SOUTHERN REGIONAL POWER COMMITTEE - Karnataka · Southern Regional Power Committee Bengaluru ......
Transcript of SOUTHERN REGIONAL POWER COMMITTEE - Karnataka · Southern Regional Power Committee Bengaluru ......
Agenda for 135th OCC Meeting to be held on 12.09.2017 at SRPC Bengaluru Page 1
Southern Regional Power Committee Bengaluru
Agenda for the 135th Meeting of Operation Coordination Committee
to be held at SRPC, Bangalore on 12th September 2017
1 Confirmation of the Minutes of the 134th Meeting of OCC of SRPC held on 11th August 2017
at NLC, Neyveli
2 Monthly Outage Plan/ Annual Outage Plan
2.1 ISGS/CGS: Generating Units
a) Shut Down Proposals for September/October 2017
b) Shut Down carried out during August 2017 along with reason for deviation, if any.
2.1.1 Reschedule of Overhauling
2.1.2 Neyveli TPS II- Planned maintenance of Unit-I
In the 134th OCC meeting held on 11.08.2017 approval was obtained to take Unit ! of TPS II under shut down for 25 days from 29.08.2017 for Annual Overhaul works. NLC vide letter dated 31.08.2017(Annexure-2A) informed that as there was slight delay in receipt of spares, the planned shut down could not be commenced on the approved date. The unit now is planned to be taken out of bars for planned works from early hours of 01.09.2017. All efforts will be taken to complete the maintenance works at the earliest and bring back the unit into service. It is noted that the Unit is taken out from 00:04 hours of 01.09.2017.
2.1.3 Rescheduling of Overhauling In the 133rd /134th OCC Meetings it was emphasized that the maintenance schedule
firmed up in OCC needed to be adhered by the generators as it had LGB, commercial,
ATC/TTC, market and grid security issues. All the generators needed to plan the
maintenance and have periodic preliminary review meeting with the OEM / Maintenance
Agency to avoid any rescheduling. Any unilateral decision by the generator could be
considered as a violation of the IEGC.
2.2 ISTS/State Sector Transmission Lines and Elements
2.2.1 All utilities are to submit the S/D proposals for the subsequent month by 3rd of the current
month. Shutdown requests for the same month needed to be avoided. An outage
coordination group had been created ([email protected]) for
review of the previous OCC approved shut downs (construction/critical).
2.2.2 Non-availing the OCC approved shut downs
SRLDC vide E-Mail dated 01.09.2017 has furnished the approved vs availed percentage of shut down approved for August 2017. States/Utilities to furnish the reasons for non availing the shutdown.
Agenda for 135th OCC Meeting to be held on 12.09.2017 at SRPC Bengaluru Page 2
2.2.3 All the utilities to furnish the details/deviations with respect to their Annual Outage plan
schedule VS maintenance carried out on a monthly basis as this information is required
for the Annual Outage Plan Deviation Report being submitted to CERC.
3 LGBR for upcoming five months
3.1 The following details to be furnished for discussion: Schedule of Hydro, Thermal Generation, RES, Purchases, Anticipated Consumption etc.
Shortfall/Surplus, if any and how the same is proposed to be met.
Arrangements to meet the Demand and Energy surplus/deficit.
Status review of Development of State of the Art load forecasting tools as per clause
5.4.2 of IEGC.
Load Generation Balance in real time.
(Item No.3 of enclosed SRLDC letter dated 30.08.2017).
3.2 LGBR for upcoming five months & TTC/ATC computations
3.2.1 All states were requested to furnish PSSE base case for January 2018.
The following details are to be updated:
State 5 months LGB
Converged PSSE Base case
ATC/TTC Computation furnished to SRLDC
ATC/TTC Computation posted on SLDC website
Nodal Officer details
AP Being Furnished
TS
KAR
TN
KER
(Item No. 3 of enclosed SRLDC letter dated 30.08.2017).
4 Review of Power Supply Position /Inflows
Constituents/ Generators to furnish the reasons for deviation:
a) Actual with respect to anticipated (MW & MU) for availability and requirement.
b) Generation variation category wise with respect to MoP targets/LGBR figures.
c) Inflows (MU) to major reservoirs: Actual w.r.t. 10 year moving average and w.r.t.
same month last year.
d) Reasons for demand -supply gap and its variation
5 MAJOR ISSUES
5.1 Presentation by States on Operational Issues
Agenda for 135th OCC Meeting to be held on 12.09.2017 at SRPC Bengaluru Page 3
5.1.1 All States/Generators/Powergrid may kindly submit the presentation in prescribed template
and specific issues which need deliberations may be highlighted separately.
5.1.2 SRLDC had requested that states may kindly upload their presentation by 5th of every month
so that SRLDC can compare with their information/data which will help in better
discussion/analysis of the issues.
5.2 Record of Proceedings of the meeting held on 18.08.2017: FoR Technical Committee
on Grid Integration of Renewable Energy (RE)
5.2.1 CERC vide their communication dated 02.05.2017 had informed that a Technical
Committee under the Chairmanship of Member, CERC, Shri A.S.Bakshi was formed at the
direction of Forum of Regulators (FOR) in November, 2015. The objectives of the
Committee include facilitating implementation of Regulations for Forecasting, Scheduling
and Deviation Settlement at the State level, implementation of ABT framework and
Ancillary Services in member States, among others.
5.2.2 The Sub Group Meeting was convened on 07.06.2017 at SRPC Bangalore and the Minutes
of the Meeting are available at SRPC website. A meeting of the Heads / Representatives of
the Sub-Groups was convened under the Chairmanship of Shri A.S.Bakshi, Member, CERC
on 18.8.2017 in CERC, New Delhi to review the progress on framework for regional co-
operation. The minutes of the Meeting at Annexure-5A
5.2.3 The following are the Observations/Deliberations in the meeting:-
States have recognized the value of electricity resource vis-à-vis the cost of
generation. Some of the States are not willing to cooperate with other States in the
Region on “cost” basis.
Some of the Regions are predominantly “Surplus” in power, leaving little scope for
co-operation within the region. This necessitates a national level framework /
product for optimum resource utilization.
Various other options for handling intra-day load / generation variation due to RE or
otherwise were also discussed viz. (i) Banking; (ii) DAM price on PX as reference;
(iii) Pool based on VC as approved by the Regulator and on payment of cost; (iv)
Pool based on VC as approved by the Regulator and on payment of MC; (v) Pool
based on auction for intra-day for the rest of the day; (vi) Pool based on auction for
intra-day on hourly basis; (vii) Pool based on auction for intra-day on intra-hour
basis i.e for 15 min. block-wise etc.
Agenda for 135th OCC Meeting to be held on 12.09.2017 at SRPC Bengaluru Page 4
5.2.4 During the meeting it was decided that the options raised may be shared with all RPCs and
may seek feedback.
5.3 CERC Order on Petition No. 84/MP/2015 with regard to inadequate/non performance of
FGMO
5.3.1 A Petition (No 84/MP/2015) was filed by National Load Despatch Centre (NLDC) with
Central Electricity Regulatory Commission (CERC) to direct all utilities to provide Primary
Response as provided for in the Indian Electricity Grid Code (IEGC) in Sections (f), (g), (h)
and (i) in the interest of power system security. In this regard, Hon'ble Commission vide its
order dated 03 rd August 2017 (available at htpps//posoco.in / spinning-reserves/ ) has
directed all Inter State Generating Stations (ISGS) to provide primary response by all
generators in accordance with IEGC which would help in further improving the frequency
profile.
5.3.2 SRLDC vide their letter dated 22.08.2017 (Annexure-5A-1)has highlighted that the Hon'ble
Commission in this order has pointed out certain areas for improvement in the FRC
assessment procedure which are listed below:
1) Para 18 (a) "Time duration window chosen for the tripping of the unit of Kudankulam was one minute thirty seconds and for Nepal earthquake, it was three minutes fifty seconds. Therefore, the primary response of the units to frequency excursion shall be measured after 30 to 60 seconds of the frequency excursion event. It is desirable that the post event instant may be determined 60 seconds later by all RLDCs/SLDCs for the sake of uniformity. It might be desirable to change the SCADA updation time at RLDCs from each regional entity station (points from where generally the state drawal is maximum) to 5-10 seconds to avoid discrepancies in FRC computation due to delay in data updation. Similar actions could be taken by SLDCs for each STU interface point.
2) Para 18 (b) "The input data for FRC calculation as indicated by NLDC in its calculations is at variance with the input data of SLDCs. The mismatch is to such a great extent that in certain cases the outcome gets totally reversed e.g in one case NLDC declares that the control area (Rajasthan) has helped the grid to some extent whereas the SLDC, Rajasthan has explained that the control area has aggravated the situation. In view of the above facts, POSOCO shall guide SLDCs with regard to FRC calculations.
3) Para 23 (a) "Considering the fact that further measures have been put in place to facilitate desirable primary response, the Commission, starting from the month of September, 2017 shall be closely watching the primary response of ISGSs as reported by POSOCO/NLDCs. At the State level, SLDCs shall report the frequency response of intraState generators to the concerned SERCs."
Agenda for 135th OCC Meeting to be held on 12.09.2017 at SRPC Bengaluru Page 5
5.3.3 In the recent past SRLDC had analyzed the RGMO performance of SR generators.
SLDCs/Generators are requested to take measures for improving the performance.
5.3.4 RGMO logic for all the generating stations shall be revised as per the IEGC 5th amendment
regulations as mentioned below.
“ There should not be any reduction in generation in case of improvement
in grid frequency to a level below 50.00 Hz. (For example, if grid frequency changes from 49.9 to 49.95 Hz, or from 49.95 to 49.99 Hz there shall not be any reduction in generation). For any fall in grid frequency, generation from the unit should increase as per generator droop upto a maximum of 5% of the generation subject to ceiling limit of 105% of the MCR of the unit having regard to machine capability”.
SLDCs/ISGS/Regional Generators are requested to confirm the revised settings.
5.3.5 The Hon'ble Commission has also directed to report the violation in case of poor primary
response by generators. It is therefore requested that SLDCs SLDCs/ISGS/Regional
Generating stations may advise all the generators to provide primary response with
immediate effect in line with the IEGC provisions, preferably no later than 0000 hours of 25th
Aug 2017. This would ensure that the Hon'ble Commission's order will be implemented in
letter and spirit with effect from 1st Sep 2017 as stated in para 23 (a) of the order.
5.4 Discrepancy in triggering of RRAS Instructions
5.4.1 SRPC vide letter dated 30.08.2017(Annexure-5B) has brought the following to kind
attention of NLDC regarding RRAS schedules:
Non-adherence of merit order based dispatch
On 23.07.2017, RRAS up was given from 18:15 hrs. to 18:45 hrs.. During the same period, Talcher Stage-II which is the cheapest generator in SR had URS of 680 MW but was not given RRAS up instruction. Instead, RRAS up was given to NLC State-II unit-I, unit – II and Expn of Stage-I which are costlier in merit order.
Triggering of RRAS instructions during Congestion Warning Notice period
On 08.08.2017 at 05:40 hrs. congestion warning notice was issued to SR on account of violation of SR import ATC. During the same time, RRAS up instruction was given for 1,500 MW due to “low frequency” and trend of load met. Except NLC Stage – II Expn, no other generator in SR was given RRAS up instruction. NTPL, Simhadri Stage – I and NTECL Vallur which were cheaper stations in merit order dispatch had URS at this time which could have contributed not only for improving frequency but also in relieving congestion. It is however observed that frequency range was from 49.95 to 50.02 Hz which is well within IEGC range.
