SMP - 11 Geotechnical Report DRAFT- 21428 Prelim Soils Rpt ...€¦ · One bulk soil sample was...
Transcript of SMP - 11 Geotechnical Report DRAFT- 21428 Prelim Soils Rpt ...€¦ · One bulk soil sample was...
APPENDIX E
GEOTECHNICAL REPORTS
www.geoteq.com
September 26, 2017 File Number 21428 Clarett West Development 1901 Avenue of the Stars, Suite 1465 Los Angeles, California 90067 Attention: Ms. Laura Doerges
Subject: Supplemental Information - Expansive Soil Proposed Mixed-Use Development – The Plaza at Santa Monica 1301-1333 4th Street and 1324-1334 5th Street, Santa Monica, California Reference: Report by Geotechnologies, Inc.: Preliminary Geotechnical Engineering Investigation, dated August 29, 2017. Dear Ms. Doerges: This purpose of this letter is to provide findings and conclusions regarding the presence of expansive soils on the subject site. To date, this firm has drilled one boring on the site and therefore there is a limited availability of soil samples for testing. The results of the laboratory tests regarding expansive soils are presented below. One bulk soil sample was taken from Boring 1 at a depth of 1 to 5 feet and tested for expansion potential. The sample has an Expansion Index of 82 which is moderately expansive. The attached Plate D shows the result of the expansion test. Separately, four undisturbed soils samples were taken at or below the proposed foundation level. Samples were taken from Boring 1 at depths of 37.5, 47.5, 57.5, and 67.5 feet below the ground surface. Upon wetting at a normal pressure of 2 kips per square foot, the samples either did not expand or expanded approximately 0.3 percent. A correlative Expansion Index value cannot be determined from this data, however, these values are considered low. The attached Plate C shows the results of the consolidation tests. In summary, testing of the on-site soils indicated the Expansion Index is moderately expansive at the ground surface and low near the foundation level. Additional reinforcing is required as noted in the "Foundation Design" and "Slabs On Grade" sections of the referenced report. The validity of the recommendations presented herein is dependent upon review of the geotechnical aspects of the project during construction by this firm. The subsurface conditions described herein have been projected from limited subsurface exploration and laboratory testing.
September 26, 2017 File No. 21428 Page 2
Geotechnologies, Inc. 439 Western Avenue, Glendale, California 91201-2837 y Tel: 818.240.9600 y Fax: 818.240.9675
www.geoteq.com
The exploration and testing presented in this report should in no way be construed to reflect any variations which may occur between the exploration locations or which may result from changes in subsurface conditions. Should you have any questions please contact this office. Respectfully submitted, GEOTECHNOLOGIES, INC. REINARD KNUR G.E. 2755 RTK:ae Enclosures: Plate C Plate D Distribution: (3) Addressee Email to: [[email protected]]
CONSOLIDATION TEST
PLATE: CGeotechnologies, Inc.
Consulting Geotechnical Engineers
.1 .2 .3 .4 .5 .6 .7 .8 .9 1.0 2 3 4 5 6 7 8 9 10
Consolidation Pressure (KSF)
WATER ADDED AT 2 KSF
Per
cent
Con
solid
atio
n
2016
B1 @ 47.5' (CL)
FILE NO. 21428
CLARETT WEST DEVELOPMENT
2
0
4
B1 @ 37.5' (ML)
2
0
4
2
0
4
B1 @ 57.5' (CH)
2
0
4
B1 @ 67.5' (ML)
PLATE: DFILE NO. 21428
CLARETT WEST DEVELOPMENT
SULFATE CONTENT:
SULFATE CONTENT
SAMPLE
< 0.1 %(percentage by weight)
COMPACTION/EXPANSION/SULFATE DATA SHEET
B1 @ 12.5'
< 0.1 %
B1 @ 22.5'
< 0.1 %
B1 @ 32.5'
< 0.1 %
B1 @ 40'
< 0.1 %
B1 @ 45'
B1 @ 50'
SULFATE CONTENT:
SAMPLE
< 0.1 %(percentage by weight)
B1 @ 55'
< 0.1 %
B1 @ 60'
< 0.1 %
B1 @ 65'
< 0.1 %
B1 @ 70'
Geotechnologies, Inc.Consulting Geotechnical Engineers
< 0.1 %
SOIL TYPE:
SAMPLE
EXPANSION INDEX
EXPANSION CHARACTER
UBC STANDARD 18-2
MODERATE
82
ASTM D 4829
SOIL TYPE:
SAMPLE
MAXIMUM DENSITY pcf.
OPTIMUM MOISTURE %
B1 @ 1-5'
ML/CL
124.9
10.6
ASTM D-1557
B1 @ 1-5'
ML/CL
www.geoteq.com
August 29, 2017 File Number 21428 Clarett West Development 1901 Avenue of the Stars, Suite 1465 Los Angeles, California 90067 Attention: Ms. Laura Doerges
Subject: Preliminary Geotechnical Engineering Investigation Proposed Mixed-Use Development – The Plaza at Santa Monica 1301-1333 4th Street and 1324-1334 5th Street, Santa Monica, California Dear Ms. Doerges: This report transmits the preliminary Geotechnical Engineering Investigation to support the Environmental Impact Report (EIR) for the subject property prepared by Geotechnologies, Inc. This report provides preliminary geotechnical recommendations for the development of the site, including earthwork, seismic design, retaining walls, excavations, shoring and foundation design. Engineering for the proposed project should not begin until approval of the geotechnical investigation is granted by the local building official. Significant changes in the geotechnical recommendations may result due to the building department review process. As indicated, this report is preliminary in nature and it is intended to be used as support to the Environmental Impact Report (EIR) for this project. This report is based on a limited field exploration and preliminary design plans. Therefore, this report is not suitable for submission to the building department for the purpose of attaining building permits. A more comprehensive report should be prepared when the site is available for additional exploration and the development plan are finalized. The validity of the recommendations presented herein is dependent upon review of the geotechnical aspects of the project during construction by this firm. The subsurface conditions described herein have been projected from limited subsurface exploration and laboratory testing. The exploration and testing presented in this report should in no way be construed to reflect any variations which may occur between the exploration locations or which may result from changes in subsurface conditions. Should you have any questions please contact this office. Respectfully submitted, GEOTECHNOLOGIES, INC. WALTER LOPEZ REINARD KNUR Staff Engineer G.E. 2755 WL/RTK:km Distribution: (3) Addressee Email to: [[email protected]]
TABLE OF CONTENTS SECTION PAGE
Geotechnologies, Inc. 439 Western Avenue, Glendale, California 91201-2837 Tel: 818.240.9600 Fax: 818.240.9675
www.geoteq.com
INTRODUCTION .......................................................................................................................... 2 PROPOSED DEVELOPMENT...................................................................................................... 2 SITE CONDITIONS ....................................................................................................................... 3
LOCAL GEOLOGY ................................................................................................................... 4 GEOTECHNICAL EXPLORATION ............................................................................................. 4
FIELD EXPLORATION ............................................................................................................ 4 Geologic Materials .................................................................................................................. 5 Groundwater ........................................................................................................................... 5 Caving ..................................................................................................................................... 6
SEISMIC EVALUATION .............................................................................................................. 6 REGIONAL GEOLOGIC SETTING ......................................................................................... 6 REGIONAL FAULTING ........................................................................................................... 6 SEISMIC HAZARDS AND DESIGN CONSIDERATIONS .................................................... 7
Surface Rupture ...................................................................................................................... 7 Santa Monica Fault Hazard Management Zone...................................................................... 8 Liquefaction ............................................................................................................................ 8 Dynamic Dry Settlement....................................................................................................... 10 Tsunamis, Seiches and Flooding........................................................................................... 10 Landsliding ........................................................................................................................... 11
CONCLUSIONS AND RECOMMENDATIONS ....................................................................... 11 SEISMIC DESIGN CONSIDERATIONS ............................................................................... 13
2016 California Building Code Seismic Parameters ............................................................ 13 WATER-SOLUBLE SULFATES ............................................................................................ 13 HYDROCONSOLIDATION .................................................................................................... 14 GRADING GUIDELINES ....................................................................................................... 14
Site Preparation ..................................................................................................................... 14 Compaction ........................................................................................................................... 15 Acceptable Materials ............................................................................................................ 15 Utility Trench Backfill .......................................................................................................... 16 Shrinkage .............................................................................................................................. 16 Weather Related Grading Considerations ............................................................................. 16 Geotechnical Observations and Testing During Grading ..................................................... 17
FOUNDATION DESIGN ......................................................................................................... 17 Conventional Footings .......................................................................................................... 18 Miscellaneous Foundations ................................................................................................... 18 Lateral Design ....................................................................................................................... 19 Foundation Settlement for Conventional Footings ............................................................... 19 Mat Foundation ..................................................................................................................... 19 Lateral Design for Mat Foundation....................................................................................... 20 Foundation Settlement for Mat Foundation .......................................................................... 21 Foundation Observations ...................................................................................................... 21
RETAINING WALL DESIGN ................................................................................................. 21 Dynamic (Seismic) Earth Pressure ....................................................................................... 22
TABLE OF CONTENTS SECTION PAGE
Geotechnologies, Inc. 439 Western Avenue, Glendale, California 91201-2837 Tel: 818.240.9600 Fax: 818.240.9675
www.geoteq.com
Surcharge from Adjacent Structures ..................................................................................... 23 Waterproofing ....................................................................................................................... 24 Retaining Wall Drainage....................................................................................................... 24 Retaining Wall Backfill ........................................................................................................ 26 Sump Pump Design............................................................................................................... 26
TEMPORARY EXCAVATIONS ............................................................................................ 27 Excavation Observations ...................................................................................................... 27
SHORING DESIGN ................................................................................................................. 28 Soldier Piles .......................................................................................................................... 28 Lagging ................................................................................................................................. 30 Lateral Pressures ................................................................................................................... 30 Tied-Back Anchors ............................................................................................................... 31 Anchor Installation................................................................................................................ 33 Deflection .............................................................................................................................. 33 Monitoring ............................................................................................................................ 34 Shoring Observations ............................................................................................................ 34 Raker Brace Foundations ...................................................................................................... 34
SLABS ON GRADE................................................................................................................. 35 Concrete Slabs-on Grade ...................................................................................................... 35 Outdoor Concrete Slabs ........................................................................................................ 35 Design of Slabs That Receive Moisture-Sensitive Floor Coverings .................................... 35 Concrete Crack Control ........................................................................................................ 36
SITE DRAINAGE .................................................................................................................... 37 STORMWATER DISPOSAL .................................................................................................. 37 DESIGN REVIEW ................................................................................................................... 39 CONSTRUCTION MONITORING ......................................................................................... 39 EXCAVATION CHARACTERISTICS ................................................................................... 40 CLOSURE AND LIMITATIONS ............................................................................................ 40 GEOTECHNICAL TESTING .................................................................................................. 41
Classification and Sampling ................................................................................................. 41 Moisture and Density Relationships ..................................................................................... 42 Direct Shear Testing ............................................................................................................. 42 Consolidation Testing ........................................................................................................... 43 Grain Size Distribution ......................................................................................................... 43 Atterberg Limits .................................................................................................................... 43
ENCLOSURES
References Vicinity Map Plot Plan Survey Plan Cross Section A-A’ Historically Highest Groundwater Levels Map
TABLE OF CONTENTS SECTION PAGE
Geotechnologies, Inc. 439 Western Avenue, Glendale, California 91201-2837 Tel: 818.240.9600 Fax: 818.240.9675
www.geoteq.com
ENCLOSURES - continued Seismic Hazard Zone Map Southern California Fault Map Earthquake Fault Zone Regional Geologic Map Geologic Hazard Map – City of Santa Monica Plate A-1 Plates B-1 and B-2 Plate C Plate D Plate E Plate F Calculation Sheets (13 pages)
Geotechnologies, Inc. 439 Western Avenue, Glendale, California 91201-2837 Tel: 818.240.9600 Fax: 818.240.9675
www.geoteq.com
PRELIMINARY GEOTECHNICAL ENGINEERING INVESTIGATION
PROPOSED MIXED-USE DEVELOPMENT
THE PLAZA AT SANTA MONICA
1301-1333 4TH STREET AND 1324-1334 5TH STREET
SANTA MONICA, CALIFORNIA
INTRODUCTION
This report presents the preliminary results of the geotechnical engineering investigation
performed on the subject property. The purpose of this investigation was to identify the
distribution and engineering properties of the earth materials underlying the site, and to provide
geotechnical recommendations for the design of the proposed development.
This report is preliminary in nature and it intended to be used as support to the Environmental
Impact Report (EIR) for this project. This report is based on a limited field exploration at the site
and preliminary design plans. Therefore, this report is not suitable for submission to the building
department for the purpose of attaining building permits. A more comprehensive report should
be prepared when the site is available for additional exploration and the development plan are
finalized.
This investigation included drilling one boring, collection of representative samples, laboratory
testing, engineering analysis, review of published geologic data, and the preparation of this
report. The boring location is shown on the enclosed Plot Plan. The results of the exploration
and the laboratory testing are presented in the Appendix of this report.
PROPOSED DEVELOPMENT
Information concerning the proposed development was furnished by Clarett West Development.
The proposed development consists of a podium style, mixed-use structure that includes multiple
August 29, 2017 File No. 21428 Page 3
Geotechnologies, Inc. 439 Western Avenue, Glendale, California 91201-2837 Tel: 818.240.9600 Fax: 818.240.9675
www.geoteq.com
4- to 11-story towers underlain by three subterranean parking levels. The development will
include a hotel, retail/restaurant spaces, children’s ice skating rink, and loading dock areas.
Structural loads were not available at this time however, it is estimated that column loads may be
between 1,000 and 1,800 kips. Wall loads are estimated to be between 10 and 30 kips per lineal
foot. The proposed finished floor elevation has not been established yet, but excavations are
expected to be up to 35 feet in depth coinciding with an elevation of approximately 58 feet above
mean sea level.
The enclosed Plot Plan, Survey Plan, and Cross Section A-A’ illustrate the location, alignment
and depth of the proposed structure.
Any changes in the design of the project or location of any structure, as outlined in this report,
should be reviewed by this office. The recommendations contained in this report should not be
considered valid until reviewed and modified or reaffirmed, in writing, subsequent to such
review.
SITE CONDITIONS
The property is located at 1301-1333 4th Street and 1324-1334 5th Street in the City of Santa
Monica, California. The project site is bounded by Arizona Avenue to the north, by Fifth Street
to the east, by two to three story buildings to the south, and by Fourth Street to the west. The site
is rectangular in shape and 2.6 acres in area.
The site ranges in elevation from 94 feet at the northern corner to 86 feet at the southern corner.
For a total relief of relatively level with approximately 8 feet in a distance of 460 feet. The
overall site gradient is 60 to 1 (horizontal to vertical).
August 29, 2017 File No. 21428 Page 4
Geotechnologies, Inc. 439 Western Avenue, Glendale, California 91201-2837 Tel: 818.240.9600 Fax: 818.240.9675
www.geoteq.com
At the time of the exploration, the site was developed with two, one-story commercial buildings,
paved parking lot areas, and an alley. The neighboring development consists of a combination of
commercial and residential structures. The enclosed Survey Plan shows the existing site
development, as well as the existing ground elevations.
Due to the existing paved conditions on the ground surface at the site, the vegetation consists of
few isolated trees.
LOCAL GEOLOGY
The site is located in the Santa Monica Plain, an alluvial deposition area that is underlain by
several hundred foot of soil derived from erosion of the Santa Monica Mountains to the north.
The sediments reflect the geology of the western Santa Monica Mountains containing clays, sand
and gravel-sized fragments of Santa Monica Slate. The geology of the site vicinity is shown on
the attached Regional Geologic Map.
GEOTECHNICAL EXPLORATION
FIELD EXPLORATION
The site was explored on June 16, 2017 by drilling one boring utilizing a truck-mounted drilling
machine equipped with 8-inch diameter hollow-stem augers. Soil samples were taken using a at
5-foot intervals using a California-Modified, split-spoon sampler lined with 2.5-inch brass rings.
In addition, samples were taken at alternating 5-foot intervals using Standard Penetration Test
(SPT) Equipment. The samplers were advances with an automatic, 140-pound trip hammer
dropped from a height of 30 inches. The depth of the boring was 91.5 feet below the existing site
grade. The boring location is shown on the Plot Plan and the geologic materials encountered are
logged on Plate A-1. Samples of the soils encountered in the boring were conveyed to the
laboratory for testing. The results of the laboratory tests are provided herein
August 29, 2017 File No. 21428 Page 5
Geotechnologies, Inc. 439 Western Avenue, Glendale, California 91201-2837 Tel: 818.240.9600 Fax: 818.240.9675
www.geoteq.com
The location of exploratory boring was determined by measurement from hardscape features
shown on the attached Plot Plan. Elevation of the exploratory boring was determined by
interpolation of elevation points shown on the Survey Plan prepared by JRN Civil Engineers,
dated August 29, 2014. The location and elevation of the exploratory boring should be
considered accurate only to the degree implied by the method used.
Geologic Materials
Asphalt concrete pavement was encountered in the boring of approximately 7.5 inches thick
without base material.
Fill soil was encountered in the exploratory boring to a depth of 3 feet. Fill material underlying
the subject site consists of sandy silt, which is dark brown, moist, and fine sand.
The underlying natural soil consists of old alluvium, which is comprised of clay, sandy clay, silty
sand and slate fragments. The soils are dark brown to yellowish brown, and dark gray to olive in
color, moist to wet, medium dense to very dense, very stiff to very stiff.
The subsurface distribution of the geologic materials is shown on the attached Cross Section A-
A’.
Groundwater
Groundwater was encountered in Boring 1 at a depth of 67.5 feet below the ground surface (bgs)
which corresponds to an elevation of 25 feet above mean sea level. The Survey Seismic Hazard
Zone Report of the Beverly Hills Quadrangle (CDMG, 2005) indicates the depth to the
historically highest groundwater level is 40 feet bgs which corresponds to an elevation of
approximately 55 feet above mean sea level. A copy of this plate is included herein as
Historically Highest Groundwater Levels Map.
August 29, 2017 File No. 21428 Page 6
Geotechnologies, Inc. 439 Western Avenue, Glendale, California 91201-2837 Tel: 818.240.9600 Fax: 818.240.9675
www.geoteq.com
Fluctuations in the level of groundwater may occur due to variations in rainfall, temperature, and
other factors not evident at the time of the measurements reported herein. Fluctuations also may
occur across the site. High groundwater levels can result in changed conditions.
Caving
Caving could not be directly observed during exploration due to the continuous-cased design of
the hollow stem auger. Based on the experience of this firm, large diameter excavations that
encounter granular, cohesionless soils and excavations below the groundwater table will most
likely experience caving.
SEISMIC EVALUATION
REGIONAL GEOLOGIC SETTING
The subject site is located in the northern portion of the Peninsular Ranges Geomorphic
Province. The Peninsular Ranges are characterized by northwest-trending blocks of mountain
ridges and sediment-floored valleys. The dominant geologic structural features are northwest
trending fault zones that either die out to the northwest or terminate at east-trending reverse
faults that form the southern margin of the Transverse Ranges.
