Siitä pienestä erosta, mikä onkin iso · • John Lennon • Change Management – Change...
Transcript of Siitä pienestä erosta, mikä onkin iso · • John Lennon • Change Management – Change...
Siitä pienestä erosta, mikä onkin iso
Heikki J Mattila
Projektinhallintapäivä TTY:llä 19.08.2015
"projektit strategian jalkauttajina".
Heikki J. Mattila, Managing Consultant +358 50 482 1120 [email protected]
• Successful real program/ project manager, 20+ years including big strategic programs and projects
• Deep understanding of the Program and Project Management Methodology. Key player in PM methodology creation and implementation in three big companies
• Quality Assurance as a key thing in program/project success • Program and Project Management Coaching of 500 + programs and projects
We are Midagon
Founded 2006
Core competence…
Change leadership
experience
• Team of experienced professionals, each fully focused
on client work with no internal responsibilities.
• Owned and operated by partners
• Profitable and seeking strong growth from productized
service concepts.
Company
Business and technology
experience
Program and project
management capability
Sisällysluettelo
• Voisiko Byrokratia olla sinunkin ystäväsi?
• Plan carefully
• Miten se voi olla niin vaikeaa erottaa eri asioita toisistaan?
• Business Benefits Realization
• Johdon tuki ja Johdon tuki
• Please do not cheat yourself
• John Lennon
• Change Management – Change Control
• Please do not reinvent the Wheel
• Take the benefits of the company’s Project Management
methodology
• Kaikki totta, vaikka…
• Kysymykset ja vastaukset
Vain Turha Byrokratia
on turhaa!
Case: Training plan
Kaksi eri asiaa:
Byrokratia &
Turha Byrokratia
Byrokratia
- Turha Byrokratia
= Tarpeellinen Byrokratia
(Minimum Must concept)
If You Fail To Plan – You Plan To Fail
Pre-Study Plan
Please note: Large pre-study may need to be conducted as a project
Deliverable Responsible Deadline Review
by
Approval
by
Status Comment
Business Owner
nominated
Person responsible for
pre-study nominated
Measurable objectives
defined
Scope defined
Current State Analysis
done
Target State Definition
done
Business Case defined
Rough implementation
plan defined
Rough Solution and
a Proposal for the Go
approval created
By Whom
When
Quality
Assurance Status
Only One
Slide!
What
Pre-Study Plan
Please note: Large pre-study may need to be conducted as a project
Deliverable Responsible Deadline Review
by
Approval
by
Status Comment
Business Owner
nominated
Person responsible for
pre-study nominated
Measurable objectives
defined
Scope defined
Current State Analysis
done
Target State Definition
done
Business Case defined
Rough implementation
plan defined
Rough Solution and
a Proposal for the Go
approval created
Miten se voi olla niin vaikeaa erottaa?
• Current State Definition - Current State Analysis
• Current State Analysis - A Need for the Change
• Target State - Solution when in Target State
• Change - Business Benefits
• Change - Measurable Objectives
• Business Case - Business Benefits Realization
CS, CSA, TS, B/C, Objectives, Solution,
Current State (CS)
1. Current State Definition • There is something wrong with Process X,
which has an important role in the strategic capability 123.
• Process X lead time is 12 days
2. Current State Analysis • Competitors’ Lead time for the same
process is 5 days
• A Need for the Change We are too slow –> We lose customers Annually 15 M€ of sales is lost
Target State (TS)
3. Target State Definition
• We are faster than the competitors
4. Business Case: Faster lead time
-> More sales - > Business Benefits
• Lead time 6 days -> 1 M€ a year
• Lead time 5 days -> 2 M€ a year
• Lead time 4 days -> 15 M€ a year
5. Measurable Objectives
• Process X Lead time to be 4 days
• Project Closing Criteria: Lead time daily max 4 days for 2 months in a row
6. Solution
1. Ensin muutos
2. Sitten Benefits
5 days is not enough to pass
the Portfolio Steering Group
Project Charter defines the Business Owner’s needs
Project Charter, Business Benefit Realization
Key Achievement Status
Status of
Business Benefit
Realization
How Business Benefit Realization is
Measured? Approved change definition and business case is the
baseline for comparison in later phases
Project Initiated - First version of objectives and business case
Project Authorized Change definition and business case matching
objectives approved
Project Planned & Organized Plan available to achieve the change and
targeted business benefits
Process/Concept Ready Concept available to bring the targeted change
and business benefits
Working Solution Ready Solution available to bring the targeted change
and business benefits
Ready for Final Go-live Organization is ready in order to meet the
targeted change to reach the targeted benefits
Objectives Achieved Change is measured,
Targeted business benefits realized / started to
flow in
Project Closed Responsibility on business benefits realization
follow-up agreed and handed-over
Milestones Status
Missä vika jos Business Benefits ei realisoidu?
• ”Projektissa tietysti ja projektipäällikössä erityisesti”
• Kyllä useissa tapauksissa, mutta ei aina
B/C Quality Not done carefully Business Owner
Project Manager
B/C Quality Done carefully, but
wrong estimations of
the Benefits
Business Owner
Project Plan and
Execution Quality
Not done carefully Project Manager
Steering Group
Change Management
Quality
Not done
carefully/enough
Business Owner
Project Manager
Not enough skills when
needed
Not enough resources
available
Company Policy
Line Management
etc.