Agenda for 135th OCC Meeting to be held on 12.09.2017 at SRPC Bengaluru Page 6
5.4.2 It had been suggested by SRPC during the Meeting held at CERC that for optimal and
economic scheduling, selection of generators should be done only at two time block advance
of triggering RRAS instruction. This can be achieved by collecting URS margin available
above Technical Minimum and RAMP rate implemented in all the generators under RRAS at
three time block in advance from all RLDCs and then deciding the scheduling, based on
Merit Order. Pre-deciding the target generator much in advance, may lead to fouling of the
Merit Order in real time operation since URS from cheaper generator may become available
only on four time block in advance. RRAS regulation has provision for triggering at least one
block in advance. With considerable efforts of POSOCO, Merit Order data portal has been
put into place. States are uploading daily details of Merit Order based dispatch. Similarly, for
Ancillary services, it may kindly be considered to upload dispatch details on a daily basis in
the MOD Portal.
5.5 Discrepancy in Scheduling
5.5.1 SRPC vide letter dated 30.08.2017(Annexure-5C) had communicated to SRLDC that it had
been observed that there are number of instances where schedule is more than DC. The
detailed list was enclosed at Annexure-A of the said letter. It is also observed that there is
mismatch between on bar DC and off bar DC though without any RSD, it should remain
same. The details in respect of NLC Stage-II Unit-I, Unit-II, NTPL etc. were furnished at
Annexure – B of the letter. SRPC had requested SRLDC that this may please be examined.
5.6 Consideration of Talcher Stage II as Upstream or Downstream based on different
congested corridors
5.6.1 In the Commercial Sub Committee Meeting held on 8th August 2017, SRLDC had raised the
following issue:
Talcher-II station of NTPC physically located in ER to be considered as not part of
SR constituents for purpose of declaring as “upstream or downstream” during
congestion. It was opined by SRLDC representative that the electrical behavior of
Talcher-II may be inverse to the desired response from SR constituents.
5.6.2 In this regard SRPC vide letter dated 23.08.2017(Annexure-5D) had brought the following
to kind attention of NLDC:
Whether Talcher stage II is upstream or downstream depends on the
corridor on which ATC is violated.
Hence, it cannot be concluded that Talcher Stage II is always upstream or
downstream for any congested corridor,
In case of ATC violation of SR import, Talcher Stage II is downstream.
In case of ATC violation along ER-SR corridor, Talcher Stage II is
downstream.
Agenda for 135th OCC Meeting to be held on 12.09.2017 at SRPC Bengaluru Page 7
In case of ATC violation along WR-SR corridor, Talcher Stage II is upstream
provided HVDC set point is not changed.
In case of ATC violation along WR-SR corridor, Talcher Stage II is upstream
provided HVDC set point is increased to import power from Talcher Stage
II/ER.
The action to be taken by Talcher Stage II should be informed clearly in
congestion warning notice since its desired action would depend upon the
corridor whose ATC is violated.
All generators who have relatively higher sensitivity (positive or negative)
towards the congested corridor should participate in relieving the congestion.
For instance in congestion warning notice issued for WR-SR corridor on
27.10.2016(17:16 hrs) Talcher stage – II was issued the same notice as for all
SR Constituents.
5.6.3 Therefore it is suggested that in future while issuing warning notices, Talcher Stage II should
be specifically informed about the desired action. This is in view of the fact that post facto
correction/changes in upstream or downstream are not possible after real time warning
notices are issued.
5.7 Inclusion of Transmission System for Solar Power Evacuation under PoC Mechanism
and its Implementation
5.7.1 In the 32nd SRPC Meeting held on 22nd August 2017, the inclusion of transmission system for
Solar Power Evacuation under POC Mechanism and its implementation under
CERC(Sharing of ISTS Charges and Losses) Regulation was discussed. After discussion it
was agreed that some of the issues which are of concern may be brought to kind attention of
Hon‟ble CERC. It was also noted that a Task Force had been constituted by Commission to
undertake review of existing Framework of Sharing of Transmission Charges and Losses.
5.7.2 Accordingly Chairperson, SRPC vide letter dated 23.08.2017(Annexure-5E) had
brought out certain issues to the notice of Ho‟ble CERC and requested that Hon‟ble
Commission may kindly bestow its attention on the listed matters.
Non consideration of solar LTA in arriving at the POC slab rate does not alter the
transmission charges payable by that state.
It is thus not clear in what manner or how the transmission charges waiver for solar and
wind power is to be actually implemented in the POC mechanism. This matter merits
kind attention of Hon‟ble Commission since this has implications not only on the host
state but also on the neighboring states.
Annexure showing the cost allocation of 400kV S/c Cuddapah – Kolar line which is
LiLoed at 400 kV NP Kunta is enclosed please. NP Kunta Solar project has entered into
PPA with Andhra Pradesh for its power. However, as per participation, entire cost of the
Agenda for 135th OCC Meeting to be held on 12.09.2017 at SRPC Bengaluru Page 8
element gets loaded on the adjoining state of Karnataka which does not have any PPA
with NP Kunta what so ever.
However, implementation of the policy regarding waiver of transmission charges merits
kind attention in view of the existing methodology of sharing of transmission charges.
5.8 Operation Of Hydro Power Projects In Peaking Mode
5.8.1 Forum of Load Despatchers (FOLD) and POSOCO have prepared a report “Report on
Operational Analysis for Optimization of Hydro Resources & facilitating Renewable
Integration in India”. MoP had constituted a sub-committee under Chairperson, CEA to
study and recommend the individual hydro power stations which can be operated to achieve
peak load capacity. The subcommittee has held three meetings with the concerned Hydro
generating stations and concluded that there was scope of about 2000 MW additional power
generation from hydro station during peak hours.
5.8.2 In the 134th OCC Meeting, RLDC made a presentation on the same. SRLDC was requested
to come out with specific suggestions/way forward since RPCs are advised to discuss the
same as a regular Agenda item in Monthly OCC Meetings as well as needed to be discussed
in TCC/SRPC Meetings.
5.8.3 Subsequently the issue was further deliberated in the TCC/SRPC Meetings held on 22nd and
23rd August 2017 respectively. After discussions the States of SR wished to bring some of
the issues to bring to the kind attention of Ministry of Power.
5.8.4 Accordingly Chairperson, SRPC vide letter dated 23.08.2017(Annexure-5F) had
communicated the following to Ministry of Power:
Hydro generation is required for grid security, deviation management, fall in availability
due to unit outages, RE withdrawal, RE intermittency, etc.
Hydro generation in merit order is considered based on the price of replaced energy in
the water cycle year and not merely on the basis of cost.
Hydro generation is also being modulated based on market price signals. Hydro also
provides necessary spinning reserve.
Hydro generation is at times based on irrigation and drinking water requirements.
Peak of a particular state need not necessarily align with that of all India peak. It was
observed that POSOCO had primarily focused on generation level witnessed at all India
peak demand instant.
Though a questionnaire had been circulated, SLDCs felt that they had not been
consulted appropriately.
This is the 3rd year of poor monsoon consecutively. Thus, analysis of peak study based
on last year‟s data may not necessarily be conclusive.
Agenda for 135th OCC Meeting to be held on 12.09.2017 at SRPC Bengaluru Page 9
With steep rise in the generation capacity of renewables (for instance TN has about
6,000 MW of RE), Hydro modulation is required during other instants also apart from that
of All India peak.
Southern Region doesn‟t have a single CGS hydro station. Thus, comparison with hydro
operation in NR/NER may have its own limitations. Hydro resources in Southern Region
are basically in the state sector.
It was felt that in the present de-regulated environment where individual control areas as
per CERC notified Grid Code are in existence, there is a need to evolve suitable market
mechanism to incentivize higher hydro support during peaking and also for other
ancillary services.
In the absence of draft market mechanism in the POSOCO report, states were unable to
take any call on this issue. Certain states expressed that this matter may also need to be
placed before the appropriate Commission (SERC).
POSOCO was therefore requested to kindly come out with a suitable market mechanism
for this purpose.
POSOCO was also requested to conduct detailed state wise consultations/analysis with
concerned SLDCs. This would help in enhanced understanding/appreciation of the hydro
optimization strategy adopted by each state and also understand the reasons for
reported under performance of few stations.
In view of the quantum jump in RE penetration, the various policy initiatives of
Government of India were well appreciated.
SRPC requested that Ministry of Power may kindly bestow its attention on the above matter.
5.9 High Voltage at Tamil Nadu Stations and N-1 Evacuation constraints at Kamuthi:
5.9.1 SRLDC vide letter dated 19.08.2017 (Annexure-5G) had informed that the pocket
comprising of Tamil Nadu 400 kV Stations namely Karaikudi, Kamudhi and Kayathar are
experiencing high voltage during most part of the day and many 400 kV lines emanating
from these stations are kept open on high voltage. In the present temporary
configuration(LILO at Kamudhi of Kayathar-Karaikkudi 400 kV line), the Kayathar-Kamudhi
transmission line section has become so long. (Approximately 400 kM). This line is kept
open from 28.03.2017 at 14:45 hours due to high voltage. Solar generation of around 648
MW from various solar parks is connected to Kamudhi 400 kV substation and the evacuation
is through the single Kamudhi-Karaikkudi 400 kV line with persistent N-1 constraint. SRLDC
expressed concern that any fault or forced outage of this line will further lead to serious
evacuation issues and will impact badly on the grid security as well. SRLDC requested
TANTRANSCO to address the following expeditiously:
Mitigate the high voltage by load rearrangement at Kamudhi and Kayatahar Stations.
Agenda for 135th OCC Meeting to be held on 12.09.2017 at SRPC Bengaluru Page 10
Expediting the commissioning of the 125 MVAR Bus Reactor at Kayathar as
approved in the 39th SC.
Completion of the bay works at Karakudi on fast track basis for completion of the
Kamudhi-Karaikudi 400 kV D/C and Kayathar-Karaikudi 400 kV DC lines.
5.10 Commissioning of 2000 MW Solar Power Generation in Pavagada Solar Park:
5.10.1 KSDPCL is developing 2000 MW Solar Power Generation in Pavagada Solar Park in 5
villages. KSPDCL vide letter dated 17.08.2017(Annexure-5H) had informed that the
following Solar Power Developers establishing Solar PV projects in 2000 MW Pavagada
Solar Park, Tumkur District have issued notice for commissioning their generation Units.
Name of SPD Capacity in
MW
Date of Synchronization with GRID
Parampujya Solar Energy Pvt.
Limited
100 31.08.2017(Final Notice)
ACME Rewari Solar Pvt. Ltd. 50 08.10.2017(Preliminary Notice)
ACME Kurukshethra Soalr
Energy Pvt Ltd
50 08.10.2017(Preliminary Notice)
Fortum Finnsurya Energy Pvt.
Ltd.
