Sound Transit Update: Sounder South King County Mobility Coalition 5/9/2019

Transcript of Sound Transit Update: Sounder 09 1… · 2010 75,508 2018 160,000 2040 PROJECTED 700,000 550,000. 6...

Page 1: Sound Transit Update: Sounder 09 1… · 2010 75,508 2018 160,000 2040 PROJECTED 700,000 550,000. 6 South King County Federal Way Link Extension Tacoma Dome Link Extension ... •

Sound Transit Update:

Sounder

South King County Mobility Coalition

5/9/2019

Page 2: Sound Transit Update: Sounder 09 1… · 2010 75,508 2018 160,000 2040 PROJECTED 700,000 550,000. 6 South King County Federal Way Link Extension Tacoma Dome Link Extension ... •

2

What we’ll cover today

• System expansion

• Kent & Auburn Stations

• Sounder capacity expansion

Page 3: Sound Transit Update: Sounder 09 1… · 2010 75,508 2018 160,000 2040 PROJECTED 700,000 550,000. 6 South King County Federal Way Link Extension Tacoma Dome Link Extension ... •

System expansion

Page 4: Sound Transit Update: Sounder 09 1… · 2010 75,508 2018 160,000 2040 PROJECTED 700,000 550,000. 6 South King County Federal Way Link Extension Tacoma Dome Link Extension ... •

4

More people, more cars

Population growth = traffic delays

Freeway delays each yearAlmost 200,000 new

neighbors added since 2015

Page 5: Sound Transit Update: Sounder 09 1… · 2010 75,508 2018 160,000 2040 PROJECTED 700,000 550,000. 6 South King County Federal Way Link Extension Tacoma Dome Link Extension ... •

5

Meeting growing demand

Average weekday ridership

2010

75,508

2018

160,000

2040

PR

OJE

CT

ED

700,000

550,000

Page 6: Sound Transit Update: Sounder 09 1… · 2010 75,508 2018 160,000 2040 PROJECTED 700,000 550,000. 6 South King County Federal Way Link Extension Tacoma Dome Link Extension ... •

6

South King County

Federal Way Link Extension

Tacoma Dome Link Extension –

Federal Way to

South Federal Way

S Boeing Access Rd light rail

infill station

I-405 BRT – Burien to Tukwila

Sounder station parking and

access improvements; track

and platform upgrades

A

B

C

D

E

Page 7: Sound Transit Update: Sounder 09 1… · 2010 75,508 2018 160,000 2040 PROJECTED 700,000 550,000. 6 South King County Federal Way Link Extension Tacoma Dome Link Extension ... •

7

About Sounder South

• Service between Seattle (King

Street Station) and Lakewood

• Thirteen daily round trips

(8 to Lakewood)

• Special event trains

• Steady ridership growth – over

16,000 daily trips in 2018

Page 8: Sound Transit Update: Sounder 09 1… · 2010 75,508 2018 160,000 2040 PROJECTED 700,000 550,000. 6 South King County Federal Way Link Extension Tacoma Dome Link Extension ... •

8

Steady ridership growth

Page 9: Sound Transit Update: Sounder 09 1… · 2010 75,508 2018 160,000 2040 PROJECTED 700,000 550,000. 6 South King County Federal Way Link Extension Tacoma Dome Link Extension ... •

Kent & Auburn Stations:

Parking & access

improvements

Page 10: Sound Transit Update: Sounder 09 1… · 2010 75,508 2018 160,000 2040 PROJECTED 700,000 550,000. 6 South King County Federal Way Link Extension Tacoma Dome Link Extension ... •

10

Overview

• New parking garages and

pedestrian, bike, and bus

improvements

• Approved by voters in ST2

• 2017 Alternatives Analyses

• ST Board identified preferred

garage locations

Page 11: Sound Transit Update: Sounder 09 1… · 2010 75,508 2018 160,000 2040 PROJECTED 700,000 550,000. 6 South King County Federal Way Link Extension Tacoma Dome Link Extension ... •

11

Kent garage concept

• Approximately 530 stalls

• 3 levels, 2 entrances

• Realigned Railroad Avenue N

• Environmental study to be

released in mid 2019

Page 12: Sound Transit Update: Sounder 09 1… · 2010 75,508 2018 160,000 2040 PROJECTED 700,000 550,000. 6 South King County Federal Way Link Extension Tacoma Dome Link Extension ... •