Missä vika jo Business Benefits ei toteudu
Väärä säästäminen
• Savings in the Resource Costs can be smaller than the lost of the Business
Benefits
• Particularly the company’s own key resources
• And especially if there are too many projects at the same time
All projects will be late
Business Benefits will realize late
Things changes round the project - Business Case does not fly any
more
No benefits at all, only costs will realize
Ilman kunnollista johdon tukea, erityisesti
johtoryhmää*) projektin on vaikea onnistua
15
*) Oikea johtoryhmä (pieni please) tai joissain tapauksissa vain Product Owner
Johtoryhmä
• Tukee
• Välittää
• Vaatii
• Hyväksyy
• Sitoutuu
• Act as
Change
Agents
Johtoryhmäkin
tarvitsee tukea
• Steering Group
Guidebook
• Coaching
• Meetings outside
the SG meetings
Case: APAC
Ilman yhteistä johtoryhmää projektin on
vaikea onnistua
Ei näin
Biz
IT
Ilman yhteistä johtoryhmää projektin on
vaikea onnistua
Projektitiimi ja johtoryhmä ovat samassa veneessä
Ja Business ja IT mahtuvat samaan veneeseen
Ja kyllä sinne mahtuvat Asiakas ja Toimittajakin
Kaikki tarvitaan
Business hyötyjen
realisoitumiseksi
R ’n’ R on tärkeää!
Roles and
Responsibilities
Ja
Rock ’n’ Roll
Quality of the Steering Group Decisions
• John Lennon
• Heikki J Mattila
Poor Steering Group
decisions are over!
If You Want It
Quality of the Steering Group Decisions
Please do not cheat yourself
Green = All done with good Review results
Red = Not completed or did not pass the Review
Yellow = Not completed and/or did not pass the Review
We should not have any Conditional approvals at all
20
Change
Management
On aivan eri asia kuin
Change Control
Change Management – Change Control
Projektipäällikkö on onnistunut
Change Managementissa, kun
projektin tuovan muutoksen tulevat
käyttäjät soittavat jatkuvasti ja
kysyvät: ”Koska me oikein saadaan
ruveta käyttämään sitä uutta hienoa
ratkaisua, minkä projekti tuo?”
Minimum Must
• Stakeholder Management Plan
• Change Impact Analysis
• Communication Plan
Change Control varmistaa
kontrolloidun muutoksen jo
hyväksyttyihin projektin tuotoksiin
(e.g. Project Scope, Schedule, Costs,
Process Definition)
Impact Analysis!
21
Tärkeää on, että yrityksessä/yksikössä on selvä yhtenäinen käsitys siitä
mikä on Change Management ja mikä on Change Control.
Miten muuten voi korostaa CM:n tärkeyttä, kun puolet käsittää sen väärin
Ota hyöty standardeista
• Templatet ovat ystäviäsi – Ne mahdollistavat sen, että voit käyttää kykysi,
aikasi ja energiasi siihen että projekti tuottaa Business Benefitit.
• Sitähän se Business Owner tilaa. Ei templatejä.
Please do not reinvent the Wheel
Case 1M€
How to ensure to take the benefits of the company’s
(unit’s) Project Management methodology
1. Provide strong visible Management support • From as high as needed
• “This is good”
• “We need this”
• “We all must use this “(All = management, SG, Program/project manager, portfolio manager etc.)
• ”Steering Group’s responsibility is to take care that we take the benefits of the Project Management Methodology”
• Coaching is available. Every project to contact the coach as the first thing when starting any work for the program/project
• Refer to this support when needed
2. Proper Change Management • Stakeholder Analysis
• Change Impact Analysis
• What does it mean to company, my unit my program/project, to each role in the program /project
• Communication Plan
3. Proper training • Normal training actions: Plan, training material preparation, training arrangements, feedback collection, enhancements
• Measure the training: Sessions held, trainees attended the trainings
• Measure the learning
4. Provide the Coaching • Do the Coaching Concept
• Nominate the Coaches, ensure there is allocated time for the coaching
• Arrange the Coaching network management
• Coach
Tarpeeksi hyvä riittää
Oikein käytetty
menetelmä takaa
onnistuneen projektin,
mikä jalkauttaa
strategian
Yhteenveto
Jos haluat menestyvän projektin strategian jalkauttamiseen, niin
• Suunnittele projekti huolella – Tee projekti suunnitelman mukaan
– Riippumatta yksikön käytössä olevasta menetelmästä
• Varmista business hyötyjen toteutuminen koko projektin ajan
• Varmista johdon voimakas tuki
• Älä narraa itseäsi eikä muita
• Tee huolella Change Management – Change Control
• Ota kaikki hyödyt yrityksen projektihallintamenetelmästä
• Älä keksi pyörää uudelleen. Keskity projektilta tilatun muutoksen
tuottamiseen
• Vain turha byrokratia on turhaa
• Muista, että hymy ei ole tehokkuuden vastakohta