100 31.08.2017(Final Notice)
5.11 Utilisation of Spare ICT/Reactor:
5.11.1 In the 30th SRPC Meeting held on 30.06.2016 it had been informed by PGCIL that Tariff for
utilization of Spare ICT/Reactor would be billed to the entity utilizing the Spare. The Tariff
would not be claimed from other beneficiaries. SRPC vide letter dated
29.08.2017(Annexure-5I) requested PGCIL to kindly examine whether in Southern Region,
the concerned entity utilizing Regional Spare ICT/Reactor is being billed as per above
SRPC decision and SRPC may kindly be informed on this matter.
5.12 NLC TPS I Expansion- RRAS down Regulation Quantity excluded from Technical
Minmum:
5.12.1 NLC vide letter dated 22.08.2017(Annexure-5J) had informed that on 20.08.2017 (revision
No.116) Block from 35 to 44 and from 47 to 54, the RRAS down quantity was included in
the Technical Minimum of 211.70 MW and from 39 to 54 block the traded quantity was also
included in the down Regulation. The Declared Capacity, Schedule, Drawal Schedule, PX
and RRAS Quantity on 20.08.2017 pertaining to TPS I Expansion were also enclosed. It is
requested by NLC that RRAS down Regulation quantity may be excluded from the
Technical Minimum and from traded quantity for the above blocks.
5.12.2 SRPC vide letter dated 24.08.2017(Annexure-5K) had submitted the following;
While implementing RRAS down instruction station technical minimum of 55% is
being ensured. The matter was ascertained from SRLDC. It is seen that the data
Agenda for 135th OCC Meeting to be held on 12.09.2017 at SRPC Bengaluru Page 11
furnished by NLC (RRAS down instructions) is actually the intended RRAS down
quantum required. However, since this quantum would have lead to station schedule
going below technical minimum, the RRAS quantum was restricted, for example in
block No.35 to 79 MW against 90 MW.
It was also stated that from block No.39 to 54, the trade enquiry was also included in
the down regulation, whereby NLC claimed that this had to be excluded from
technical minimum as per discussions in the OCC Meeting. In this regard, it is
brought to kind attention that there is no provision to exclude trade quantity for
arriving technical minimum schedule for a station.
5.13 Grid Impact Study Due to establishment of 350 MVA Short Circuit Transformer Test
Facility at CPRI, Uppal Hyderabad.
The remarks/observations of TSTRANSCO regarding the Draft report on Grid Impact Study
Due to establishment of 350 MVA Short Circuit Transformer Test Facility at CPRI, Uppal
Hyderabad had been communicated to CEA by TSTRANSCO vide letter dated
18.08.2017(Annexure-5L)
5.14 Powergrid elements which were observed to be in an advanced stage construction/
Commissioning with schedule as per Investment Approval, subsequent to the
proposed commissioning /COD.
5.14.1 In the 32nd Meeting of SRPC held on 22.08.2017 Power Grid had submitted status of
various upcoming elements in the Region. Some of these elements were observed to be in
an advanced stage of construction/ commissioning with schedule as per Investment
Approval, subsequent to the proposed commissioning /COD. After discussions, it was
agreed that a Meeting would be conducted in SRPC with participation of officers from
States as well as CTU. Status/ readiness of corresponding downstream elements in state
system as well as system benefits that would accrue after commissioning of such elements
would be prepared and submitted to Chairperson, SRPC for necessary approval. All states
had concurred for these working arrangements.
5.14.2 Accordingly, a Special Meeting was conducted on 1st September 2017 in SRPC, Bengaluru
with participation of CTU, States, SRLDC and SRPC. Based on the deliberations and also
the studies conducted during the special Meeting, a report had been prepared. Copy of this
report had been submitted to Chairperson SRPC vide SRPC letter dated
04.09.2017(Annexure-5M) and had requested that approval for this report may kindly be
arranged to be communicated for further need ful in this regard.
5.15 Optimum harnessing of RE in Southern Region
5.15.1 A Meeting was held on 10th February 2017 in MoP on matters relating to optimum
harnessing of Renewable Energy Integration in SR without endangering Grid Security. A
number of actionable points had been finalized in that Meeting and time lines for compliance
Agenda for 135th OCC Meeting to be held on 12.09.2017 at SRPC Bengaluru Page 12
of the same also had been specified. SRPC vide letter dated 02.05.2017 had requested the
concerned utilities that the matter may kindly be arranged to be reviewed and urgent action
arranged wherever necessitated. A Special TCC Meeting was also convened on 20th May
2017 in SRPC, Bengaluru. A Special Meeting of SRPC Members of the constituent states
was held on 31st July 2017 at Hyderabad.
5.15.2 Subsequently the issue was further discussed in the 32nd SRPC Meeting held on 22nd August
2017. It may be noted that except Tamil Nadu, all the States had signed the agreement.
5.15.3 TANTRANSCO vide letter dated 17.08.2017(Annexure-5N) had informed that the rate of
energy of power to be exchanged as per item (7) of Draft Overarching Agreement is not
viable for TANGEDCO. However if Surplus Power is anticipated, TANGEDCO is willing for
sale of Surplus Energy/Swap with pther SR Constituents at mutually agreed price.
5.15.4 SRPC vide letter dated 18.08.2017(Annexure-5O) had further requested TANTRANSCO to
consider the sighing of the Agreement to avail the advantage of the Agreement, mutual
cooperation among SR states and it may also facilitate higher RE absorption.
5.15.5 SRPC had analysed the Under Drawal pattern of TANTRANSCO during the period from 1st
June 2017 to 13th August 2017(more than 4 Blocks and above 150 MW). Enclosing the
analysis SRPC vide letter dated 24.08.2017(Annexure-5P) had requested TANTRANSCO
to examine the same and in case of surplus power availability arrangements to sell/swap
power under Overarching Agreement may kindly be explored.
5.16 Terms and Reference for the proposed study on Renewable Integration
5.16.1 It was noted that in the 31st SRPC Meeting held on 25th February 2017
TANGEDCO/TANTRANSCO had agreed to take up the matter of funding this study by RE
Developers with them. SRPC vide letter dated 03.05.2017 had requested TANTRANSCO
that the matter regarding possible funding of the consultancy may kindly be arranged to be
taken up with RE Developer Associations.
5.16.2 Subsequently TANTRANSCO vide letter dated 08.06.2017 had communicated the
deliberations of the Meeting held on 30.05.2017 with Wind Developers. The issue was
further deliberated in 31st TCC/32nd SRC meetings and it was agreed that a separate
meeting would be held at SRPC with participation from constituents/RE Developers.
TANTRANSCO would coordinate for RE Developers participation.
5.17 Compliance of CEA Regulations for Grid connectivity of Renewable Energy Sources
5.17.1 CEA vide letter dated 12.04.2017 had informed that in compliance to the Clauses 6(3) and
6(4)(b) of Central Electricity Authority (Technical Standards for Connectivity to Grid)
Agenda for 135th OCC Meeting to be held on 12.09.2017 at SRPC Bengaluru Page 13
Regulations 2007 and Central Electricity Authority (Technical Standards for Connectivity of
the Distributed Generation Resources) Regulations 2013 notified on 30th September 2013 it
is obligatory for all the grid connected renewable generators to provide necessary facilities
for data-communication and data-storage and other parameters as may be stipulated. The
said CEA Regulations also places onus on the generating plants including renewable to
coordinate with appropriate licenses on issues including but not limited to protection safety
and metering.
5.17.2 With the above perspective as emerging from the CEA Regulations in force, the SLDCs are
requested to take up the matter with all the renewable generators to ensure transfer of
data to the appropriate Load Despatch Centre, so that the real time generation data is
available with them for centralized monitoring. It was also requested that to indicate the
present status in this regard and the action plan with definite time frame to ensure real time
data telemetry from all the grid connected Renewable Generators/Plants to the SLDCs.
5.17.3 CEA had requested SRPC to take up the issue with the concerned SLDC/utility operating the
SLDC and desired that this may be kept as an agenda item for OCC Meetings for periodical
review of the status of real time data telemetry from all the Grid Connected Renewable
Generators/Plants to the SLDCs.
5.17.4 Subsequently CEA vide letter dated 08.05.2017 had enclosed MoP letter dated 06.04.2017
on the above issue. SRPC had informed that this matter had been deliberated in the Special
TCC Meeting held on 20.05.2017. The minutes of the Meeting are available at SRPC
website. States were requested to take immediate action as per the Meeting Minutes.
5.17.5 CEA had held a meeting on „Receipt of online operational data in real time mode at SLDC
from renewable energy generation sources (RES) and related issues‟ at New Delhi on
28.06.2017. The following was concluded in the meeting:
The following was concluded in the meeting:
Summing up the discussions, Member (Planning), CEA, stated that all states should have in place the urgent time bound plans to ensure the availability of 100% operational data in real time mode at the SLDC/RLDC/NLDC. It was decided that the respective states will submit weekly reports of data communication status to CEA as well as to respective RPC/RLDC and NLDC.
Till the time, the State Regulations are not in place the Central Electricity Regulatory Commission (Communication System for inter-State transmission of electricity) Regulations, 2017” shall be followed.
5.17.6 It was noted that a Special Meeting was held in CEA on 11.07.2017 under Chairmanship of
Member (Planning), to discuss the modalities for devising suitable framework for National
Level Data Registry for electricity generating units so as to have easy availability of their
Agenda for 135th OCC Meeting to be held on 12.09.2017 at SRPC Bengaluru Page 14
generating capacity and other details. CEA vide letter dated 19.07.2017 had communicated
the Minutes of the Meeting.
5.17.7 TSTRANSCO vide letter dated 18.08.2017 had submitted the weekly report which is at
Annexure- 5Q
5.17.8 Further CEA had called a Meeting on the same on 11.09.2017 at CEA, New
Delhi(Annexure-5R)
(Item No.11(d) of enclosed SRLDC letter dated 30.08.2017).
5.18 Ramp down/up during sudden solar increase/decrease during morning/evening
5.18.1 In the 129th OCC Meeting SRLDC had expressed concern regarding the ramp down/up
during sudden increase/decrease during morning/evening hours. SRPC/SRLDC had
cautioned that Solar Capacity would be coming up very intensively in coming six months and
SR should be ready with contingency plan for managing the LGB during the solar ramp
up/ramp down period.
5.18.2 Subsequently a Meeting of Sub- Group of Southern Region formed under the Technical
Committee constituted by CEA for study of optimal location of the various types of balancing
energy sources/energy storage devises to facilitate grid integration of Renewable Energy
Sources and associate issues was conducted on 24.03.2017 with participation from CEA.
The minutes of the Meeting issued on 20.04.2017
5.18.3 All the states are requested to take action in this regard.
(Item No.11(c) of enclosed SRLDC letter dated 30.08.2017).
5.19 Shifting of PMU from GMR-Vemagiri to NP Kunta-Status
5.19.1 In the 134th Meeting APTRANSCO informed that instead of shifting PMU from GMR Vemagiri
to NP Kunta, it may be shifted to Uravakonda.
5.19.2 SRPC had informed that Protection Committee had agreed for NP Kunta and actions had
been initiated and the requirement at Uravakonda may be considered subsequently.
(Item No.4(d&e) of enclosed SRLDC letter dated 30.08.2017).
5.20 Preparedness of Load Change Over during Morning and Evening Peak hours.
(Item No.4(b) of enclosed SRLDC letter dated 30.08.2017).
5.21 Non Availability of Kaiga, Trichy & Hyderabad Voltage(SCADA) data at SRLDC
(Item No.4(a) of enclosed SRLDC letter dated 30.08.2017).