REGIONAL FAULTING
Based on criteria established by the California Division of Mines and Geology (CDMG) now
called California Geologic Survey (CGS), faults may be categorized as active, potentially active,
or inactive. Active faults are those which show evidence of surface displacement within the last
11,000 years (Holocene-age). Potentially-active faults are those that show evidence of most
recent surface displacement within the last 1.6 million years (Quaternary-age). Faults showing
no evidence of surface displacement within the last 1.6 million years are considered inactive for
most purposes, with the exception of design of some critical structures.
August 29, 2017 File No. 21428 Page 7
Geotechnologies, Inc. 439 Western Avenue, Glendale, California 91201-2837 Tel: 818.240.9600 Fax: 818.240.9675
www.geoteq.com
Buried thrust faults are faults without a surface expression but are a significant source of seismic
activity. They are typically broadly defined based on the analysis of seismic wave recordings of
hundreds of small and large earthquakes in the southern California area. Due to the buried
nature of these thrust faults, their existence is usually not known until they produce an
earthquake. The risk for surface rupture potential of these buried thrust faults is inferred to be
low (Leighton, 1990). However, the seismic risk of these buried structures in terms of
recurrence and maximum potential magnitude is not well established. Therefore, the potential
for surface rupture on these surface-verging splays at magnitudes higher than 6.0 cannot be
precluded.
SEISMIC HAZARDS AND DESIGN CONSIDERATIONS
The primary geologic hazard at the site is moderate to strong ground motion (acceleration)
caused by an earthquake on any of the local or regional faults. The potential for other
earthquake-induced hazards was also evaluated including surface rupture, liquefaction, dynamic
settlement, inundation and landsliding.
Surface Rupture
Surface rupture is defined as displacement which occurs along the surface trace of the causative
fault during an earthquake. Based on research of available literature and results of site
reconnaissance, no known active or potentially active faults underlie the subject site. The subject
site is not located within an Alquist-Priolo Earthquake Fault Zone (CDMG, 2017). The site is
located approximately 0.85-mile south of the nearest earthquake Fault Zone. In addition, the site
is located 0.45 mile south of the nearest Fault Hazard Management Zone for the Santa Monica
Fault (City of Santa Monica, 2014). Based on these considerations, the potential for surface
ground rupture at the subject site is considered low. A copy of the newly issued, Preliminary
Earthquake Fault Zone map for the Beverly Hills Quadrangle is attached to this report. A copy
of the City of Santa Monica, Geologic Hazards Map is also attached.
August 29, 2017 File No. 21428 Page 8
Geotechnologies, Inc. 439 Western Avenue, Glendale, California 91201-2837 Tel: 818.240.9600 Fax: 818.240.9675
www.geoteq.com
Santa Monica Fault Hazard Management Zone
The City of Santa Monica has identified zones requiring additional fault studies. These zones
were created based on geologic evidence of active fault movement (within the last 11,000 years,
Dolan, J.F., Sieh, K., and Rockwell, T.K., 2000) along the Santa Monica Fault. The CGS has
zoned a portion of the Santa Monica Fault with an Earthquake Fault Zone in accordance with the
Alquist-Priolo Earthquake Fault Zoning Act of 1972.
The Safety Element of the City of Santa Monica General Plan (Leighton, 1994) established a
“Fault Hazard Management Zone” for the Santa Monica Fault. The Fault Hazard Management
Zone includes all areas located between approximately 500 feet north of the North Branch and
approximately 500 feet south of the South Branch of the Santa Monica Fault. The Fault Hazard
Management Zones Map also includes areas where researchers have mapped interpreted
“Strong” and “Weak” geomorphic expressions of the Santa Monica Fault.
Crook and Proctor (1992) reported the results of trenching performed at locations along the Santa
Monica Fault in the vicinity of University High School and the Veterans Administration
Hospital. Evidence of a groundwater level difference at a foundation excavation at Wilshire and
Bundy Drive was also cited. Based on the findings of the report, Holocene movement of the
Santa Monica Fault could not be proved in spite of geomorphic evidence. This portion of the
Santa Monica Fault is inferred to connect with a Holocene offset at Potrero Canyon to the west-
southwest. This portion of the Santa Monica Fault is termed the South Branch of the Santa
Monica Fault.
Liquefaction
Liquefaction is a phenomenon in which saturated silty to cohesionless soils below the
groundwater table are subject to a temporary loss of strength due to the buildup of excess pore
pressure during cyclic loading conditions such as those induced by an earthquake. Liquefaction-
August 29, 2017 File No. 21428 Page 9
Geotechnologies, Inc. 439 Western Avenue, Glendale, California 91201-2837 Tel: 818.240.9600 Fax: 818.240.9675
www.geoteq.com
related effects include loss of bearing strength, amplified ground oscillations, lateral spreading,
and flow failures.
The Seismic Hazards Maps of the State of California (CDMG, 1999), does not classify the site as
part of the potentially “Liquefiable” area. This determination is based on groundwater depth
records, soil type and distance to a fault capable of producing a substantial earthquake.
A site-specific liquefaction analysis was performed following the Recommended Procedures for
Implementation of the California Geologic Survey Special Publication 117A, Guidelines for
Analyzing and Mitigating Seismic Hazards in California (CGS, 2008), and the EERI Monograph
(MNO-12) by Idriss and Boulanger (2008). This semi-empirical method is based on a
correlation between measured values of Standard Penetration Test (SPT) resistance and field
performance data.
Groundwater was encountered at 67.5 feet below existing grade. According to the Seismic
Hazard Zone Report of the Beverly Hills 7½-Minute Quadrangle (SHZR 023), the historic-high
groundwater level for the site was 40 feet below the ground surface. The historic highest
groundwater level was conservatively utilized for the enclosed liquefaction analysis.
The peak ground acceleration (PGA) and modal magnitude were obtained from the USGS
websites, using the Probabilistic Seismic Hazard Deaggregation program (USGS, 2008) and the
U.S. Seismic Design Maps tool (USGS, 2013). A modal magnitude (MW) of 6.8 is obtained
using the USGS Probabilistic Seismic Hazard Deaggregation program (USGS, 2008). A peak
ground acceleration of 0.77g (2 percent in 50 years ground motion) was obtained using the
USGS Probabilistic Seismic Hazard Deaggregation program. These parameters are used in the
enclosed liquefaction analyses.
The enclosed “Empirical Estimation of Liquefaction Potential” is based on Boring 1. Standard
Penetration Test (SPT) data were collected at 5-foot intervals. Samples of the collected materials
August 29, 2017 File No. 21428 Page 10
Geotechnologies, Inc. 439 Western Avenue, Glendale, California 91201-2837 Tel: 818.240.9600 Fax: 818.240.9675
www.geoteq.com
were conveyed to the laboratory for testing and analysis. The percent passing a Number 200
sieve, Atterberg Limits, and the plasticity index (PI) of representative samples of the soils
encountered in the exploratory boring are presented on the enclosed E-Plate and F-Plate. Based
on CGS Special Publication 117A (CDMG, 2008), the vast majority of liquefaction hazards are
associated with sandy soils and silty soils of low plasticity. Furthermore, cohesive soils with PI
between 7 and 12 and moisture content greater than 85 percent of the liquid limit are susceptible
to liquefaction.
Based on the adjusted blow count data, results of laboratory testing, and the calculated factor of
safety against the occurrence of liquefaction, it is the opinion of this firm that the potential for
liquefaction at the site is considered to be remote.
Dynamic Dry Settlement
Seismically-induced settlement or compaction of dry or moist, cohesionless soils can be an effect
related to earthquake ground motion. Such settlements are typically most damaging when the
settlements are differential in nature across the length of structures.
Calculations based on the corrected SPT blow counts indicate that seismically induced settlement
on the site will be very minimal, on the order of 0.042 inch. Therefore, due to the uniform nature
of the underlying geologic material, excessive differential settlements are considered to be
negligible and within the tolerance of a well-designed structure.
Tsunamis, Seiches and Flooding
Tsunamis are large ocean waves generated by sudden water displacement caused by a submarine
earthquake, landslide, or volcanic eruption. Review of the County of Los Angeles Flood and
Inundation Hazards Map, Leighton (1990), indicates the site does not lie within the mapped
tsunami inundation boundaries.
August 29, 2017 File No. 21428 Page 11
Geotechnologies, Inc. 439 Western Avenue, Glendale, California 91201-2837 Tel: 818.240.9600 Fax: 818.240.9675
www.geoteq.com
Seiches are oscillations generated in enclosed bodies of water which can be caused by ground
shaking associated with an earthquake. No major water-retaining structures are located
immediately up gradient from the project site. Therefore, the risk of flooding from a seismically-
induced seiche is considered to be remote.
Review of the County of Los Angeles Flood and Inundation Hazards Map, Leighton (1990),
indicates the site does not lie within mapped inundation boundaries due to a seiche or a breached
upgradient reservoir.
Landsliding
The probability of seismically-induced landslides occurring on the site is considered to be low
due to the general lack of elevation difference slope geometry across or adjacent to the site.
CONCLUSIONS AND RECOMMENDATIONS
Based upon the exploration, laboratory testing, and research, it is the preliminary finding of
Geotechnologies, Inc. that construction of the proposed mixed-use development is considered
feasible from a geotechnical engineering standpoint provided the advice and recommendations
presented herein are followed and implemented during construction.
This report is considered preliminary in nature and it is intended to be used as support to the
Environmental Impact Report (EIR) for this project. Therefore, this report is not suitable for
submission to the building department for the purpose of attaining building permits. The client
shall be aware that, due to preliminary nature of the design phase, additional exploration will be
necessary in order to achieve a thorough investigation of the site when the project achieves more
definition. A comprehensive report should be prepared when the site is available for additional
exploration and the development plans are completed. Whenever structural loads become
available, we should evaluate them to confirm our design parameters based on assumptions
provided in this report.
August 29, 2017 File No. 21428 Page 12
Geotechnologies, Inc. 439 Western Avenue, Glendale, California 91201-2837 Tel: 818.240.9600 Fax: 818.240.9675
www.geoteq.com
Three feet of fill soil was encountered during exploration at the site. It is anticipated that
excavation of the proposed subterranean levels will remove the existing fill material and expose
the underlying natural alluvial soils. The natural alluvial soil consists of a mixtures of clay, silt,
sand and gravel. The alluvium is firm to stiff and dense.
Groundwater was encountered at a depth of 67.5 feet below the existing grade during our field
exploration. The historic-high groundwater level for the site was 40 feet below the ground
surface, according to the Beverly Hills 7.5 Minute Quadrangle.
The site is not subject to liquefaction during the design seismic event, nor is dry settlement
considered significant. The site is not located in an Earthquake Fault Zone or in a City of Santa
Monica Fault Hazard Management Zone.
Based on proposed finished floor for the lowest subterranean parking level, it is expected that
excavations will be up to 35 feet in depth for the construction of the subterranean levels and
foundation system. Shoring will be required to provide a stable excavation.
It is recommended that proposed structure be supported on spread footings bearing on the natural
alluvial soil expected at the subgrade elevation. As an alternative, the structure may be
supported on a mat foundation.
Due to the narrow elevation difference between the bottom of the proposed foundations and the
historically highest groundwater level, stormwater infiltration is not considered feasible for this
site. Also, the proposed foundation system will be located within a layer of sandy silt overlain by
a thick layer of lean clay and fat clay extending to a depth of 67.5 feet below the existing grade,
where groundwater level was encountered during exploration. The clay is not considered to be
sufficiently permeable to permit stormwater infiltration. Some other means of stormwater
disposal should be considered.
August 29, 2017 File No. 21428 Page 13
Geotechnologies, Inc. 439 Western Avenue, Glendale, California 91201-2837 Tel: 818.240.9600 Fax: 818.240.9675
www.geoteq.com
SEISMIC DESIGN CONSIDERATIONS
2016 California Building Code Seismic Parameters
According to Table 20.3-1 presented in ASCE 7-10, the subject site is classified as Site Class D,
which corresponds to a “Stiff Soil” Profile. This information and the site coordinates were input
into the USGS U.S. Seismic Design Maps tool (Version 3.1.0) to calculate the ground motions
for the site.
2016 CALIFORNIA BUILDING CODE SEISMIC PARAMETERS
Site Class D
Mapped Spectral Acceleration at Short Periods (SS) 2.017g
Site Coefficient (Fa) 1.0
Maximum Considered Earthquake Spectral Response for Short Periods (SMS)
2.017g
Five-Percent Damped Design Spectral Response Acceleration at Short Periods (SDS)
1.345g
Mapped Spectral Acceleration at One-Second Period (S1) 0.750g
Site Coefficient (Fv) 1.5
Maximum Considered Earthquake Spectral Response for One-Second Period (SM1)
1.124g
Five-Percent Damped Design Spectral Response Acceleration for One-Second Period (SD1)
0.750g
WATER-SOLUBLE SULFATES
The Portland cement portion of concrete is subject to attack when exposed to water-soluble
sulfates. Usually the two most common sources of exposure are from soil and marine
environments. The source of natural sulfate minerals in soils include the sulfates of calcium,
magnesium, sodium, and potassium. When these minerals interact and dissolve in subsurface
August 29, 2017 File No. 21428 Page 14
Geotechnologies, Inc. 439 Western Avenue, Glendale, California 91201-2837 Tel: 818.240.9600 Fax: 818.240.9675
www.geoteq.com
water, a sulfate concentration is created, which will react with exposed concrete. Over time
sulfate attack will destroy improperly proportioned concrete well before the end of its intended
service life.
The water-soluble sulfate content of the onsite geologic materials was tested by California Test
417. The water-soluble sulfate content was determined to be less than 0.1% percentage by
weight for the soils tested. Based on American Concrete Institute (ACI) Standard 318-08, the
sulfate exposure is considered to be negligible for geologic materials with less than 0.1% and
Type I cement may be utilized for concrete foundations in contact with the site soils. Concrete
strength should be a minimum of 2,500psi.
HYDROCONSOLIDATION
Hydroconsolidation is a phenomena wherein soils lose volume when they are saturated and cause
overlying structures to settle. The hydroconsolidation potential was considered in this provision
of four consolidation tests. None of the tests exhibited collapse upon saturation. Based on the
laboratory testing, it is the opinion of Geotechnologies, Inc. that the potential for damaging
settlement due to hydrocollapse is anticipated to be insignificant.
GRADING GUIDELINES
The following may be utilized for any miscellaneous site grading which may be required as part
of the proposed development.
Site Preparation
A thorough search should be made for possible underground utilities and/or structures. Any existing or abandoned utilities or structures located within the footprint of the proposed grading should be removed or relocated as appropriate.
August 29, 2017 File No. 21428 Page 15
Geotechnologies, Inc. 439 Western Avenue, Glendale, California 91201-2837 Tel: 818.240.9600 Fax: 818.240.9675
www.geoteq.com
All vegetation, existing fill, and soft or disturbed geologic materials should be removed from the areas to receive controlled fill. All existing fill materials and any disturbed geologic materials resulting from grading operations shall be completely removed and properly recompacted prior to foundation excavation.
Any vegetation or associated root system located within the footprint of the proposed
structures should be removed during grading.
Subsequent to the indicated removals, the exposed grade shall be scarified to a depth of six inches, moistened to optimum moisture content, and recompacted in excess of the minimum required comparative density.
The excavated areas shall be observed by the geotechnical engineer prior to placing
compacted fill.
Compaction
All fill should be mechanically compacted in layers not more than 8 inches thick. All fill shall
be compacted to at least 90 percent of the maximum laboratory density for the material used.
The maximum density shall be determined by the laboratory operated by Geotechnologies, Inc.
using the test method described in the most recent revision of ASTM D 1557.
Field observation and testing shall be performed by a representative of the geotechnical engineer
during grading to assist the contractor in obtaining the required degree of compaction and the
proper moisture content. Where compaction is less than required, additional compactive effort
shall be made with adjustment of the moisture content, as necessary, until a minimum of 90
percent compaction is obtained.
Acceptable Materials
The excavated onsite materials are considered satisfactory for reuse in the controlled fills as long
as any debris and/or organic matter is removed. Any imported materials shall be observed and
tested by the representative of the geotechnical engineer prior to use in fill areas. Imported
materials should contain sufficient fines so as to be relatively impermeable and result in a stable
August 29, 2017 File No. 21428 Page 16
Geotechnologies, Inc. 439 Western Avenue, Glendale, California 91201-2837 Tel: 818.240.9600 Fax: 818.240.9675
www.geoteq.com
subgrade when compacted. Any required import materials should consist of geologic materials
with an expansion index of less than 50. The water-soluble sulfate content of the import
materials should be less than 0.1% percentage by weight.
Imported materials should be free from chemical or organic substances which could affect the
proposed development. A competent professional should be retained in order to test imported
materials and address environmental issues and organic substances which might affect the
proposed development.
Utility Trench Backfill
Utility trenches should be backfilled with controlled fill. The utility should be bedded with clean
sands at least one foot over the crown. The remainder of the backfill may be onsite soil
compacted to 90 percent of the laboratory maximum density. Utility trench backfill should be
tested by representatives of this firm in accordance with the most recent revision of ASTM D-
1557.
Shrinkage
Shrinkage results when a volume of soil removed at one density is compacted to a higher
density. A shrinkage factor between 5 and 10 percent should be anticipated when excavating and
recompacting the existing fill and underlying native geologic materials on the site to an average
comparative compaction of 92 percent.
Weather Related Grading Considerations
When rain is forecast all fill that has been spread and awaits compaction shall be properly
compacted prior to stopping work for the day or prior to stopping due to inclement weather.
These fills, once compacted, shall have the surface sloped to drain to an area where water can be
removed.
August 29, 2017 File No. 21428 Page 17
Geotechnologies, Inc. 439 Western Avenue, Glendale, California 91201-2837 Tel: 818.240.9600 Fax: 818.240.9675
www.geoteq.com
Temporary drainage devices should be installed to collect and transfer excess water to the street
in non-erosive drainage devices. Drainage should not be allowed to pond anywhere on the site,
and especially not against any foundation or retaining wall. Drainage should not be allowed to
flow uncontrolled over any descending slope.
Work may start again, after a period of rainfall, once the site has been reviewed by a
representative of this office. Any soils saturated by the rain shall be removed and aerated so that
the moisture content will fall within three percent of the optimum moisture content.
Surface materials previously compacted before the rain shall be scarified, brought to the proper
moisture content and recompacted prior to placing additional fill, if considered necessary by a
representative of this firm.
Geotechnical Observations and Testing During Grading
Geotechnical observations and testing during grading are considered to be a continuation of the
geotechnical investigation. It is critical that the geotechnical aspects of the project be reviewed
by representatives of Geotechnologies, Inc. during the construction process. Compliance with
the design concepts, specifications or recommendations during construction requires review by
this firm during the course of construction. Any fill which is placed should be observed, tested,
and verified if used for engineered purposes. Please advise this office at least twenty-four hours
prior to any required site visit.
FOUNDATION DESIGN
It is recommended that the proposed mixed-use structure be supported on a system of
conventional spread footings bearing in the undisturbed native soils. As an alternative, the
structure may be supported on a mat foundation. Recommendations for both options are provided
below.
August 29, 2017 File No. 21428 Page 18
Geotechnologies, Inc. 439 Western Avenue, Glendale, California 91201-2837 Tel: 818.240.9600 Fax: 818.240.9675
www.geoteq.com
Conventional Footings
Conventional spread footings bearing in the competent native soils expected to be exposed at the
proposed subterranean level may be utilized for support of the proposed building.
