SSI Project Profile

2
Project Profles  April 2009 © 2008 ShipConstructor Software Inc. All Rights Reserved. ShipConstructor is a registered trademark of ShipConstructo r Software Inc.  www.ShipConstructor.com Synthetic Diesel Fuel Production Facility Designer Ship Architects Inc., USA Project Chemical Plant Project Highlights ShipConstructor, well-known for its eciency and quality for ships and oshore projects, has now proven its capabilities on the successful completion of the rst land-based chemical plant project. Cello Energy produces synthetic diesel fuel by using waste wood, hay, straw, paper, plastic and tires within a reactor system. The plant is sized to produce 20 mil lion gallons of synthetic diesel per year. Cello Energy and the local community government are planning to divert city solid waste to the Cello Energy facility, to save landll space, reduce transportation costs for the city and provide raw materials for the diesel production, creating a “win-win” situation. ShipConstructor was chosen by Ship Architects Inc., Alabama, to prepare a detailed 3D piping model for the process part of the plant. The intent was to develop a process plant that requires very small volume for proper operation. The owner, a former US Navy ocer and Chief Engineer, said, “I want an ecient “engine room” layout that is functional, easy to operate and very easy to maintain.” To complete the ShipConstructor piping and equipment model, CAD drawings from the building manufacturer containing wire ways and structure were included. Navisworks was then used to check for interferences and to communicate with the owner on operational requirements and maintenance envelopes. The deliverables included 3D model drawings, arrangement drawings, as well as pipe spool drawings for pre-fabrication. Cello Energy intends to build additional plants, with future plant systems to be skid mounted and installed on sites with minimal local fabrication required. There a re more than 200 valves in the system covering approximately 4800 square feet of process area. As the rst production plant operates, the model will be corrected to as-built conditions and process improvements will be incorporated. The following plants site plans and support systems will be developed using the updated product model information. The ShipConstructor 3D Product Information Model with the incorporated database together with the integration with Autodesk products such as Navisworks and Inventor provides essential functions to make this optimization process throughout the life cycle a simple process. Suezmax Tankers Shipbuilder Estaleiro Atlântico Sul (EAS) Brazil Project Ten Suezmax Tankers Project Highlights Construction of the EAS Shipyard on Brazil’s east coast began in mid-2007 and will be the largest shipyard in the southern hemisphere. Upon completion it will have a d rydock measuring 400 metres long and 73 metres wide and have a ship production capacity of 160,000 tons. The shipyard is expected to be completed  by September 2009 but EAS has already received orders to design and build ten Suezmax tankers. The Suezmax vessels are part of a batch of 26 ships to be built in the rst phase of the Programme of Modernization and expansion of the eet of Transpetro, a subsidiary of Petrobras. ShipConstructor 2008 was chosen to design the Suezmax tankers and platform aer extensive reviewing and testing by Sincronia, a Brazilian IT consultant and integrator for the oshore and shipbuilding sectors. Sirconia found Sh ipConstructor to b e the clear leader in t erms of exibility , customer support, pricing and its ability to meet the cuing-edge technology requirements of EAS. As well, ShipConstructor is easily learned which expedites a fully operational 3D CAD/Cam engineering environment to meet project demands and production schedules. Project Split and Merge (PS&M) is another ShipConstructor innovation which is being used by EAS. PS&M enables EAS to optimize utilization of their workforce by allowing work on a single project to be split and delegated to designers in dierent locations while maintaining the regularly updated master project. By using Project Split and Merge EAS will increase eciency and reduce or eliminate costly production delays. 3D model of a chemical plant design Image courtesy Cello Energy LLC, Alabama, USA  A Suezmax tanker in port 

Transcript of SSI Project Profile

Page 1: SSI Project Profile

8/3/2019 SSI Project Profile

http://slidepdf.com/reader/full/ssi-project-profile 1/2

Project Profles

 April 2009 © 2008 ShipConstructor Software Inc. All Rights Reserved. ShipConstructor is a registered trademark of ShipConstructor Software Inc.  www.ShipConstructor.co

Synthetic Diesel Fuel Production Facility

DesignerShip Architects Inc., USA

ProjectChemical Plant

Project HighlightsShipConstructor, well-known for its eciency and quality for

ships and oshore projects, has now proven its capabilities onthe successful completion of the rst land-based chemical plantproject. Cello Energy produces synthetic diesel fuel by using wastewood, hay, straw, paper, plastic and tires within a reactor system.The plant is sized to produce 20 million gallons of synthetic dieselper year.

Cello Energy and the local community government are planningto divert city solid waste to the Cello Energy facility, to savelandll space, reduce transportation costs for the city and provideraw materials for the diesel production, creating a “win-win”situation.

ShipConstructor was chosen by Ship Architects Inc., Alabama,to prepare a detailed 3D piping model for the process part of theplant. The intent was to develop a process plant that requires verysmall volume for proper operation. The owner, a former US Navyocer and Chief Engineer, said, “I want an ecient “engine room”layout that is functional, easy to operate and very easy to maintain.”To complete the ShipConstructor piping and equipment model,CAD drawings from the building manufacturer containing wireways and structure were included. Navisworks was then usedto check for interferences and to communicate with the owneron operational requirements and maintenance envelopes. Thedeliverables included 3D model drawings, arrangement drawings,as well as pipe spool drawings for pre-fabrication.