5.22 Confirmation for the indicated plan for FGD/Phasing Out Plan for implementation of
new Environmental Norms for Thermal Plants issued by MOEF & CC
Agenda for 135th OCC Meeting to be held on 12.09.2017 at SRPC Bengaluru Page 15
5.22.1 In regard to Phasing Plan for implementation of new Environmental Norms for Thermal
Plants, issued by MOEF&CC, CEA has firmed up the FGD phasing plan and uploaded on its
website. Phasing Out Plan confirmation are not received from most of the generators. It was
requested that all the concerned to kindly furnish the information at the earliest which would
be forwarded to CEA.
5.22.2 Subsequently CEA had requested to furnish the confirmation regarding the FGD installation
of NLC Units. NLC vide letter dated 18.08.2017 has furnished their views. It was informed
that consultant had taken the field measurements and recommendations are awaited.
5.22.3 All the generators to keep CEA appraised of the developments in FGD/Phasing out plan.
5.22.4 Funding from PSDF was further discussed in the 32nd SRPC Meeting held on 22nd August
2017. During discussions it was expressed that funding, either from PSDF or any other fund
could again be kindly sought from GoI to meet the stipulated revised environmental norms.
State Utilities had expressed that capital cost of FGD installation being quite high
implementation was considered on account of resource constraints.
5.22.5 Accordingly Chair Person, SRPC Chair Person vide letter dated 28.08.2017(Annexure-5S)
had taken up the issue with MoP.
5.22.6 CEA vide letter dated 01.09.2017(Annexure-5T) had communicated regarding convening of
Special Meeting at TCC Level to revise the Phasing Plan for identified units for ESP up
gradation and FGD installation.
5.23 State-wise allocation of 540 MW power from RGPPL to Railways
5.23.1 CEA vide letter No. 5/AI/CSA/GM/2017 dated 22.03.2017 had enclosed MoP Order No.
4/22/2011-Th-Vol-III) dated 17.03.2017 in which 540 MW power from Ratnagiri Gas and
Power Private Limited (RGPPL) has been allocated to Indian Railways. Allocation to SR
States (out of 540 MW) would be as under:
State Nodal Railway Maximum load in MW after availability of corridor between NEW Grid and SR*
Telangana SCR 50*
Tamil Nadu SR 100*
date of effectiveness subject to availability of transmission corridor as per
assessment of CTU.
5.23.2 Subsequently CEA vide letter dated 22.05.2017 had endorsed MoP letter dated 18.05.2017
in which 35 MW of power is allocated to KPTCL (SR). CEA vide letter dated13.06.2017
had communicated the allocation to Karnataka with slight modification in the conditions.
Agenda for 135th OCC Meeting to be held on 12.09.2017 at SRPC Bengaluru Page 16
5.23.3 CTU vide letter dated 20.04.2017 & 08.06.2017 had informed that ATC to SR from new
Grid has already been allocated to LTA/MTOA applicants for transfer of power to
constituent states of Southern Region including Telangana, Tamil Nadu & Karnataka.
Transfer of 150 + 35 MW can be affected upon commissioning of upcoming Nizamabad-
Maheswaram 765 kV D/C line, which is likely to be commissioned by October 2017.
5.23.4 The following were noted in the earlier Meetings :
TSTRANSCO had convened a Meeting with Railways, SRLDC & SRPC on
28.04.2017.
TANTRANSCO had stated that APTEL Order was expected on 18.07.2017.
KSEBL informed that there were issues like Railway‟s Deemed Licensee status
was still subjudice, only balanced three phase supply is possible from STU as per
CEA Connectivity Regulations & there were Metering issues as per IEGC and
such restrictions were not there in Supply Code of Discoms under which Railway
was getting its supply presently.
KPTCL and TANTRANSCO were once again requested to call for a meeting with
Railways to address procedural & infrastructural issues.
5.23.5 CEA vide letter dated 16.08.2017(Annexure-5U) had forwarded MoP letter regarding Review of Power Projects by Hon‟ble Prime Minister under PRAGATI and requested to submit the status report on the states which have not granted NOC for Open Access to Railways and reason there of.
5.23.6 The views communicated by AP, TS and Tamil Nadu is at Annexure- 5V.
5.23.7 This issue was further deliberated in the 32nd SRPC Meeting held on 22nd August 2017 in which CTU had informed that the Transmission Corridor for the above allocationis likely to be available from 1st October 2017.
5.23.8 SRPC vide letter dated 27.08.2017(Annexure-5W) had taken up the issue with the concerned States and requested that the matter be taken up with Indian Railways urgently, so that all pending issues such as metering etc. are resolved well before 1st October 2017.
5.24 Scheduling of Simhadri Stage I Station
5.24.1 Simhadri Stage-I scheduling had been started by SRLDC from 01.05.2017 onwards. Main/Check meters at Simhadri Stage - I end of Inter connector is not installed.
5.25 Monitoring of scheme funded from PSDF
5.25.1 NPC vide letter dated 25.08.2017 had furnished the Agenda for next Meeting of NPC scheduled on 08.09.2017 at Vijay Nagar, Indore, MP. It was noted that w.r.t SR for 20 Schemes approved, against 1751.28 Cores Rupees sanctioned 104.39 cores rupees of Grant only Disbursed. The actual disbursement is quite less due to slow implementation of projects by entities. NPC expressed concern regarding this slow improvement and requested RPCs to examine the implementation of schemes in OCC/TCC Meetings and intimate NPC about the bottle necks. The relevant pages of NPC Agenda is at Annexure-5X.
Agenda for 135th OCC Meeting to be held on 12.09.2017 at SRPC Bengaluru Page 17
5.25.2 The Status update of the Schemes as updated from the information received from Constituents/Entities is at Annexure-5Y. It is requested that this information may kindly be reviewed and the reason for less utilization may kindly be furnished at the earliest.
5.26 Right of Way issue of 400 kV Nelamangala-Hoody Line/ commissioning of 400 kV
Yelahanka substation/220 kV evacuation system of KPTCL at Yelahanka substation
5.26..1 SR II Powergrid had informed that the compensation issues were being settled for LILO of
Nelamangala - Hoody at Yelahanka. Regarding Madhugiri – Yelahanka in three districts,
Bengaluru Urban, Bengaluru Rural and Tumkur ROW issues are being faced. The
connectivity at Yelahanka will not be useful until the 220 kV side cables are made through
by KPTCL.
5.26..2 SR II, PGCIL had informed that the issue is being followed up with State Administration for
removal of ROW issues.
5.26..3 KPTCL had informed that cable has received and scheduled to be commissioned in
December 2017. ROW issues are being resolved.
5.27 Daily Load Forecasting by SLDCs/RLDCS/NLDC
5.27..1 The mean absolute error (forecast Vs actual demand) for the month of August 2017 as
furnished by SRLDC.
(Item No.5 (b) of enclosed SRLDC letter dated 30.08.2017).
5.27..2 In the 126th OCC Meeting, SRLDC had informed that a Pilot Project for RE forecasting had
been started. Pilot Project for load forecasting was yet to commence. RE Connect has been
entrusted the work. They wanted past three years‟ data in specific format. The block wise
difference in forecast and actual and the reason for the inter block difference were also
needed. SRLDC had started the work. Weather input would be incorporated by RE
Connect.
5.21 Scheduling of NTPC Ramagundam Solar Power Plant(10 MW)
NTPC had informed that written communication in this regard to MoP would be shared with
SRLDC/SRPC.
5.22 Upcoming Wind/Solar Projects
5.22.1 In the earlier OCC Meetings the following were noted:
It was noted that procedure for RE Frameworks had been notified and is available
at NLDC website. It was requested to all the concerned to take up with generators
and whatever information as mentioned in the Notified Procedure are to be
collected/ensured from RE generators.
SRPC had informed that the progress of works of RE Generators and evacuation
system are available in TCC/SRPC Minutes. All the concerned were requested to
update the same and revert back at the earliest incorporating appropriate changes.
5.23 Status Review of REMC project implementation.
5.23.1 In the 134th OCC Meeting SRLDC had informed that the proposal has been put up to
Empowered Committee. Approval had been delayed due to administrative issues and
Agenda for 135th OCC Meeting to be held on 12.09.2017 at SRPC Bengaluru Page 18
approval is expected by this month end. Execution period is 15 months from approval date.
There are four schemes for three states namely for Andhra Pradesh, Karnataka and Tamil
Nadu and one for SRLDC. Separate SCADA will come for renewables with existing RTUs
and communication system.
(Item No.11(e) of enclosed SRLDC letter dated 30.08.2017).
5.24 Wind and Solar power forecasting by States.
(Item No.11(a) of enclosed SRLDC letter dated 30.08.2017).
5.25 Power Flow Analysis under high RE scenario
5.25.1 A project has been undertaken jointly by POSOCO, USAID and NREL for power flow
analysis under high RE scenario.
5.25.2 In the 134th OCC Meeting the following was noted:
TSTRANSCO, TANTRANSCO and KPTCL had furnished the information.
APTRANSCO informed that stress study had been carried out through a Spanish
Consultant.
SRLDC requested APTRANSCO and KSEBL to furnish the information.
5.26 PSS Tuning of generators
5.26.1 5th Meeting to review the status of PSS tuning of the generators was convened on 26th
July 2017 and minutes of the Meeting are available at SRPC website. All the generators
to follow the action plan finalized in the 5th PSS meeting.
5.27 Implementation of URTDSM (PMU) project in Southern Region
5.27.1 URTDSM - Status update in respect of the Meeting held on 07.02.2017/subsequent OCC Meetings are as below:
Sl No
Activity Status/Remarks
1 Status of URTDSM Project (SR Portion)
PMUs to be installed in SR as per URTDSM Project Package–II had further increased from 240 to 270 on account of commissioning of certain new stations and additional feeders. (As per LOA-212)
Status
Total Envisaged
Survey completed
S/S PMU
SS PMU Installed
SR I
128
Pending in Hyderabad, Khammam
and Vemagiri.
20 Supplied: 107 Commissioned:
97 Integrated: 85
SR II
41 142 Completed 39 Supplied: 138 Commissioned:
Agenda for 135th OCC Meeting to be held on 12.09.2017 at SRPC Bengaluru Page 19
112 Integrated: 110
Kalamassery integrated. KSEB to extend the bus
voltage. Forum expressed concern that project was getting
delayed and requested PGCIL / GE to share monthly project execution plan up to Sep 2017 and monthly progress ( installation and integration to Control Centre) status by end of every month.
2 Contractual amendment
Final Amendment had been issued on 19.05.2017 and system expected to be commissioned by Sep 2017.
3 Requirement of Auxiliary Power Supply System (APS) as per revised BOQ (excluding input ACDB and one battery bank of the proposed two battery banks).
Survey completed. Space in SRLDC is not sufficient for APS solution under URTDSM project. APS system not supplied due to space constraint in TN & SRLDC.
4 Capacity of Battery & charger
None of the constituents requested 48 V DC power supply source. Hence this point is not applicable now.
5 Responsibilities under
Entities
SR-II confirmed that Dismantling of panels, any civil works etc required to prepare site for installing APS System was not under the scope of the Project and thus was in the scope of respective constituents.
Supply, erection& commissioning of UPS, ACDB Input &Output panels, Battery Bank and associated cabling works for establishing APS system was under the scope of the Project.
