Variable Stars and Their Light Curves Arne Henden Director, AAVSO [email protected].
Stability and Failure Mechanisms of Dams A dam safety research project Kjetil Arne Vaskinn.
-
Upload
martha-pascal -
Category
Documents
-
view
231 -
download
3
Transcript of Stability and Failure Mechanisms of Dams A dam safety research project Kjetil Arne Vaskinn.
Stability and Failure Mechanisms of Dams
A dam safety research project
Kjetil Arne Vaskinn
During the latest year there have been a strong focus on dam safety. This has been reflected by:
• several reassessments of dam safety• new dam safety regulations• introduction of risk analysis• dam-break flood routing • etc.
Background
Reassessment:
Uncertainty and discussion about the dam regarding the demand of:
• Stability • Slide or erosion during large throughflow• Drainage capacity
The cost of rehabilitation is several millions of NOK at each dam
Simulation of flood propagation resultingfrom dam-break
Breach development:
Size of the breach as a function of time
Teton Teton
Increase the knowledge about:
• Safety of the downstream shell in Norwegian dams during large throughflow. • Breach formation in embankment and concrete dams.
The results shall be user-friendly, so that it can easily be used in the damowners safety work:
• Design tool• Design criteria• Simplified point of view
Results are hoped to become a base for new “accept criteria".
Aim of the project
Subproject no. 1: Shear strength and permability of rock-fillings
• Find shear strength and stability of different embankment material• Find correct material parameters • Find realistic analyse methods
Project manager: Kaare Høeg, NGI
• Literature study • Discussions with international experts • Summarize experiences from dams• Evaluation of earlier tests and calculations• Field tests
Subproject no. 2: Stability and failure
mechanisms of dams
Develop tools/routines for evaluating the stability based on tests and international experiences from similar topics.
Project manager: Einar Ødemark, Statkraft Grøner AS
Piping
Damtoe
Support fillingWater tight core
Filter
Overtopping Subproject status:
• Field tests, carried out/new are planned• Laboratory tests, carried out/new are planned• Data reports, nearly finished• Analysis, ongoing
Parameters that are studied:•Particle size•Grading of the material•Downstream slope•Tailwater level•Scale effects
Subproject no. 3: Breach formation in embankments
Study the failure mechanisms of rockfill dams using tests and data from earlier failures.
Develop methods for breach analysis. Design and layers of the dam should be included.
Project manager: Einar Ødemark, Statkraft Grøner AS
Subproject status:• Literature study• Field tests • Field- and laboratory tests from subproject no. 2 and IMPACT
Subproject no. 4: Breach formation in concrete dams
Study the failure mechanisms of different kind of concrete dams using Finite Element Method.
Project manager: Per Magnus Johansen, Norconsult
Subproject status:• Initial phase• Literature study planned and started? • •
Laboratory model – 0.6 m high dam
1:31:1.5
1:1
Water-level measurement
1:1.5
1.8 meter0.40.90.7
QutQinn
0.5 m
0.5 m
1.2 m
Laboratory model - scale 1:10
Downstream slope: 1:1.5Tailwater level: LowUniformly graded materiald10 = 5 mm d50 = 11 mm
Smallest particle size tested in this flume
Downstream slope: 1:1.5Tailwater level: LowUniformly graded materiald10 = 78 mm d50 = 100 mm
Largest particle size tested in this flume
s
Filt
er
1.20
1.20
1.60
1:3
Qm
ax =
60
0 l/s
1.0 3.6 meter
4.00
Qut
Water-level measurement
1:1
1:1
1.8 3.6
Laboratory model – 1.2 m high dam
Test-flume scale 1:5
Downstream slope: 1:1.5Tailwater level: LowUniformly graded materiald10 = 66 mm d50 = 88 mm
Project scheme, 2002
Finalise data reports from the tests in 2001
Analysis based on tests and literature
Field tests
Laboratory tests
Literature studies
Workshop