Site C Technical Briefing
Don Wright Deputy Minister to the Premier
December 11, 2017
![Page 2: Site C - British Columbia · Technical Briefing Don Wright Deputy Minister to the Premier December 11, 2017 . ... and lengthy deliberation Cabinet has made the difficult decision](https://reader036.fdocuments.us/reader036/viewer/2022070109/604563e4dfa5ed7d4008e1e4/html5/thumbnails/2.jpg)
After review by BCUC, meeting with Treaty 8
First Nations, advice from independent experts and lengthy deliberation
Cabinet has made the difficult decision to
complete Site C construction
2
![Page 3: Site C - British Columbia · Technical Briefing Don Wright Deputy Minister to the Premier December 11, 2017 . ... and lengthy deliberation Cabinet has made the difficult decision](https://reader036.fdocuments.us/reader036/viewer/2022070109/604563e4dfa5ed7d4008e1e4/html5/thumbnails/3.jpg)
Outline of Technical Presentation
I. Historical Context
II. Government’s Decision Criteria
III. Revised Cost Estimates
IV. Ratepayer Impacts
V. Fiscal Impacts/Risks
VI. Concluding Comments
3
![Page 4: Site C - British Columbia · Technical Briefing Don Wright Deputy Minister to the Premier December 11, 2017 . ... and lengthy deliberation Cabinet has made the difficult decision](https://reader036.fdocuments.us/reader036/viewer/2022070109/604563e4dfa5ed7d4008e1e4/html5/thumbnails/4.jpg)
I. Historical Context
4
![Page 5: Site C - British Columbia · Technical Briefing Don Wright Deputy Minister to the Premier December 11, 2017 . ... and lengthy deliberation Cabinet has made the difficult decision](https://reader036.fdocuments.us/reader036/viewer/2022070109/604563e4dfa5ed7d4008e1e4/html5/thumbnails/5.jpg)
Hydro Rates Have Been Rising Significantly Since 2003
5
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017
BC Hydro Rate Increases 2000 - 2017
![Page 6: Site C - British Columbia · Technical Briefing Don Wright Deputy Minister to the Premier December 11, 2017 . ... and lengthy deliberation Cabinet has made the difficult decision](https://reader036.fdocuments.us/reader036/viewer/2022070109/604563e4dfa5ed7d4008e1e4/html5/thumbnails/6.jpg)
New Power More Expensive Than Heritage Assets
Heritage Assets Average of IPP Projected Site C
$32 / Mwh $100 / Mwh $60 / Mwh
6
Heritage Assets Average of IPP Projected Site C
$32 / MWh $100 / MWh $60 / MWh
![Page 7: Site C - British Columbia · Technical Briefing Don Wright Deputy Minister to the Premier December 11, 2017 . ... and lengthy deliberation Cabinet has made the difficult decision](https://reader036.fdocuments.us/reader036/viewer/2022070109/604563e4dfa5ed7d4008e1e4/html5/thumbnails/7.jpg)
IPP Share of Supply Growing
7
-
2,000
4,000
6,000
8,000
10,000
12,000
14,000
16,000
2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017
IPP Historical Generation (GWh)
![Page 8: Site C - British Columbia · Technical Briefing Don Wright Deputy Minister to the Premier December 11, 2017 . ... and lengthy deliberation Cabinet has made the difficult decision](https://reader036.fdocuments.us/reader036/viewer/2022070109/604563e4dfa5ed7d4008e1e4/html5/thumbnails/8.jpg)
-
5,000
10,000
15,000
20,000
25,000
2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017
BC Hydro Net Long-Term Debt ($ Millions)
BC Hydro Debt is Growing
8
![Page 9: Site C - British Columbia · Technical Briefing Don Wright Deputy Minister to the Premier December 11, 2017 . ... and lengthy deliberation Cabinet has made the difficult decision](https://reader036.fdocuments.us/reader036/viewer/2022070109/604563e4dfa5ed7d4008e1e4/html5/thumbnails/9.jpg)