Air Conditioning System was required and Constituents were to make necessary arrangements.
Kerala yet to provide clear site by removing existing old EMS SCADA system and dismantled materials.
KPTCL has yet to provide Air-conditioning system to match with the commissioning schedule i.e. Sept. 17.
TANTRANSCO yet to provide the earthing connection point for the panels
6 Redundancy for PMUs PGCIL confirmed that all PMUs are provided with redundant communication path and schematic diagram of communication flow had been shared with the constituents.
7 SAT procedure FAT completed for all 4 Nos control centers. Equipment supplied to all 4 Nos control centers and installation under progress at SRLDC , Karnataka SLDC & TN SLDC.
8 SR Region Training Training had been firmed up by M/s GE and one batch training is over.
Agenda for 135th OCC Meeting to be held on 12.09.2017 at SRPC Bengaluru Page 20
9 Availability of necessary communication ports for connection of servers under URTDSM
Except TANTRANSCO, all constituents extended the required communication ports at PDS.
10 Training on Application
part
Application part is in development stage. Would communicate the details in due course.
11 Update the Drawings Constituents‟ requested PGCIL to update the Drawings with changes done in the CT/PT/Status wiring for the PMU system and submit as built drawing.
PGCIL had informed that it will be submitted on closure to commissioning.
12 Completion of the commissioning activity at each site
M/s Alstom and PGCIL representatives were requested by constituents to certify the completion of the commissioning activity at each site.
13 Mandatory spares PGCIL had agreed to furnish the details about the
mandatory spares supplied at each site. Mandatory
spares (servers and switches) supplied at each control
centre where main hardware supplied.
Mandatory spares (servers & switches) supplied at
each control center where main hardware
supplied.
5.28 Status of Voice communication between regional entities and SRLDC
(Item No. 17 (d) of enclosed SRLDC letter dated 30.08.2017)
5.29 Video Conferencing facility at SLDCs
AP PUDU
APSLDC informed that they would be taking up themselves and claim from M/s ALSTOM.
Puducherry would take up VC requirement in the next financial year 2017-18.
5.30 Status of important elements
ICT at Madurai It was noted that the provision of one No. of 500 MVA additional ICT at Checkanoorani 400/230 kV S/s in PGCIL end 400 kV side was commissioned on 29.12.2017. LV side 230 kV Bay work is under progress and would be completed on 30.09.2017. In the 134th OCC Meeting TANTRANSCO had informed that tender was opened on 16.05.2017 Completion of Kamudhi bay at Karaikkudi – PGCIL and TN SLDC to update In the 134th OCC Meeting, PGCIL had informed that the works will be completed by November 2017. TANTRANSCO had expressed concern over commissioning of bays.
5.31 Advance intimation regarding first time synchronization of transmission elements with all necessary
Agenda for 135th OCC Meeting to be held on 12.09.2017 at SRPC Bengaluru Page 21
5.31.1 The approved procedure needs to be followed.
5.32 Communication requirement for ensuring data /voice to RLDC/ SLDC during Natural
Disasters SRPC vide letter dated 10.07.2017 had taken up the issue with CEA on
Communication requirement for ensuring data /voice to RLDC/ SLDC during Natural
Disasters. It was requested to CEA that the way forward to the above issue may kindly
be suggested.
5.33 Letter from MNRE 5.33.1 In the 134th OCC Meeting SRLDC informed that SRLDC has received a letter from MNRE.
The following was noted.
Ministry of Defense has requested MNRE to formulate a methodology to switch
ON or OFF the wind farms/turbines near to IAF/Railways during war time using
centralized system in order to avoid any interference to IAF operations in the
war.
Wind power division of MNRE has come up with the methodology that could be
adopted by the wind turbine operators in foreseen situations.
Installed capacity of wind mills and wind farms that are commissioned near the
vicinity of IAF are required to be submitted to MNRE.
Power project developers should establish a centralized monitoring and control
system and such CMCS should be capable of switching all the wind turbines in
the respective wind farms. The communication between CMCS and the
individual WTG in the wind farm should be independent of internet.
In addition to this wind farm developers should have internet based control
system, SCADA which can be put at any of the locations depending on the
requirement.
Wind farms should have SCADA and CMCS operational. Each wind generator
should have the provision to switch ON manually also.
Wind developers should demonstrate the operating procedure to nearby Air
force officials once in a year, respective state nodal agency and STU.
Wind developers should assure that all prerequisite approvals including all
safety measures are obtained from respective STU/CTU in order to assure the
above mentioned activities whenever required.
MNRE had requested SRLDC to review the procedure/contents and furnish the
comments/suggestions by taking the views of SLDCs also.
6.41.2 SRLDC had informed that SRLDC is writing a letter to all the concerned and States are
requested to furnish the information as sought by MNRE. They would seek clarity on
„vicinity‟ from MNRE.
6 GRID FREQUENCY
6.1 High Frequency
a) High frequency at Load Change Over.
Agenda for 135th OCC Meeting to be held on 12.09.2017 at SRPC Bengaluru Page 22
b) Status review of implementation of staggered load change over within the constituents
as per the decision of 23rd SRPC meeting, moderating own generation, surrendering of
ISGS power in advance and other actions by Regional Entities to avert high frequency
excursion.
c) Pump Mode Operation of Nagarjunasagar/Srisailam LB/Kadamparai HEP units. 6.2 Low Frequency
a) Summary statement of different violation messages issued by SRLDC to each constituent as per new IEGC Amendment.
b) In the 124th OCC Meeting it was suggested that SRLDC may identify incidents of UD/OD for Analysis by States. SRLDC to furnish the incidence for analysis, if any.
c) In the earlier OCC Meetings SRLDC had suggested that ADMS settings may be changed to 49.9 Hz. and contingency plan w.r.t Tamil Nadu needs to be reviewed considering generation loss at pooling station level. TANTRANSCO was suggested to revert back.
(Item No. 5 of enclosed SRLDC letter dated 30.08.2017)
7 VOLTAGE PROFILE
7.1 Low voltage
a) Details of Capacitors installed during August 2017. Details of the healthy/faulty
capacitors to be furnished.
b) KPTCL to furnish the updated status of the following:
Issues with BESCOM
Commissioning of 30 MVAR Capacitor banks at Somanahalli.
UV Relay
State Location identified for implementation
Status of implementation /Remarks
KPTCL Somanahalli
Nelamangala
Hoody
For Second Stage a letter had been communicated to BESCOM to identify the new set of feeders as the existing list of feeders configured will not suffice the required relief.
In the 134th OCC Meeting KPTCL was suggested that in case of BESCOM was not able to
identify the feeders; feeders at higher voltage level may be identified to trip through
SCADA.
(Item No. 6 (a) of enclosed SRLDC letter dated 30.08.2017).
7.1.1 Installation of Shunt Capacitors
Agenda for 135th OCC Meeting to be held on 12.09.2017 at SRPC Bengaluru Page 23
7.1.1.1 The information regarding installation/healthy capacitors in the required format needed to be
regularly furnished every month. SRLDC requested that installation & ensuring healthiness
of capacitor banks at distribution level should be ensured by all the constituents.
7.1.1.2 PSS/E Base Case model was received from the states of SR for low voltage scenario. In the
134th OCC Meeting it was noted that CPRI may submit the Report within a Weeks time.
7.2 High Voltage
7.2.1 High Voltage at Nizamabad 765 S/s., Mamidippili, Malkaram, Bhoopalappalli, Gajvel,
Singreni, Suryapet, Srisailam, Shakarappalli, Mahaboobnagar, Dindi, Kurnool765kV,
Satenappalli, UVKonda, Jamalamadgu, Narnnor,Ghani, Raichur,Narendra,
Kaiga,Udupi,Talguppa, Hassam,Mysore,Tumkur,Hiriyur,Tiruvalam,Almathy,Kayathar,
Karaikudi, Kamudhi
(Item No. 7 (a) of enclosed SRLDC letter dated 30.08.2017).
7.2.2 Status review of GT Tap positions
7.2.2.1 GT tap Positions - GT taps yet to change as per recommendation:
Station
Unit Present Tap And Corresponding Voltage(In kV)
Recommended Tap And Corresponding Voltage(In kV)
Remarks
ISTS connected Generators:
Kaiga I 1 & 2 6 & 229.125 7 & 223.25 MVAR interchange as per Special Meeting to be ensured. Kaiga II 3 & 4 3 & 409.5 4 & 399
APGENCO/APSLDC
IPPs of AP It is recommended that all IPPS under APSLDC could be advised to change their Tap position corresponding to voltage level of 400 kV / 220 kV.
KPCL/KAR SLDC
Sharavathi 9 & 10 2 & 231 4 & 220 KPCL informed that at Sharavathi new GTs (Thoshiba Make) were procured for Units 9 & 10 which were expected within one years. Tap change would be carried out after receiving the ICTs.
UPCL 1 & 2 4 & 409.5 5 & 400 Observed rotor teeth temperature issues. 2 x 125 MVAR reactors agreed in 39th SCPSPSR. It was suggested that their MVAR absorption should be around 50-60 MVAR in case
Agenda for 135th OCC Meeting to be held on 12.09.2017 at SRPC Bengaluru Page 24
they are not able to change Tap.
TANGEDCO/TN SLDC
Tuticorin TPS 1,2,3,4 5
8 & 243 230 All the GTs in TTPS are kept in Tap No. 10.
MTPS St.III 1 6 & 409.5 7 & 399 Provision of Bus Reactor is being carried out by GCC/TANTRANSCO, Salem. After the provision of Bus Reactor the GT Tap will be increased to 7(399 kV) from Tap-6. Reactor bay works were completed at present and allotment of reactor is awaited.
7.2.2.2 GT taps of all new units getting synchronized to grid should be kept at the nominal grid
voltage level of 400 kV or 220/230 kV. SRLDC would ensure the requirement for ISTS
connected generators while SLDCs should ensure it for their embedded generators.
7.2.2.3 A Special Meeting was convened on 04.04.2017 to discuss on the MVAR
absorption/injection. The minutes of the Meeting are available at SRPC Website.
7.2.2.4 MVAR Interchange/MVAR capability testing
Nodal Officers may kindly ensure that the data reaches SRLDC/SRPC in time (by
fourth of every month) so that SRLDC can correlate it with SCADA data and analysis
could be done facilitating actions for further improvement.
Recommendations finalized in the Special Meetings were required to be implemented.
All the SLDCs to kindly monitor VAR absorption/injection of generating units in their respective control areas in real-time.
7.2.2.5 Status review of Bus/Line Reactors, Line Reactors and STATCOM
7.2.2.5.1 Status of implementation of Bus / Line Reactors approved in the Standing Committee /
SRPC pending for commissioning by the SR constituents is furnished below:
Entity Bus Name Status REMARKS
KPTCL
Hoody Reactor erected on platform.
October 2017
Nelamangala Reactor erected on platform
December 2017
Entity Bus Name Capacity in MVAR
Approved in
Type
Remarks
PGCIL Yelahanka 2x63 Bus
Deferred as per 40th SCPSSR. When Madhugiri line will come it will be expedited.