Cello Energy intends to build additional plants, with futureplant systems to be skid mounted and installed on sites withminimal local fabrication required. There are more than 200 valvesin the system covering approximately 4800 square feet of processarea. As the rst production plant operates, the model will becorrected to as-built conditions and process improvements will beincorporated. The following plants site plans and support systemswill be developed using the updated product model information.

The ShipConstructor 3D Product Information Model with theincorporated database together with the integration with Autodeskproducts such as Navisworks and Inventor provides essentialfunctions to make this optimization process throughout the lifecycle a simple process.

Suezmax Tankers

ShipbuilderEstaleiro Atlântico Sul (EAS) Brazil

ProjectTen Suezmax Tankers

Project HighlightsConstruction of the EAS Shipyard on Brazil’s east coast began

in mid-2007 and will be the largest shipyard in the southernhemisphere. Upon completion it will have a drydock measuring400 metres long and 73 metres wide and have a ship productioncapacity of 160,000 tons. The shipyard is expected to be completed

 by September 2009 but EAS has already received orders to design

and build ten Suezmax tankers.

The Suezmax vessels are part of a batch of 26 ships to be built inthe rst phase of the Programme of Modernization and expansionof the eet of Transpetro, a subsidiary of Petrobras.

ShipConstructor 2008 was chosen to design the Suezmaxtankers and platform aer extensive reviewing and testing bySincronia, a Brazilian IT consultant and integrator for the oshoreand shipbuilding sectors. Sirconia found ShipConstructor to bethe clear leader in terms of exibility, customer support, pricingand its ability to meet the cuing-edge technology requirements oEAS. As well, ShipConstructor is easily learned which expedites afully operational 3D CAD/Cam engineering environment to meeproject demands and production schedules.

Project Split and Merge (PS&M) is another ShipConstructorinnovation which is being used by EAS. PS&M enables EAS tooptimize utilization of their workforce by allowing work on asingle project to be split and delegated to designers in dierenlocations while maintaining the regularly updated master projectBy using Project Split and Merge EAS will increase eciency andreduce or eliminate costly production delays.

3D model of a chemical plant design Image courtesy Cello Energy LLC, Alabama, USA

 A Suezmax tanker in port 

Page 2: SSI Project Profile

8/3/2019 SSI Project Profile

http://slidepdf.com/reader/full/ssi-project-profile 2/2

Project Profles

 April 2009 © 2008 ShipConstructor Software Inc. All Rights Reserved. ShipConstructor is a registered trademark of ShipConstructor Software Inc.  www.ShipConstructor.co

Super M2 Jack-Up Rig

ShipbuilderMaritime Industrial Services Co. Ltd. (MIS) Engineering,

Sharjah, United Arab Emirates

ProjectSixteen new-build jack-up rigs

Project HighlightsConstruction of MIS’s third Super M-2 rig began with the hull

components being cut on the CNC machines using the directinterface with ShipConstructor. The entire 3D product modelwas successfully developed using ShipConstructor 3D modelingsoware. The changeover to the new soware was so smooththat MIS was able to start the steel cuing one month ahead ofschedule. Following the steel cuing, the keel for the Hull waslaid, once again ahead of contract schedule.

The capability to directly provide CNC information to theautomatic cuing machines is a signicant step toward thedevelopment of a truly ecient shipyard. Integrating all aspects ofproduction engineering in a single clash-free 3D ShipConstructor

environment drastically reduces the design process enabling platenesting and component prefabrication to begin earlier.

The increased productivity on the new-build jack-up rigprogram at MIS is testimony to the eectiveness, eciency andvalue of using the ShipConstructor suite for shipbuilding projects.

P-55 Semi-submersible Platform

ShipbuilderEstaleiro Atlântico Sul (EAS) Brazil

ProjectHull construction for a P-55 semi-submersible productionplatform

Project HighlightsConstruction of the EAS Shipyard on Brazil’s east coast began

in mid-2007 and will be the largest shipyard in the southernhemisphere. Upon completion it will have a drydock measuring400 metres long and 73 metres wide and have a ship productioncapacity of 160,000 tons. The shipyard is expected to be completed

 by September 2009 but EAS has already received orders to designthe Hull for a p-55 semi-submersible production platform.

The P-55 semi-sub production platform being built for Petrobrashas a production capacity of 180,000 barrels per day, and is destinedto be anchored at the Roncador eld at a depth of 1,790m, locatedwithin the Bacia de Campos. The P-55 hull construction alone wilconsume 21,000 tons of steel.

ShipConstructor 2008 was chosen to design the platformaer extensive reviewing and testing by Sincronia, a BrazilianIT consultant and integrator for the oshore and shipbuildingsectors. Sirconia found ShipConstructor to be the clear leaderin terms of exibility, customer support, pricing and its abilityto meet the cuing-edge technology requirements of EAS. Aswell, ShipConstructor is easily learned which expedites a fully

operational 3D CAD/Cam engineering environment to meetproject demands and production schedules.

Project Split and Merge (PS&M) is another ShipConstructorinnovation which is being used by EAS. PS&M enables EAS tooptimize utilization of their workforce by allowing work on asingle project to be split and delegated to designers in dierenlocations while maintaining the regularly updated master projectBy using Project Split and Merge EAS will increase eciency andreduce or eliminate costly production delays.

Example of a semi-submersible production platform

Super M2 jac k-up rig Image cour tesy Maritime Ind ustrial Ser vices Co. Ltd. (MIS) Engineering