BC Hydro’s Regulatory Account Balance Is Growing
-1000
0
1000
2000
3000
4000
5000
6000
7000
2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017
BC Hydro Regulatory Account Balances ($ Millions)
9
![Page 10: Site C - British Columbia · Technical Briefing Don Wright Deputy Minister to the Premier December 11, 2017 . ... and lengthy deliberation Cabinet has made the difficult decision](https://reader036.fdocuments.us/reader036/viewer/2022070109/604563e4dfa5ed7d4008e1e4/html5/thumbnails/10.jpg)
Current 10-Year Rate Plan Schedules Further Increases
0
5
10
15
20
25
30
35
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028
%
10
10-Year Rate Plan Increases
![Page 11: Site C - British Columbia · Technical Briefing Don Wright Deputy Minister to the Premier December 11, 2017 . ... and lengthy deliberation Cabinet has made the difficult decision](https://reader036.fdocuments.us/reader036/viewer/2022070109/604563e4dfa5ed7d4008e1e4/html5/thumbnails/11.jpg)
How Our Rates Compare, Residential
0
5
10
15
20
25
30
35
Quebec British Columbia Oregon Washington Ontario California
Cents / KWh
Source: Hydro Quebec, NRCAN, US EIA
11
![Page 12: Site C - British Columbia · Technical Briefing Don Wright Deputy Minister to the Premier December 11, 2017 . ... and lengthy deliberation Cabinet has made the difficult decision](https://reader036.fdocuments.us/reader036/viewer/2022070109/604563e4dfa5ed7d4008e1e4/html5/thumbnails/12.jpg)
Sources of Electricity
0
10
20
30
40
50
60
70
80
90
100
Quebec BritishColumbia
Oregon Washington Ontario California
Fossil
Solar & Wind
Hydro
Source: Hydro Quebec, NRCAN, US EIA Other sources to 100% includes biomass, nuclear
12
%
![Page 13: Site C - British Columbia · Technical Briefing Don Wright Deputy Minister to the Premier December 11, 2017 . ... and lengthy deliberation Cabinet has made the difficult decision](https://reader036.fdocuments.us/reader036/viewer/2022070109/604563e4dfa5ed7d4008e1e4/html5/thumbnails/13.jpg)
II. Government’s Decision Criteria
13
![Page 14: Site C - British Columbia · Technical Briefing Don Wright Deputy Minister to the Premier December 11, 2017 . ... and lengthy deliberation Cabinet has made the difficult decision](https://reader036.fdocuments.us/reader036/viewer/2022070109/604563e4dfa5ed7d4008e1e4/html5/thumbnails/14.jpg)
Criteria
1. Ratepayer Impact
2. Fiscal Impact / Risks
3. First Nation Impacts
4. GHG Targets
5. Agriculture / Food Security
14
![Page 15: Site C - British Columbia · Technical Briefing Don Wright Deputy Minister to the Premier December 11, 2017 . ... and lengthy deliberation Cabinet has made the difficult decision](https://reader036.fdocuments.us/reader036/viewer/2022070109/604563e4dfa5ed7d4008e1e4/html5/thumbnails/15.jpg)
III. Revised Cost Estimates
15
![Page 16: Site C - British Columbia · Technical Briefing Don Wright Deputy Minister to the Premier December 11, 2017 . ... and lengthy deliberation Cabinet has made the difficult decision](https://reader036.fdocuments.us/reader036/viewer/2022070109/604563e4dfa5ed7d4008e1e4/html5/thumbnails/16.jpg)
Projected Cost to Complete: $10.7 Billion
• 2014 approval was for $8.335 billion • With an additional $440 million risk reserve • For a total of $8.775 billion
• Costs to date have exceed budgeted amounts
• One-year delay of river diversion estimated to increase costs by $610 million
• Future contracts projected to be higher than budgeted amounts