Continuous foundations may be designed for a bearing capacity of 4,000 pounds per square foot,
and should be a minimum of 12 inches in width, 24 inches in depth below the lowest adjacent
grade and 24 inches into the recommended bearing material.
Column foundations may be designed for a bearing capacity of 4,500 pounds per square foot,
and should be a minimum of 24 inches in width, 24 inches in depth below the lowest adjacent
grade and 24 inches into the recommended bearing material.
The bearing capacity increase for each additional foot of width is 200 pounds per square foot.
The bearing capacity increase for each additional foot of depth is 250 pounds per square foot.
The maximum recommended bearing capacity is 7,000 pounds per square foot.
A minimum factor of safety of 3 was utilized in determining the allowable bearing capacities.
The bearing values indicated above are for the total of dead and frequently applied live loads,
and may be increased by one third for short duration loading, which includes the effects of wind
or seismic forces. Since the recommended bearing value is a net value, the weight of concrete in
the foundations may be taken as 50 pounds per cubic foot and the weight of the soil backfill may
be neglected when determining the downward load on the foundations.
Miscellaneous Foundations
Foundations for small miscellaneous outlying structures, such as property line fence walls,
planters, exterior canopies, and trash enclosures, which will not be tied-in to the proposed
structure, may be supported on conventional foundations bearing in the native soils. Wall
August 29, 2017 File No. 21428 Page 19
Geotechnologies, Inc. 439 Western Avenue, Glendale, California 91201-2837 Tel: 818.240.9600 Fax: 818.240.9675
www.geoteq.com
footings may be designed for a bearing value of 1,500 pounds per square foot, and should be a
minimum of 12 inches in width, 24 inches in depth below the lowest adjacent grade and 24
inches into the recommended bearing material. No bearing value increases are recommended.
Lateral Design
Resistance to lateral loading may be provided by friction acting at the base of foundations and by
passive earth pressure. An allowable coefficient of friction of 0.35 may be used with the dead
load forces.
Passive geologic pressure for the sides of foundations poured against undisturbed or recompacted
soil may be computed as an equivalent fluid having a density of 350 pounds per cubic foot with a
maximum earth pressure of 3,500 pounds per square foot. The passive and friction components
may be combined for lateral resistance without reduction. A one-third increase in the passive
value may be used for short duration loading such as wind or seismic forces.
Foundation Settlement for Conventional Footings
Settlement of the foundation system is expected to occur on initial application of loading. The
maximum static settlement is expected to be 1 inch and occur below the heaviest loaded
columns. Differential settlement is not expected to exceed ¼ inch.
Mat Foundation
The proposed structure will be constructed over three subterranean parking levels extending up
to 35 feet below grade. No structural loads have been provided at this time. However, based on
prior similar projects, we have estimated an average bearing pressure of 2,500 pounds per square
foot. Foundation bearing pressure will vary across the mat footings, with the highest
concentrated loads located at the central cores of the mat foundations.
August 29, 2017 File No. 21428 Page 20
Geotechnologies, Inc. 439 Western Avenue, Glendale, California 91201-2837 Tel: 818.240.9600 Fax: 818.240.9675
www.geoteq.com
Given the size of the proposed mat foundation, the average bearing pressure of 2,500 pounds per
square foot is well below the allowable bearing pressures, with factor of safety well exceeding 3.
For design purposes, an average bearing pressure of 5,000 pounds per square foot, with locally
higher pressures up to 7,000 pounds per square foot may be utilized in the mat foundation
design. The mat foundation may be designed utilizing a modulus of subgrade reaction of 350
pounds per cubic inch. This value is a unit value for use with a one-foot square footing. The
modulus should be reduced in accordance with the following equation when used with larger
foundations.
K = K1 * [ (B + 1) / (2 * B) ]2 where K = Reduced Subgrade Modulus
K1 = Unit Subgrade Modulus B = Foundation Width (feet)
The bearing values indicated above are for the total of dead and frequently applied live loads,
and may be increased by one third for short duration loading, which includes the effects of wind
or seismic forces. Since the recommended bearing value is a net value, the weight of concrete in
the foundations may be taken as 50 pounds per cubic foot and the weight of the soil backfill may
be neglected when determining the downward load on the foundations.
Lateral Design for Mat Foundation
Resistance to lateral loading may be provided by soil friction, and by the passive resistance of
the soils. A coefficient of friction of 0.35 may be used with the dead load forces between
footings and the underlying supporting soils.
Passive earth pressure for the sides of footings poured against undisturbed soil may be computed
as an equivalent fluid having a density of 350 pounds per cubic foot, with a maximum earth
pressure of 3,500 pounds per square foot. When combining passive and friction for lateral
resistance, the passive component should be reduced by one third. A one-third increase in the
August 29, 2017 File No. 21428 Page 21
Geotechnologies, Inc. 439 Western Avenue, Glendale, California 91201-2837 Tel: 818.240.9600 Fax: 818.240.9675
www.geoteq.com
passive value may be used for wind or seismic loads. A minimum safety factor of 2 has been
utilized in determining the allowable passive pressure.
Foundation Settlement for Mat Foundation
The majority of the foundation settlement is expected to occur on initial application of loading.
It is anticipated that total settlement up to 3 inches will occur below the more heavily loaded
central core portions of the mat foundation beneath the tower. Settlement on the edges of the
mat foundation is expected to be between 1½ to 2 inches.
Foundation Observations
It is critical that all foundation excavations are observed by a representative of this firm to verify
penetration into the recommended bearing materials. The observation should be performed prior
to the placement of reinforcement. Foundations should be deepened to extend into satisfactory
geologic materials, if necessary. Foundation excavations should be cleaned of all loose soils
prior to placing steel and concrete. Any required foundation backfill should be mechanically
compacted, flooding is not permitted.
RETAINING WALL DESIGN
Retaining walls on the order of 35 feet in height are anticipated for the proposed subterranean
levels. It is anticipated these walls will be restrained.
Cantilever retaining walls supporting a level backslope may be designed utilizing a triangular
distribution of active earth pressure. Restrained retaining walls may be designed utilizing a
triangular distribution of at-rest earth pressure. Retaining walls may be designed utilizing the
following table:
August 29, 2017 File No. 21428 Page 22
Geotechnologies, Inc. 439 Western Avenue, Glendale, California 91201-2837 Tel: 818.240.9600 Fax: 818.240.9675
www.geoteq.com
Height of Retaining Wall (feet)
Cantilever Retaining Wall Triangular Distribution of
Active Earth Pressure (pcf)
Restrained Retaining Wall Triangular Distribution of
At-Rest Earth Pressure (pcf)
Up to 10 feet 30
55 10 to 20 feet 38
20 to 30 feet 43
30 to 40 feet 45
The lateral earth pressures recommended above for retaining walls assume that a permanent
drainage system will be installed so that external water pressure will not be developed against the
walls. Additional active pressure should be added for a surcharge condition due to sloping
ground, vehicular traffic or adjacent structures.
The upper ten feet of the retaining wall adjacent to streets, driveways or parking areas should be
designed to resist a uniform lateral pressure of 100 pounds per square foot, acting as a result of
an assumed 300 pounds per square foot surcharge behind the walls due to normal street traffic.
If the traffic is kept back at least ten feet from the retaining walls, the traffic surcharge may be
neglected. Foundations may be designed using the allowable bearing capacities, friction, and
passive earth pressure found in the “Foundation Design” section above.
Dynamic (Seismic) Earth Pressure
Retaining walls exceeding 6 feet in height shall be designed to resist the additional earth pressure
caused by seismic ground shaking. A triangular pressure distribution should be utilized for the
additional seismic loads, with an equivalent fluid pressure of 21 pounds per cubic foot. When
using the load combination equations from the building code, the seismic earth pressure should
be combined with the lateral active earth pressure for analyses of restrained basement walls
under seismic loading condition. The comparison is made is the following table:
August 29, 2017 File No. 21428 Page 23
Geotechnologies, Inc. 439 Western Avenue, Glendale, California 91201-2837 Tel: 818.240.9600 Fax: 818.240.9675
www.geoteq.com
Use of Seismic Wall pressure
(All Pressure Distributions are Triangular)
Wall Height (feet) Active pressure (psf) Active +Seismic (psf) At-Rest (psf)
Up to 10 30 51 55
10 to 20 38 59 55
20 to 30 43 64 55
30 to 40 45 66 55
Surcharge from Adjacent Structures
As indicated herein, additional active pressure should be added for a surcharge condition due to
sloping ground, vehicular traffic or adjacent structures for retaining walls and shoring design.
The following surcharge equation provided in the LADBS Information Bulletin Document No.
P/BC 2008-83, may be utilized to determine the surcharge loads on basement walls and shoring
system for existing structures located within the 1:1 (h:v) surcharge influence zone of the
excavation and basement.
Resultant lateral force: R = (0.3*P*h2)/(x2+h2) Location of lateral resultant: d = x*[(x2/h2+1)*tan-1(h/x)-(x/h)] Where: R = resultant lateral force measured in pounds per foot of wall width. P = resultant surcharge loads of continuous or isolated footings measured in
pounds per foot of length parallel to the wall. x = distance of resultant load from back face of wall measured in feet. h = depth below point of application of surcharge loading to top of wall
footing measured in feet. d = depth of lateral resultant below point of application of surcharge loading
measure in feet. tan-1(h/x) = the angle in radians whose tangent is equal to h/x.
August 29, 2017 File No. 21428 Page 24
Geotechnologies, Inc. 439 Western Avenue, Glendale, California 91201-2837 Tel: 818.240.9600 Fax: 818.240.9675
www.geoteq.com
The structural engineer and shoring engineer may use this equation to determine the surcharge
loads based on the loading of the adjacent structures located within the surcharge influence zone.
Waterproofing
Moisture effecting retaining walls is one of the most common post construction complaints.
Poorly applied or omitted waterproofing can lead to efflorescence or standing water inside the
building. Efflorescence is a process in which a powdery substance is produced on the surface of
the concrete by the evaporation of water. The white powder usually consists of soluble salts
such as gypsum, calcite, or common salt. Efflorescence is common to retaining walls and does
not affect their strength or integrity.
It is recommended that retaining walls be waterproofed. Waterproofing design and inspection of
its installation is not the responsibility of the geotechnical engineer. A qualified waterproofing
consultant should be retained in order to recommend a product or method which would provide
protection to below grade walls.
Retaining Wall Drainage
All retaining walls shall be provided with a subdrain in order to minimize the potential for future
hydrostatic pressure buildup behind the proposed retaining walls. Subdrains may consist of four-
inch diameter perforated pipes, placed with perforations facing down. The pipe shall be encased
in at least one-foot of gravel around the pipe. The gravel may consist of three-quarter inch to
one inch crushed rocks.
A compacted fill blanket or other seal shall be provided at the surface. Retaining walls may be
backfilled with gravel adjacent to the wall to within 2 feet of the ground surface. The onsite
earth materials are acceptable for use as retaining wall backfill as long as they are compacted to a
minimum of 90 percent of the maximum density as determined by ASTM D 1557.
August 29, 2017 File No. 21428 Page 25
Geotechnologies, Inc. 439 Western Avenue, Glendale, California 91201-2837 Tel: 818.240.9600 Fax: 818.240.9675
www.geoteq.com
Certain types of subdrain pipe are not acceptable to the various municipal agencies, it is
recommended that prior to purchasing subdrainage pipe, the type and brand is cleared with the
proper municipal agencies. Subdrainage pipes should outlet to an acceptable location.
Where retaining walls are to be constructed adjacent to property lines, there is usually not
enough space for placement of a standard perforated pipe and gravel drainage system. Under
these circumstances, every other head joints may be left out, or 2-inch diameter weepholes may
be placed at the 8 feet on center along the base of the wall. The wall shall be backfilled with a
minimum of 1 foot of gravel above the base of the retaining wall. The gravel may consist of
three-quarter inch to one inch crushed rocks.
Where retaining walls are to be constructed adjacent to property lines there is usually not enough
space for emplacement of a standard pipe and gravel drainage system. Under these
circumstances, the use of a flat drainage produce is acceptable.
Some municipalities do not allow the use of flat-drainage products. The use of such a product
should be researched with the building official. As an alternative, omission of one-half of a
block at the back of the wall on eight foot centers is an acceptable method of draining the walls.
The resulting void should be filled with gravel. A collector is placed within the gravel which
directs collected waters through the wall to a sump or standard pipe and gravel system
constructed under the slab. This method should be approved by the retaining wall designer prior
to implementation.
The lateral earth pressures recommended above for retaining walls assume that a permanent
drainage system will be installed so that external water pressure will not be developed against the
walls. If a drainage system is not provided, the walls should be designed to resist an external
hydrostatic pressure due to water in addition to the lateral earth pressure. In any event, it is
recommended that retaining walls be waterproofed.
August 29, 2017 File No. 21428 Page 26
Geotechnologies, Inc. 439 Western Avenue, Glendale, California 91201-2837 Tel: 818.240.9600 Fax: 818.240.9675
www.geoteq.com
Retaining Wall Backfill
Any required backfill should be mechanically compacted in layers not more than 8 inches thick,
to at least 90 percent of the maximum density obtainable by the ASTM Designation D-1557
method of compaction. Flooding should not be permitted. Proper compaction of the backfill
will be necessary to reduce settlement of overlying walks and paving. Some settlement of
required backfill should be anticipated, and any utilities supported therein should be designed to
accept differential settlement, particularly at the points of entry to the structure.
Proper compaction of the backfill will be necessary to reduce settlement of overlying walks and
paving. Some settlement of required backfill should be anticipated, and any utilities supported
therein should be designed to accept differential settlement, particularly at the points of entry to
the structure.
Sump Pump Design
The purpose of the recommended retaining wall backdrainage system is to relieve hydrostatic
pressure. Groundwater was encountered during exploration to a depth of 67.5 feet which
corresponds to approximately 32.5 feet below the lowest proposed finished floor. Therefore the
only water which could affect the proposed retaining walls would be irrigation waters and
precipitation. Additionally, the proposed site grading is such that all drainage is directed to the
street and the structure has been designed with adequate non-erosive drainage devices.
Based on these considerations the retaining wall backdrainage system is not expected to
experience an appreciable flow of water, and in particular, no groundwater will affect it.
However, for the purposes of design, a flow of 5 gallons per minute may be assumed.
August 29, 2017 File No. 21428 Page 27
Geotechnologies, Inc. 439 Western Avenue, Glendale, California 91201-2837 Tel: 818.240.9600 Fax: 818.240.9675
www.geoteq.com
TEMPORARY EXCAVATIONS
It is anticipated that excavations on the order of 37 feet in vertical height will be required for the
proposed subterranean levels and foundation elements. The excavations are expected to expose
fill and dense native soils, which are suitable for vertical excavations up to 5 feet where not
surcharged by adjacent traffic or structures. Excavations which will be surcharged by adjacent
traffic, public way, or adjacent structures should be shored.
Where sufficient space is available, temporary unsurcharged embankments could be sloped back
at a uniform 1:1 slope gradient to a maximum depth of 35 feet. A uniform sloped excavation
does not have a vertical component.
Where sloped embankments are utilized, the tops of the slopes should be barricaded to prevent
vehicles and storage loads near the top of slope within a horizontal distance equal to the depth of
the excavation. If the temporary construction embankments are to be maintained during the
rainy season, berms are suggested along the tops of the slopes where necessary to prevent runoff
water from entering the excavation and eroding the slope faces. The soils exposed in the cut
slopes should be inspected during excavation by personnel from this office so that modifications
of the slopes can be made if variations in the soil conditions occur.
Excavation Observations
It is critical that the soils exposed in the cut slopes are observed by a representative of
Geotechnologies, Inc. during excavation so that modifications of the slopes can be made if
variations in the geologic material conditions occur. Many building officials require that
temporary excavations should be made during the continuous observations of the geotechnical
engineer. All excavations should be stabilized within 30 days of initial excavation.
August 29, 2017 File No. 21428 Page 28
Geotechnologies, Inc. 439 Western Avenue, Glendale, California 91201-2837 Tel: 818.240.9600 Fax: 818.240.9675
www.geoteq.com
SHORING DESIGN
The following information on the design and installation of the shoring is as complete as possible
at this time. It is suggested that a review of the final shoring plans and specifications be made by
this office prior to bidding or negotiating with a shoring contractor be made.
One method of shoring would consist of steel soldier piles, placed in drilled holes and backfilled
with concrete. The soldier piles may be designed as cantilevers or laterally braced utilizing
drilled tie-back anchors or raker braces.
Soldier Piles
Drilled cast-in-place soldier piles should be placed no closer than 2 diameters on center. The
minimum diameter of the piles is 18 inches. Structural concrete should be used for the soldier
piles below the excavation; lean-mix concrete may be employed above that level. As an
alternative, lean-mix concrete may be used throughout the pile where the reinforcing consists of
a wideflange section. The slurry must be of sufficient strength to impart the lateral bearing
pressure developed by the wideflange section to the earth materials. For design purposes, an
allowable passive value for the earth materials below the bottom plane of excavation may be
assumed to be 500 pounds per square foot per foot. To develop the full lateral value, provisions
should be implemented to assure firm contact between the soldier piles and the undisturbed earth
materials.
The frictional resistance between the soldier piles and retained earth material may be used to
resist the vertical component of the anchor load. The coefficient of friction may be taken as 0.35
based on uniform contact between the steel beam and lean-mix concrete and retained earth. The
portion of soldier piles below the plane of excavation may also be employed to resist the
downward loads. The downward capacity may be determined using a frictional resistance of 500
pounds per square foot. The minimum depth of embedment for shoring piles is 5 feet below the
August 29, 2017 File No. 21428 Page 29
Geotechnologies, Inc. 439 Western Avenue, Glendale, California 91201-2837 Tel: 818.240.9600 Fax: 818.240.9675
www.geoteq.com
bottom of the footing excavation, or 7 feet below the bottom of excavated plane, whichever is
deeper.
Casing may be required should caving be experienced in the saturated earth materials. If casing
is used, extreme care should be employed so that the pile is not pulled apart as the casing is
withdrawn. At no time should the distance between the surface of the concrete and the bottom of
the casing be less than 5 feet.
Piles placed below the water level will require the use of a tremie to place the concrete into the
bottom of the hole. A tremie shall consist of a water-tight tube with a diameter no less than 4
inches and connected to a concrete pump. The tube shall be equipped with a device that will
close the discharge end and prevent water from entering the tube while it is being charged with
concrete. The tremie shall be supported so as to permit free movement of the discharge end over
the entire top surface of the work and to permit rapid lowering when necessary to retard or stop
the flow of concrete. The discharge end shall be closed at the start of the work to prevent water
entering the tube and shall be entirely sealed at all times, except when the concrete is being
placed. The tremie tube shall be kept full of concrete. The flow shall be continuous until the
work is completed and the resulting concrete seal shall be monolithic and homogeneous. The tip
of the tremie tube shall always be kept about five feet below the surface of the concrete and
definite steps and safeguards should be taken to insure that the tip of the tremie tube is never
raised above the surface of the concrete.
