Shri. Narendra Modi's Kalpsar project

39
PRESENTATION ON GULF OF KHAMBHAT DEVELOPMENT PROJECT(WR) alpasar as a prospective Water solution lpasar as a prospective Water solution - Saurashtra A Truly Matchless Project

Transcript of Shri. Narendra Modi's Kalpsar project

Page 1: Shri. Narendra Modi's Kalpsar project

PRESENTATION ON

GULF OF KHAMBHAT DEVELOPMENT PROJECT(WR)

Kalpasar as a prospective Water solutionKalpasar as a prospective Water solution - Saurashtra

A Truly Matchless Project

Page 2: Shri. Narendra Modi's Kalpsar project

MISSION MISSION

Page 3: Shri. Narendra Modi's Kalpsar project

VISIONVISION

To create world’s largest fresh water reservoir

in sea, by constructing 30 km long dam in the

Gulf of Khambhat, to store more than 10,000

MCM of surface water, i.e. 25% of volume of

State’s average annual rain water inflow.

Page 4: Shri. Narendra Modi's Kalpsar project
Page 5: Shri. Narendra Modi's Kalpsar project
Page 6: Shri. Narendra Modi's Kalpsar project
Page 7: Shri. Narendra Modi's Kalpsar project

Per Capita Availability of Water

Bhuj

MEHSANA

PALANPUR

GANDHINAGAR

GODHRAKHEDA

VADODARA

BHARUCH

BHAVNAGAR

AMRELIJUNAGADH

RAJKOTJAMNAGAR

SURENDRANAGAR

RANN OF KUTCH

LITTLE RANN

AHMEDABAD

SURAT

DANGVALSAD

KutchNorth

Gujarat

Saurashtra

Central & South

Gujarat

730 m3/Annum 343 m3/Annum

540 m3/Annum

1880 m3/Annum

Note : As per M. Falkenmark if renewable freshwater availability falls below 1000 M3 per capita, water supply begins to hamper health, economy growth and human well being.

Per Capita Availability of Water (Year 2001)

Page 8: Shri. Narendra Modi's Kalpsar project
Page 9: Shri. Narendra Modi's Kalpsar project

Why Project is required ?Why Project is required ?

Page 10: Shri. Narendra Modi's Kalpsar project

1. Gujarat is a water scarce state, with 6.39% of geographical area, 5% of population & only 2% of water resources.

2. 71% of water resources available in 25% of geographical area of central & south Gujarat.

3. In Saurashtra region per capita water availability is only 540 M3/annum against 1700 m3/annum minimum requirement.

4. In Saurashtra region,only 15 lakh ha agricultural land will cover under irrigation (including Sardar Sarovar Project), against 42 lakh ha agricultural land. Hence, 27 lakh ha agricultural land will remain rainfed.

Page 11: Shri. Narendra Modi's Kalpsar project

5. The excessive pumping of groundwater resulted in intrusion of saline water up to 10 km of entire coastal belt of Saurashtra.

6. The water storage capacity of Gujarat state is 20480 Mm3 in 196 medium & major reservoirs, against the total rainwater availability of 38000 MCM per annum.

7. Non availability of any suitable site for major irrigation scheme in the state, the “Gulf of Khambhat Development Project” is the only option available to store 10,000 MCM rainwater.

Page 12: Shri. Narendra Modi's Kalpsar project
Page 13: Shri. Narendra Modi's Kalpsar project

GULF OF KHAMBHAT DEVELOPMENT PROJECT (W.R.)