• Current mid-point estimate is now $9.992 billion • $1.657 billion over 2014 estimate
• Given what has happened to date, risk reserve has been increased
16
![Page 17: Site C - British Columbia · Technical Briefing Don Wright Deputy Minister to the Premier December 11, 2017 . ... and lengthy deliberation Cabinet has made the difficult decision](https://reader036.fdocuments.us/reader036/viewer/2022070109/604563e4dfa5ed7d4008e1e4/html5/thumbnails/17.jpg)
Change in Cost Estimate
Cost 2014 Current
Direct Costs 4,940 5,839
Indirect and Overhead 1,194 2,010
Contingency 794 858
Interest before completion 1,407 1,285
Total Before Risk Reserve 8,335 9,992
Risk Reserve 440 708
Total 8,775 10,700
17
$ millions
![Page 18: Site C - British Columbia · Technical Briefing Don Wright Deputy Minister to the Premier December 11, 2017 . ... and lengthy deliberation Cabinet has made the difficult decision](https://reader036.fdocuments.us/reader036/viewer/2022070109/604563e4dfa5ed7d4008e1e4/html5/thumbnails/18.jpg)
Comments on Cost Escalation
• Government will be putting in place enhanced oversight to ensure final costs are at or below $10.7 billion
• $10.7 billion is used in making comparisons of the continue versus terminate scenarios
18
![Page 19: Site C - British Columbia · Technical Briefing Don Wright Deputy Minister to the Premier December 11, 2017 . ... and lengthy deliberation Cabinet has made the difficult decision](https://reader036.fdocuments.us/reader036/viewer/2022070109/604563e4dfa5ed7d4008e1e4/html5/thumbnails/19.jpg)
IV. Rate Impacts
19
![Page 20: Site C - British Columbia · Technical Briefing Don Wright Deputy Minister to the Premier December 11, 2017 . ... and lengthy deliberation Cabinet has made the difficult decision](https://reader036.fdocuments.us/reader036/viewer/2022070109/604563e4dfa5ed7d4008e1e4/html5/thumbnails/20.jpg)
Comparison of Load Forecasts
40,000
45,000
50,000
55,000
60,000
65,000
70,000
75,000
80,000
85,000
90,000
Ene
rgy
(GW
h)
Low-High Load Forecast Range BC Hydro Mid-Load Forecast
Deloitte Alternative Load Scenario Electrification
Mid-Load Forecast
Deloitte
Electrification
20
![Page 21: Site C - British Columbia · Technical Briefing Don Wright Deputy Minister to the Premier December 11, 2017 . ... and lengthy deliberation Cabinet has made the difficult decision](https://reader036.fdocuments.us/reader036/viewer/2022070109/604563e4dfa5ed7d4008e1e4/html5/thumbnails/21.jpg)
Rate Impact Analysis Assumptions
• BCUC Low Load Forecast
• BCUC “Alternative Portfolio” assumptions
• $10.7 B Site C Cost
• 10 year amortization of $4 billion in termination scenario
21
![Page 22: Site C - British Columbia · Technical Briefing Don Wright Deputy Minister to the Premier December 11, 2017 . ... and lengthy deliberation Cabinet has made the difficult decision](https://reader036.fdocuments.us/reader036/viewer/2022070109/604563e4dfa5ed7d4008e1e4/html5/thumbnails/22.jpg)
22
Rate Impacts Under a Low Load Forecast
0%
20%
40%
60%
80%
100%
120%
F2019 F2024 F2029 F2034 F2039 F2044 F2049
L1 - Low load, continue with Site C, BCH portfolio L2 - Low load, terminate Site C, pursue BCUC portfolio
Terminate Site C Continue Site C
![Page 23: Site C - British Columbia · Technical Briefing Don Wright Deputy Minister to the Premier December 11, 2017 . ... and lengthy deliberation Cabinet has made the difficult decision](https://reader036.fdocuments.us/reader036/viewer/2022070109/604563e4dfa5ed7d4008e1e4/html5/thumbnails/23.jpg)
What Is The Impact On Ratepayers?