A special concrete mix should be used for concrete to be placed below water. The design shall
provide for concrete with a strength of 1,000 psi over the initial job specification. An admixture
that reduces the problem of segregation of paste/aggregates and dilution of paste shall be
included. The slump shall be commensurate to any research report for the admixture, provided
that it shall also be the minimum for a reasonable consistency for placing when water is present.
August 29, 2017 File No. 21428 Page 30
Geotechnologies, Inc. 439 Western Avenue, Glendale, California 91201-2837 Tel: 818.240.9600 Fax: 818.240.9675
www.geoteq.com
Lagging
Soldier piles and anchors should be designed for the full anticipated pressures. Due to the
cohesionless nature of the underlying earth materials, lagging will be required throughout the
entire depth of the excavation. Due to arching in the geologic materials, the pressure on the
lagging will be less. It is recommended that the lagging should be designed for the full design
pressure but be limited to a maximum of 400 pounds per square foot. It is recommended that a
representative of this firm observe the installation of lagging to insure uniform support of the
excavated embankment.
Lateral Pressures
A triangular distribution of lateral earth pressure should be utilized for the design of cantilevered
shoring system. A trapezoidal distribution of lateral earth pressure would be appropriate where
shoring is to be restrained at the top by bracing or tie backs. The design of trapezoidal
distribution of pressure is shown in the diagram below. Equivalent fluid pressures for the design
of cantilevered and restrained shoring are presented in the following table:
Height of Shoring
(feet)
Cantilever Shoring System Equivalent Fluid Pressure
Triangular Distribution of Pressure Active Earth Pressure (pcf)
Restrained Shoring System Lateral Earth Pressure (psf)*
Trapezoidal Distribution of Pressure
Up to 10 25 18H
10 to 20 30 19H
20 to 30 34 22H
30 to 40 37 24H
40 to 50 38 24H *Where H is the height of the shoring in feet.
August 29, 2017 File No. 21428 Page 31
Geotechnologies, Inc. 439 Western Avenue, Glendale, California 91201-2837 Tel: 818.240.9600 Fax: 818.240.9675
www.geoteq.com
Where a combination of sloped embankment and shoring is utilized, the pressure will be greater
and must be determined for each combination. Additional active pressures should be applied
where the shoring will be surcharged by adjacent traffic or structures.
The upper ten feet of the retaining wall adjacent to streets, driveways or parking areas should be
designed to resist a uniform lateral pressure of 100 pounds per square foot, acting as a result of
an assumed 300 pounds per square foot surcharge behind the walls due to normal street traffic.
If the traffic is kept back at least ten feet from the retaining walls, the traffic surcharge may be
neglected. Foundations may be designed using the allowable bearing capacities, friction, and
passive earth pressure found in the “Foundation Design” section above.
Tied-Back Anchors
Tied-back anchors may be used to resist lateral loads. Friction anchors are recommended. For
design purposes, it may be assumed that the active wedge adjacent to the shoring is defined by a
August 29, 2017 File No. 21428 Page 32
Geotechnologies, Inc. 439 Western Avenue, Glendale, California 91201-2837 Tel: 818.240.9600 Fax: 818.240.9675
www.geoteq.com
plane drawn 35 degrees with the vertical through the bottom plane of the excavation. Friction
anchors should extend a minimum of 20 feet beyond the potentially active wedge.
Drilled friction anchors may be designed for a skin friction of 500 pounds per square foot.
Pressure grouted anchor may be designed for a skin friction of 2,000 pounds per square foot.
Where belled anchors are utilized, the capacity of belled anchors may be designed by assuming
the diameter of the bonded zone is equivalent to the diameter of the bell. Only the frictional
resistance developed beyond the active wedge would be effective in resisting lateral loads.
It is recommended that at least 3 of the initial anchors have their capacities tested to 200 percent
of their design capacities for a 24-hour period to verify their design capacity. The total
deflection during this test should not exceed 12 inches. The anchor deflection should not exceed
0.75 inches during the 24 hour period, measured after the 200 percent load has been applied.
All anchors should be tested to at least 150 percent of design load. The total deflection during
this test should not exceed 12 inches. The rate of creep under the 150 percent test load should
not exceed 0.1 inch over a 15 minute period in order for the anchor to be approved for the design
loading.
After a satisfactory test, each anchor should be locked-off at the design load. This should be
verified by rechecking the load in the anchor. The load should be within 10 percent of the design
load. Where satisfactory tests are not attained, the anchor diameter and/or length should be
increased or additional anchors installed until satisfactory test results are obtained. The
installation and testing of the anchors should be observed by the geotechnical engineer. Minor
caving during drilling of the anchors should be anticipated.
August 29, 2017 File No. 21428 Page 33
Geotechnologies, Inc. 439 Western Avenue, Glendale, California 91201-2837 Tel: 818.240.9600 Fax: 818.240.9675
www.geoteq.com
Anchor Installation
Tied-back anchors may be installed between 20 and 40 degrees below the horizontal. Caving of
the anchor shafts, particularly within sand deposits, should be anticipated and the following
provisions should be implemented in order to minimize such caving. The anchor shafts should
be filled with concrete by pumping from the tip out, and the concrete should extend from the tip
of the anchor to the active wedge. In order to minimize the chances of caving, it is
recommended that the portion of the anchor shaft within the active wedge be backfilled with
sand before testing the anchor. This portion of the shaft should be filled tightly and flush with
the face of the excavation. The sand backfill should be placed by pumping; the sand may contain
a small amount of cement to facilitate pumping.
Deflection
It is difficult to accurately predict the amount of deflection of a shored embankment. It should
be realized that some deflection will occur. It is estimated that the deflection could be on the
order of one inch at the top of the shored embankment. Shoring deflection shall be limited to ½
inch at the top of the shored embankment, where a structure is located within a 1:1 (h:v)
surcharge plane projected up from the base of the excavation.
If greater deflection occurs during construction, additional bracing may be necessary to minimize
settlement of adjacent buildings and utilities in adjacent street and alleys. If desired to reduce the
deflection, a greater active pressure could be used in the shoring design.
Where internal bracing is used, the rakers should be tightly wedged to minimize deflection. The
proper installation of the raker braces and the wedging will be critical to the performance of the
shoring.
August 29, 2017 File No. 21428 Page 34
Geotechnologies, Inc. 439 Western Avenue, Glendale, California 91201-2837 Tel: 818.240.9600 Fax: 818.240.9675
www.geoteq.com
Monitoring
Because of the depth of the excavation, some means of monitoring the performance of the
shoring system is suggested. The monitoring should consist of periodic surveying of the lateral
and vertical locations of the tops of all soldier piles and the lateral movement along the entire
lengths of selected soldier piles. Also, some means of periodically checking the load on selected
anchors will be necessary, where applicable.
Some movement of the shored embankments should be anticipated as a result of the relatively
deep excavation. It is recommended that photographs of the existing buildings on the adjacent
properties be made during construction to record any movements for use in the event of a
dispute.
Shoring Observations
It is critical that the installation of shoring is observed by a representative of Geotechnologies,
Inc. Many building officials require that shoring installation should be performed during
continuous observation of a representative of the geotechnical engineer. The observations insure
that the recommendations of the geotechnical report are implemented and so that modifications
of the recommendations can be made if variations in the geologic material or groundwater
conditions warrant. The observations will allow for a report to be prepared on the installation of
shoring for the use of the local building official, where necessary.
Raker Brace Foundations
An allowable bearing pressure of 3,500 pounds per square foot may be used for the design a
raker foundations. This bearing pressure is based on a raker foundation a minimum of 4 feet in
width and length as well as 4 feet in depth. The base of the raker foundations should be
horizontal. Care should be employed in the positioning of raker foundations so that they do not
interfere with the foundations for the proposed structure.
August 29, 2017 File No. 21428 Page 35
Geotechnologies, Inc. 439 Western Avenue, Glendale, California 91201-2837 Tel: 818.240.9600 Fax: 818.240.9675
www.geoteq.com
SLABS ON GRADE
Concrete Slabs-on Grade
Concrete floor slabs should be a minimum of 5 inches in thickness. Slabs-on-grade should be
cast over undisturbed native soils or properly controlled fill materials. Any earth materials
loosened or over-excavated should be wasted from the site or properly compacted to 90 percent
of the maximum dry density.
Outdoor Concrete Slabs
Outdoor concrete flatwork should be a minimum of 4 inches in thickness. Outdoor concrete
flatwork should be cast over undisturbed natural geologic materials or properly controlled fill
materials. Any geologic materials loosened or over-excavated should be wasted from the site or
properly compacted to 90 percent of the maximum dry density.
Outdoor flatwork should be reinforced with a minimum of #3 steel bars on 18-inch center each
way.
Design of Slabs That Receive Moisture-Sensitive Floor Coverings
Geotechnologies, Inc. does not practice in the field of moisture vapor transmission evaluation
and mitigation. Therefore it is recommended that a qualified consultant be engaged to evaluate
the general and specific moisture vapor transmission paths and any impact on the proposed
construction. The qualified consultant should provide recommendations for mitigation of
potential adverse impacts of moisture vapor transmission on various components of the structure.
August 29, 2017 File No. 21428 Page 36
Geotechnologies, Inc. 439 Western Avenue, Glendale, California 91201-2837 Tel: 818.240.9600 Fax: 818.240.9675
www.geoteq.com
Where dampness would be objectionable, it is recommended that the floor slabs should be
waterproofed. A qualified waterproofing consultant should be retained in order to recommend a
product or method which would provide protection for concrete slabs-on-grade.
All concrete slabs-on-grade should be supported on vapor retarder. The design of the slab and
the installation of the vapor retarder should comply with the most recent revisions of ASTM E
1643 and ASTM E 1745. The vapor retarder should comply with ASTM E 1745 Class A
requirements.
Where a vapor retarder is used, a low-slump concrete should be used to minimize possible
curling of the slabs. The barrier can be covered with a layer of trimable, compactible, granular
fill, where it is thought to be beneficial. See ACI 302.2R-32, Chapter 7 for information on the
placement of vapor retarders and the use of a fill layer.
Concrete Crack Control
The recommendations presented in this report are intended to reduce the potential for cracking of
concrete slabs-on-grade due to settlement. However even where these recommendations have
been implemented, foundations, stucco walls and concrete slabs-on-grade may display some
cracking due to minor soil movement and/or concrete shrinkage. The occurrence of concrete
cracking may be reduced and/or controlled by limiting the slump of the concrete used, proper
concrete placement and curing, and by placement of crack control joints at reasonable intervals,
in particular, where re-entrant slab corners occur.
For standard control of concrete cracking, a maximum crack control joint spacing of 12 feet
should not be exceeded. Lesser spacings would provide greater crack control. Joints at curves
and angle points are recommended. The crack control joints should be installed as soon as
practical following concrete placement. Crack control joints should extend a minimum depth of
one-fourth the slab thickness. Construction joints should be designed by a structural engineer.
August 29, 2017 File No. 21428 Page 37
Geotechnologies, Inc. 439 Western Avenue, Glendale, California 91201-2837 Tel: 818.240.9600 Fax: 818.240.9675
www.geoteq.com
Complete removal of the existing fill soils beneath outdoor flatwork such as walkways or patio
areas, is not required, however, due to the rigid nature of concrete, some cracking, a shorter
design life and increased maintenance costs should be anticipated. In order to provide uniform
support beneath the flatwork it is recommended that a minimum of 12 inches of the exposed
subgrade beneath the flatwork be scarified and recompacted to 90 percent relative compaction.
SITE DRAINAGE
Proper surface drainage is critical to the future performance of the project. Saturation of a soil
can cause it to lose internal shear strength and increase its compressibility, resulting in a change
in the designed engineering properties. Proper site drainage should be maintained at all times.
All site drainage, with the exception of any required to disposed of onsite by stormwater
regulations, should be collected and transferred to the street in non-erosive drainage devices.
The proposed structure should be provided with roof drainage. Discharge from downspouts, roof
drains and scuppers should not be permitted on unprotected soils within five feet of the building
perimeter. Drainage should not be allowed to pond anywhere on the site, and especially not
against any foundation or retaining wall. Drainage should not be allowed to flow uncontrolled
over any descending slope. Planters which are located within a distance equal to the depth of a
retaining wall should be sealed to prevent moisture adversely affecting the wall. Planters which
are located within five feet of a foundation should be sealed to prevent moisture affecting the
earth materials supporting the foundation.
STORMWATER DISPOSAL
Recently regulatory agencies have been requiring the disposal of a certain amount of stormwater
generated on a site by infiltration into the site soils. Increasing the moisture content of a soil can
cause it to lose internal shear strength and increase its compressibility, resulting in a change in
the designed engineering properties. This means that any overlying structure, including
buildings, pavements and concrete flatwork, could sustain damage due to saturation of the
August 29, 2017 File No. 21428 Page 38
Geotechnologies, Inc. 439 Western Avenue, Glendale, California 91201-2837 Tel: 818.240.9600 Fax: 818.240.9675
www.geoteq.com
subgrade soils. Structures serviced by subterranean levels could be adversely impacted by
stormwater disposal by increasing the design fluid pressures on retaining walls and causing leaks
in the walls. Proper site drainage is critical to the performance of any structure in the built
environment.
It is anticipated that the proposed structure will extend to the property lines, which would not
allow for a proper horizontal setback distance between a shallow infiltration system and
structures or property lines. A deep infiltration system would not be suitable either, as the
proposed foundation system will be located within a layer of sandy silt overlain by a thick layer
of lean clay and fat clay extending to a depth of 67.5 feet below the existing grade, where
groundwater level was encountered during exploration. Clay soils have been characterized to
have very low permeability and water will take a lot longer to infiltrate. Therefore, based on
limits of excavation for the proposed subterranean levels, soil type below the footings, and
groundwater level, it is the opinion of this firm that stormwater infiltration is not feasible for the
proposed project.
Where percolation of stormwater into the subgrade soils is not advisable, most Building Officials
have allowed the stormwater to be filtered through soils in planter areas. Once the water has
been filtered through a planter it may be released into the storm drain system. It is recommended
that overflow pipes are incorporated into the design of the discharge system in the planters to
prevent flooding. In addition, the planters shall be sealed and waterproofed to prevent leakage.
Please be advised that adverse impact to landscaping and periodic maintenance may result due to
excessive water and contaminants discharged into the planters.
It is recommended that the design team (including the structural engineer, waterproofing
consultant, plumbing engineer, and landscape architect) be consulted in regard to the design and
construction of infiltration system.
August 29, 2017 File No. 21428 Page 39
Geotechnologies, Inc. 439 Western Avenue, Glendale, California 91201-2837 Tel: 818.240.9600 Fax: 818.240.9675
www.geoteq.com
DESIGN REVIEW
Engineering of the proposed project should not begin until approval of the geotechnical report by
the Building Official is obtained in writing. Significant changes in the geotechnical
recommendations may result during the building department review process.
It is recommended that the geotechnical aspects of the project be reviewed by this firm during
the design process. This review provides assistance to the design team by providing specific
recommendations for particular cases, as well as review of the proposed construction to evaluate
whether the intent of the recommendations presented herein are satisfied.
CONSTRUCTION MONITORING
Geotechnical observations and testing during construction are considered to be a continuation of
the geotechnical investigation. It is critical that this firm review the geotechnical aspects of the
project during the construction process. Compliance with the design concepts, specifications or
recommendations during construction requires review by this firm during the course of
construction. All foundations should be observed by a representative of this firm prior to placing
concrete or steel. Any fill which is placed should be observed, tested, and verified if used for
engineered purposes. Please advise Geotechnologies, Inc. at least twenty-four hours prior to any
required site visit.
If conditions encountered during construction appear to differ from those disclosed herein, notify
Geotechnologies, Inc. immediately so the need for modifications may be considered in a timely
manner.
It is the responsibility of the contractor to ensure that all excavations and trenches are properly
sloped or shored. All temporary excavations should be cut and maintained in accordance with
applicable OSHA rules and regulations.
August 29, 2017 File No. 21428 Page 40
Geotechnologies, Inc. 439 Western Avenue, Glendale, California 91201-2837 Tel: 818.240.9600 Fax: 818.240.9675
www.geoteq.com
EXCAVATION CHARACTERISTICS
The exploration performed for this investigation is limited to the geotechnical excavations
described. Direct exploration of the entire site would not be economically feasible. The owner,
design team and contractor must understand that differing excavation and drilling conditions may
be encountered based on boulders, gravel, oversize materials, groundwater and many other
conditions. Fill materials, especially when they were placed without benefit of modern grading
codes, regularly contain materials which could impede efficient grading and drilling. Southern
California sedimentary bedrock is known to contain variable layers which reflect differences in
depositional environment. Such layers may include abundant gravel, cobbles and boulders.
Similarly bedrock can contain concretions. Concretions are typically lenticular and follow the
bedding. They are formed by mineral deposits. Concretions can be very hard. Excavation and
drilling in these areas may require full size equipment and coring capability. The contractor
should be familiar with the site and the geologic materials in the vicinity.
CLOSURE AND LIMITATIONS
The purpose of this report is to aid in the design and completion of the described project.
Implementation of the advice presented in this report is intended to reduce certain risks
associated with construction projects. The professional opinions and geotechnical advice
contained in this report are sought because of special skill in engineering and geology and were
prepared in accordance with generally accepted geotechnical engineering practice.
Geotechnologies, Inc. has a duty to exercise the ordinary skill and competence of members of the
engineering profession. Those who hire Geotechnologies, Inc. are not justified in expecting
infallibility, but can expect reasonable professional care and competence.
The scope of the geotechnical services provided did not include any environmental site
assessment for the presence or absence of organic substances, hazardous/toxic materials in the
soil, surface water, groundwater, or atmosphere, or the presence of wetlands.
August 29, 2017 File No. 21428 Page 41
Geotechnologies, Inc. 439 Western Avenue, Glendale, California 91201-2837 Tel: 818.240.9600 Fax: 818.240.9675
www.geoteq.com
Proper compaction is necessary to reduce settlement of overlying improvements. Some
settlement of compacted fill should be anticipated. Any utilities supported therein should be
designed to accept differential settlement. Differential settlement should also be considered at
the points of entry to the structure.
The City of Santa Monica does not require corrosion testing. However, if corrosion sensitive
improvements are planned, it is recommended that a comprehensive corrosion study should be
commissioned. The study will develop recommendations to avoid premature corrosion of buried
pipes and concrete structures in direct contact with the soils.
GEOTECHNICAL TESTING
Classification and Sampling
The soil is continuously logged by a representative of this firm and classified by visual
examination in accordance with the Unified Soil Classification system (USCS). The field
classification is verified in the laboratory, also in accordance with the Unified Soil Classification
System. Laboratory classification may include visual examination, Atterberg Limit Tests and
grain size distribution. The final classification is shown on the boring logs.
Samples of the geologic materials encountered in the exploratory excavations were collected and
transported to the laboratory. Undisturbed samples of soil are obtained at frequent intervals.
Unless noted on the excavation logs as an SPT sample, samples acquired while utilizing a
hollow-stem auger drill rig are obtained by driving a thin-walled, California Modified Sampler
with successive 30-inch drops of a 140-pound hammer. The soil is retained in brass rings of 2.50
inches outside diameter and 1.00 inch in height. The central portion of the samples are stored in
close fitting, waterproof containers for transportation to the laboratory. Samples noted on the
excavation logs as SPT samples are obtained in accordance with the most recent revision of
ASTM D 1586. Samples are retained for 30 days after the date of the geotechnical report.
