1 SOUTHERN REGIONAL LOAD DESPATCH CENTRE POWER GRID CORPORATION OF INDIA LIMITED.
SOUTHERN REGIONAL LOAD DESPATCH CENTRE
description
Transcript of SOUTHERN REGIONAL LOAD DESPATCH CENTRE
SOUTHERN REGIONAL LOAD DESPATCH CENTRE
POWER GRID CORPORATION OF INDIA LIMITED
SPECIAL PROTECTION SCHEMEin
INTRODUCTION LEVEL TRAINING PROGRAMME(POWER SYSTEM)
TO THE OFFICERS OFPOWERGRID G.E.T. 10th BATCH
On
17th June, 2005
by
V.K. AGRAWAL
AGM, SRLDC
SOUTHERN REGIONAL GRID
An Overview
GRID OPERATION AND CONTROL
SPECIAL PROTECTION SCHEME
KHAMMAM
VIJAYAWADANAGARJUNASAGAR
VISAKHAPATNAM
(POWERGRID)HYDERABAD
RAICHUR
GOOTY
HOODY
SALEM
UDUMALPET
TRICHUR
MADURAI
TRICHY
MADRAS
NEYVELI
CUDDAPAHDAVANAGERE
KAIGA
115
317
RSTPP
BHADRAVATI
130x216
4x2
182
151
181
173
302
308172
277
279
155
178x
2
PONDICHERY
BANGALORE
SIRSI
MUNIRABAD
PP
P
P
P
P
P
P
P
P
P
PP
P
P
N
KOLAR
PALLOM
KAYANKULAM EDAMON
TALCHER
JEYPORE
63
187
2x78
2x221
54
HOSUR
KADRA
KODASAALY
Nagjhari
1
120
60
MAPS
P
SSLMM
MMDP
THIRUVANATHAPURAM
ALMATHI
NELLORE
400 KV LINE PRESENTLY
OPERATED AT 220 KV
NELAMANGALA
KURNOOL
GAZUWAKA(AP)
SIMHADRI NTPC
HIRIYUR
189
195
267x
2
258
242
175
179
127
130x
2
221x2
146x252x2
197x2
301x2
8x4
15x2
300
28
330
ABOUT 12000 CKM
400KV TRANSMISSION
TALGUPPA
3500 MW TRANSFER CAPABILITY ON HVDC.ANOTHER 500 MW POLE TO BE ADDED AT GZK. TALCHER POLE CAPABILITY TO BE ENHANCED TO 2500 MW
GRID MAPGRID MAP
TYPICAL FLOWS ARE FROM NORTH TO SOUTH
GRID FOCAL POINT SHIFTED TO KOLAR AFTER COMMISSIONING OF HVDC
QUANTUM CHANGES IN FLOW PATTERN LIKELY AFTER COMMISSIONING OF KOODANKULAM 2000 MW
THE FIRST SCHEME: 1996THE FIRST SCHEME: 1996
KHAMMAM
VIJAYAWADA
NAGARJUNASAGAR
HYDERABAD
RAICHUR
GOOTY
HOODY
SALEM
UDUMALPET
TRICHUR
MADURAI
TRICHY
MADRAS
NEYVELI
CUDDAPAHDAVANAGERE
KAIGA
115
317
RSTPP
BHADRAVATI
130x2
164x
2
182
151
181
173
302
308
172
277
279
155
178x
2BANGALORE
SIRSI
MUNIRABAD
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
N
JEYPORE
63
187
2x221
54
Kadra
Kodasally
Nagjhari
1
120
60
MAPS
P
NELLORE
By Tripping of Salem-Bangalore and
Cudddapah-Madras Southern Grid was
getting devided into two blocks
NELAMANGALA
GAZUWAKA
HIRIYUR
189
267x
2
258
242
175
179
127 130x
2
221x2
146x2
52x2
301x2
300
28
330
FIG-2
THE SR GRID IN
1996
THE FIRST SCHEME: 1996THE FIRST SCHEME: 1996CONDITIONSCONDITIONS
Line Name Frequency Below (Hz)
POWER FLOW(MW)
Time delay (second)
Type of Relay
CUDAPPA-MADRAS 47.8 0.5 UF
SALEM- BANGALORE
47.8 1 UF
CUDAPPA-MADRAS 48.0 100 MW towards CUDAPPA
0.5 RPUF
SALEM- BANGALORE
48.0 300 MW towards BANGALORE
1 RPUF
GRID OPERATION:GRID OPERATION: A TIGHT ROPE WALK A TIGHT ROPE WALK
BLACK-OUTVOLTAGE
COLLAPSE IN-ECONOMIC
OPERATION
INSTABILITYPOWER
SWINGSINCREASED
LOSSES
SPECIAL PROTECTION SPECIAL PROTECTION SCHEMESSCHEMES
DEFINITIONDEFINITIONPROTECTION SCHEME DESIGNED PROTECTION SCHEME DESIGNED
TOTO
DETECT ABNORMAL SYSTEM DETECT ABNORMAL SYSTEM CONDITIONSCONDITIONS AND TAKE AND TAKE
PREDETERMINED CORRECTIVE ACTIONPREDETERMINED CORRECTIVE ACTION
(Other than isolation of faulty element)(Other than isolation of faulty element)
TO TO
PRESERVE SYSTEM INTEGRITY AND PRESERVE SYSTEM INTEGRITY AND PROVIDE ACCEPTABLE SYSTEM PROVIDE ACCEPTABLE SYSTEM
PERFORMANCEPERFORMANCE
TRADITIONAL TRADITIONAL PROTECTION SCHEMES PROTECTION SCHEMES
AND SPSAND SPS TRADITIONAL TRADITIONAL
SCHEMESSCHEMES1.1. PROTECTS PROTECTS
