Title 24 Non‐Res CertificationProcess
Rick Miller, PE, LC, LEED AP, CLCATT President, RNM Engineering, Inc.
Wed, Oct 1, 2014
SLO GB Alliance
Just to Make Sure
2
Effective July 1, 2014
10/9/2014
2
Course Description
You know about the allowable watts for lighting and about the required controls for lighting, now learn about the required paperwork! Yes, Title 24 requires paperwork and lots of it. “Passing grades” are required by the designer, commissioning agent, manufacturers and vendors, installing contractor, and acceptance testing technician.
Any failures means no Occupancy Certificate.
3
Learning Objectives
• Learn about the quantity of required Certificates.
• Review the Certificates required of the Designer, CxA, Installer and Tester.
• Clarify the Commissioning Process.
• Examine the requirements for Manufacturers, Suppliers and Builders.
4
10/9/2014
3
Title 24 Part 6 Covers
• Building Energy Efficiency Standards
– Covers the technical requirements for Envelope, Fenestration (Windows), HVAC, Appliances, Water Heaters, Boilers, Roofing, Insulation, Air Leakage, Pools & Spas, Lighting Power, Lighting Controls, and Electrical Distribution, and related paperwork.
• This seminar is about the required Certificates,
5
Title 24 Part 6 Covers
• Building Energy Efficiency Standards
– Covers the technical requirements for Envelope, Fenestration (Windows), HVAC, Appliances, Water Heaters, Boilers, Roofing, Insulation, Air Leakage, Pools & Spas, Lighting Power, Lighting Controls, and Electrical Distribution, and related paperwork.
• This seminar is about the required Certificates,
i.e. the Paperwork.
6
10/9/2014
4
Sec 10‐103 Requirements for Designers, Installers, Builders, Manuf, and Testers
• Certificate of Compliance (CC) & (CC‐CXR)• Application for a Building Permit• Certificate of Installation (CI)• Certificate of Acceptance (CA)• Certificate of Verification (CV) [for homes]• Information to be provided by Builder• Information to be provided by Manufacturer or Supplier
• Enforcement Agency Requirements
7
Sec 10‐103 Requirements for Designers, Installers, Builders, Manuf, and Testers
• CC Forms by Designer (C10, C20 Contractor if less than 50,000 SF) or Design Engineer (PE)
• CC‐CXR Forms by Commissioning Engineer.
• CI Forms by person in charge of Construction or Installation.
• CA Forms by CLCATT or CMATT.
• CV Forms by HERS Rater.
• Equipment Info by Manufacturer and Supplies.
• O&M Manual by Builder.
8
10/9/2014
5
The JourneyThe Beginning – . . . .
9
OWNER
The JourneyThe Beginning – The Goal
10
OWNER
Certificate ofOccupancy
10/9/2014
6
The JourneyMany Parties Along the Way
11
OWNER
Cx Agent
INSTALLER
DESIGNER PLANS EXAMINER
OWNER
ACCEPT. TESTER
BLDG INSPECTOR
Certificate ofOccupancy
The Journey1. Owner
12
OWNEROPR
Cx Agent
INSTALLER
DESIGNER PLANS EXAMINER
OWNER
ACCEPT. TESTER
BLDG INSPECTOR
Certificate ofOccupancy
10/9/2014
7
Owner Project Requirements (OPR)
This document shall include the following:
1. Energy efficiency goals;
2. Ventilation requirements;
3. Project program, including facility functions and hours of operation, and need for after hours operation; and
4. Equipment and systems expectations.
Sec 120.8(b)
13
The Journey2. Designer
14
OWNEROPR
Cx Agent
INSTALLER
DESIGNERBODCC forms
PLANS EXAMINER
OWNER
ACCEPT. TESTER
BLDG INSPECTOR
Certificate ofOccupancy
10/9/2014
8
Basis of Design (BOD)
The BOD shall cover the following systems:
