Golden Gate Ferry
Golden Gate Transit
Napa/Solano Group
SamTrans
San Francisco Bay Ferry
SFMTA
SMART
Sonoma County Transit
\nA
Total
l69
130
025
3
11
126
2
11
37
644
29
4
19
111
$1,071
$5,271
$11,913
$61
$551
$3
$285
$252
$13,211
$7
$33,301
l
2
11 The reason for drops in the Float Account is delayed payment from retailers, particularly ' W/algreens, at the cnd of the month.12 Drops in the PCF balance are due to operator distributions concurrent with their recurring bad debt adjustment
SRI 7-265 Attachment 316
26 of 29
Clippers Uodate October 1 1 , 201 7
Clipper Contractor Perf ormance
Table 11: Cubic Cardholder Support Perf ormance. August 1-31, 201 7
13 IVR: Interactive voice response, also referred to as the Clipper automated phone system14 ACD: Automated CaU Distributor, the sl'stem that routes calls to customer service representatives
17
SRI 7-265 Attachment 3
l
2
3
27 of 29
Cliooere Uodate October 1 1 , 201 7
Table 12: Cubic Device and System Perf ormance. June August 201 7
The above key performance measures were developed to monitor and evaluate the performance of variousdevices and overall sl'stem functions. For example, accuracy performance is measured by the percentage of allcard transactions received and processed by the central system by type of device. The objective is to measurethe ability of the system to transmit all field transactions to the central system. For de6lnitions of satisfactory(green), marginal (yellow) and unsatisfactory (red) performance levels for all of the categories above, seehttp://mtcmedia.s3.amazonaws.com/fines/Device.andSystem rformance.Level.Rating.Scale.pdf.
15 Contract-based performance levels are basedreported after the 1" increase the accuracy rate.16 ibis KPI was missed due to a fault(corrupt ti
hours of the problem being reported.
these figures, which are based on data :oorted as of the ]" of the month. Additional transactions
=tion batch) in the online server on ogle day. End-of-day successfuU}' completed within 12
18
SRI 7-265 Attachment 3
Monthly KPls
Accuracy Performance
CIDs Accuracy By Transaction CountlS
AVMs Accuracy By Transaction Count
TOTS Accuracy By Transaction Count
Device Reliability
CIDIA Reliability
CIDIB Reliability
CID2A Reliability
AVM Reliability
HCR3 Reliability
28 of 29
A4ETRO P OLITAN
TRANS PO RTATI O N
C OA{MISS ION.IVI T
Bay Area Metro Center375 Beale Street. Suite 800San Francisco, CA 941 05
Clippers Program Management ReportPublished monthly
Executive Director:Steve Heminger
Deputy Executive Directors:Alix Bockelman, PolicyAndrew Fremier; Operations
Director, Electronic Payments:Carol Kuester
Clippers Project Principals:Lynn ValdiviaJason Weinstein
Managing Editor: Lysa Hale
Data Editor: hopi Purohit
Cover Design and Layout: MTC Graphics SRI 7-265 Attachment 329 of 29