INDIVIDUAL INDIVIDUAL ELEMENTSELEMENTS
2.2. STANDARDISEDSTANDARDISED3.3. MANUFACTURER MANUFACTURER
DRIVENDRIVEN4.4. NARROW ‘VISION’NARROW ‘VISION’
LIMITED TO THE LIMITED TO THE FAULTY ELEMENTFAULTY ELEMENT
MAY DEGRADE SYSTEM MAY DEGRADE SYSTEM CONDITIONS FURTHERCONDITIONS FURTHER
SPSSPS1.1. DESIGNED TO DETECT DESIGNED TO DETECT
SYSTEM DEFICIENCIES SYSTEM DEFICIENCIES AND TAKE CORRECTIVE AND TAKE CORRECTIVE ACTIONACTION
2.2. EVOLVED BY EVOLVED BY EXPERIENCEEXPERIENCE
3.3. UNIQUEUNIQUE4.4. HOLISTIC APPROACHHOLISTIC APPROACH
PRE-EMPTIVE IN NATUREPRE-EMPTIVE IN NATURE PREVENTS SYSTEM PREVENTS SYSTEM
DETERIORATIONDETERIORATION
WHY SPS? WHY SPS? OPERATIONAL OPERATIONAL REASONSREASONS
OUTAGE OF HIGH CAPACITY GENERATING OUTAGE OF HIGH CAPACITY GENERATING UNITS,HVDC INTERCONNECTION OF UNITS,HVDC INTERCONNECTION OF LARGE TRANSFER CAPABILITYLARGE TRANSFER CAPABILITY
WIDE SEASONAL FLUCTUATION IN WIDE SEASONAL FLUCTUATION IN LOADING PATTERNLOADING PATTERN
STAGGERING AND ROSTERING OF LOADS STAGGERING AND ROSTERING OF LOADS
SUDDEN IMPACT ON LARGE GRIDS DUE SUDDEN IMPACT ON LARGE GRIDS DUE TO SYATEM DYANAMICS AND SWINGS.TO SYATEM DYANAMICS AND SWINGS.
WHY SPS? WHY SPS? COMMERCIAL COMMERCIAL REASONSREASONS
SKEWED GENERATION AND LOAD SKEWED GENERATION AND LOAD PATTERN AND PRESSURE ON PATTERN AND PRESSURE ON RELIABILITY MARGINS DUE TORELIABILITY MARGINS DUE TO DRIVEN BY COMMERCIAL MECHANISMS DRIVEN BY COMMERCIAL MECHANISMS
OPEN ACCESS INCREASE IN TRADE OPEN ACCESS INCREASE IN TRADE VOLUMEVOLUME
INCREASE IN COMPETITIONINCREASE IN COMPETITION
MERIT ORDER OPERATIONMERIT ORDER OPERATION
WHY SPS? WHY SPS? PLANNING PLANNING ISSUESISSUES ECONOMY OF SCALEECONOMY OF SCALE
THE SYSTEM PLANNERS TEND TO UTILIZE THE SYSTEM PLANNERS TEND TO UTILIZE THE EXISTING NETWORKTHE EXISTING NETWORK
DELAYS IN NETWORK EXPANSION DUE TO DELAYS IN NETWORK EXPANSION DUE TO ENVIRONMENTAL PROBLEMS ENVIRONMENTAL PROBLEMS
SEASONAL OVER LOADSSEASONAL OVER LOADS
LINES AND GENERATORS NOT COMING IN LINES AND GENERATORS NOT COMING IN TANDEMTANDEM
WHY SPS?WHY SPS?
Mission of power system engineers is to Mission of power system engineers is to provide Stable Secured and Reliable power provide Stable Secured and Reliable power supply at least possible cost to the end supply at least possible cost to the end consumer. SPS is an important tool in consumer. SPS is an important tool in achieving thisachieving this For System Planner It reduce the compromise For System Planner It reduce the compromise
between between cost and qualitycost and quality
For operational planner It enables to manage For operational planner It enables to manage severe severe contingencies like contingencies like
tripping of tripping of generators multiple generators multiple outage of outage of transmission lines transmission lines etcetc
POSSIBLE SYSTEM POSSIBLE SYSTEM PROLEMSPROLEMS
UNIT FAILURE
INSUFFICIENTGENERATION
TRANSFORMER/LINE FAILURE
LOSS OFLOAD
REDUCEDNETWORK
REDUNDANCY
LINE OVERLOADOR
UNSATISFACTORYBUS VOLTAGE
BUS ISOLATED
LOSS OFGENERATION
ISLANDING
SYSTEM SYSTEM COLLAPSCOLLAPS
EE
RESTORATIVE
NORMAL
A L E R T
EMERGENCYDISTURBANCE
RESTORATIVE
NORMAL
A L E R T
EMERGENCYDISTURBANCE
HIGH SPEED INTER-TRIP HIGH SPEED INTER-TRIP SCHEME AT KOLARSCHEME AT KOLAR
GOOTY
HOODY
SALEM
TRICHUR
MADURAI
TRICHY
SPBDR
NLC II
CUDDAPAH
PONDICHERY
SOMANHALLIKOLAR
HOSUR
NLC -1 EXP.