12

Kent: Potential Pedestrian, Bicycle, and Bus Improvements

Page 13: Sound Transit Update: Sounder 09 1… · 2010 75,508 2018 160,000 2040 PROJECTED 700,000 550,000. 6 South King County Federal Way Link Extension Tacoma Dome Link Extension ... •

13

Auburn garage concept

• Site located at 1st and A

Streets NW

• Approximately 535 parking

spaces for commuters

• Environmental study to be

released in fall

Page 14: Sound Transit Update: Sounder 09 1… · 2010 75,508 2018 160,000 2040 PROJECTED 700,000 550,000. 6 South King County Federal Way Link Extension Tacoma Dome Link Extension ... •

14

Auburn: Potential

Pedestrian,

Bicycle, and Bus

Improvements

Page 15: Sound Transit Update: Sounder 09 1… · 2010 75,508 2018 160,000 2040 PROJECTED 700,000 550,000. 6 South King County Federal Way Link Extension Tacoma Dome Link Extension ... •

Next Steps: Kent & Auburn

Now: Complete early engineering and environmental review

• Open Houses – Fall 2019

• Sound Transit Board actions – Fall 2019

Next: Design

• Permitting, property acquisition, hire construction firm

Page 16: Sound Transit Update: Sounder 09 1… · 2010 75,508 2018 160,000 2040 PROJECTED 700,000 550,000. 6 South King County Federal Way Link Extension Tacoma Dome Link Extension ... •

• Approved by voters in 2016

• Add capacity to meet growing ridership demand

Sounder capacity expansion

Page 17: Sound Transit Update: Sounder 09 1… · 2010 75,508 2018 160,000 2040 PROJECTED 700,000 550,000. 6 South King County Federal Way Link Extension Tacoma Dome Link Extension ... •

17

Overview

• Expanded platforms to

accommodate up to 10-car trains.

• Potential track and signal upgrades

for possible additional trips.

• Access improvements for

pedestrians, bicyclists, buses and

cars.

Platform extension

Track improvements Station access

Page 18: Sound Transit Update: Sounder 09 1… · 2010 75,508 2018 160,000 2040 PROJECTED 700,000 550,000. 6 South King County Federal Way Link Extension Tacoma Dome Link Extension ... •

18

Planning

• First step: Strategic Development & Implementation Plan

• Define the program and schedule

• Analyze existing service

• Model service scenarios

Page 19: Sound Transit Update: Sounder 09 1… · 2010 75,508 2018 160,000 2040 PROJECTED 700,000 550,000. 6 South King County Federal Way Link Extension Tacoma Dome Link Extension ... •

19

Things to consider about expansion

• BNSF owns tracks from Tacoma to

Seattle; new train trips costly

• Freight traffic concentrated outside of

peak commute period

• Midday train storage is limited

• King Street Station tracks and center

platform are constrained

• Restrictions on crew hours

Page 20: Sound Transit Update: Sounder 09 1… · 2010 75,508 2018 160,000 2040 PROJECTED 700,000 550,000. 6 South King County Federal Way Link Extension Tacoma Dome Link Extension ... •

20

Things to consider: Ridership demand

Average weekday boardings, January 2019

0

200

400

600

800

1000

1200

Southbound

0

200

400

600

800

1000

1200

Northbound

Page 21: Sound Transit Update: Sounder 09 1… · 2010 75,508 2018 160,000 2040 PROJECTED 700,000 550,000. 6 South King County Federal Way Link Extension Tacoma Dome Link Extension ... •

21

Public Outreach & Next Steps

• Two rounds of outreach

• July/August: share service scenarios

and learn community priorities

• Fall: share draft Strategic Plan

• Online & in-person engagement

• Sound Transit Board adopts Strategic

Plan – first quarter 2020

• Planning for first round of projects

begins - 2020

Page 22: Sound Transit Update: Sounder 09 1… · 2010 75,508 2018 160,000 2040 PROJECTED 700,000 550,000. 6 South King County Federal Way Link Extension Tacoma Dome Link Extension ... •

Questions?