August 29, 2017 File No. 21428 Page 42
Geotechnologies, Inc. 439 Western Avenue, Glendale, California 91201-2837 Tel: 818.240.9600 Fax: 818.240.9675
www.geoteq.com
Moisture and Density Relationships
The field moisture content and dry unit weight are determined for each of the undisturbed soil
samples, and the moisture content is determined for SPT samples by the most recent revision of
ASTM D 4959 or ASTM D 4643. This information is useful in providing a gross picture of the
soil consistency between exploration locations and any local variations. The dry unit weight is
determined in pounds per cubic foot and shown on the “Boring Logs”, A-Plate. The field
moisture content is determined as a percentage of the dry unit weight.
Direct Shear Testing
Shear tests are performed by the most recent revision of ASTM D 3080 with a strain controlled,
direct shear machine manufactured by Soil Test, Inc. or a Direct Shear Apparatus manufactured
by GeoMatic, Inc. The rate of deformation is approximately 0.005 inches per minute. Each
sample is sheared under varying confining pressures in order to determine the Mohr-Coulomb
shear strength parameters of the cohesion intercept and the angle of internal friction. Samples
are generally tested in an artificially saturated condition. Depending upon the sample location
and future site conditions, samples may be tested at field moisture content. The results are
plotted on the "Shear Test Diagram," B-Plates.
The most recent revision of ASTM 3080 limits the particle size to 10 percent of the diameter of
the direct shear test specimen. The sheared sample is inspected by the laboratory technician
running the test. The inspection is performed by splitting the sample along the sheared plane and
observing the soils exposed on both sides. Where oversize particles are observed in the shear
plane, the results are discarded and the test run again with a fresh sample.
August 29, 2017 File No. 21428 Page 43
Geotechnologies, Inc. 439 Western Avenue, Glendale, California 91201-2837 Tel: 818.240.9600 Fax: 818.240.9675
www.geoteq.com
Consolidation Testing
Settlement predictions of the soil's behavior under load are made on the basis of the
consolidation tests using the most recent revision of ASTM D 2435. The consolidation
apparatus is designed to receive a single one-inch high ring. Loads are applied in several
increments in a geometric progression, and the resulting deformations are recorded at selected
time intervals. Porous stones are placed in contact with the top and bottom of each specimen to
permit addition and release of pore fluid. Samples are generally tested at increased moisture
content to determine the effects of water on the bearing soil. The normal pressure at which the
water is added is noted on the drawing. Results are plotted on the "Consolidation Test," C-
Plates.
Grain Size Distribution
These tests cover the quantitative determination of the distribution of particle sizes in soils.
Sieve analysis is used to determine the grain size distribution of the soil larger than the Number
200 sieve. The most recent revision of ASTM D 422 is used to determine particle sizes smaller
than the Number 200 sieve. A hydrometer is used to determine the distribution of particle sizes
by a sedimentation process. The grain size distributions are plotted on the enclosed E-Plates.
Atterberg Limits
Depending on their moisture content, cohesive soils can be solid, plastic, or liquid. The water
content corresponding to the transition from solid to plastic or plastic to liquid are known as the
Atterberg Limits. The transitions are called the plastic limit and liquid limit. The difference
between the liquid limit and plastic limit is known as the plasticity index. ASTM D 4318 is
utilized to determine the Atterberg Limits. The results are shown on the enclosed F-Plate.
Geotechnologies, Inc. 439 Western Avenue, Glendale, California 91201-2837 Tel: 818.240.9600 Fax: 818.240.9675
www.geoteq.com
REFERENCES California Department of Conservation, 2008, Guidelines for Evaluating and Mitigating Seismic
Hazards in California, Special Publication 117A, California Geological Survey. California Department of Conservation, Division of Mines and Geology, 1999, Seismic Hazard
Zones Map, Beverly Hills 7½-minute Quadrangle, CDMG Seismic Hazard Zone Mapping Act of 1990.
California Department of Conservation, Division of Mines and Geology, 1998 (Revised 2005),
Seismic Hazard Zone Report of the Beverly Hills 7½-Minute Quadrangle, Los Angeles County, California., C.D.M.G. Seismic Hazard Zone Report 023, map scale 1:24,000.
California Geological Survey, 2017, Earthquake Fault Zones, Preliminary Review Map, Beverly
Hills 7 ½-minute Quadrangle, map scale 1:24,000. City of Santa Monica, Department of Building and Safety, March 2010, Guidelines for
Geotechnical Reports, Version 1.6. City of Santa Monica, Department of Building and Safety, 2014, Geological Hazards Map, Map
scale 1:26,000. Leighton and Associates, Inc., 1995, Technical Background Report to the Safety Element of the
City of Santa Monica General Plan, Project No. 2910399-01. Leighton and Associates, Inc., 1990, Technical Appendix to the Safety Element of the Los
Angeles County General Plan: Hazard Reduction in Los Angeles County. Los Angeles Department of Public Works, 2010, Groundwater Wells Website http://gis.dpw.lacounty.gov/wells/viewer.asp. Tinsley, J.C., and Fumal, T.E., 1985, Mapping quaternary Sedimentary Deposits for Areal
Variations in Shaking Response, in Evaluation Earthquake Hazards in the Los Angeles Region- An Earth Science Perspective, U.S. Geological Survey Professional Paper 1360, Ziony, J.I. ed., pp 101-125.
United States Geological Survey, 2017, U.S.G.S. Ground Motion Parameter Calculator (Version
5.1.0). http://earthquake.usgs.gov/hazards/designmaps/ United States Geological Survey, 2017, U.S.G.S. Interactive Deaggregation Program.
http://eqint.cr.usgs.gov/deaggint/2008/index.php. U.S. Department of the Interior, U.S. Geological Survey, Preliminary Geologic Map of the Los
Angeles 30' x 60' Quadrangle, Southern California, Version 1.0, 2005, Compiled by Robert F. Yerkes and Russell H. Campbell.
Yerkes, R.F., et al. 1965, Geology of the Los Angeles, Basin, California- An Introduction, U.S.
Geological Survey Professional Paper 420-A.
REFERENCE:
VICINITY MAP
FILE NO. 21428
BEVERLY HILLS, CA QUADRANGLEU.S.G.S. TOPOGRAPHIC MAPS, 7.5 MINUTE SERIES,
CLARETT WEST DEVELOPMENTGeotechnologies, Inc.Consulting Geotechnical Engineers
N
Well No. 2537
Well No. 2546L
Well No. 2539L
SEISMIC STATION 24538LAT: 34.0110 / LONG: 118.4900
SEISMIC STATION 24048LAT: 34.0289 / LONG: 118.4820
SEISMIC STATION 24202LAT: 34.0300 / LONG: 118.4790
SUBJECT SITESUBJECT SITELAT: 34.0177 / LONG: 118.4959
4TH STREET AND ARIZONA AVENUE
ELEVATION IN FEET
A
8090100 6070 01020304050 -20
-10
110
120
130
140
A'
ELEVATION IN FEET
PRO
POSE
D S
TRU
CTU
RE
8090100
6070 01020304050 -20
-10
110
120
130
140
P.L
.P
.L.
4TH
ST
RE
ET
5TH
ST
RE
ET
BO
RIN
G 1
GR
OU
ND
WA
TE
R L
EV
EL
EN
CO
UN
TE
RE
D I
N B
OR
ING
CR
OS
S-S
EC
TIO
N A
-A'
160
800
SC
AL
E I
N F
EE
T
N46
E
Con
sult
ing
Geo
tech
nic
al
En
gin
eers
FIL
E N
o.
2142
8D
RA
WN
BY
: T
CGe
otec
hnol
ogie
s, In
c.D
AT
E:
Ju
ly 2
017
RE
FER
EN
CE
S:
AL
TA
/AC
SM
LA
ND
TIT
LE
SU
RV
EY
PR
OV
IDE
D B
Y J
RN
CIV
IL E
NG
INE
ER
SD
AT
ED
AU
GU
ST
29,
201
4
CL
AR
ET
T W
ES
T D
EV
EL
OP
ME
NT
Exi
stin
g G
.S.
Fill
Old
All
uvi
um
?Fi
ll?
?
1301
‐1333 4TH STR
EET & 132
4‐13
34 5TH
STR
EET, SAN
TA M
ONICA
ES
TIM
AT
ED
F.F
.E.:
58'
Old
All
uvi
um
Old
All
uvi
um
GR
OU
ND
WA
TE
R L
EV
EL
HIS
TO
RIC
AL
LY H
IGH
ES
T
Ele
v.54
'
WML
HISTORICALLY HIGHEST GROUNDWATER LEVELS
REFERENCE:
20 Depth to groundwater in feet
Geotechnologies, Inc.Consulting Geotechnical Engineers
SUBJECT SITE
N
CDMG, SEISMIC HAZARD ZONE REPORT, 023BEVERLY HILLS 7.5 - MINUTE QUADRANGLE, LOS ANGELES COUNTY, CALIFORNIA (1998, REVISED 2005)
FILE NO. 21428
CLARETT WEST DEVELOPMENT4TH STREET AND ARIZONA AVENUE
SEISMIC HAZARD ZONE MAP
GGeeootteecchhnnoollooggiieess,, IInncc..Consulting Geotechnical Engineers
LIQUEFACTION AREA
REFERENCE:1999, DIVISION OF MINES AND GEOLOGYSEISMIC HAZARD ZONE MAP, BEVERLY HILLS QUADRANGLE,
N
SUBJECT SITE
FILE NO. 21428
CLARETT WEST DEVELOPMENT4TH STREET AND ARIZONA AVENUE
22 AArrrroowwhheeaadd ffaauulltt33 BBaaiilleeyy ffaauulltt44 BBiigg MMoouunnttaaiinn ffaauulltt55 BBiigg PPiinnee ffaauulltt66 BBllaakkee RRaanncchh ffaauulltt77 CCaabbrriilllloo ffaauulltt88 CChhaattsswwoorrtthh ffaauulltt99 CChhiinnoo ffaauulltt
1100 CCllaammsshheellll--SSaawwppiitt ffaauulltt1111 CClleeaarrwwaatteerr ffaauulltt1122 CClleegghhoorrnn ffaauulltt1133 CCrraaffttoonn HHiillllss ffaauulltt zzoonnee1144 CCuuccaammoonnggaa ffaauulltt zzoonnee1155 DDrryy CCrreeeekk ffaauulltt1166 EEaaggllee RRoocckk ffaauulltt1177 EEll MMooddeennoo ffaauulltt1188 FFrraazziieerr MMoouunnttaaiinn tthhrruusstt1199 GGaarrlloocckk ffaauulltt zzoonnee2200 GGrraassss VVaalllleeyy ffaauulltt
2211 HHeelleennddaallee ffaauulltt2222 HHoollllyywwoooodd ffaauulltt2233 HHoollsseerr ffaauulltt2244 LLiioonn CCaannyyoonn ffaauulltt2255 LLllaannoo ffaauulltt2266 LLooss AAllaammiittooss ffaauulltt2277 MMaalliibbuu CCooaasstt ffaauulltt2288 MMiinntt CCaannyyoonn ffaauulltt2299 MMiirraaggee VVaalllleeyy ffaauulltt zzoonnee3300 MMiissssiioonn HHiillllss ffaauulltt3311 NNeewwppoorrtt IInngglleewwoooodd ffaauulltt zzoonnee3322 NNoorrtthh FFrroonnttaall ffaauulltt zzoonnee3333 NNoorrtthhrriiddggee HHiillllss ffaauulltt3344 OOaakk RRiiddggee ffaauulltt3355 PPaallooss VVeerrddeess ffaauulltt zzoonnee3366 PPeelloonnaa ffaauulltt3377 PPeerraallttaa HHiillllss ffaauulltt3388 PPiinnee MMoouunnttaaiinn ffaauulltt3399 RRaayymmoonndd ffaauulltt4400 RReedd HHiillll ((EEttiiwwaannddaa AAvvee)) ffaauulltt
4411 RReeddoonnddoo CCaannyyoonn ffaauulltt4422 SSaann AAnnddrreeaass FFaauulltt4433 SSaann AAnnttoonniioo ffaauulltt4444 SSaann CCaayyeettaannoo ffaauulltt4455 SSaann FFeerrnnaannddoo ffaauulltt zzoonnee4466 SSaann GGaabbrriieell ffaauulltt zzoonnee4477 SSaann JJaacciinnttoo ffaauulltt4488 SSaann JJoossee ffaauulltt4499 SSaannttaa CCrruuzz--SSaannttaa CCaattaalliinnaa RRiiddggee ff..zz..5500 SSaannttaa MMoonniiccaa ffaauulltt5511 SSaannttaa YYnneezz ffaauulltt5522 SSaannttaa SSuussaannaa ffaauulltt zzoonnee5533 SSiieerrrraa MMaaddrree ffaauulltt zzoonnee5544 SSiimmii ffaauulltt5555 SSoolleeddaadd CCaannyyoonn ffaauulltt5566 SSttooddddaarrdd CCaannyyoonn ffaauulltt5577 TTuunnnneell RRiiddggee ffaauulltt5588 VVeerrdduuggoo ffaauulltt5599 WWaatteerrmmaann CCaannyyoonn ffaauulltt6600 WWhhiittttiieerr ffaauulltt
11 AAllaammoo tthhrruusstt
hhttttpp::////ppaassaaddeennaa..wwrr..uussggss..ggoovv//iinnffoo//iimmaaggeess//LLAA%%2200FFaauullttss..ppddff
SOUTHERN CALIFORNIA FAULT MAPRREEFFEERREENNCCEE::
Geotechnologies, Inc.CCoonnssuullttiinngg GGeeootteecchhnniiccaall EEnnggiinneeeerrss
SUBJECT SITE
FILE NO. 21428
CLARETT WEST DEVELOPMENT4TH STREET AND ARIZONA AVENUE
EARTHQUAKE FAULT ZONE
FILE NO. 21428
CLARETT WEST DEVELOPMENTGeotechnologies, Inc.
Consulting Geotechnical Engineers
Earthquake Fault ZonesAlquist-Priolo Earthquake Fault Zone
N
REFERENCE: PRELIMINARY EARTHQUAKE FAULT ZONES, BEVERLY HILLS QUADRANGLE,CALIFORNIA GEOLOGICAL SURVEY, JULY 2017
4TH STREET AND ARIZONA AVENUE
SUBJECT SITE
Cons
ulting
Geo
techn
ical E
ngine
ers
RE
GIO
NA
L G
EO
LO
GIC
MA
P
Geot
echn
olog
ies,
Inc.
RE
FE
RE
NC
E:
U.S
. DE
PA
RT
ME
NT
OF
TH
E I
NT
ER
IOR
, U.S
. GE
OL
OG
ICA
L S
UR
VE
Y, P
RE
LIM
INA
RY
GE
OL
OG
IC M
AP
OF
TH
E L
OS
AN
GE
LE
S 3
0' X
60'
QU
AD
RA
NG
LE
, SO
UT
HE
RN
CA
LIF
OR
INA
,V
ER
SIO
N 1
.0, 2
005,
CO
MP
ILE
D B
Y R
OB
ER
T F
. YE
RK
ES
AN
D R
US
SE
LL
H. C
AM
PB
EL
L.
SU
BJE
CT
SIT
E
2 M
ile R
adiu
s
LE
GE
ND
Qaf
: A
rtif
icia
l F
ill
Qa:
All
uvi
um
Qf:
All
uvi
al-F
an D
epos
its
Qof
: O
ld A
llu
vial
-Fan
Dep
osit
s
Tm
: M
odel
o F
orm
atio
nT
t: T
op
anga
Gro
up
TK
b:
Sed
imen
tary
Roc
k i
n t
he
Bev
erly
Hil
ls A
rea
Jsm
: S
anta
Mon
ica
Sla
te
Qoa
: O
ld A
llu
viu
m
Kt:
Tu
na
Can
yon
For
mat
ion
Fa
ult
- S
olid
wh
ere
accu
rate
ly l
ocat
ed, d
ash
ed w
her
e ap
pro
xim
atel
ylo
cate
d,
dot
ted
wh
ere
con
ceal
ed, q
uie
ried
wh
ere
loca
tion
or
exis
ten
ceu
nce
rta
in.
incl
ud
es s
trik
e sl
ip, n
orm
al, r
ever
se, o
bli
qu
e, a
nd
un
spec
ifie
d s
lip
.
FIL
E N
O.
2142
8
CL
AR
ET
T W
ES
T D
EV
EL
OP
ME
NT
4TH
ST
RE
ET
AN
D A
RIZ
ON
A A
VE
NU
E
Consu
lting G
eotech
nical E
nginee
rs
GE
OL
OG
IC H
AZ
AR
D M
AP
Geot
echn
olog
ies,
Inc.
FIL
E N
O.
2142
8
CL
AR
ET
T W
ES
T D
EV
EL
OP
ME
NT
4TH STR
EET AND ARIZO
NA AV
ENUE
SU
BJE
CT
SIT
E
Clarett West Development Date: 06/16/17 Elevation: 92.5'*
File No. 21428 Method: 8-inch Hollow Stem Augerkm *Ref: ALTA/ACSM Land Title Survey by JRN Civil Engineers, dated 8/29/14
Sample Blows Moisture Dry Density Depth in USCS DescriptionDepth ft. per ft. content % p.c.f. feet Class. Surface Conditions: Asphalt Parking Lot
0 -- 7½-inch Thick Asphalt, No Base-
1 -- FILL: Sandy Silt, dark brown, moist-
2 --2.5 33 15.7 117.4 -
3 --- CL OLD ALLUVIUM: Lean Clay, dark brown, moist, hard
4 ---
5 34 14.1 SPT 5 --- gravel to 1" (slate), some fine Sand
6 ---
7 --7.5 49 7.4 128.7 -
8 -- CL Sandy Lean Clay, dark brown, moist, very stiff, fine Sand, - gravel (up to 1½ inch in size)
9 ---
10 27 12.2 SPT 10 --- some slate gravel (up to 1 inch in size)
11 ---
12 --12.5 48 3.3 137.2 -
13 -- dark brown, moist, fine Sand, abundant slate (up to 1 inch in- size), some Clay
14 ---
15 29 6.3 SPT 15 --- SM Silty Sand, dark gray, medium dense, fine grained, abundant
16 -- slate (up to 1 inch in size)-
17 --17.5 48 5.3 118.4 -
18 -- dark and yellowish brown, moist, dense, fine grained, some- cementation
19 ---
20 25 7.3 SPT 20 --- dark brown, moist, medium dense, fine gravel
21 ---
22 --22.5 68 4.4 139.2 -
23 -- dense, fine grained, abundant slate and gravel (up to 1 inch in - size)
24 ---
25 24 13.9 SPT 25 --- CL Sandy Lean Clay, brown, moist, very stiff, fine Sand, some
slate (up to 1 inch in size)
GEOTECHNOLOGIES, INC. Plate A-1a
BORING LOG NUMBER 1
Clarett West Development
File No. 21428km
Sample Blows Moisture Dry Density Depth in USCS DescriptionDepth ft. per ft. content % p.c.f. feet Class.
