SP00060_RR_BNSF (2015 Specifications: 01-0804-23-15) (This Section requires SP00170.) (Use this when Burlington Northern Santa Fe Railway is within project limits. The included requirements and exhibits are for information and reference only. Do not make any modifications to this document.) BURLINGTON NORTHERN SANTA FE RAILWAY COMPANY Exhibit C: Contractor Requirements Exhibit C-1 Overpass Exhibit C-1 The following Burlington Northern Santa Fe Railway exhibits are included in this project for information and reference only. The actual Exhibit C: Contractor Requirements, and Exhibit C-1, and Overpass Exhibit C-1 will be provided and executed by the Burlington Northern Santa Fe Railway Company. The Contractor shall obtain all necessary permits and licenses and pay all fees and obtain a fully executed copy of the railway agreement according to 00170.01(e). In addition, when railroad flagger services are required, the Agency will pay for the services according to 00170.01(e).

Transcript of SP00060 RR BNSF (2015 Specifications: 01-0804-23-15) · PDF file ·...

Page 1: SP00060 RR BNSF (2015 Specifications: 01-0804-23-15) · PDF file · 2016-12-281.01.01 The Contractor must cooperate with BNSF RAIL ... ing, not included in the contract plans and

SP00060_RR_BNSF (2015 Specifications: 01-0804-23-15) (This Section requires SP00170.)

(Use this when Burlington Northern Santa Fe Railway is within project limits. The included requirements and exhibits are for information and reference only. Do not make any modifications to this document.)

BURLINGTON NORTHERN SANTA FE RAILWAY COMPANY

Exhibit C: Contractor Requirements Exhibit C-1

Overpass Exhibit C-1 The following Burlington Northern Santa Fe Railway exhibits are included in this project for information and reference only. The actual Exhibit C: Contractor Requirements, and Exhibit C-1, and Overpass Exhibit C-1 will be provided and executed by the Burlington Northern Santa Fe Railway Company. The Contractor shall obtain all necessary permits and licenses and pay all fees and obtain a fully executed copy of the railway agreement according to 00170.01(e). In addition, when railroad flagger services are required, the Agency will pay for the services according to 00170.01(e).

Page 2: SP00060 RR BNSF (2015 Specifications: 01-0804-23-15) · PDF file · 2016-12-281.01.01 The Contractor must cooperate with BNSF RAIL ... ing, not included in the contract plans and
Page 3: SP00060 RR BNSF (2015 Specifications: 01-0804-23-15) · PDF file · 2016-12-281.01.01 The Contractor must cooperate with BNSF RAIL ... ing, not included in the contract plans and
Page 4: SP00060 RR BNSF (2015 Specifications: 01-0804-23-15) · PDF file · 2016-12-281.01.01 The Contractor must cooperate with BNSF RAIL ... ing, not included in the contract plans and
Page 5: SP00060 RR BNSF (2015 Specifications: 01-0804-23-15) · PDF file · 2016-12-281.01.01 The Contractor must cooperate with BNSF RAIL ... ing, not included in the contract plans and
Page 6: SP00060 RR BNSF (2015 Specifications: 01-0804-23-15) · PDF file · 2016-12-281.01.01 The Contractor must cooperate with BNSF RAIL ... ing, not included in the contract plans and
Page 7: SP00060 RR BNSF (2015 Specifications: 01-0804-23-15) · PDF file · 2016-12-281.01.01 The Contractor must cooperate with BNSF RAIL ... ing, not included in the contract plans and
Page 8: SP00060 RR BNSF (2015 Specifications: 01-0804-23-15) · PDF file · 2016-12-281.01.01 The Contractor must cooperate with BNSF RAIL ... ing, not included in the contract plans and
Page 9: SP00060 RR BNSF (2015 Specifications: 01-0804-23-15) · PDF file · 2016-12-281.01.01 The Contractor must cooperate with BNSF RAIL ... ing, not included in the contract plans and
Page 10: SP00060 RR BNSF (2015 Specifications: 01-0804-23-15) · PDF file · 2016-12-281.01.01 The Contractor must cooperate with BNSF RAIL ... ing, not included in the contract plans and
Page 11: SP00060 RR BNSF (2015 Specifications: 01-0804-23-15) · PDF file · 2016-12-281.01.01 The Contractor must cooperate with BNSF RAIL ... ing, not included in the contract plans and
Page 12: SP00060 RR BNSF (2015 Specifications: 01-0804-23-15) · PDF file · 2016-12-281.01.01 The Contractor must cooperate with BNSF RAIL ... ing, not included in the contract plans and
Page 13: SP00060 RR BNSF (2015 Specifications: 01-0804-23-15) · PDF file · 2016-12-281.01.01 The Contractor must cooperate with BNSF RAIL ... ing, not included in the contract plans and
Page 14: SP00060 RR BNSF (2015 Specifications: 01-0804-23-15) · PDF file · 2016-12-281.01.01 The Contractor must cooperate with BNSF RAIL ... ing, not included in the contract plans and
Page 15: SP00060 RR BNSF (2015 Specifications: 01-0804-23-15) · PDF file · 2016-12-281.01.01 The Contractor must cooperate with BNSF RAIL ... ing, not included in the contract plans and
Page 16: SP00060 RR BNSF (2015 Specifications: 01-0804-23-15) · PDF file · 2016-12-281.01.01 The Contractor must cooperate with BNSF RAIL ... ing, not included in the contract plans and
Page 17: SP00060 RR BNSF (2015 Specifications: 01-0804-23-15) · PDF file · 2016-12-281.01.01 The Contractor must cooperate with BNSF RAIL ... ing, not included in the contract plans and
Page 18: SP00060 RR BNSF (2015 Specifications: 01-0804-23-15) · PDF file · 2016-12-281.01.01 The Contractor must cooperate with BNSF RAIL ... ing, not included in the contract plans and
Page 19: SP00060 RR BNSF (2015 Specifications: 01-0804-23-15) · PDF file · 2016-12-281.01.01 The Contractor must cooperate with BNSF RAIL ... ing, not included in the contract plans and
Page 20: SP00060 RR BNSF (2015 Specifications: 01-0804-23-15) · PDF file · 2016-12-281.01.01 The Contractor must cooperate with BNSF RAIL ... ing, not included in the contract plans and
Page 21: SP00060 RR BNSF (2015 Specifications: 01-0804-23-15) · PDF file · 2016-12-281.01.01 The Contractor must cooperate with BNSF RAIL ... ing, not included in the contract plans and
Page 22: SP00060 RR BNSF (2015 Specifications: 01-0804-23-15) · PDF file · 2016-12-281.01.01 The Contractor must cooperate with BNSF RAIL ... ing, not included in the contract plans and
Page 23: SP00060 RR BNSF (2015 Specifications: 01-0804-23-15) · PDF file · 2016-12-281.01.01 The Contractor must cooperate with BNSF RAIL ... ing, not included in the contract plans and
Page 24: SP00060 RR BNSF (2015 Specifications: 01-0804-23-15) · PDF file · 2016-12-281.01.01 The Contractor must cooperate with BNSF RAIL ... ing, not included in the contract plans and
Page 25: SP00060 RR BNSF (2015 Specifications: 01-0804-23-15) · PDF file · 2016-12-281.01.01 The Contractor must cooperate with BNSF RAIL ... ing, not included in the contract plans and