1. Heating, ventilation, air conditioning (HVAC) systems and controls.
2. Indoor & outdoor lighting system and controls.
3. Water heating systems and controls.
4. Covered processes.
Sec 120.8(c)
15
Forms to be completed by Design Architect
1. NRCC‐ENV‐01‐E (4+4)Envelope Component Approach
2. NRCC‐ENV‐02‐E (3+3)Fenestration Worksheet
3. NRCC‐ENV‐03‐E (2+1)CoolRoof and SRI Worksheet
4. NRCC‐ENV‐04‐E (2+1)Daylit Zone
5. NRCC‐ENV‐05‐E (2+1)Fenestration Certificate Label
6. NRCC‐ENV‐06‐E (2+1) Area Weighted Average Calculation
7. NRCC‐SRA‐01‐E (2) Solar Ready Areas
8. NRCC‐SRA‐02‐E (3) Minimum Solar Zone Area
9. NRCC‐STH‐01‐E (2+2)Solar Water Heating
16
# of pages of forms
# of pages of instructions
10/9/2014
9
Forms to be completed by Electrical Design Engineer
1. NRCC‐ELC‐01‐E (9) Electrical Power Distribution
2. NRCC‐LTI‐01‐E (5) Field Inspection Checklist
3. NRCC‐LTI‐02‐E (3) Lighting Controls Credit Worksheet
4. NRCC‐LTI‐03‐E (4) Indoor Lighting Power Allowance
5. NRCC‐LTI‐04‐E (7) Tailored Method Worksheet
6. NRCC‐LTI‐05‐E (2) Line Voltage Track Lighting Worksheet
7. NRCC‐LTO‐01‐E (3) Outdoor Lighting
8. NRCC‐LTO‐02‐E (3) Outdoor Lighting Controls
9. NRCC‐LTO‐03‐E (4) Outdoor Lighting Power Allowance
10.NRCC‐LTS‐01‐E (4) Sign Lighting
17
Forms to be completed by Mechanical Design Engineer
1. NRCC‐MCH‐01‐E (3) Declarations
2. NRCC‐MCH‐02‐E (3) Dry System and Wet System
3. NRCC‐MCH‐03‐E (2) Mechanical Ventilation and Reheat
4. NRCC‐MCH‐04‐E (3) Declarations ‐ Single Zone Systems
5. NRCC‐MCH‐05‐E (2) Requirements ‐ Single Zone Systems
6. NRCC‐MCH‐06‐E (1+1)Maximum Cycles of Concentration
18
10/9/2014
10
Forms to be completed by Process Design Engineer
1. NRCC‐PLB‐01‐E (3+1)Water Heating Systems
2. NRCC‐PRC‐01‐E (3) Covered Process
3. NRCC‐PRC‐02‐E (1) Garage Exhaust
4. NRCC‐PRC‐03‐E (2) Commercial Kitchens
5. NRCC‐PRC‐04‐E (1) Data Centers
6. NRCC‐PRC‐05‐E (5) Commercial Refrigeration
7. NRCC‐PRC‐06‐E (3) Refrigerated Warehouses
8. NRCC‐PRC‐07‐E (3) Refrigerated Warehouses‐ >3,000 SF
9. NRCC‐PRC‐08‐E (5) Refrigerated Warehouses‐ >3,000 SF
10.NRCC‐PRC‐09‐E (1) Laboratory Exhaust
11.NRCC‐PRC‐10‐E (2) Compressed Air Systems
12.NRCC‐PRC‐11‐E (1) Process Boilers19
The Journey3. Manufacturer
20
OWNEROPR
Cx Agent
INSTALLER
DESIGNERBODCC forms
PLANS EXAMINER
OWNER
ACCEPT. TESTER
BLDG INSPECTOR
Certificate ofOccupancy
MANUF.Product Info
10/9/2014
11
Manufacturers
• The manufacturer or supplier of any manufactured device shall, upon request, provide to building designers and installers information about the device. The information shall include the efficiency (and other characteristics regulated by Part 6). This information shall be in paper or electronic format. Sec 10‐103(c)
21
The Journey4. Commissioning Agent
22
OWNEROPR
Cx AgentCXR forms
INSTALLER
DESIGNERBODCC forms
PLANS EXAMINER
OWNER
ACCEPT. TESTER
BLDG INSPECTOR
Certificate ofOccupancy
MANUF.Product Info
10/9/2014
12
• BUILDING COMMISSIONING is a systematic quality assurance process that spans the entire design and construction process, including verifying and documenting that building systems and components are planned, designed, installed, tested, operated and maintained to meet the owner’s project requirements.
Sec 100.1 Definitions
23
Sec 120.8 Building Commissioning
• For buildings less than 10,000 sf, design phase design review may be completed by the design engineer PE.