Complete Site C Terminate Site C
Rate impact 1.1% in 2025, and 1.1% in 2026 under a rate smoothing scenario over 10 years, then decreasing (assuming revised $10.7B project cost)
Increases rates, starting in 2020 to recover sunk and termination costs
A 12% rate increase would need to be in place for 10 years
![Page 24: Site C - British Columbia · Technical Briefing Don Wright Deputy Minister to the Premier December 11, 2017 . ... and lengthy deliberation Cabinet has made the difficult decision](https://reader036.fdocuments.us/reader036/viewer/2022070109/604563e4dfa5ed7d4008e1e4/html5/thumbnails/24.jpg)
Impact of Terminating Site C on Customers
Results in a rate increase of 12%, effective 2020
Single Family Home, Vancouver Island • Annual hydro bill $1,650 +$198 / year
Lumber Mill, BC Interior • Annual hydro bill $1.6 million +$192,000 / year
Medium Data Centre • Annual hydro bill $1.5 million +$180,000 / year
Large Lower Mainland Hospital • Annual hydro bill $3.1 million +$372,000 / year
24
![Page 25: Site C - British Columbia · Technical Briefing Don Wright Deputy Minister to the Premier December 11, 2017 . ... and lengthy deliberation Cabinet has made the difficult decision](https://reader036.fdocuments.us/reader036/viewer/2022070109/604563e4dfa5ed7d4008e1e4/html5/thumbnails/25.jpg)
Demand Affects Relative Rate Impact
• If demand exceeds low load forecast, relative advantage of complete scenario increases over terminate scenario
25
![Page 26: Site C - British Columbia · Technical Briefing Don Wright Deputy Minister to the Premier December 11, 2017 . ... and lengthy deliberation Cabinet has made the difficult decision](https://reader036.fdocuments.us/reader036/viewer/2022070109/604563e4dfa5ed7d4008e1e4/html5/thumbnails/26.jpg)
26
0.0%
20.0%
40.0%
60.0%
80.0%
100.0%
120.0%
140.0%
F2019 F2024 F2029 F2034 F2039 F2044 F2049
Option M1 - Mid load, continue Site C Option M2 - Mid load, terminate Site C, pursue BCH portfolio
Terminate Site C
Continue Site C
Rate Impacts Under a Mid Load Forecast
![Page 27: Site C - British Columbia · Technical Briefing Don Wright Deputy Minister to the Premier December 11, 2017 . ... and lengthy deliberation Cabinet has made the difficult decision](https://reader036.fdocuments.us/reader036/viewer/2022070109/604563e4dfa5ed7d4008e1e4/html5/thumbnails/27.jpg)
V. Fiscal Impacts / Risks
27
![Page 28: Site C - British Columbia · Technical Briefing Don Wright Deputy Minister to the Premier December 11, 2017 . ... and lengthy deliberation Cabinet has made the difficult decision](https://reader036.fdocuments.us/reader036/viewer/2022070109/604563e4dfa5ed7d4008e1e4/html5/thumbnails/28.jpg)
Some Inconvenient Arithmetic
• If government decided to terminate, $4 billion in debt has to be absorbed by someone • Ratepayers
• BC Hydro
• Taxpayers
• The previous section looked at the implications if ratepayers absorbed the cost
28
![Page 29: Site C - British Columbia · Technical Briefing Don Wright Deputy Minister to the Premier December 11, 2017 . ... and lengthy deliberation Cabinet has made the difficult decision](https://reader036.fdocuments.us/reader036/viewer/2022070109/604563e4dfa5ed7d4008e1e4/html5/thumbnails/29.jpg)
Could BC Hydro Absorb Termination Costs?