UDUMALPET
BAHOOR
KURNOOL
SOMYAZULA PALLI
TO TALCHER
HIGH SPEED INTER-TRIP HIGH SPEED INTER-TRIP SCHEME AT KOLARSCHEME AT KOLAR
GOOTY
HOODY
SALEM
TRICHUR
MADURAI
TRICHY
SPBDR
NLC II
CUDDAPAH
PONDICHERY
SOMANHALLIKOLAR
HOSUR
NLC -1 EXP.KOZIKODE
UDUMALPET
NLC II EXPBAHOOR
KURNOOL
ANANTPUR
KARAIKUDI
THIRUVARUR
INGUR
SOMYAZULA PALLI
TO TALCHER
HIGH SPEED INTER-TRIP HIGH SPEED INTER-TRIP SCHEME AT KOLARSCHEME AT KOLAR
MODE OF OPERATION
POWER LEVEL FOR GENERATING INTERTRIP SIGNAL
MONO POLAR >400 MW AND THE POLE TRIPS
BI-POLAR IF BOTH POLE ARE CARRYING > 800 MW EACH AND ONE POLE TRIPS
BI-POLAR IF POWER FLOW ON EACH > 200 MW AND BOTH POLE TRIP
KAIGA EVACUATION KAIGA EVACUATION PROBLEMPROBLEM
SPS BASED SOLUTIONSPS BASED SOLUTION
KAIGA
440 MW SIRSI
KADRA
150 MW
KODASHALLI
120 MW
GUTTUR
NAGJHERI
855 MW
HUBLI
400 KV LINE OPERATED AT 220 KV
PROBLEM OF OVERLOADING WHEN HIGH GENERATION AT KALI COMPLEX
THESE LINES ARE TRIPPED IF
>600 AMPS FOR 1SEC OR > 900 AMPS FOR 300 MSEC,
PROPOSED SPS AT PROPOSED SPS AT RAICHURRAICHUR
RAICHURN’SAGAR
MUNIRABAD
DAVANGERE
HIRIYUR
NELAMANGALA
HOODY
GOOTY
CUDDAPAH
KOLAR
HVDC LINES
FROM ER
SOMANAHALLYTRIPPING OF THESE LINES INCREASES THE FLOW ON RAICHUR-N’SAGAR LINE
LOAD CENTRE
PROPOSED SPS BASED SOLUTION
RTPS UNITS TO BACK-DOWN BASED ON FLOW ON
RAICHUR-N’SAGAR LINE
INDUSTRY EXPERIENCE WITH INDUSTRY EXPERIENCE WITH SPSSPS
REPORTED SCHEMESREPORTED SCHEMES 111111 FIRST SPS INSTALLEDFIRST SPS INSTALLED IN 1930IN 1930 SCHEMES REPORTED BY GEOGRAPHICAL SCHEMES REPORTED BY GEOGRAPHICAL
REGIONSREGIONSGEOGRAPHICAGEOGRAPHICAL L
REGIONREGION
% OF % OF SCHEMESSCHEMES
GEOGRAPHICAL GEOGRAPHICAL
REGIONREGION% OF % OF SCHEMESSCHEMES
USAUSA 20.7%20.7% EUROPEEUROPE 16.2%16.2%
JAPANJAPAN 20.7%20.7% AUSTRALIAAUSTRALIA 9%9%
CANADACANADA 19.8%19.8% OTHERSOTHERS 13.6%13.6%
SURVEY IS ONLY INDICATIVE
TypeType %% TypeType %%Generation Generation RejectionRejection
21.621.6 Out Of Step RelayOut Of Step Relay 2.72.7
Load RejectionLoad Rejection 10.610.6 Discrete Excitation Discrete Excitation ControlControl
1.81.8
U/F freq Load U/F freq Load SheddingShedding
8.28.2 Dynamic breakingDynamic breaking 1.81.8
System SeparationSystem Separation 6.36.3 Generator RunbackGenerator Runback 1.81.8
Turbine Valve Turbine Valve ControlControl
6.36.3 Var CompensationVar Compensation 1.8%1.8%
Load & Gen Load & Gen RejectionRejection
4.54.5 Combination of Combination of SchemesSchemes
11.711.7
StabilizersStabilizers 4.54.5 OthersOthers 12.612.6
HVDC ControlsHVDC Controls 3.63.6
PERCENTAGE OF MOST PERCENTAGE OF MOST COMMON SPSCOMMON SPS