• Buildings between 10,000sf and 50,000 sf require completion of the Design Review Checklist by either an engineer PE in‐house to the design firm but not associated with the building project, or a third party design engineer PE.
• For buildings larger than 50,000 sf or for buildings with complex mechanical systems, an independent, review of these documents by a third party design engineer PE is required.
24
10/9/2014
13
Commissioning Matrix
25
Description of Project <10kSF10k‐50kSF with Simple Mech
>50kSF or with Complex Mech>10kSF
(d) SD Kickoff & CD Design ReviewPE or C10,C20
Note 1PE or C10,C20
Note 23rd Party PE
(e) Cx Measures in Specs and on Drawings
Req’d Req’d Req’d
(b)Owner Project Req (OPR)(c) Basis of Design (BOD)(f) Cx Plan(g) Functional Performance Tests(h) Systems Manual & Training(i) Cx Report
N/A Req’d Req’d
Note 1: By design engineer, or licensed contractor accepting responsibility of engineer.Note 2: By In-house engineer not associated with project, or 3rd party engineer, or
licensed contractor accepting responsibility of engineer.Complex Mech System: Multi-Zone AH, Built-Up Units, Steam heating, or Hydronic heat or cool
Title 24 Sec 120.8 and Sec 10-103(a)1
© Rick Miller, PE 2014
Sec 120.8 Building Commissioning
(b) Owner Project Requirements (OPR)(c) Basis of Design (BOD)
(d) SD & CD Design Reviews
(e) Cx Measures in Specs and on Drawings
(f) Cx Plan(g) Functional Performance Tests(h) Systems Manual & Training(i) Cx Report
26
10/9/2014
14
Forms to be completed by Commissioning Engineer
1. NRCC‐CXR‐01‐E (2) Design Review Kickoff
2. NRCC‐CXR‐02‐E (8) Construction Documents Review
3. NRCC‐CXR‐03‐E (2) Simple HVAC Systems
4. NRCC‐CXR‐04‐E (6) Complex Mechanical Systems
5. NRCC‐CXR‐05‐E (2) Design Review Signature Page
27
NRCC‐CXR‐02‐EConstruction Document Review
28
10/9/2014
15
The Journey5. Plan Examiner
29
OWNEROPR
Cx AgentCXR forms
INSTALLER
DESIGNERBODCC forms
PLANS EXAMINERReviews CC, Cx formsIssues Bldg Permit
OWNER
ACCEPT. TESTER
BLDG INSPECTOR
Certificate ofOccupancy
MANUF.Product Info
Plans Examiner Responsibilities
The plans examiner is responsible for:A. Reviewing the plans and supporting material to
verify that they contain the necessary information for a plan review.
B. Checking the calculations and data contained on the worksheets.
C. Indicating by checking a box on the summary forms that the compliance documentation is acceptable.
D. Making notes for the field inspector about which items require special attention.
30
10/9/2014
16
Sec 10‐103 Requirements for Designers, Installers, Builders, Manuf, and Testers
• Application for a Building Permit. Each application for a building permit subject to Part 6 shall contain at least one copy of the documents specified in Sections 10‐103(a)2A, 10‐103(a)2B, and 10‐103(a)2C.
2A. Certificate of Compliance included in the Plans.2B. Plans and specs shall provide acceptance
requirements for code compliance.2C. May be required to include electronic input
file for the compliance software tool.31
Sec 10‐103 Requirements for Designers, Installers, Builders, Manuf, and Testers
• (d) Enforcement Agency Requirements.
– 1. Permits. An enforcement agency shall not issue a Building Permit for any construction unless the enforcement agency determines in writing that the construction is designed to comply with the requirements of Part 6 that are in effect on the date the building permit was applied for. The enforcement agency determination shall confirm that the documentation requirements of Sections 10‐103(a)1 and 10‐103(a)2 have been met.