Cuddapah 50 to 125 39th SC Yet to be awarded
APTRANSC Vemagiri 125 Bus Kalpakka, Vemagiri and
Agenda for 135th OCC Meeting to be held on 12.09.2017 at SRPC Bengaluru Page 25
O Kurnool 125 36th SC
Bus Kurnool is expected by October 2017. LoA issued on 18.06.2017. Engineering and foundation works are under progress. Awaiting for APERC approval for Chitttoor Reactor. Commissioning by March 2018.
Kalpakka 125 Bus
Chittoor 125 39th SC
Vijayawada 125 39th SC
It was noted that a separate reactor at Vijayawada in scope of AP had been identified. The exact location could be firmed up by APTRANSCO.
APTRANSCO/ APGENCO
VTPS Stage IV
125 39th SC
APGENCO informed that reactor enquiry was being taken up. It was noted that this reactor was different from the APTRANSCO reactor.
KPTCL
Davangere 125 39th SC KPTCL informed that they had taken up with CEA for reviewing. During studies no reactors had been considered at that area and arrived at 125 MVAR requirement. Now two reactors had come at Guttur and Talaguppa.
Talguppa 125 39th SC
TANTRANSCO
Almathy 125 39th SC Tender under progress
Kayathar 125 39th SC Tender under progress
TANTRANSCO/ TANGEDCO
Mettur 125 39th SC Diverted from Palavadi. Structural works are over
TSTRANSCO
Mamidipalli 125
36th SC
Bus Gazwel: Commissioned on 31.03.2017 Expected to be commissioned in September 2017. Malkaram commissioned
Gajwel 125 Bus
Sankarapalli 125 Bus
Mehboob Nagar
125 Bus
Malkaram 125 Bus
TSTRANSCO: Sanction of funding from PSDF is received for 5 Nos of 125 MVAR reactors from MoP on 05.09.2016. Works for all five reactors awarded in September 2016 and works are in progress.
TSTRANSCO/ TSGENCO
Srisailam LB 125
39th SC
Erection of GIS Bus reactor is not suggestible due to financial implications and space constraint in 400 kV GIS of SLBHES. Hence, the erection of Bus reactors
Agenda for 135th OCC Meeting to be held on 12.09.2017 at SRPC Bengaluru Page 26
will be examined at other end. TSGENCO was requested to take up the issue with Standing Committee.
NPCIL Kaiga 2 x 125
Bus
KGS informed that both the reactors are expected to be commissioned by December 2019. Financial approval had been received. They were in the process of floating the tender.
UPCL Udupi 2 x 125
39th SC
KPTCL had informed that the line is planned to be LILOed at Drinking water substation between UPCL and Hassan. Subsequently the studies would be put up to Standing Committee. UPCL will submit the issues to KPTCL and KPTCL will discuss with PCKL to sort out issues. UPCL had submitted all the information as required.
In the 134th OCC Meeting APTRANSCO had informed that first 125 MVAR reactor at
Ghani had been commissioned on 24.04.2017. Additional 125 MVAR bus reactor works
are under progress. 80 MVAR reactor at Jammalamagudu and Uravakkonda would be
commissioned in December 2017.
7.2.2.6 NGR bypass of Reactors
7.2.2.6.1 Commissioning of NGR bypass breaker/isolator for all reactors in SRTS I had been
completed except the following
400 kV Nellore-Thiruvalam line I & II ,Thiruvalam-Kurnool I & II, Kozhikode-Mysore I & II line reactors : November 2017
(Item No. 7(b) of enclosed SRLDC letter dated 30.08.2017).
7.2.2.7 Reactive Power Planning
7.2.2.7.1 Status update on capacitor installation is given below:
Utility Reactive Power Planning Voltage level
Remarks
APTRANS Kadapa: 273.6MVAR On 33 kV side
14.4 MVAR commissioned
Agenda for 135th OCC Meeting to be held on 12.09.2017 at SRPC Bengaluru Page 27
CO
Vijayawada: 136.8 MVAR
Visakhapatanam:151.2 MVAR
0 MVAR commissioned
7.2 MVAR commissioned
APSPDCL 802 MVAR
70 MVAR commissioned
APEPDCL 276 MVAR
0 MVAR commissioned.
KPTCL Bengaluru Tr. Zone:708.8 MVAR
12.1 kV LOA issued.
Bagalkot Tr. Zone :258.1 MVAR
12.1 kV Material supplied. Erection completed/under progress.
Hassan Tr. Zone 150.8 MVAR
Material supplied. Erection completed/under progress.
Mysore Tr. Zone :60.9 MVAR
3x2.9 MVAR commissioned
Gulbarga Tr. Zone :98.60 MVAR
No update
Tumkur Tr. Zone :281.3 MVAR
12.1 kV 40.6 MVAR commissioned. 34.8 MVAR EI approval awaited.
KSEBL
360 MVAR
66 kV Works will be taken up after approval.
11kV
TANGEDCO
34 x 2.4 MVAR 11 kV
16 x 2.4 MVAR 22 kV 14 x 2.4 commissioned
35 x 2.4 MVAR 11 kV Tender to be floated.
51 x 2.4 MVAR 22 kV Tender to be floated
13 x 24 MAVR 110 kV Tender under negotiation.
82 sets of 11 kV, 2.4 MVAR Capacitor Banks in Coimbatore Region
11 kV Tender to be floated.
822 MVAR capacitors at Distribution level had been commissioned out of 931 MVAR capacitors planned.
Balance 109 MVAR to be commissioned. However, for further enhancement of Reactive Power, Capacitor bank provisions have to be arranged by Planning/Transmission wings.
7.2.2.7.2 SRPC/SRLDC had requested all the states to come up with the updated information like till
date commissioned, plan for new commissioning, quantum in working condition, action
taken to rectify/replace faulty capacitors, etc.
8 Network Protection/Security issues
8.1 U/F & df/dt Relays Schemes
8.1.1 Implementation of SRPC recommended quantum
Agenda for 135th OCC Meeting to be held on 12.09.2017 at SRPC Bengaluru Page 28
It was noted that all the States had implemented and df/dt schemes fully. All the
Constituents were requested to furnish the details of the feeders implemented in AUFR &
df/dt schemes along with the status of SCADA mapping as per the specified Formats.
In accordance with clause 9 (2) of CEA (Grid Standards) Regulations, 2010, all
constituents shall submit a detailed report of operation of AUFR at different frequencies to
SRLDC and SRPC on daily basis. It was noted that only KSEBL and PED were submitting
the daily report regarding operation of relays.
8.2 SCADA mapping of feeders of AUFR & df/dt schemes
8.2.1 As per CERC vide Order dated 27.11.2015 on Petition No. 60/MP/2014, SRPC vide letter
dated 29.01.2016 had submitted the status report duly certified by SRLDC and SRPC
w.r.t implementation of SCADA mapping of all the constituents to Hon‟ble CERC. SCADA
mapping confirmation report of KSEBL had also been submitted to Hon‟ble CERC.
(Item No.8 (a) of enclosed SRLDC letter dated 30.08. 2017).
The status as updated in 134th OCC Meeting is as follows:
State SCADA mapped
%
Status
AP 64 APTRANSCO informed that 20 RTUs had been
commissioned out of 25 and have achieved 64 %.
5 would be commissioned shortly. Balance RTUs
are covered under OPGW scheme approved
through PSDF.
TS 79 TSSLDC had informed that with 6 RTUs they were
likely to achieve 100% mapping.
TN 92 Additional RTUs needed to be procured for 100%
SCADA mapping. 100 % data visibility will be
ensured by June 2017. Transducers to be procured
and expected by June 2017.
SRPC/SRLDC requested that a monthly report on the action taken to reach 100 %
availability may be furnished to SRPC/SRLDC.
8.2.2 APTRANSCO and TANTRANSCO were requested to initiate the action to achieve the 100
% SCADA visibility.
8.2.3 Status update on action taken on Joint Validation Report
8.3 Special Protection Systems
8.3.1 SRPC had observed that the requirement of SPS may be required to be reviewed. There is
no ATC/TTC linked with it.
8.4 System Protection using Optimization Technique (SPOT)- SRLDC proposal
Agenda for 135th OCC Meeting to be held on 12.09.2017 at SRPC Bengaluru Page 29
a) Integration of all the SPS status information and indication of which SPS signal is
generated to be ensured by all entities in SRLDC SCADA system.
b) Additional DTPC requirement may be given by constituents to Powergrid for SPS
singal transmission
c) Discussion on action plan required
8.5 SPS operations
8.5.1 The SPS Operations during the month of August 2017 if any to be furnished by SRLDC.
8.5.2 HVDC Talcher - Kolar Pole 1&2 tripped on 23rd July 2017 at 17:07 Hrs. SPS trip signal 1
and 2 operated and load shedding details had been furnished by respective states. It is seen
that there was no load relief in Andhra Pradesh and Kerala upon operation of SPS trip signal
1 & 2. Also in case of Karnataka and Tamil Nadu the actual load relief was not as per the
desired values. It was noted that a total expected relief of 1,655 MW the realised relief
was only 564 MW which is quite alarming.
8.5.3 The following was informed by the states:
AP informed non receipt of SPS from Kolar end at 220 kV Chinakkapilly for trip
signal I and Gooty, Anathpur, somayajapally, Narnoor for trip signal II.
KSEBL had informed that no trip signal was received at DTPC installed at
Madakkathara and Kanhirode stations. Also a major alarm was persisting at
kanhirode DTPC.
TN informed that trip signal 1 was not extended to KR Thoppur station of
TANTRANSCO from the DTPC installed at KR Thoppur station of PGCIL. Hence
the trip pulse could not be extended to loads at Unjani, Pudansandhai and
Deviakurchi being fed from KR Thoppur TANTRANSCO.
8.5.4 SRPC had suggested that once again mock exercise may be carried out and identify
the problems. This issue would be put up in the next communication/SCADA
meeting.
8.5.5 Subsequently SRLDC vide letter dated 18.08.2017 had requested SRTS II,
Powergrid to kindly examine the healthiness of communication link from Kolar to
respective states locations and healthiness of DTPCs so as to ensure that the
desired load relief is obtained.
8.6 Automatic Demand Side Management Scheme (Petition No. 250/MP/2012) & GSES
(Petition No. 265/MP/2012)
8.6.1 It was noted that the issue of changing the frequency setting to 49.9 Hz was discussed in the
TCC/ SRPC Meetings it was agreed to retain the settings at 49.8 Hz till the next TCC/SRPC
meetings.
Agenda for 135th OCC Meeting to be held on 12.09.2017 at SRPC Bengaluru Page 30
8.6.2 SRLDC had pointed out that similar to existing ADMS logic (O/D), backing down of
generation during the sustained U/Ds during high grid frequency may be required.
8.6.3 SRLDC had pointed out that ADMS was set at much lower point at 49.80 Hz which needs to
be enhanced to, 49.90 Hz.
OCC forum had felt that it could be reviewed in the next TCC/SRPC Meeting
8.7 Grouping of loads (IEGC clause 5.4.2 (e))
8.7.1 As per IEGC, to maintain the frequency within stipulated band and also to ensure network
security, the interruptible loads were to be arranged in four groups of loads, This was for the
purpose of scheduled power cuts/load shedding, loads for unscheduled load shedding,
loads to be shed through UF relays, df/dt relays and loads to be shed under any SPS
scheme. These loads are to be grouped in such a manner that there is no overlapping
between different groups of loads.
8.7.2 The issue was to be noted for compliance by the concerned utilities. SRLDC requested all
the states to kindly furnish the updated details in this regard.