-26 --
-27 --
27.5 72 9.8 127.6 -28 -- dark brown, interlayer of fine Sand, rock fragment (Santa
- Monica slate (up to 2½ inches in size)29 --
-30 27 12.1 SPT 30 --
- ML Sandy Silt, brown, moist, fine Sand, very stiff31 --
-32 --
32.5 29 14.5 99.9 -33 -- SM Silty Sand, dark brownish gray, medium dense, fine Sand
-34 --
-35 18 11.3 SPT 35 --
- dark brown and gray, medium dense, fine grained, some slate36 -- (up to 1 inch in size)
-37 --
37.5 55 21.9 104.6 -38 -- ML Sandy Silt, brown, moist, hard, fine Sand
-39 --
-40 19 21.0 SPT 40 --
- CL Sandy Lean clay, brown, very moist, very stiff, fine Sand41 --
-42 --
42.5 31 12.9 100.3 -43 -- ML Sandy Silt, moist, brown, hard, fine Sand
-44 --
-45 17 19.0 SPT 45 --
- CL Lean Clay, reddish brown, moist, very stiff46 --
-47 --
47.5 39/6" 10.2 117.4 -50/4" 48 -- hard
-49 --
-50 36 19.3 SPT 50 --
- becomes dark brownish gray, hard
GEOTECHNOLOGIES, INC. Plate A-1b
BORING LOG NUMBER 1
Clarett West Development
File No. 21428km
Sample Blows Moisture Dry Density Depth in USCS DescriptionDepth ft. per ft. content % p.c.f. feet Class.
-51 --
-52 --
52.5 76 18.4 102.0 -53 -- ML Sandy Silt, olive brown and dark brown mottled, moist, hard,
- fine Sand54 --
-55 33 26.9 SPT 55 --
- CH Fat Clay, olive, hard, some fine Sand, some Silt56 -- fine grained
-57 --
57.5 72 24.4 100.4 -58 -- dark brown and orange brown mottled, hard
-59 --
-60 32 26.8 SPT 60 --
- CL Lean Clay, dark brownish gray, moist, hard61 --
-62 --
62.5 54 27.6 89.5 -63 -- dark grayish brown, very moist
-64 --
-65 25 27.0 SPT 65 --
- CH Fat Clay, dark gray, very stiff, very moist66 --
-67 --
67.5 50/4" 15.8 111.2 -68 -- ML Sandy Silt, dark orange brown, moist, hard, fine Sand, some
- Clay69 --
-70 37 18.9 SPT 70 --
- SM Silty Sand, orange brown, very moist, fine to medium dense71 --
-72 --
72.5 88 27.5 96.5 -73 -- CL Lean Clay, dark gray, hard
-74 --
- SP Poorly Graded Sand, moist, orange brown, very dense, fine to75 78 12.8 SPT 75 -- medium grained
-
GEOTECHNOLOGIES, INC. Plate A-1c
BORING LOG NUMBER 1
Clarett West Development
File No. 21428km
Sample Blows Moisture Dry Density Depth in USCS DescriptionDepth ft. per ft. content % p.c.f. feet Class.
-76 --
-77 --
77.5 75 13.5 Disturbed -78 -- wet
-79 --
-80 80 13.2 SPT 80 --
- SW Well-Graded Sand, yellowish brown, very moist, very dense,81 -- fine to coarse grained
-82 --
82.5 50/5" 13.2 Disturbed - SP Poorly Graded Sand, yellowish brown, wet, very dense, fine to83 -- medium grained, some Silt
-84 --
-85 50/3" 18.5 SPT 85 --
- dark olive gray, becomes fine grained, very dense86 --
-87 --
87.5 50/5" 14.0 Disturbed -88 --
-89 --
-90 50/4" 25.5 SPT 90 -- gray to dark gray
-91 --
-92 -- Total Depth 90 feet
- Water at 67½ feet93 -- Fill to 3 feet
-94 --
- NOTE: The stratification lines represent the approximate95 -- boundary between earth types; the transition may be gradual.
-96 -- Used 8-inch diameter Hollow-Stem Auger
- 140-lb. Automatic Hammer, 30-inch drop97 -- Modified California Sampler used unless otherwise noted
-98 -- SPT=Standard Penetration Test
-99 --
-100 --
-
GEOTECHNOLOGIES, INC. Plate A-1d
BORING LOG NUMBER 1
SHEAR TEST DIAGRAMDirect Shear, Saturated
C = 170 PSF
PHI = 33 DEGREES
3.5
3.0
Normal Pressure (KSF)
She
ar S
tren
gth
(KS
F)
0.5
03.02.52.01.51.00.50
SAMPLE MOISTURE(%)INITIAL
MOISTURE(%)FINAL
SOIL TYPEB1 @ 12.5' CL 137.2 3.3 12.8
DENSITY (PCF)DRY
B1 @ 22.5' SM 139.2 4.4 14.0B1 @ 32.5' SM 99.9 14.5 21.6
1.0
1.5
2.0
2.5
PLATE: B-1FILE NO. 21428
CLARETT WEST DEVELOPMENTGeotechnologies, Inc.Consulting Geotechnical Engineers
B1 @ 12.5'
B1 @ 22.5'
B1 @ 32.5'
B1 @ 42.5'
B1 @ 12.5'
B1 @ 12.5'B1 @ 22.5'
B1 @ 22.5'
B1 @ 32.5'
B1 @ 32.5'
B1 @ 42.5'
B1 @ 42.5'
B1 @ 42.5' CL 100.3 12.9 22.7
SHEAR TEST DIAGRAMDirect Shear, Saturated
C = 250 PSF
PHI = 30 DEGREES
3.5
3.0
Normal Pressure (KSF)
She
ar S
tren
gth
(KS
F)
0.5
03.02.52.01.51.00.50
SAMPLE MOISTURE(%)INITIAL
MOISTURE(%)FINAL
SOIL TYPE DENSITY (PCF)DRY
B1 @ 32.5' SM 99.9 14.5 21.6B1 @ 42.5' CL 100.3 12.9 22.7B1 @ 47.5' CL 117.4 10.2 27.5
1.0
1.5
2.0
2.5
B1 @ 52.5' ML 102.0 18.4 25.4B1 @ 62.5' CL 89.5 27.6 35.8
PLATE: B-2FILE NO. 21428
CLARETT WEST DEVELOPMENTGeotechnologies, Inc.Consulting Geotechnical Engineers
B1 @ 42.5'
B1 @ 47.5'
B1 @ 52.5'B1 @ 62.5'
B1 @ 47.5'
B1 @ 47.5'
B1 @ 42.5'
B1 @ 42.5'
B1 @ 52.5'
B1 @ 52.5',B1 @ 62.5'
B1 @ 62.5'
B1 @ 32.5'
B1 @ 32.5',
B1 @ 32.5'
CONSOLIDATION TEST
PLATE: CGeotechnologies, Inc.
Consulting Geotechnical Engineers
.1 .2 .3 .4 .5 .6 .7 .8 .9 1.0 2 3 4 5 6 7 8 9 10
Consolidation Pressure (KSF)
WATER ADDED AT 2 KSF
Per
cent
Con
solid
atio
n
2016
B1 @ 47.5' (CL)
FILE NO. 21428
CLARETT WEST DEVELOPMENT
2
0
4
B1 @ 37.5' (ML)
2
0
4
2
0
4
B1 @ 57.5' (CH)
2
0
4
B1 @ 67.5' (ML)
PLATE: DFILE NO. 21428
CLARETT WEST DEVELOPMENT
SULFATE CONTENT:
SULFATE CONTENT
SAMPLE
< 0.1 %(percentage by weight)
COMPACTION/EXPANSION/SULFATE DATA SHEET
B1 @ 12.5'
< 0.1 %
B1 @ 22.5'
< 0.1 %
B1 @ 32.5'
< 0.1 %
B1 @ 40'
< 0.1 %
B1 @ 45'
B1 @ 50'
SULFATE CONTENT:
SAMPLE
< 0.1 %(percentage by weight)
B1 @ 55'
< 0.1 %
B1 @ 60'
< 0.1 %
B1 @ 65'
< 0.1 %
B1 @ 70'
Geotechnologies, Inc.Consulting Geotechnical Engineers
< 0.1 %
PLATE: E
100
90
80
70
60
50
40
30
20
10
0
CLAYSILTSAND
MEDIUM TO COARSE FINE
GRAVEL
U.S. Standard Sieve Sizes
PE
RC
EN
T P
AS
SIN
G B
Y W
EIG
HT
GRAIN SIZE DISTRIBUTION
FILE NO. 21428
3 in
.
3/4
in.
3/8
in.
NO
. 4
NO
. 10
NO
.20
NO
. 40
NO
. 100
NO
. 200
100.
0
10.0 1.0
0.1
0.01
0.00
1
76.2
0
19.0
5
9.52
4.75
2.00
0.84
0
0.42
0
0.15
0
0.07
5
CLARETT WEST DEVELOPMENT
GRAIN DIAMETER (mm)
25.4
1 in
.
Geotechnologies, Inc.Consulting Geotechnical Engineers
B1 @ 35'
B1 @ 50'B1 @ 45'
B1 @ 40'
B1 @ 60'
B1 @ 55'
B1 @ 65'
B1 @ 70'
B1 @ 42.5'
Geotechnologies, Inc.Consulting Geotechnical Engineers FILE NO. 21428 PLATE: F
ATTERBERG LIMITS DETERMINATIONCLARETT WEST DEVELOPMENT
0 10 20 30 40 50 60 70 80 90 100 1100
10
20
30
40
60
50
70
80
CL
CL-ML
andOH MH
CH
A LINE
LIQUID LIMIT, LL
0 10 20 30 40 50 60 70 80 90 100 1100
10
20
30
40
60
50
70
80
CL
CL-ML
ML and OL
andOH MH
CH
A LINE
LIQUID LIMIT, LL
PLA
STI
CIT
Y IN
DE
X, P
I
ML and OL
ASTM D4318
BORINGNUMBER
DEPTH(FEET) LL PL PI DESCRIPTIONTEST
SYMBOLB1 40 34 21 13 CL
B1 45 37 21 CLB1 50 53 33B1 55 82 59B1 60 49 25B1 65 52 28 CH
1620232424
CHCHCL
B1 42.5 38 19 19 CL
Geotechnologies, Inc.Project: Clarett West DevelopmentFile No.: 21428Description: Liquefaction AnalysisBoring Numbe 1
EARTHQUAKE INFORMATION: BOREHOLE AND SAMPLER INFORMATION:Earthquake Magnitude (M): 6.8 Borehole Diameter (inches): 8Peak Ground Horizontal Acceleration, PGA (g): 0.77 SPT Sampler with room for Liner (Y/N): YCalculated Mag.Wtg.Factor: 1.196 LIQUEFACTION BOUNDARY:GROUNDWATER INFORMATION: Plastic Index Cut Off (PI): 12Current Groundwater Level (ft): 67.5 Minimum Liquefaction FS: 1.3Historically Highest Groundwater Level* (ft): 40.0Unit Weight of Water (pcf): 62.4* Based on California Geological Survey Seismic Hazard Evaluation Report
Depth to Total Unit Current Historical Field SPT Depth of SPT Fines Content Plastic Vetical Effective Fines Stress Cyclic Shear Cyclic Factor of Safety LiquefactionBase Layer Weight Water Level Water Level Blowcount Blowcount #200 Sieve Index Stress Vert. Stress Corrected Reduction Ratio Resistance CRR/CSR Settlment
(feet) (pcf) (feet) (feet) N (feet) (%) (PI) vc, (psf) vc', (psf) (N1)60-cs Coeff, rd CSR Ratio (CRR) (F.S.) Si (inches)
1 135.8 Unsaturated Unsaturated 34 5.5 0.0 0 135.8 135.8 81.0 1.00 0.504 2.000 Non-Liq. 0.002 135.8 Unsaturated Unsaturated 34 5.5 0.0 0 271.6 271.6 81.0 1.00 0.502 2.000 Non-Liq. 0.003 131.5 Unsaturated Unsaturated 34 5.5 0.0 0 403.1 403.1 73.7 1.00 0.501 2.000 Non-Liq. 0.004 131.5 Unsaturated Unsaturated 34 5.5 0.0 0 534.6 534.6 68.4 0.99 0.499 2.000 Non-Liq. 0.005 131.5 Unsaturated Unsaturated 34 5.5 0.0 0 666.1 666.1 68.8 0.99 0.497 2.000 Non-Liq. 0.006 131.5 Unsaturated Unsaturated 34 5.5 0.0 0 797.6 797.6 65.7 0.99 0.495 2.000 Non-Liq. 0.007 131.5 Unsaturated Unsaturated 34 5.5 0.0 0 929.1 929.1 63.1 0.98 0.493 2.000 Non-Liq. 0.008 138.2 Unsaturated Unsaturated 27 10.5 0.0 0 1067.3 1067.3 49.4 0.98 0.491 2.000 Non-Liq. 0.009 138.2 Unsaturated Unsaturated 27 10.5 0.0 0 1205.5 1205.5 50.2 0.98 0.489 2.000 Non-Liq. 0.00
10 138.2 Unsaturated Unsaturated 27 10.5 0.0 0 1343.7 1343.7 48.7 0.97 0.487 2.000 Non-Liq. 0.0011 138.2 Unsaturated Unsaturated 27 10.5 0.0 0 1481.9 1481.9 47.4 0.97 0.485 2.000 Non-Liq. 0.0012 138.2 Unsaturated Unsaturated 27 10.5 0.0 0 1620.1 1620.1 46.2 0.96 0.483 2.000 Non-Liq. 0.0013 141.7 Unsaturated Unsaturated 27 10.5 0.0 0 1761.8 1761.8 45.1 0.96 0.481 2.000 Non-Liq. 0.0014 141.7 Unsaturated Unsaturated 27 10.5 0.0 0 1903.5 1903.5 44.1 0.95 0.478 2.000 Non-Liq. 0.0015 141.7 Unsaturated Unsaturated 27 10.5 0.0 0 2045.2 2045.2 48.3 0.95 0.476 2.000 Non-Liq. 0.0016 124.7 Unsaturated Unsaturated 29 15.5 0.0 0 2169.9 2169.9 51.1 0.94 0.473 2.000 Non-Liq. 0.0017 124.7 Unsaturated Unsaturated 29 15.5 0.0 0 2294.6 2294.6 50.4 0.94 0.471 2.000 Non-Liq. 0.0018 124.7 Unsaturated Unsaturated 29 15.5 0.0 0 2419.3 2419.3 49.7 0.93 0.468 2.000 Non-Liq. 0.0019 124.7 Unsaturated Unsaturated 29 15.5 0.0 0 2544.0 2544.0 49.0 0.93 0.466 2.000 Non-Liq. 0.0020 124.7 Unsaturated Unsaturated 29 15.5 0.0 0 2668.7 2668.7 48.4 0.92 0.463 2.000 Non-Liq. 0.0021 145.3 Unsaturated Unsaturated 25 20.5 0.0 0 2814.0 2814.0 41.0 0.92 0.460 2.000 Non-Liq. 0.0022 145.3 Unsaturated Unsaturated 25 20.5 0.0 0 2959.3 2959.3 40.4 0.91 0.458 2.000 Non-Liq. 0.0023 145.3 Unsaturated Unsaturated 25 20.5 0.0 0 3104.6 3104.6 39.7 0.91 0.455 2.000 Non-Liq. 0.0024 145.3 Unsaturated Unsaturated 25 20.5 0.0 0 3249.9 3249.9 39.0 0.90 0.452 2.000 Non-Liq. 0.0025 145.3 Unsaturated Unsaturated 25 20.5 0.0 0 3395.2 3395.2 38.4 0.90 0.450 2.000 Non-Liq. 0.0026 140.1 Unsaturated Unsaturated 24 25.5 0.0 0 3535.3 3535.3 35.7 0.89 0.447 1.329 Non-Liq. 0.0027 140.1 Unsaturated Unsaturated 24 25.5 0.0 0 3675.4 3675.4 35.2 0.88 0.444 1.176 Non-Liq. 0.0028 140.1 Unsaturated Unsaturated 24 25.5 0.0 0 3815.5 3815.5 37.2 0.88 0.441 1.836 Non-Liq. 0.0029 140.1 Unsaturated Unsaturated 24 25.5 0.0 0 3955.6 3955.6 36.7 0.87 0.438 1.605 Non-Liq. 0.0030 140.1 Unsaturated Unsaturated 24 25.5 0.0 0 4095.7 4095.7 36.3 0.87 0.435 1.424 Non-Liq. 0.0031 114.4 Unsaturated Unsaturated 27 30.5 0.0 0 4210.1 4210.1 42.0 0.86 0.432 1.905 Non-Liq. 0.0032 114.4 Unsaturated Unsaturated 27 30.5 0.0 0 4324.5 4324.5 41.6 0.86 0.429 1.886 Non-Liq. 0.0033 114.4 Unsaturated Unsaturated 18 35.5 0.0 0 4438.9 4438.9 23.5 0.85 0.426 0.273 Non-Liq. 0.0034 114.4 Unsaturated Unsaturated 18 35.5 0.0 0 4553.3 4553.3 23.2 0.84 0.423 0.267 Non-Liq. 0.0035 114.4 Unsaturated Unsaturated 18 35.5 40.8 0 4667.7 4667.7 28.5 0.84 0.420 0.413 Non-Liq. 0.0036 114.4 Unsaturated Unsaturated 18 35.5 40.8 0 4782.1 4782.1 28.3 0.83 0.417 0.400 Non-Liq. 0.0037 114.4 Unsaturated Unsaturated 18 35.5 40.8 0 4896.5 4896.5 28.0 0.83 0.414 0.389 Non-Liq. 0.0038 127.5 Unsaturated Unsaturated 18 35.5 0.0 0 5024.0 5024.0 22.2 0.82 0.411 0.247 Non-Liq. 0.0039 127.5 Unsaturated Unsaturated 18 35.5 0.0 0 5151.5 5151.5 22.0 0.81 0.408 0.242 Non-Liq. 0.0040 127.5 Unsaturated Unsaturated 18 35.5 0.0 0 5279.0 5279.0 21.7 0.81 0.405 0.238 Non-Liq. 0.0041 118.3 Unsaturated Saturated 19 40.5 79.4 13 5397.3 5334.9 28.9 0.80 0.407 0.416 Non-Liq. 0.0042 118.3 Unsaturated Saturated 19 40.5 79.4 13 5515.6 5390.8 28.8 0.80 0.409 0.410 Non-Liq. 0.0043 118.3 Unsaturated Saturated 19 40.5 64.0 19 5633.9 5446.7 28.7 0.79 0.410 0.407 Non-Liq. 0.0044 118.3 Unsaturated Saturated 19 40.5 64.0 19 5752.2 5502.6 28.6 0.78 0.411 0.402 Non-Liq. 0.0045 118.3 Unsaturated Saturated 19 40.5 64.0 19 5870.5 5558.5 28.5 0.78 0.413 0.397 Non-Liq. 0.0046 129.4 Unsaturated Saturated 17 45.5 92.5 21 5999.9 5625.5 25.0 0.77 0.413 0.292 Non-Liq. 0.0047 129.4 Unsaturated Saturated 17 45.5 92.5 21 6129.3 5692.5 24.9 0.77 0.414 0.289 Non-Liq. 0.0048 129.4 Unsaturated Saturated 17 45.5 92.5 21 6258.7 5759.5 24.8 0.76 0.415 0.286 Non-Liq. 0.0049 129.4 Unsaturated Saturated 17 45.5 92.5 21 6388.1 5826.5 24.7 0.76 0.415 0.284 Non-Liq. 0.0050 129.4 Unsaturated Saturated 17 45.5 92.5 21 6517.5 5893.5 24.6 0.75 0.416 0.281 Non-Liq. 0.0051 120.8 Unsaturated Saturated 36 50.5 94.3 33 6638.3 5951.9 56.7 0.74 0.416 1.660 Non-Liq. 0.0052 120.8 Unsaturated Saturated 36 50.5 94.3 33 6759.1 6010.3 56.6 0.74 0.416 1.653 Non-Liq. 0.0053 120.8 Unsaturated Saturated 