32
10/9/2014
17
The Journey6. Installer
33
OWNEROPR
Cx AgentCXR forms
INSTALLERCI forms Submittals
DESIGNERBODCC forms
PLANS EXAMINERReviews CC, Cx formsIssues Bldg Permit
OWNER
ACCEPT. TESTER
BLDG INSPECTOR
Certificate ofOccupancy
MANUF.Product Info
Forms to be completed by General Construction Foreman
1. NRCI‐ENV‐01‐E (2) Envelope
34
10/9/2014
18
Forms to be completed by Electrical Construction Foreman
1. NRCI‐ELC‐01‐E (2) Electrical Power Distribution2. NRCI‐LTI‐01‐E (2) Validation of Certificate of Compliance3. NRCI‐LTI‐02‐E (5) EMCS or Lighting Control System4. NRCI‐LTI‐03‐E (3) Line‐Voltage Track Lighting5. NRCI‐LTI‐04‐E (2) Two Interlocked Lighting Systems6. NRCI‐LTI‐05‐E (5) Power Adjustment Factors7. NRCI‐LTI‐06‐E (2) Videoconference Studio Lighting8. NRCI‐LTO‐01‐E (2) Outdoor Lighting9. NRCI‐LTO‐02‐E (5) EMCS ‐ Lighting Control System10.NRCI‐LTS‐01‐E (2) Sign Lighting11.NRCI‐SPV‐06‐E (2) Solar Photovoltaic System
35
Forms to be completed by Mechanical Construction Foreman
1. NRCI‐MCH‐01‐E (2) Mechanical
2. NRCI‐PLB‐01‐E (2) Water Heating Systems
3. NRCI‐PLB‐02‐E (4) HRR, H/M Single Dwell Unit Hot Water
4. NRCI‐PLB‐03‐E (3) HRR, H/M Central Hot Water System
5. NRCI‐PLB‐04‐E (2) Non‐Res Single Dwell Unit Hot Water
6. NRCI‐PLB‐05‐E (2) Non‐Res Central Hot Water System
7. NRCI‐PRC‐01‐E (2) Refrigerated Warehouse
8. NRCI‐STH‐01‐E (2) Solar Water Heating System
36
10/9/2014
19
The Journey7. Manufacturer
37
OWNEROPR
Cx AgentCXR forms
INSTALLERCI forms Submittals
DESIGNERBODCC forms
PLAN EXAMINERReviews CC, Cx formsIssues Bldg Permit
OWNER
ACCEPT. TESTER
BLDG INSPECTOR
Certificate ofOccupancy
MANUF.Submittal Literature
MANUF.Installation Instructions
MANUF.Startup Technician
MANUF.Product Info
Manufacturers
• The manufacturer or supplier of any manufactured device shall, upon request, provide to building designers and installers information about the device. The information shall include the efficiency (and other characteristics regulated by Part 6). This information shall be in paper or electronic format. Sec 10‐103(c)
38
10/9/2014
20
The Journey8. Acceptance Tester
39
OWNEROPR
Cx AgentCXR forms
INSTALLERCI forms Submittals
DESIGNERBODCC forms
PLAN EXAMINERReviews CC, Cx formsIssues Bldg Permit
OWNER
ACCEPT. TESTERCA forms BLDG INSPECTOR
Certificate ofOccupancy
MANUF.Submittal Literature
MANUF.Installation Instructions
MANUF.Startup Technician
MANUF.Product Info
• ACCEPTANCE REQUIREMENTS FOR CODE COMPLIANCE is a description of test procedures in the Reference Nonresidential Appendices that includes equipment and systems to be tested, functions to be tested, conditions under which the test shall be performed, the scope of the tests, results to be obtained, and measurable criteria for acceptable performance.
Sec 100.1 Definitions
40
10/9/2014
21
Sec 10‐103A Non‐Res Lighting Controls Acceptance Training Provider
• Certified Training Provider of Lighting Controls Acceptance Test Technicians
• Certified Lighting Controls Acceptance Test Technician (CLCATT).
• Effective upon reaching more than 300 CLCATT throughout the State. [Requirements were met as of July 1, 2014.]
41
Sec 10‐103A Non‐Res Acceptance Testing Training
Technician
• CATT training program
• CATT training curricula
• CATT Employer training
• CATT Review
Provider
• CATP Provider of ATT training
• CATP Accountability
• CATP Revocation of Certificate42
10/9/2014
22
The CLCATT Confirms the CI Forms
43
“I have confirmed that the Certificate(s) of Installation for the construction or installation identified on the Certificate of Acceptance has been completed and signed by the responsible builder/installer and has been posted or made available with the building permit(s) issued for the building.”