Page 14: Shri. Narendra Modi's Kalpsar project
Page 15: Shri. Narendra Modi's Kalpsar project

1 Length of dam between two shores of Gulf Approx. 30 km2 Top of dam 100m wide

10 lane road + railway3 Reservoir features: (i) Full Reservoir Level(FRL) (ii) Maximum Water Level(MWL) (iii) Minimum Draw Down Level(MDDL) (iv) Live storage (v) Storage between MWL & FRL (vi) Reservoir area

(+) 3.0m(+) 4.0m(-) 4.0m10500 Mm3 1900 Mm3 2000 Sq.km

4 Bhadbhut Barrage & Narmada Diversion Canal

(i) Barrage including earthen dykes(ii) Narmada Diversion Canal

DischargeLength

10 to 12 km

100000 cusecs32 km

Salient features (Tentative)

Page 16: Shri. Narendra Modi's Kalpsar project

5 Irrigation Command(i) Water envisaged for irrigation 6558 Mm3

(ii) Envisaged three garland canal Discharge 4000 to 6000 cusecs

Length 600 to 700 km

Elevation EL50 m, EL80 m, EL100 m

6 Life of reservoir 400 to 500 years7 Ground Water Quality

Improvement in Catchment area

7,00000 Ha

8 Land recover between EL + 5.0m to EL+ 8.0m

150000 to 200000 ha

Page 17: Shri. Narendra Modi's Kalpsar project

9 Reduction in distance Bhavnagar – Dahej 200 km

Bhavnagar – South Gujarat 225 km10 Ports Bhavnagar port will be

rejuvenate, Dahej port will be outside of reservoir, New ports are proposed at down stream of dam.

11 Rivers debouching in the reservoir

Sabarmati, Mahi, Dhadhar, Narmada (through diversion canal), Limbadi Bhogavo, Sukhbhadar, Utavali, Keri, and Vagad

12 Construction of dam 5 to 7 years

Page 18: Shri. Narendra Modi's Kalpsar project

• Earlier the dam was envisaged between Ghogha to Hansot having length of 64 km. wherein tidal power component was combined alongwith development of fresh water reservoir in the Gulf.

• As per pre-feasibility report of the project, the cost of project was estimated of Rs. 53,000 crore (base year 1998) in which the tidal power component was Rs.33000 crore. Considering, average 8% inflation per annum present cost works out to approximate Rs.1,40,000 crore, in which the tidal power component is Rs.86,000 crore.

Estimated Cost of the Project

Page 19: Shri. Narendra Modi's Kalpsar project

• Recently, tidal power component is delinked from the project and the dam alignment is shifted northward by 15 km, leads to reduction of length of dam from 64 km to 30 km & height of dam is also reduced from 55 m to 35 m.

• Considering above the approximate project cost at present is Rs. 50,000 to 60,000 crore.

Page 20: Shri. Narendra Modi's Kalpsar project

Benefits of the ProjectBenefits of the Project

Page 21: Shri. Narendra Modi's Kalpsar project

GULF OF KHAMBHAT DEVELOPMENT PROJECT (W.R.)

Irrigation Benefit

Page 22: Shri. Narendra Modi's Kalpsar project

10.54 lakh ha. land in 39 talukas of 6 districts of Saurashtra region will get irrigation facilities including rejuvenation of rivers and filling of more than 60 existing dams as well as check dams, tidal regulators, spreading channels permanently.

Irrigation BenefitIrrigation Benefit

Page 23: Shri. Narendra Modi's Kalpsar project

PerceivedPerceived Agricultural BenefitsAgricultural Benefits

Page 24: Shri. Narendra Modi's Kalpsar project

Transportation BenefitsTransportation Benefits

Page 25: Shri. Narendra Modi's Kalpsar project

• Substantial saving in travel time and fuel due to reduction in distance by about 200 km between Bhavnagar and Surat.

• Surat is one of the fastest growing city in the country and the diamond oriented business hub of the world.

• Most of the diamond workers (more than 10 lakhs) are migrated from Saurashtra (Mostly, from Bhavanagr, Amreli district).

Transportation BenefitTransportation Benefit

Page 26: Shri. Narendra Modi's Kalpsar project

• After the completion of dam and Bhadbhut Barrage, the route from Bhavnagar to Surat will be Bhavnagar—Dahej—Hansot—Olpad—Surat.

• New coastal highway will be developed to connect present petro-chemical hub Hazira (Surat) to future petro-chemical hub PCPIR (Dahej).