36 50.5 0.0 0 6879.9 6068.7 50.9 0.73 0.417 1.646 4.0 0.0054 120.8 Unsaturated Saturated 36 50.5 0.0 0 7000.7 6127.1 50.8 0.73 0.417 1.640 3.9 0.0055 120.8 Unsaturated Saturated 36 50.5 0.0 0 7121.5 6185.5 50.7 0.72 0.417 1.633 3.9 0.0056 124.9 Unsaturated Saturated 33 55.5 89.7 59 7246.4 6248.0 51.9 0.72 0.416 1.626 Non-Liq. 0.0057 124.9 Unsaturated Saturated 33 55.5 89.7 59 7371.3 6310.5 51.7 0.71 0.416 1.619 Non-Liq. 0.0058 124.9 Unsaturated Saturated 33 55.5 89.7 59 7496.2 6373.0 51.6 0.70 0.416 1.612 Non-Liq. 0.0059 124.9 Unsaturated Saturated 33 55.5 89.7 59 7621.1 6435.5 51.5 0.70 0.416 1.605 Non-Liq. 0.0060 124.9 Unsaturated Saturated 33 55.5 89.7 59 7746.0 6498.0 51.4 0.69 0.415 1.598 Non-Liq. 0.0061 114.2 Unsaturated Saturated 32 60.5 97.4 25 7860.2 6549.8 49.9 0.69 0.415 1.593 Non-Liq. 0.0062 114.2 Unsaturated Saturated 32 60.5 97.4 25 7974.4 6601.6 49.8 0.68 0.414 1.587 Non-Liq. 0.0063 114.2 Unsaturated Saturated 32 60.5 97.4 25 8088.6 6653.4 49.7 0.68 0.414 1.582 Non-Liq. 0.0064 114.2 Unsaturated Saturated 32 60.5 97.4 25 8202.8 6705.2 49.6 0.67 0.414 1.576 Non-Liq. 0.0065 114.2 Unsaturated Saturated 32 60.5 97.4 25 8317.0 6757.0 49.5 0.67 0.413 1.571 Non-Liq. 0.0066 114.2 Unsaturated Saturated 25 65.5 98.2 28 8431.2 6808.8 37.4 0.66 0.412 1.518 Non-Liq. 0.0067 114.2 Unsaturated Saturated 25 65.5 98.2 28 8545.4 6860.6 37.3 0.66 0.412 1.478 Non-Liq. 0.0068 128.8 Saturated Saturated 37 70.5 0.0 0 8674.2 6927.0 50.6 0.65 0.411 1.553 3.8 0.0069 128.8 Saturated Saturated 37 70.5 0.0 0 8803.0 6993.4 50.4 0.65 0.410 1.546 3.8 0.0070 128.8 Saturated Saturated 37 70.5 0.0 0 8931.8 7059.8 50.3 0.65 0.410 1.540 3.8 0.0071 128.8 Saturated Saturated 37 70.5 33.3 0 9060.6 7126.2 55.7 0.64 0.409 1.533 3.8 0.0072 128.8 Saturated Saturated 37 70.5 33.3 0 9189.4 7192.6 55.5 0.64 0.408 1.527 3.7 0.0073 123.0 Saturated Saturated 37 70.5 0.0 0 9312.4 7253.2 50.0 0.63 0.407 1.521 3.7 0.0074 123.0 Saturated Saturated 37 70.5 0.0 0 9435.4 7313.8 49.9 0.63 0.406 1.515 3.7 0.0075 125.0 Saturated Saturated 78 75.5 0.0 0 9560.4 7376.4 104.9 0.62 0.405 1.509 3.7 0.0076 125.0 Saturated Saturated 78 75.5 0.0 0 9685.4 7439.0 104.6 0.62 0.405 1.503 3.7 0.0077 125.0 Saturated Saturated 78 75.5 0.0 0 9810.4 7501.6 104.4 0.62 0.404 1.497 3.7 0.0078 125.0 Saturated Saturated 78 75.5 0.0 0 9935.4 7564.2 104.2 0.61 0.403 1.491 3.7 0.0079 125.0 Saturated Saturated 78 75.5 0.0 0 10060.4 7626.8 103.9 0.61 0.402 1.485 3.7 0.0080 125.0 Saturated Saturated 78 75.5 0.0 0 10185.4 7689.4 103.7 0.60 0.401 1.479 3.7 0.0081 125.0 Saturated Saturated 80 80.5 0.0 0 10310.4 7752.0 106.1 0.60 0.400 1.474 3.7 0.0082 125.0 Saturated Saturated 80 80.5 0.0 0 10435.4 7814.6 105.9 0.60 0.400 1.468 3.7 0.0083 125.0 Saturated Saturated 100 85.5 0.0 0 10560.4 7877.2 132.1 0.59 0.399 1.462 3.7 0.0084 125.0 Saturated Saturated 100 85.5 0.0 0 10685.4 7939.8 131.9 0.59 0.398 1.457 3.7 0.0085 125.0 Saturated Saturated 100 85.5 0.0 0 10810.4 8002.4 131.6 0.59 0.397 1.451 3.7 0.0086 125.0 Saturated Saturated 100 85.5 0.0 0 10935.4 8065.0 131.3 0.58 0.397 1.446 3.6 0.0087 125.0 Saturated Saturated 100 85.5 0.0 0 11060.4 8127.6 131.0 0.58 0.396 1.440 3.6 0.0088 125.0 Saturated Saturated 100 90.5 0.0 0 11185.4 8190.2 130.8 0.58 0.395 1.435 3.6 0.0089 125.0 Saturated Saturated 100 90.5 0.0 0 11310.4 8252.8 130.5 0.57 0.395 1.429 3.6 0.0090 125.0 Saturated Saturated 100 90.5 0.0 0 11435.4 8315.4 130.3 0.57 0.394 1.424 3.6 0.0091 125.0 Saturated Saturated 100 90.5 0.0 0 11560.4 8378.0 130.0 0.57 0.393 1.419 3.6 0.00
Total Liquefaction Settlement, S = 0.00 inches
LIQUEFACTION EVALUATION (Idriss & Boulanger, EERI NO 12)
Geotechnologies, Inc.Project: Clarette West DevelopmentFile No.: 21428Description: Retaining Walls up to 10 feet
Input:Retaining Wall Height (H) 10.00 feet
Unit Weight of Retained Soils ( ) 120.0 pcfFriction Angle of Retained Soils ( ) 33.0 degreesCohesion of Retained Soils (c) 170.0 psfFactor of Safety (FS) 1.50
Factored Parameters: ( FS) 23.4 degrees(cFS) 113.3 psf
Failure Height of Area of Weight of Length of ActiveAngle Tension Crack Wedge Wedge Failure Plane Pressure
( ) (HC) (A) (W) (LCR) a b (PA)degrees feet feet2 lbs/lineal foot feet lbs/lineal foot lbs/lineal foot lbs/lineal foot
45 3.3 44 5334.3 9.4 2665.7 2668.5 1056.046 3.2 43 5182.9 9.4 2541.3 2641.5 1099.047 3.2 42 5030.9 9.3 2425.1 2605.8 1137.948 3.1 41 4879.0 9.3 2316.3 2562.7 1172.849 3.1 39 4727.8 9.2 2214.7 2513.2 1203.650 3.0 38 4577.7 9.1 2119.5 2458.3 1230.551 3.0 37 4429.1 9.0 2030.3 2398.8 1253.552 2.9 36 4282.0 9.0 1946.7 2335.4 1272.853 2.9 34 4136.7 8.9 1868.1 2268.6 1288.354 2.9 33 3993.3 8.8 1794.2 2199.0 1300.055 2.9 32 3851.7 8.7 1724.6 2127.1 1308.156 2.9 31 3711.9 8.6 1658.9 2053.1 1312.557 2.9 30 3574.1 8.5 1596.8 1977.3 1313.258 2.9 29 3438.0 8.4 1537.9 1900.1 1310.359 2.9 28 3303.7 8.3 1482.0 1821.7 1303.860 2.9 26 3171.2 8.2 1428.8 1742.3 1293.561 2.9 25 3040.2 8.1 1378.1 1662.1 1279.662 3.0 24 2910.8 8.0 1329.5 1581.3 1261.963 3.0 23 2782.8 7.9 1282.9 1499.9 1240.464 3.0 22 2656.2 7.7 1238.1 1418.1 1215.165 3.1 21 2530.8 7.6 1194.7 1336.1 1185.9 Design Equations (Vector Analysis):66 3.1 20 2406.5 7.5 1152.6 1254.0 1152.7 a = cFS*LCR*sin(90+ FS)/sin( - FS)67 3.2 19 2283.3 7.4 1111.5 1171.8 1115.5 b = W-a68 3.3 18 2160.9 7.2 1071.2 1089.6 1074.2 PA = b*tan( - FS)69 3.4 17 2039.2 7.1 1031.5 1007.7 1028.6 EFP = 2*PA/H2
70 3.5 16 1918.1 6.9 992.1 926.0 978.9
Maximum Active Pressure ResultantPA, max 1313.24 lbs/lineal foot
Equivalent Fluid Pressure (per lineal foot of wall)EFP = 2*PA/H2
EFP 26.3 pcf
Design Wall for an Equivalent Fluid Pressure: 30 pcf
Retaining Wall Design with Level Backfill(Vector Analysis)
W
b
a
PA
N
cFS*LCR
WLCR
c
LT
H
HC
Geotechnologies, Inc.Project: Clarette West DevelopmentFile No.: 21428Description: Retaining Walls up to 20 feet
Input:Retaining Wall Height (H) 20.00 feet
Unit Weight of Retained Soils ( ) 120.0 pcfFriction Angle of Retained Soils ( ) 33.0 degreesCohesion of Retained Soils (c) 170.0 psfFactor of Safety (FS) 1.50
Factored Parameters: ( FS) 23.4 degrees(cFS) 113.3 psf
Failure Height of Area of Weight of Length of ActiveAngle Tension Crack Wedge Wedge Failure Plane Pressure
( ) (HC) (A) (W) (LCR) a b (PA)degrees feet feet2 lbs/lineal foot feet lbs/lineal foot lbs/lineal foot lbs/lineal foot
45 3.3 194 23334.3 23.6 6663.0 16671.3 6597.446 3.2 188 22565.3 23.3 6305.2 16260.1 6765.247 3.2 182 21816.2 23.0 5978.5 15837.6 6916.148 3.1 176 21086.3 22.7 5679.5 15406.7 7050.649 3.1 170 20375.0 22.4 5405.1 14969.8 7169.250 3.0 164 19681.5 22.2 5152.7 14528.9 7272.551 3.0 158 19005.2 21.9 4919.9 14085.3 7360.652 2.9 153 18345.2 21.6 4704.7 13640.5 7434.153 2.9 148 17700.7 21.4 4505.4 13195.3 7493.054 2.9 142 17071.0 21.1 4320.4 12750.6 7537.855 2.9 137 16455.4 20.9 4148.4 12307.1 7568.556 2.9 132 15853.1 20.7 3988.0 11865.1 7585.257 2.9 127 15263.4 20.4 3838.3 11425.1 7588.158 2.9 122 14685.7 20.2 3698.2 10987.5 7577.059 2.9 118 14119.2 20.0 3566.9 10552.4 7552.160 2.9 113 13563.5 19.7 3443.5 10119.9 7513.161 2.9 108 13017.8 19.5 3327.5 9690.3 7460.062 3.0 104 12481.6 19.3 3218.0 9263.6 7392.563 3.0 100 11954.3 19.1 3114.5 8839.7 7310.464 3.0 95 11435.4 18.9 3016.5 8418.8 7213.465 3.1 91 10924.3 18.7 2923.5 8000.9 7101.1 Design Equations (Vector Analysis):66 3.1 87 10420.6 18.4 2834.8 7585.8 6973.2 a = cFS*LCR*sin(90+ FS)/sin( - FS)67 3.2 83 9923.8 18.2 2750.2 7173.6 6829.1 b = W-a68 3.3 79 9433.3 18.0 2669.1 6764.3 6668.2 PA = b*tan( - FS)69 3.4 75 8948.7 17.8 2591.0 6357.7 6490.1 EFP = 2*PA/H2
70 3.5 71 8469.6 17.6 2515.6 5953.9 6294.0
Maximum Active Pressure ResultantPA, max 7588.08 lbs/lineal foot
Equivalent Fluid Pressure (per lineal foot of wall)EFP = 2*PA/H2
EFP 37.9 pcf
Design Wall for an Equivalent Fluid Pressure: 38 pcf
Retaining Wall Design with Level Backfill(Vector Analysis)
W
b
a
PA
N
cFS*LCR
WLCR
c
LT
H
HC
Geotechnologies, Inc.Project: Clarette West DevelopmentFile No.: 21428Description: Retaining Walls up to 30 feet
Input:Retaining Wall Height (H) 30.00 feet
Unit Weight of Retained Soils ( ) 120.0 pcfFriction Angle of Retained Soils ( ) 33.0 degreesCohesion of Retained Soils (c) 170.0 psfFactor of Safety (FS) 1.50
Factored Parameters: ( FS) 23.4 degrees(cFS) 113.3 psf
Failure Height of Area of Weight of Length of ActiveAngle Tension Crack Wedge Wedge Failure Plane Pressure
( ) (HC) (A) (W) (LCR) a b (PA)degrees feet feet2 lbs/lineal foot feet lbs/lineal foot lbs/lineal foot lbs/lineal foot
45 3.3 444 53334.3 37.7 10660.2 42674.1 16887.646 3.2 429 51536.0 37.2 10069.0 41467.0 17252.847 3.2 415 49791.6 36.7 9532.0 40259.6 17580.948 3.1 401 48098.4 36.2 9042.7 39055.7 17873.149 3.1 387 46453.6 35.7 8595.6 37858.0 18130.750 3.0 374 44854.5 35.2 8185.9 36668.7 18354.651 3.0 361 43298.7 34.8 7809.4 35489.3 18545.752 2.9 348 41783.8 34.3 7462.7 34321.0 18704.953 2.9 336 40307.3 33.9 7142.7 33164.6 18832.854 2.9 324 38867.3 33.5 6846.6 32020.7 18929.755 2.9 312 37461.6 33.1 6572.1 30889.5 18996.256 2.9 301 36088.4 32.7 6317.1 29771.3 19032.557 2.9 290 34745.6 32.3 6079.8 28665.9 19038.658 2.9 279 33431.8 32.0 5858.5 27573.3 19014.759 2.9 268 32145.1 31.6 5651.7 26493.3 18960.660 2.9 257 30884.0 31.3 5458.2 25425.7 18876.261 2.9 247 29647.0 30.9 5276.8 24370.2 18761.162 3.0 237 28432.8 30.6 5106.5 23326.4 18614.863 3.0 227 27240.0 30.3 4946.1 22293.9 18436.864 3.0 217 26067.3 30.0 4795.0 21272.4 18226.465 3.1 208 24913.6 29.7 4652.2 20261.3 17982.8 Design Equations (Vector Analysis):66 3.1 198 23777.5 29.4 4517.1 19260.4 17704.9 a = cFS*LCR*sin(90+ FS)/sin( - FS)67 3.2 189 22658.1 29.1 4388.9 18269.2 17391.7 b = W-a68 3.3 180 21554.1 28.8 4266.9 17287.2 17041.8 PA = b*tan( - FS)69 3.4 171 20464.7 28.5 4150.5 16314.1 16653.8 EFP = 2*PA/H2
70 3.5 162 19388.7 28.2 4039.2 15349.5 16226.2
Maximum Active Pressure ResultantPA, max 19038.61 lbs/lineal foot
Equivalent Fluid Pressure (per lineal foot of wall)EFP = 2*PA/H2
EFP 42.3 pcf
Design Wall for an Equivalent Fluid Pressure: 43 pcf
Retaining Wall Design with Level Backfill(Vector Analysis)
W
b
a
PA
N
cFS*LCR
WLCR
c
LT
H
HC
Geotechnologies, Inc.Project: Clarette West DevelopmentFile No.: 21428Description: Shoring Walls up to 40 feet
Input:Shoring Height (H) 40.00 feet
Unit Weight of Retained Soils ( ) 120.0 pcfFriction Angle of Retained Soils ( ) 33.0 degreesCohesion of Retained Soils (c) 170.0 psfFactor of Safety (FS) 1.25
Factored Parameters: ( FS) 27.5 degrees(cFS) 136.0 psf
Failure Height of Area of Weight of Length of ActiveAngle Tension Crack Wedge Wedge Failure Plane Pressure
( ) (HC) (A) (W) (LCR) a b (PA)degrees feet feet2 lbs/lineal foot feet lbs/lineal foot lbs/lineal foot lbs/lineal foot
45 4.7 789 94664.7 49.9 19973.7 74691.0 23617.346 4.6 763 91505.8 49.3 18697.2 72808.5 24427.747 4.4 737 88434.6 48.7 17554.4 70880.2 25165.448 4.3 712 85448.1 48.1 16526.7 68921.4 25833.049 4.2 688 82542.8 47.5 15598.9 66943.9 26433.350 4.1 664 79715.3 46.9 14758.2 64957.1 26968.551 4.0 641 76961.8 46.3 13993.7 62968.1 27440.752 3.9 619 74278.6 45.8 13296.4 60982.2 27851.653 3.9 597 71662.3 45.2 12658.5 59003.8 28202.754 3.8 576 69109.2 44.7 12073.2 57036.0 28495.555 3.8 555 66616.0 44.2 11534.9 55081.2 28730.856 3.8 535 64179.6 43.7 11038.4 53141.2 28909.757 3.7 515 61796.8 43.2 10579.6 51217.2 29032.758 3.7 496 59464.7 42.8 10154.5 49310.2 29100.459 3.7 477 57180.4 42.3 9759.8 47420.6 29112.860 3.7 458 54941.4 41.9 9392.7 45548.7 29070.261 3.8 440 52745.0 41.4 9050.4 43694.6 28972.362 3.8 422 50588.8 41.0 8730.7 41858.1 28818.863 3.8 404 48470.6 40.6 8431.5 40039.1 28609.164 3.9 387 46388.0 40.2 8150.8 38237.2 28342.565 3.9 369 44338.9 39.8 7887.1 36451.9 28018.0 Design Equations (Vector Analysis):66 4.0 353 42321.4 39.4 7638.6 34682.7 27634.3 a = cFS*LCR*sin(90+ FS)/sin( - FS)67 4.0 336 40333.4 39.1 7404.1 32929.2 27190.1 b = W-a68 4.1 320 38373.1 38.7 7182.2 31190.8 26683.7 PA = b*tan( - FS)69 4.2 304 36438.6 38.3 6971.7 29466.9 26113.2 EFP = 2*PA/H2
70 4.3 288 34528.2 37.9 6771.3 27756.9 25476.4
Maximum Active Pressure ResultantPA, max 29112.85 lbs/lineal foot
Equivalent Fluid Pressure (per lineal foot of shoring)EFP = 2*PA/H2
EFP 36.4 pcf
Design Shoring for an Equivalent Fluid Pressure: 37 pcf
Shoring Design with Level Backfill (Vector Analysis)
W
b
a
PA
N
cFS*LCR
WLCR
c
LT
H
HC
Geotechnologies, Inc.Project: Clarette West DevelopmentFile No.: 21428Description: Shoring Walls up to 10 feet