Acceptance Tests requiredbefore getting Occupancy Permit
44
“Before an occupancy permit is granted for a newly constructed building or area, or a new lighting system serving a building, area, or site is operated for normal use, indoor lighting controls serving the building, area, or site shall be certified as meeting the Acceptance Requirements for Code Compliance in accordance with Section 130.4.(a). “
10/9/2014
23
Forms to be completed by Lighting Controls Acceptance Tester
1. NRCA‐LTI‐02‐E (6) Lighting Controls
2. NRCA‐LTI‐03‐E (9) Automatic Daylighting
3. NRCA‐LTI‐04‐E (5) Demand Responsive Lighting Controls
4. NRCA‐LTO‐02‐E (3) Outdoor Motion Sensor and Outdoor Automatic Shut‐off Controls
45
Forms to be completed by Mechanical Acceptance Tester
1. NRCA‐MCH‐02‐E (3) Mechanical Outdoor Air
2. NRCA‐MCH‐03‐E (3) Constant Volume Single Zone
3. NRCA‐MCH‐04‐E (5) Air Distribution Duct Leakage
4. NRCA‐MCH‐05‐E (3) Air Economizer Controls
5. NRCA‐MCH‐06‐E (2) Demand Control Ventilation (DVC)
6. NRCA‐MCH‐07‐E (3) Supply Fan Variable Flow Controls
7. NRCA‐MCH‐08‐E (2) Valve Leakage Test
8. NRCA‐MCH‐09‐E (3) Supply Water Temperature Reset
9. NRCA‐MCH‐10‐E (3) Hydronic System Variable Flow
10.NRCA‐MCH‐11‐E (2) Automatic Demand Shed Controls
11.NRCA‐MCH‐12‐E (2) Fault Detection & Diagnostics for DX Units46
10/9/2014
24
Forms to be completed by Mechanical Acceptance Tester
12. NRCA‐MCH‐13‐E (4) Fault Detection & Diagnostics for AHU
13. NRCA‐MCH‐14‐E (2) Dist Energy Storage DX AC Systems
14. NRCA‐MCH‐15‐E (3) Thermal Energy Storage System
15. NRCA‐MCH‐16‐E (3) Supply Air Temp Reset Controls
16. NRCA‐MCH‐17‐E (3) Condenser Water Supply Temp Reset
17. NRCA‐MCH‐18‐E (2) Energy Management Control System
47
Forms to be completed by Process Acceptance Tester
1. NRCA‐PRC‐01‐E (4) Compressed Air Systems
2. NRCA‐PRC‐02‐E (3) Commercial Kitchen Exhaust
3. NRCA‐PRC‐03‐E (3) Enclosed Parking Garage Exhaust
4. NRCA‐PRC‐04‐E (2) Refri Wrh‐Evap Fan System Motor Controls
5. NRCA‐PRC‐05‐E (4) Refri Wrh‐Evap Condenser Controls
6. NRCA‐PRC‐06‐E (4) Refri Wrh‐Air‐Cooled Condenser Controls
7. NRCA‐PRC‐07‐E (3) Refri Wrh‐Variable Speed Compressor
8. NRCA‐PRC‐08‐E (2) Refri Wrh‐Electric Resistance UnderslabHeating System
48
10/9/2014
25
The Journey9. Owner
49
OWNEROPR
Cx AgentCXR forms
INSTALLERCI forms Submittals
DESIGNERBODCC forms
PLANS EXAMINERReviews CC, Cx formsIssues Bldg Permit
OWNERCx ReportO&M Manual
ACCEPT. TESTERCA forms BLDG INSPECTOR
Certificate ofOccupancy
MANUF.Submittal Literature
MANUF.Installation Instructions
MANUF.Startup Technician
MANUF.Product Info
Owner
Owner receives copies of:
• All CC, CXR, CI, CA forms
• Cx Report
• O&M Manual
50
10/9/2014
26
Sec 10‐103 Requirements for Designers, Installers, Builders, Manuf, and Testers
• (b) Compliance, Operating, Maintenance, and Ventilation Information to be provided by Builder: “at final inspection, the enforcement agency shall require the builder to leave in the building”:
– 1. Compliance information.
– 2. Operating information.
– 3. Maintenance information.
– 4. Ventilation information.