• 10 lane road is proposed on the top of the dam. 75000 vehicles per day is estimated for year 2020, and 1,00,000 vehicles per day for year 2030.

Page 27: Shri. Narendra Modi's Kalpsar project

• The toll-tax generation is estimated approximately Rs. 1500 crore for year 2020 and Rs. 2000 crore for year 2030.

• Considering 10% I.R.R., Capital investment of Rs.15,000 crore to Rs. 20,000 crore may likely available from transport component (30% to 40% cost of the project)

Page 28: Shri. Narendra Modi's Kalpsar project

• Gulf of Khambhat is one of the Gulf in world having maximum tide of 11 m and the average tide of 8.8 m .

• During the high tide and flood in Narmada, Mahi, Sabarmati river etc., the sea water rise up to level of +7.0 m to +8.0 m from MSL.

• After closure of the Gulf of Khambhat, land which is frequently submerged during high tide will be permanently opened.

• About 1.5 to 2 lakh ha land along the periphery of reservoir will be opened which can be used for the project development.

Land Reclamation BenefitsLand Reclamation Benefits

Page 29: Shri. Narendra Modi's Kalpsar project
Page 30: Shri. Narendra Modi's Kalpsar project

Land recovery (As per BISAG Study)Land recovery (As per BISAG Study)

Page 31: Shri. Narendra Modi's Kalpsar project

Value Addition Of LandValue Addition Of Land

Projects in vicinity of Kalpasar project

• Dholera SIR • Fedara International Airport • PCPIR at Dahej• SEZ, GIDC etc. • Delhi- Mumbai Industrial Corridor

Page 32: Shri. Narendra Modi's Kalpsar project

• Proposed 10 lane road for Ahmedabad-Bhavnagar route

• 2000 sq. km world’s biggest fresh water reservoir (in sea) with 6-lane periphery road of 270 km long

• Solar and Wind power, Tourism, Bio-fuel park, Transportation, Fisheries etc. project components / benefits

Page 33: Shri. Narendra Modi's Kalpsar project

In coastal region of Saurashtra and Central Gujarat, saline ground water will be converted into sweet water, resulting reduction in inland salinity

Benefit -Reduction in Salinity Benefit -Reduction in Salinity

Page 34: Shri. Narendra Modi's Kalpsar project

Benefit- Port Development on d/s of Dam

Project presents highly attractive locational attributes for port development downstream of the dam such as increased water level, lower current velocity, reduced sedimentation

Page 35: Shri. Narendra Modi's Kalpsar project

NIO MODEL STUDY

i. Model study results show that after the construction of the dam the tide level increases at all the port locations.

i. The currents decrease at the locations near to the dam (Bhavnagar, Ghoga).

i. Sediment transport results indicate that the sediment concentration reduces in the southern gulf (outside the dam) with a maximum reduction at Dahej and Gogha.

Bhavnagar port will be rejuvenated, therefore this region will be speedily developed

Page 36: Shri. Narendra Modi's Kalpsar project

Wind and solar power would be generated which will also be used for lifting of fresh water of reservoir.

Benefits- Generation of Benefits- Generation of Non-conventional EnergyNon-conventional Energy

Page 37: Shri. Narendra Modi's Kalpsar project

Wind EnergyWind EnergyWind energy is planned to be used for pumping of irrigation water. Approximately 250 crore unit will be required for lifting irrigation water. As per Suzlon study, 1600 MW with an estimated cost of about Rs. 9000 crore can be generated by installing wind mills/ solar units. Wind mill will have added benefit of its installation after dam construction.

Page 38: Shri. Narendra Modi's Kalpsar project

Benefits-fisheries DevelopmentBenefits-fisheries Development

• Fish production to the tune of 3,00,000 tonnes per annum amounting to Rs.22,500 Million at full development stage

• Direct employment to approximately 1,00,000 beneficiaries and indirect employment to approximately 3,00,000 beneficiaries.