8.7.3 Tripping Details/Reports
In various forums SRLDC had raised concern that it was not getting tripping
information/data within 24 hrs as per IEGC/CEA regulations and sometimes the
information from both the ends was not being received. Also at times, tripping details only
were being received without DR& EL details. SRLDC was unable to analyze events on
account of non-receipt of details of tripping in a timely manner. SRLDC had stated that all
tripping details should be uploaded on the SRLDC web portal. Para 29 of Hon‟ble CERC
Order dated 20.02.2014 in respect of Petition No.146/MP/2013 was brought to attention of
the OCC. Non furnishing of timely tripping details would be treated as non-compliance.
Procedure for timely furnishing information was needed to be streamlined by the utilities. It
was noted that tripping information details were to be uploaded within the stipulated time
frames.
8.7.4 Declaration of availability and healthiness of various protection / defense mechanism
8.7.4.1 SRLDC had stated that the healthiness certification was not being received in timely manner
from all the constituents.
8.7.4.2 Healthiness certificates and other reports were being sought as per directives of higher
bodies. Validated certificates needed to be communicated in a timely manner.
9 LVRT Implementation
9.1 Hon‟ble CERC has passed Order in respect of Petition No. 420/MP/2014 on 05.01.2016. The
Order directs a number of actionable points by various utilities for compliance of LVRT, CEA
& CERC Regulations etc. Three Special Meeting were conducted at SRPC Bangalore on
Agenda for 135th OCC Meeting to be held on 12.09.2017 at SRPC Bengaluru Page 31
05.02.2016, 18.04.2016 & 05.07.2016 (Meeting minutes are available at SRPC website).
This issue was further discussed in the Special TCC Meeting held on 02.08.2016.
9.2 The following had been noted in the earlier OCC Meetings:
SRLDC had pointed out that PMU at Pooling station was required to assess LVRT
performance.
Status update on P&C SCADA scheme by TANTRANSCO
TANGEDCO scheme at WTG level
SLDCs to furnish the company wise installed capacity and LVRT/HVRT characteristic
at Renewable energy pooling stations.
9.3 Geographic picture of the Wind/Solar generators and extend it to SRLDC through ICCP.
9.4 All the constituents were requested to ensure provision and enabling of LVRT feature in all the
upcoming wind/solar generators before declaring COD. SLDCs were requested to approve
connectivity to new generators only on confirmation of availability of LVRT feature and other
CEA/CERC requirements. Monthly report of compliance needs to be furnished for new
wind/solar generators added to the grid.
9.5 Formulation of plan for procurement and Placement of Emergency Restoration
System (ERS) in the country
9.5.1 As per ERS requirement outlined in MoP letter dated 05.12.2014 status update on ERS is
given below:
Transmission Utility
Requirement as per MoP
Existing Status/Remarks
APTRANSCO 3 2 ERS III-submitted for approval of PSDF funding.
TSTRANSCO 1 TSTRANSCO had informed that earlier tender had been cancelled and it was being retendered. Subsequently, it would be taken up for PSDF funding.
KPTCL 2 2
KSEBL 1 Tenders to be floated. Being followed up.
TANTRANSCO 2 Retendering.
PED NIL NIL
PGCIL 4 (2 Nos. Additional)
4 (SR I & SR II is having 2 no. Each)
765 KV ERS (one each for SR-I and SR-II) tendering under progress.
Agenda for 135th OCC Meeting to be held on 12.09.2017 at SRPC Bengaluru Page 32
9.5.2 CEA vide letter dated 21.07.2017 had informed that a Meeting was held in the Cabinet
secretariat under the Chairmanship of Secretary (Security) on 28th June 2017 to discuss
the action taken report on the decisions taken at the early meeting on 9.03.2016 on the
Crisis Management Plan in respect MoP. It was noted that ERS were in procurement
stage in most of the states and the response from the states was not very encouraging.
Secretary (Security) has sought a note from CEA in the matter so that he may take up the
matter with the concerned States at the highest level. CEA requested that state wise
requirement and current availability of ERS and the action taken on/status of procurement
of ERS may please be sent to GM Division for onward transmission to Cabinet
Secretariat.
9.6 SCADA & COMMUNICATION ISSUES
9.6.1 A Special Meeting was held on 07.02.2017 to deliberate on pending
SCADA/Communication issues. Minutes of the Meeting is uploaded on SRPC website. The
status of pending Items as deliberated in the Special Meeting/subsequent OCC Meeting is
as follows:
S.No Issue Action Plan
1 Meeting with M/s ALSTOM
regarding AMC issues,
punch points
8.5 Alstom completed the pending works except some of the on-site training modules, for which schedule was given Alstom to complete by September 2017.
8.6 PGCIL informed that deduction amount had been communicated.
8.7 KSEBL requested for detailed breakup of the payments. 8.8 SR I informed that they had requested AP & TS for the
deductions on account of delay. 8.9 TSTRANSCO informed that they had requested for
modification in EMS package which they would be taking up as a separate order with M/s ALSTOM for around 77 Lacks.
8.10 TSTRANSCO had requested estimate for back up SLDC. PGCIL informed that the request had been communicated to Head Quarters.
2 ICCP link between RTAMC and SRLDC
Link is established and database tables have been exchanged. ICCP association is in progress by SRLDC and NTAMC/Manesar. SR II RTAMC provided the data & SRLDC to further carry out the job.
3 Data discrepancies in ISGS/IPP/PGCIL/STUs
Fresh list of points received from SRLDC on 05.07.2017 and same shall be attended by July end.
4 Providing additional RTU at NTPC Talcher
RTU procurement is under progress.
5 Protection coupler replacement for Kayamkulam Transmission system
Letter from KSEBL received on 23.05.2017. Actual expenditure of Protection Couplers towards PGCIL assets shall be borne by PGCIL at the rates of LOA to be placed by M/s KSEBL. KSEBL to examine the option of buyback of the old panels to be looked into or handover the panels to PGCIL. .
6 OPGW stringing on balance portion of KPTCL lines
Except Hassan-Santhigrama(7.4 kM) OPGW stringing is completed on all the lines of KPTCL. Because of non-readiness of direct line, KPTCL recommended to execute the connectivity through 3 different lines of 35 km and the same may not be possible in the on-going project as the supplies are completed.
Agenda for 135th OCC Meeting to be held on 12.09.2017 at SRPC Bengaluru Page 33
7 Migration of SCADA periphery in line with SEM
Both AP & TS: Migrated to SEM based philosophy from 11:00 hours of 09.05.2017. TN migrated on 08.06.2017. KPTCL migrated from 04.07.2017.
8 SCADA Data failure Protocol
RTU not reporting/data failure would be communicated to the concerned entity/user with a copy to PGCIL. User would take lead role in getting the issue resolved. User/SRLDC would ensure necessary verification at their ends as explained in the training. Parallely, PGCIL would look into communication issues. User/SRLDC would appraise PGCIL about the verification at their end for PGCIL to sort out the communication issues.
Official email ID for SCADA issues to be created for each entity/User involved for easier communication and proper delivery of information. All correspondences regarding any SCADA issue to be made through this mail ID only. Details to be communicated to SRLDC/SRPC within a weeks‟ time.
SR II informed that the procedure is being followed
9 Integration of new elements in SRLDC/SLDC SCADA
SR I /SRII noted and shall be complied.
10 Issues with Orange Exchange
It was noted in the Meeting that a Meeting was held on 16.03.2017 at SR II Bangalore and the issues are being addressed. Except Remote sub-scriber units with PLCC links, all issues have been addressed.
9.7 220kV station network and 220 kV station real time data from SR constituents may also be
emphasized and integrated. Although the above is discussed in SCADA Meeting it can be a
part of OCC Meeting also.
9.8 SRLDC had invited attention of the forum that CERC had brought out Order on Suo moto
Petition 007/SM/2014 dated 29.01.2016 regarding SCADA. It was directed by Hon‟ble
CERC that NLDC and respective RLDC are directed to update the status of telemetry every
month at their website and persistent non availability of data from the generating
stations/substations be taken up in RPC meeting for appropriate direction and action. Also
NLDC is directed to submit user wise latest telemetry by 31.08.2016. SRLDC informed that
they have started posting this information from February 2016 on their website
9.9 Compiled Telemetry status – Utility wise- as directed by Hon’ble Commission
Hon‟ble Commission vide order dated 19.12.2013 on Suo-moto petition No.
56/SM/2013 had directed all the utilities to provide the required telemetry within six
months of this order.
It was requested that MAPS, KGS & KKNPP may please furnish the compliance
status of pending SCADA inputs the earliest. Details in this regard were available on
SRLDC web site.
For KKNPP only 2 points are pending w.r.t GT tap position. Re -tendering was going
on and it will take 5 more months to complete the works.
Agenda for 135th OCC Meeting to be held on 12.09.2017 at SRPC Bengaluru Page 34
10 PHYSICAL AND CYBER SECURITY/CRISIS MANAGEMENT PLAN/BLACK START
PROCEDURE
11 Physical and Cyber Security
Status update on Crisis Management Plan(C&DMP) of Power Sector is to be furnished every
quarter. Information regarding Cyber Security was to be furnished to Chief Engineer, DPD,
CEA, Sewa Bhavan, and New Delhi-110066. Report on Physical Security, other Mock Drills
for CMP, Mock Drill for Black Start Restoration was to be furnished Chief Engineer, DMLF,
CEA, Sewa Bhavan, and New Delhi-110066. A copy of the reports was to be sent to SRPC
Secretariat ([email protected] and [email protected]). Information required by CEA
(vide letter dated 26.11.2013) regarding Security of power installations was to be furnished
to CEA.
12 Black Start Procedure
Status needs to be furnished in the following format :
State BSRP reports for Jan 2017 to June 2017
BSRP schedule for July 2017 – Dec 2017
Point to point mock exercise report being furnished
Updated list of Nodal Officer
Workshop Schedule
12.1 Planning of Black Start Mock drill of Nuclear Power Plants
Mock drill at KKNPP, KGS and MAPS. Kaiga and KKNPP.
Development of mock exercise procedure for Individual Stations/Systems.
Point to point mock exercise for black start by all constituents.
Conducting mock exercise from RTPS to Jurala, Nagheri to BTPS and Kaiga NPP.
12.2 Conducting mock exercise from RTPS to Jurala, Nagheri to BTPS
SRLDC appraised the forum of the proposed Black Start from Nagjheri to BTPS. KPTCL
was requested to revert back with the details. It was agreed that Black Start from Jurala
to RTPS would also be carried out subject to the generation at Jurala. It was agreed that
SRLDC would furnish a draft procedure and coordinate for the final date.
12.3 The format needed to be filled by the respective states and sent to SRLDC within 10 days. It
was also requested to submit the reports of mock exercise carried out within 7 days.
(Item No. 9(a),(b),(d) & (f) of enclosed SRLDC letter dated 30.08.2017).
12.4 Priority for Railways/Metros in the matter of Restoration of Supply
The following were noted earlier:
Agenda for 135th OCC Meeting to be held on 12.09.2017 at SRPC Bengaluru Page 35
KPTCL: to expedite on the actionable points of KPTCL/BMRCL which were finalized in
the Special Meeting.
KSEBL: Vide letter dated 06.06.2016 had furnished the Operating Procedure for
extending supply of power to Kochi Metro.