51
The Journey10. Building Inspector
52
OWNEROPR
Cx AgentCXR forms
INSTALLERCI forms Submittals
DESIGNERBODCC forms
PLANS EXAMINERReviews CC, Cx formsIssues Permit
OWNERCx ReportO&M Manual
ACCEPT. TESTERCA forms BLDG INSPECTOR
Reviews CI, CA formsConfirms O&M
Certificate ofOccupancy
MANUF.Submittal Literature
MANUF.Installation Instructions
MANUF.Startup Technician
MANUF.Product Info
10/9/2014
27
Field Inspector Responsibilities
The field inspector is responsible for:
A. Verifying that the building or system is constructed according to the plans.
B. Checking off appropriate items on the summary form at each relevant inspection.
C. Verifying that all of the required compliance documentation (Certificate(s) of Installation, Acceptance, and Field Verification and Diagnostic Testing) is completed, dated, signed, and registered (when applicable).
53
Sec 10‐103 Requirements for Designers, Installers, Builders, Manuf, and Testers
• (d) Enforcement Agency Requirements.
– 2. Inspection. The enforcement agency shall inspect newly constructed buildings and additions, and alterations to existing buildings to determine whether the construction or installation is consistent with the agency's approved plans and specifications, and complies with Part 6. Final Certificate of Occupancy shall not be issued until such consistency and compliance is verified.
54
10/9/2014
28
The Journey11. Certificate of Occupancy
55
OWNEROPR
Cx AgentCXR forms
INSTALLERCI forms Submittals
DESIGNERBODCC forms
PLANS EXAMINERReviews CC, Cx formsIssues Bldg Permit
OWNERCx ReportO&M Manual
ACCEPT. TESTERCA forms BLDG INSPECTOR
Reviews CI, CA formsConfirms O&M
Certificate ofOccupancy
MANUF.Submittal Literature
MANUF.Installation Instructions
MANUF.Startup Technician
MANUF.Product Info
Decoding the Forms
NRCA‐LTI‐02‐E (Sample)
NR = Non ResidentialCC = Certificate of ComplianceCI = Certificate of InstallationCA = Certificate of Acceptance
CXR = Commissioning ReviewELC = ElectricalLTI = Lighting IndoorLTO = Lighting Outdoor
E = Enforcement AgencyA = Acceptance Testing TechnicianF = Field TechnicianH = HERS Rater
56
10/9/2014
29
Who Signs the CC, CI, CA Forms
• Persons who prepare Certificates (documentation authors) shall sign and certify the documentation is accurate and complete.
‐ AND ‐• The responsible person eligible under Division 3 of the Business and Professions Code to accept responsibility for the applicable scope of work specified on the Certificate shall sign and submit all applicable Certificates.– Licensed Architect– Licensed Engineer– Licensed Contractor
57
Who Signs the Cx Design Review
58
Owner/ Owner’s RepresentativeDesign Engineer
Design Reviewer
Owner/ Owner’s RepresentativeDesign Engineer
Design Reviewer
Design Review Kickoff
Construction Document Checklist
Date
Date
General Checklist for all BuildingsHVAC Simple or HVAC Complex
10/9/2014
30
Under Penalty of Perjury
59
DOCUMENTATION AUTHOR'S DECLARATION STATEMENT
Lighting Control Narrative
• Provide a lighting control narrative or sequence of operation for each different room type in sufficient detail so that the vendor can program it, the CxA can write a functional performance test for it, and for the CLCATT to test it.
• The narrative needs to include general lighting, specialty light, egress lighting, emergency lighting, occupancy sensing, vacancy sensing, daylight harvesting, adaptive time delays, task tuning, personal controls, daytime, nighttime, weekends, holidays, demand response, event programming, high trims, low trims, fade rates, scene settings, etc.
60
10/9/2014
31
“Grandpa! That’s Boring. ‐You gotta talk about video games!”
61
Eliminate Paperwork.Go Electronic !
• January 1, 2015 – All CA forms shall be registered electronically to a Data Registry approved by the Commission. Sec 10‐103(a)1D.
• January 1, 2015 – All signatures on CA forms shall be electronically authenticated in accordance with JA7.6. (7 pages) Sec 10‐103(a)1D
• All CC, CXR and CI forms shall be registered electronically to a Data Registry as soon as one is approved by the Commission. Sec 10‐103(a)
62
10/9/2014
32
Summary
• Need “passing grades” on all forms in order to be granted a Certificate of Occupancy.
63
The End