Input:Shoring Height (H) 10.00 feet
Unit Weight of Retained Soils ( ) 120.0 pcfFriction Angle of Retained Soils ( ) 33.0 degreesCohesion of Retained Soils (c) 170.0 psfFactor of Safety (FS) 1.25
Factored Parameters: ( FS) 27.5 degrees(cFS) 136.0 psf
Failure Height of Area of Weight of Length of ActiveAngle Tension Crack Wedge Wedge Failure Plane Pressure
( ) (HC) (A) (W) (LCR) a b (PA)degrees feet feet2 lbs/lineal foot feet lbs/lineal foot lbs/lineal foot lbs/lineal foot
45 4.7 39 4664.7 7.5 2990.4 1674.2 529.446 4.6 38 4593.8 7.6 2873.8 1720.0 577.147 4.4 38 4508.2 7.6 2758.3 1749.9 621.348 4.3 37 4411.7 7.7 2645.6 1766.1 662.049 4.2 36 4307.0 7.7 2536.7 1770.3 699.050 4.1 35 4196.3 7.7 2432.2 1764.2 732.451 4.0 34 4081.2 7.7 2332.2 1749.0 762.252 3.9 33 3962.9 7.7 2236.9 1726.0 788.353 3.9 32 3842.4 7.7 2146.2 1696.2 810.754 3.8 31 3720.3 7.6 2059.9 1660.4 829.555 3.8 30 3597.3 7.6 1977.9 1619.5 844.756 3.8 29 3473.8 7.5 1899.8 1574.1 856.357 3.7 28 3350.1 7.5 1825.4 1524.7 864.358 3.7 27 3226.4 7.4 1754.5 1472.0 868.759 3.7 26 3103.0 7.3 1686.7 1416.3 869.560 3.7 25 2979.9 7.2 1621.8 1358.0 866.761 3.8 24 2857.2 7.1 1559.6 1297.6 860.462 3.8 23 2735.0 7.0 1499.8 1235.2 850.463 3.8 22 2613.3 6.9 1442.1 1171.2 836.964 3.9 21 2492.0 6.8 1386.2 1105.9 819.765 3.9 20 2371.2 6.7 1331.8 1039.4 798.9 Design Equations (Vector Analysis):66 4.0 19 2250.8 6.6 1278.8 972.0 774.5 a = cFS*LCR*sin(90+ FS)/sin( - FS)67 4.0 18 2130.6 6.5 1226.7 903.9 746.4 b = W-a68 4.1 17 2010.7 6.3 1175.4 835.3 714.6 PA = b*tan( - FS)69 4.2 16 1890.8 6.2 1124.4 766.4 679.2 EFP = 2*PA/H2
70 4.3 15 1770.9 6.0 1073.4 697.5 640.2
Maximum Active Pressure ResultantPA, max 869.50 lbs/lineal foot
Equivalent Fluid Pressure (per lineal foot of shoring)EFP = 2*PA/H2
EFP 17.4 pcf
Design Shoring for an Equivalent Fluid Pressure: 25 pcf (Recommended)
Shoring Design with Level Backfill (Vector Analysis)
W
b
a
PA
N
cFS*LCR
WLCR
c
LT
H
HC
Geotechnologies, Inc.Project: Clarette West DevelopmentFile No.: 21428Description: Shoring Walls up to 20 feet
Input:Shoring Height (H) 20.00 feet
Unit Weight of Retained Soils ( ) 120.0 pcfFriction Angle of Retained Soils ( ) 33.0 degreesCohesion of Retained Soils (c) 170.0 psfFactor of Safety (FS) 1.25
Factored Parameters: ( FS) 27.5 degrees(cFS) 136.0 psf
Failure Height of Area of Weight of Length of ActiveAngle Tension Crack Wedge Wedge Failure Plane Pressure
( ) (HC) (A) (W) (LCR) a b (PA)degrees feet feet2 lbs/lineal foot feet lbs/lineal foot lbs/lineal foot lbs/lineal foot
45 4.7 189 22664.7 21.6 8651.5 14013.2 4431.046 4.6 183 21976.2 21.5 8148.3 13827.9 4639.447 4.4 177 21293.5 21.3 7690.3 13603.2 4829.748 4.3 172 20619.0 21.2 7272.6 13346.3 5002.549 4.2 166 19954.2 21.0 6890.8 13063.4 5158.250 4.1 161 19300.1 20.8 6540.8 12759.3 5297.351 4.0 155 18657.3 20.6 6219.4 12438.0 5420.352 3.9 150 18026.1 20.4 5923.4 12102.6 5527.553 3.9 145 17406.4 20.2 5650.3 11756.1 5619.254 3.8 140 16798.1 20.0 5397.7 11400.4 5695.755 3.8 135 16201.1 19.8 5163.5 11037.5 5757.356 3.8 130 15615.0 19.6 4946.0 10669.0 5804.157 3.7 125 15039.4 19.4 4743.4 10296.0 5836.358 3.7 121 14474.1 19.2 4554.5 9919.6 5854.159 3.7 116 13918.5 19.0 4377.7 9540.7 5857.360 3.7 111 13372.2 18.8 4212.1 9160.1 5846.261 3.8 107 12834.8 18.6 4056.6 8778.2 5820.562 3.8 103 12305.8 18.4 3910.1 8395.7 5780.363 3.8 98 11784.7 18.2 3771.9 8012.9 5725.464 3.9 94 11271.2 18.0 3641.0 7630.2 5655.765 3.9 90 10764.8 17.8 3516.9 7247.9 5570.9 Design Equations (Vector Analysis):66 4.0 86 10264.9 17.5 3398.7 6866.2 5470.8 a = cFS*LCR*sin(90+ FS)/sin( - FS)67 4.0 81 9771.2 17.3 3285.9 6485.3 5355.0 b = W-a68 4.1 77 9283.2 17.1 3177.7 6105.5 5223.3 PA = b*tan( - FS)69 4.2 73 8800.4 16.9 3073.5 5726.9 5075.1 EFP = 2*PA/H2
70 4.3 69 8322.3 16.7 2972.7 5349.6 4910.1
Maximum Active Pressure ResultantPA, max 5857.33 lbs/lineal foot
Equivalent Fluid Pressure (per lineal foot of shoring)EFP = 2*PA/H2
EFP 29.3 pcf
Design Shoring for an Equivalent Fluid Pressure: 30 pcf
Shoring Design with Level Backfill (Vector Analysis)
W
b
a
PA
N
cFS*LCR
WLCR
c
LT
H
HC
Geotechnologies, Inc.Project: Clarette West DevelopmentFile No.: 21428Description: Shoring Walls up to 30 feet
Input:Shoring Height (H) 30.00 feet
Unit Weight of Retained Soils ( ) 120.0 pcfFriction Angle of Retained Soils ( ) 33.0 degreesCohesion of Retained Soils (c) 170.0 psfFactor of Safety (FS) 1.25
Factored Parameters: ( FS) 27.5 degrees(cFS) 136.0 psf
Failure Height of Area of Weight of Length of ActiveAngle Tension Crack Wedge Wedge Failure Plane Pressure
( ) (HC) (A) (W) (LCR) a b (PA)degrees feet feet2 lbs/lineal foot feet lbs/lineal foot lbs/lineal foot lbs/lineal foot
45 4.7 439 52664.7 35.8 14312.6 38352.1 12126.946 4.6 425 50946.8 35.4 13422.7 37524.1 12589.647 4.4 411 49268.9 35.0 12622.3 36646.6 13011.048 4.3 397 47631.1 34.6 11899.7 35731.4 13392.849 4.2 384 46032.8 34.2 11244.8 34788.0 13736.350 4.1 371 44473.1 33.8 10649.5 33823.6 14042.751 4.0 358 42950.9 33.5 10106.6 32844.3 14313.152 3.9 346 41464.6 33.1 9609.9 31854.7 14548.653 3.9 333 40013.0 32.7 9154.4 30858.6 14749.854 3.8 322 38594.4 32.3 8735.5 29858.9 14917.755 3.8 310 37207.3 32.0 8349.2 28858.1 15052.656 3.8 299 35850.2 31.6 7992.2 27858.0 15155.257 3.7 288 34521.7 31.3 7661.5 26860.2 15225.858 3.7 277 33220.2 31.0 7354.5 25865.7 15264.659 3.7 266 31944.3 30.6 7068.8 24875.5 15271.860 3.7 256 30692.7 30.3 6802.4 23890.3 15247.361 3.8 246 29464.0 30.0 6553.5 22910.5 15191.262 3.8 235 28257.0 29.7 6320.4 21936.6 15103.163 3.8 226 27070.5 29.4 6101.7 20968.8 14982.964 3.9 216 25903.2 29.1 5895.9 20007.3 14830.065 3.9 206 24754.0 28.8 5702.0 19052.0 14643.9 Design Equations (Vector Analysis):66 4.0 197 23621.8 28.5 5518.7 18103.1 14424.1 a = cFS*LCR*sin(90+ FS)/sin( - FS)67 4.0 188 22505.4 28.2 5345.0 17160.4 14169.6 b = W-a68 4.1 178 21404.0 27.9 5179.9 16224.0 13879.6 PA = b*tan( - FS)69 4.2 169 20316.3 27.6 5022.6 15293.7 13553.1 EFP = 2*PA/H2
70 4.3 160 19241.4 27.3 4872.0 14369.4 13188.8
Maximum Active Pressure ResultantPA, max 15271.78 lbs/lineal foot
Equivalent Fluid Pressure (per lineal foot of shoring)EFP = 2*PA/H2
EFP 33.9 pcf
Design Shoring for an Equivalent Fluid Pressure: 34 pcf
Shoring Design with Level Backfill (Vector Analysis)
W
b
a
PA
N
cFS*LCR
WLCR
c
LT
H
HC
Geotechnologies, Inc.Project: Clarette West DevelopmentFile No.: 21428Description: Shoring Walls up to 40 feet
Input:Shoring Height (H) 40.00 feet
Unit Weight of Retained Soils ( ) 120.0 pcfFriction Angle of Retained Soils ( ) 33.0 degreesCohesion of Retained Soils (c) 170.0 psfFactor of Safety (FS) 1.25
Factored Parameters: ( FS) 27.5 degrees(cFS) 136.0 psf
Failure Height of Area of Weight of Length of ActiveAngle Tension Crack Wedge Wedge Failure Plane Pressure
( ) (HC) (A) (W) (LCR) a b (PA)degrees feet feet2 lbs/lineal foot feet lbs/lineal foot lbs/lineal foot lbs/lineal foot
45 4.7 789 94664.7 49.9 19973.7 74691.0 23617.346 4.6 763 91505.8 49.3 18697.2 72808.5 24427.747 4.4 737 88434.6 48.7 17554.4 70880.2 25165.448 4.3 712 85448.1 48.1 16526.7 68921.4 25833.049 4.2 688 82542.8 47.5 15598.9 66943.9 26433.350 4.1 664 79715.3 46.9 14758.2 64957.1 26968.551 4.0 641 76961.8 46.3 13993.7 62968.1 27440.752 3.9 619 74278.6 45.8 13296.4 60982.2 27851.653 3.9 597 71662.3 45.2 12658.5 59003.8 28202.754 3.8 576 69109.2 44.7 12073.2 57036.0 28495.555 3.8 555 66616.0 44.2 11534.9 55081.2 28730.856 3.8 535 64179.6 43.7 11038.4 53141.2 28909.757 3.7 515 61796.8 43.2 10579.6 51217.2 29032.758 3.7 496 59464.7 42.8 10154.5 49310.2 29100.459 3.7 477 57180.4 42.3 9759.8 47420.6 29112.860 3.7 458 54941.4 41.9 9392.7 45548.7 29070.261 3.8 440 52745.0 41.4 9050.4 43694.6 28972.362 3.8 422 50588.8 41.0 8730.7 41858.1 28818.863 3.8 404 48470.6 40.6 8431.5 40039.1 28609.164 3.9 387 46388.0 40.2 8150.8 38237.2 28342.565 3.9 369 44338.9 39.8 7887.1 36451.9 28018.0 Design Equations (Vector Analysis):66 4.0 353 42321.4 39.4 7638.6 34682.7 27634.3 a = cFS*LCR*sin(90+ FS)/sin( - FS)67 4.0 336 40333.4 39.1 7404.1 32929.2 27190.1 b = W-a68 4.1 320 38373.1 38.7 7182.2 31190.8 26683.7 PA = b*tan( - FS)69 4.2 304 36438.6 38.3 6971.7 29466.9 26113.2 EFP = 2*PA/H2
70 4.3 288 34528.2 37.9 6771.3 27756.9 25476.4
Maximum Active Pressure ResultantPA, max 29112.85 lbs/lineal foot
Equivalent Fluid Pressure (per lineal foot of shoring)EFP = 2*PA/H2
EFP 36.4 pcf
Design Shoring for an Equivalent Fluid Pressure: 37 pcf
Shoring Design with Level Backfill (Vector Analysis)
W
b
a
PA
N
cFS*LCR
WLCR
c
LT
H
HC
Geotechnologies, Inc.Project: Clarette West DevelopmentFile No.: 21428Description: Shoring Walls up to 50 feet
Input:Shoring Height (H) 50.00 feet
Unit Weight of Retained Soils ( ) 120.0 pcfFriction Angle of Retained Soils ( ) 33.0 degreesCohesion of Retained Soils (c) 170.0 psfFactor of Safety (FS) 1.25
Factored Parameters: ( FS) 27.5 degrees(cFS) 136.0 psf
Failure Height of Area of Weight of Length of ActiveAngle Tension Crack Wedge Wedge Failure Plane Pressure
( ) (HC) (A) (W) (LCR) a b (PA)degrees feet feet2 lbs/lineal foot feet lbs/lineal foot lbs/lineal foot lbs/lineal foot
45 4.7 1239 148664.7 64.0 25634.7 123029.9 38902.046 4.6 1197 143653.0 63.2 23971.7 119681.2 40153.947 4.4 1157 138790.4 62.3 22486.4 116304.0 41292.748 4.3 1117 134069.9 61.5 21153.7 112916.1 42323.149 4.2 1079 129484.3 60.7 19953.0 109531.4 43249.350 4.1 1042 125026.7 59.9 18866.8 106159.9 44074.851 4.0 1006 120690.1 59.2 17880.9 102809.2 44802.952 3.9 971 116468.1 58.5 16982.9 99485.1 45436.553 3.9 936 112354.2 57.8 16162.6 96191.6 45977.854 3.8 903 108342.5 57.1 15411.0 92931.5 46429.055 3.8 870 104427.2 56.4 14720.5 89706.7 46791.856 3.8 838 100603.1 55.8 14084.6 86518.4 47067.557 3.7 807 96864.8 55.2 13497.6 83367.2 47257.158 3.7 777 93207.6 54.6 12954.5 80253.1 47361.359 3.7 747 89626.9 54.0 12450.9 77176.0 47380.560 3.7 718 86118.3 53.4 11983.0 74135.3 47314.961 3.8 689 82677.7 52.9 11547.4 71130.3 47164.062 3.8 661 79301.2 52.4 11141.0 68160.1 46927.463 3.8 633 75984.9 51.8 10761.3 65223.7 46604.364 3.9 606 72725.5 51.3 10405.7 62319.8 46193.365 3.9 579 69519.5 50.9 10072.1 59447.4 45693.0 Design Equations (Vector Analysis):66 4.0 553 66363.7 50.4 9758.6 56605.1 45101.5 a = cFS*LCR*sin(90+ FS)/sin( - FS)67 4.0 527 63255.0 49.9 9463.3 53791.7 44416.6 b = W-a68 4.1 502 60190.5 49.5 9184.5 51006.0 43635.5 PA = b*tan( - FS)69 4.2 476 57167.2 49.0 8920.8 48246.5 42755.4 EFP = 2*PA/H2
70 4.3 452 54182.6 48.6 8670.6 45512.0 41772.7
Maximum Active Pressure ResultantPA, max 47380.55 lbs/lineal foot
Equivalent Fluid Pressure (per lineal foot of shoring)EFP = 2*PA/H2
EFP 37.9 pcf
Design Shoring for an Equivalent Fluid Pressure: 38 pcf
Shoring Design with Level Backfill (Vector Analysis)
W
b
a
PA
N
cFS*LCR
WLCR
c
LT
H
HC
Geotechnologies, Inc.Project: Clarett West DevelopmentFile No.: 21428Seismically Induced Lateral Soil Pressure on Retaining Wall
Input:Height of Retaining Wall: (H) 40.0 feetRetained Soil Unit Weight: ( ) 120.0 pcfPeak Ground Acceleraction: (PGAM) 0.77 gHorizontal Ground Acceleration: (kh) 0.26 g
Seismic Increment ( PAE):kh = 0.5*0.67*PGAM
PAE = (0.5* *H2)*(0.75*kh)PAE = 18572.4 lbs/ft
T*(2/3)*H = PAE*0.6*HT = 16715.2 lbs/ft
EFP = 2*T/H2
EFP = 20.9 pcftriangular distribution of pressure, applied to the proposed retaining wall.
Geotechnologies, Inc.Project: Clarett West DevelopmentFile No.: 21428
Soil Weight 120 pcfInternal Friction Angle 33 degreesCohesion c 170 psfHeight of Retaining Wall H 35 feet
NON-HYDROSTATIC (DRAINED) DESIGNRestrained Retaining Wall Design based on At Rest Earth Pressure
'h = Ko 'vKo = 1 - sin 0.455
'v = H 4200.0 psf'h = 1912.5 psf
EFP = 54.6 pcfPo = 33469.0 lbs/ft (based on a triangular distribution of pressure)
Design wall for an EFP of 55 pcf
Geotechnologies, Inc.Tiebacks Calculations (Ref: Bowles, 1982)Project: Clarett West DevelopmentFile No. 21428
Soil Parameters:Weight of Soil 120.00 lbs/ft 3
Friction Angle 33.00 degreesCohesion c 170.00 lbs/ft 2
Tieback Angle 35.00 degreesDesign Assumptions:
Diameter of Grout d 1.00 feetLength of Embeddment L 20.00 feetDepth to midpoint of Embeddment h 12.00 feetEarth Pressure Coefficient K 0.65Factor of Safety Applied F.S. 1.50
Ultimate Resistance: Rult 55.61 kipsEq: pi*d* *L*h*cos(a)*tan( )+c*pi*d*L
Allowable Resistance: Rallow = Rult/F.S. 37.07 kipsAllowable Skin Friction: Rallow/2/pi/r/L 590.02 psf
Allowable Skin Friction Design Value 500 psf
h