TANTRANSCO/Southern Railway: The follow up of actionable points finalized in the
special meeting in respect of Chennai Metro may be expedited.
TSTRANSCO: was requested to take proactive action in respect of Hyderabad Metro.
13 RGMO
13.1 RGMO response had been deliberated in various Special/OCC/TCC/SRPC meetings.
Inadequate response was an area of serious concern and there was no noticeable
improvement.
13.2 In earlier OCC Meetings, the following had been noted:
SLDCs were requested to analyze the RGMO instances posted by SRLDC for the
generators in their control area and take up action as per 84/MP/2015.
Inadequate Response to be taken up with SERC (Petition No.302/MP/2013).
Action on recommendations finalized in the Special Meetings needed to be taken
by generators/states. All generators were kindly requested to take all steps to
ensure intended RGMO/FGMO response.
As per the order in RGMO Petition No. 302/MP/2013, the units (including state
embedded) shall not be scheduled beyond their ex-bus generation corresponding
to 100% of their installed capacity.
13.3 RGMO implementation/ Extension of RGMO status point to SLDC
State/Entity RGMO Status extension to
SLDC/SRLDC
Comment
TS Thermal updated. Hydro
Manually updated at the
TSSLDC
TSTRANSCO is requested to take up the
issue with GENCO and solve the issue
KAR RTPS-4, Supa and LDPH RTPS Unit IV: will be made available
during R & M works. LDPH: Carried out
the works. Complete wiring is over.
Extended upto SLDC. Supa: yet to be
carried out.
KER Sholayar Sholayar: one unit extended. Rest will be
extended during R & M.
Agenda for 135th OCC Meeting to be held on 12.09.2017 at SRPC Bengaluru Page 36
14 TRANSMISSION NETWORK ISSUES AND SYSTEM OPERATION ISSUES
14.1 Loadability of ICTs and revisit of the associated protection settings to prevent cascaded
tripping of ICTs / high loading of transmission lines
Over loading of both ICTs and N-1 violation at Hoody, Gazuwaka,Nellore.
Status of Operationalization of ICT -3 at Madurai. (230 kV side works are
pending)
14.2 Insufficient action in controlling the loading of ICTs leads to N-1 criteria violation in
compliance of Regulation 3.1 f(8) of CEA(Grid Standards) Regulations 2010 and Regulation
3.5 a(i) of CERC Indian Electricity Grid Code Regulations 2010.
14.3 SRLDC had requested all the constituents that whenever real time messages were issued
to control over ICT loadings, constituents should be committed to take necessary steps/load
shedding to curtail the overloading. SRLDC requested for urgent action to alleviate the
loading of 400/220 kV ICTs. A long term solution of augmentation/load reconfiguration
needed to be considered / implemented in view of grid security. Action Plan of constituents
to restrict the loading to permissible limit may kindly be furnished to SRLDC and immediate
action needs to be initiated.
(Item No. 8(c) of enclosed SRLDC letter dated 30.08.2017).
15 Prolonged Outages
15.1 Status review of prolonged outage of grid elements in SR & Realistic Action plan for revival
of the prolonged outage was awaited from some of the constituents. Monthly reports are
required to be submitted to CERC.
(Item No. 12(a) of enclosed SRLDC letter dated 30.08.2017).
16 Upper Sileru - Balimela line had been idle charged from 8th January 2015 from Upper Sileru
end. Revival of the line.
17 Upcoming Generating Stations
17.1 Central Sector
Station Unit Installed Capacity
MW
Scheduled date of synchronizing / commissioning
Remarks
NTPC
Kudgi TPS Stage-I
I,II, III
3 x 800= 2400
Unit-I
CoD from
31.07.2017
Unit-II.
CoD by Sep 17
Unit–III
CoD by Dec 17
NTPC had confirmed that
full DC would be ensured
from April 2018.
Telangana STPP Phase I
2 x 800 U-I CoD Jan 2020 U-2 CoD June 2020
Pudimadaka AP 4 x 1000 52 Months from Zero Date
85% share to AP. Zero date yet to be finalized. AP requested NTPC to firm up the zero date at the earliest.
Agenda for 135th OCC Meeting to be held on 12.09.2017 at SRPC Bengaluru Page 37
AP informed evacuation system would be developed by PGCIL
30th TCC: NTPC informed that the domestic coal was yet to be tied up. APTRANSCO informed that they would apply for LTA with CTU after the coal linkage is firmed up.
NLC
New Thermal Power Project
I 500 April 2018 CTU had informed that for evacuation LILO of Neyveli - Puducherry and 400 kV D/C to Araliyur lines are planned. NLC had applied for LTA of 340 MW which could be managed with the LILO of Neyveli – Puducherry. Balance 600 MW would be catered by 230 kV system of TANTRANSCO. Araliyur S/S was being developed by TANTRASCO and was expected by June 2018
II 500 April 2018
NPCIL
BHAVINI
Kalpakkam (PFBR)
I 500 Synchronization by
2017-18
COD by 2017-18
Synchronization by March 2017 COD by Sep 2017
UMPP
Krishnapatnam 3960 (6 x 660)
APEPDCL and PCKL had taken steps with their legal counsel to expedite the hearing before Honorable High Court of Delhi
Cheyyur 4000 New bids would be called
NEW PROJECTS OF STATE SECTOR & IPP
Updated status of new projects of State sector is furnished below:
Sl No
Name of project Located in
Capacity in MW
Commissioning Schedule /Remarks
1 Rayalaseema TPS ST-IV
AP 1 x 600 Synchronization by June 2017 COD by Dec 2017
2 Dr. NTTPS, Vijayawada
AP 1 x 800 2017-18
3 Krishnapatnam Stage II (U3)
AP 1 x 800
4 Polaki AP 4000 (5 x 800 MW)
5 Edlapur KAR 1 x 800
6 North Chennai Stage III TN 1 x 800 2019-20
7 North Chennai Stage IV
TN 2 x 800 Beyond 2019-20
8 Ennore TPS Exp TN 1 x 660 2018
Agenda for 135th OCC Meeting to be held on 12.09.2017 at SRPC Bengaluru Page 38
9 Ennore replacement TN 1 x 660 2018
10 Udangudi Stage I TN 2 x 660 2019-20
11 Uppur TPP (TBCB) TN 2 x 800 2019-20
12 Manuguru PPP Telangana 4 x 270 U1 : 20.03.2017 U2: 20.05.2017 U3: 20.09.2017 U4:20.09.2017
13 Kakatiya TPP Stage III Telangana 1 x 800 2017-18
14 Kothagudem TPS Phase VII
Telangana 1 x 800
15 Damaracherla (Yadadri)
Telangana 5 x 800 2018-19
Updated status of new projects of IPPs is furnished below:
Sl No.
Name of project Located in
Capacity in MW
Commissioning Schedule /Remarks
1 Meenakshi PH-II AP 2 x 350 2017-18 Untied: 640 MW
2 East Coast Energy Thermal
AP 2 x 660
2017-18 AP : 300 MW
3 Thermal Powertech (TPCIL) Unit-III
AP 1 x 660
2017-18
5 Godhna TPP, Janjir – Champa Dist, Chhattisgarh
For KAR 2 x 800 2017-18
SRLDC pointed out those new ISTS connected units should come out with detailed
metering scheme for various units commissioning schedule at least one year prior to
synchronization. The scheme needed to be discussed and finalized in the Meeting of
Commercial Sub Committee.
17.2 ATS for Yeramarus, BTPS Unit III.
(Item No. 16 (a)of enclosed SRLDC letter dated 30.08.2017).
18 LGBR & OUTAGE PLANNING
18.1 Status Review on development of load forecasting tools by SLDCs as per IEGC
Clause 5.4.2
The issue was noted for compliance by the states/SLDCs.
18.2 The following was noted from the Order dated 19.12.2013 on Petition No.
249/250/251/MP/2012
“We direct all STUs/SLDCs of the Northern Region, Southern Region and Eastern Region to
forecast their demand and make adequate arrangements to avoid dependence on
Unscheduled Interchange for meeting their demand or for injecting short term surplus power,
irrespective of the frequency”
Agenda for 135th OCC Meeting to be held on 12.09.2017 at SRPC Bengaluru Page 39
There was need for further involvement of DISCOMs for their 96 block load forecast and by
state generators of their 96 block generation forecast. SLDCs needed to play more proactive
role in this regard.
18.3 Outage deviation report for the period April 2017 –August 2017 in respect of
Generating Units/Transmission Elements of Southern Region
Outage deviation report for the period April 2017- August 2017 in respect of Generating
Units/Transmission Elements of Southern Region need to be submitted by all the
constituents which is to be communicated to Hon‟ble CERC.
19 Constituents/Generators are also requested to furnish the following Data/Information:
a. Minimum/Maximum Demand Ratio of Constituent States: Information and measures adopted may please be shared.
b. Forced/Planned outages of thermal units.
c. Status of Srisailam/Kadamparai/Nagrjunasagar: Pump mode operation.
d. Installed Capacity in MW as on 31.08.2017. Additions to Installed Capacity in July
2017.
e. Submission of details of new elements to be provided on monthly basis in the
agreed format by all the Regional Entities.
(Item No. 13 of enclosed SRLDC letter dated 30.08.2017).
f. Load Shedding in MW & MU carried out during August 2017 on daily/hourly basis.
g. Capacity in MW of Wind Mills/Renewable (Category wise) added in August 2017
by State Sector and Private Sector - to be furnished separately.
h. PLF & PAF of Thermal & Nuclear Power Stations/ISTS connected MPPs.
i. Details of Energy Exchanges by the states (including embedded IPPs/CPPs)
through Power Exchanges.
j. Constituents may apprise the OCC of surplus power available, if any.
k. Progress of works of generating units to be commissioned in 2017-18 and also
coming up in future.
l. Details of Power Cuts on Industries, Load Shedding and Power supply to
Agriculture Sector may please be furnished in the Proforma prescribed by CEA
vide their letter No. 1/AI/COR/GM-2004/3405 dated 23.11.2004.
m. Coal Stock Position to be submitted on monthly basis by Generators
(States/ISGS).
n. Uploading of hourly Load Shedding details (both scheduled and unscheduled)
effected in previous day by all the constituents in SR.
Agenda for 135th OCC Meeting to be held on 12.09.2017 at SRPC Bengaluru Page 40
o. Loss of generation due to coal shortage/technical problem needs to be furnished
for onward transmission to NLDC by 1000 hrs on daily basis.
p. Collection of data regarding Power Supply to Rural Areas
In the Meeting held at MoP on 09.04.2014 it had been decided to collect the data
invariably from DISCOMs. It is requested that the data in this regard in the
required format may please be arranged to be communicated to SRPC
Secretariat at the following E-mail addresses: msssrpc-
[email protected]/[email protected]
Data to be communicated by first week of the month for previous month.
q. Reporting the Status of implementation of the recommendations of the Enquiry Committee
Status as on last day of the month to be forwarded by 3rd day of the following
month, and that as on 15th of the month to be forwarded by 17th of the month All
the constituents were requested to furnish timely status updates
r. Energy Generation data Management from Renewable Energy Sources Monthly generation data in respect of Renewable Energy Sources was to be submitted to CEA with a copy to SRPC.
20 Any other point with the permission of the Chair.
21 Date and Venue of the next Meeting.