• They could
• But this would • Wipe out more than 80% of BC Hydro’s equity
• The $4 billion loss would still be consolidated on the books of the Government Reporting Entity
• Involve ongoing debt interest costs of $120-150 million per year
29
![Page 30: Site C - British Columbia · Technical Briefing Don Wright Deputy Minister to the Premier December 11, 2017 . ... and lengthy deliberation Cabinet has made the difficult decision](https://reader036.fdocuments.us/reader036/viewer/2022070109/604563e4dfa5ed7d4008e1e4/html5/thumbnails/30.jpg)
Biggest Risk Of The Hydro Absorb Scenario
• In a scenario where BC Hydro was to absorb the $4 billion termination costs: • Credit rating agencies could determine that BC Hydro was no longer a
commercially viable entity Resulting in $20 billion debt being reclassified as taxpayer-supported debt • Likely leading to a downgrade of the Province’s credit rating
• Resulting in higher interest costs for the (then) $65 billion in taxpayer-supported debt
30
![Page 31: Site C - British Columbia · Technical Briefing Don Wright Deputy Minister to the Premier December 11, 2017 . ... and lengthy deliberation Cabinet has made the difficult decision](https://reader036.fdocuments.us/reader036/viewer/2022070109/604563e4dfa5ed7d4008e1e4/html5/thumbnails/31.jpg)
Could the Minister of Finance Absorb Termination Costs?
• Central Government’s Consolidated Revenue Fund would take on the $4 billion of debt and recapitalize BC Hydro
• This would likely preserve BC Hydro’s status as a commercial entity
• But…
31
![Page 32: Site C - British Columbia · Technical Briefing Don Wright Deputy Minister to the Premier December 11, 2017 . ... and lengthy deliberation Cabinet has made the difficult decision](https://reader036.fdocuments.us/reader036/viewer/2022070109/604563e4dfa5ed7d4008e1e4/html5/thumbnails/32.jpg)
Having the Minister of Finance Absorb Termination Costs Would • Still entail a $4 billion loss in Government Reporting Entity
• Still involve $120-$150 million / year in interest costs that would have to be serviced
• Could lead to a credit rating downgrade, adding even more debt interest costs to taxpayers
• Crowd out room for new capital project spending • Schools, hospitals, housing, bridges, highways, etc.
32
![Page 33: Site C - British Columbia · Technical Briefing Don Wright Deputy Minister to the Premier December 11, 2017 . ... and lengthy deliberation Cabinet has made the difficult decision](https://reader036.fdocuments.us/reader036/viewer/2022070109/604563e4dfa5ed7d4008e1e4/html5/thumbnails/33.jpg)
What is $4 Billion Equivalent To?
66 secondary schools ($60 million each); or,
11 hospital projects similar to the North Island Hospitals (Province’s share $365 million); or,
12 highway projects similar to the Okanagan Valley Corridor Project (Province’s share $ 330 million); or,
3 Pattullo Bridges ($1.3 billion each).
33
![Page 34: Site C - British Columbia · Technical Briefing Don Wright Deputy Minister to the Premier December 11, 2017 . ... and lengthy deliberation Cabinet has made the difficult decision](https://reader036.fdocuments.us/reader036/viewer/2022070109/604563e4dfa5ed7d4008e1e4/html5/thumbnails/34.jpg)
VI. Concluding Comments
34
![Page 35: Site C - British Columbia · Technical Briefing Don Wright Deputy Minister to the Premier December 11, 2017 . ... and lengthy deliberation Cabinet has made the difficult decision](https://reader036.fdocuments.us/reader036/viewer/2022070109/604563e4dfa5ed7d4008e1e4/html5/thumbnails/35.jpg)
In Summary
• Very tough decision for Government
• Decision to proceed primarily driven by need to: • Minimize impacts on BC Hydro ratepayers
• Preserve the fiscal room to build schools, hospitals, housing, bridges etc.
35
![Page 36: Site C - British Columbia · Technical Briefing Don Wright Deputy Minister to the Premier December 11, 2017 . ... and lengthy deliberation Cabinet has made the difficult decision](https://reader036.fdocuments.us/reader036/viewer/2022070109/604563e4dfa5ed7d4008e1e4/html5/thumbnails/36.jpg)
Questions?
36
Questions?