SECTION 033150 - CONCRETE PART 1 – GENERAL 1.01 ...

26
MAHG-101089 / MAHG-101089 Building 4430 4431 033150 - 1 CONCRETE SECTION 033150 - CONCRETE PART 1 – GENERAL 1.01 DESCRIPTION A. Scope: Contractor shall provide all labor, materials, equipment and incidentals as shown, specified and required to furnish and install cast-in-place concrete, reinforcement and related materials. B. Coordination: Review installation procedures under other Sections and coordinate the installation of items that must be installed in the concrete. 1.02 QUALITY ASSURANCE A. Source Quality Control: 1. Concrete Testing Service: a. Contractor shall employ acceptable testing laboratory to perform materials evaluation, testing and design of concrete mixes. b. Owner’s laboratory shall evaluate concrete delivered to and placed at the site. 2. Certificates, signed by concrete producer and Contractor, may be submitted in lieu of material testing when acceptable to Engineer. B. Quality Control: Perform sampling and testing during concrete placement, as follows: 1. Sampling: ASTM C 172. 2. Slump: ASTM C 143, one test for each load at point of discharge. 3. Air Content: ASTM C 31, one for each set of compressive strength specimens. 4. Compressive Strength: ASTM C 39, one set for each 50 cubic yards or fraction thereof for each class of concrete; a minimum of one for each pour of structural concrete; 1 specimen tested at 7 days, 2 specimens tested at 28 days. When the total quantity of concrete is less than 50 cubic yards, the strength tests may be waived by Engineer if field experience indicates evidence of satisfactory strength. 5. Reference Standards: Comply with the applicable provisions and recommendations of the following, except as otherwise shown or specified. 6. ACI 301, Specifications for Structural Concrete for Building (includes ASTM Standards referred to herein except ASTM A 36). 7. ACI 347, Recommended Practice for Concrete Formwork. 8. ACI 304, Recommended Practice for Measuring, Mixing, Transporting, and Placing Concrete. 9. ACI 315, Manual of Standard Practice for Detailing Reinforced Concrete Structures. 10. ACI 305, Recommended Practice for Hot Weather Concreting. 11. ACI 306, Recommended Practice for Cold Weather Concreting 12. ASTM A 36, Structural Steel. 13. Concrete Reinforcing Steel Institute, Manual of Standard Practice, include ASTM Standards referred herein. 1.03 SUBMITTALS A. Samples: Submit samples of materials as specified and may be requested by the Engineer including names, sources and descriptions. B. Shop Drawings: Submit the following for approval in accordance with the General Requirements and with additional requirements as specified. 1. Copies of manufacturer's specifications with application and installation instructions for proprietary materials and items, including admixtures and bonding agents. 2. Drawings for fabrication, bending, and placement of concrete reinforcement. Comply with ACI 315, Chapters 1 thru 8. For walls, show elevations to a minimum scale of 3 inch to 1 foot. Show bar schedules, stirrup spacing, diagrams of bent bars, arrangements and assemblies, as required for the fabrication and placement of concrete reinforcement. 3. List of concrete materials and concrete mix designs proposed for use. Include the results of all tests performed to qualify the materials and to establish the mix designs in

Transcript of SECTION 033150 - CONCRETE PART 1 – GENERAL 1.01 ...

MAHG-101089 / MAHG-101089 Building 4430 4431

033150 - 1 CONCRETE

SECTION 033150 - CONCRETE PART 1 – GENERAL 1.01 DESCRIPTION

A. Scope: Contractor shall provide all labor, materials, equipment and incidentals as shown, specified and required to furnish and install cast-in-place concrete, reinforcement and related materials.

B. Coordination: Review installation procedures under other Sections and coordinate the installation of items that must be installed in the concrete.

1.02 QUALITY ASSURANCE A. Source Quality Control:

1. Concrete Testing Service: a. Contractor shall employ acceptable testing laboratory to perform materials evaluation,

testing and design of concrete mixes. b. Owner’s laboratory shall evaluate concrete delivered to and placed at the site.

2. Certificates, signed by concrete producer and Contractor, may be submitted in lieu of material testing when acceptable to Engineer.

B. Quality Control: Perform sampling and testing during concrete placement, as follows: 1. Sampling: ASTM C 172. 2. Slump: ASTM C 143, one test for each load at point of discharge. 3. Air Content: ASTM C 31, one for each set of compressive strength specimens. 4. Compressive Strength: ASTM C 39, one set for each 50 cubic yards or fraction thereof for

each class of concrete; a minimum of one for each pour of structural concrete; 1 specimen tested at 7 days, 2 specimens tested at 28 days. When the total quantity of concrete is less than 50 cubic yards, the strength tests may be waived by Engineer if field experience indicates evidence of satisfactory strength.

5. Reference Standards: Comply with the applicable provisions and recommendations of the following, except as otherwise shown or specified.

6. ACI 301, Specifications for Structural Concrete for Building (includes ASTM Standards referred to herein except ASTM A 36).

7. ACI 347, Recommended Practice for Concrete Formwork. 8. ACI 304, Recommended Practice for Measuring, Mixing, Transporting, and Placing

Concrete. 9. ACI 315, Manual of Standard Practice for Detailing Reinforced Concrete Structures. 10. ACI 305, Recommended Practice for Hot Weather Concreting. 11. ACI 306, Recommended Practice for Cold Weather Concreting 12. ASTM A 36, Structural Steel. 13. Concrete Reinforcing Steel Institute, Manual of Standard Practice, include ASTM

Standards referred herein. 1.03 SUBMITTALS

A. Samples: Submit samples of materials as specified and may be requested by the Engineer including names, sources and descriptions.

B. Shop Drawings: Submit the following for approval in accordance with the General Requirements and with additional requirements as specified. 1. Copies of manufacturer's specifications with application and installation instructions for

proprietary materials and items, including admixtures and bonding agents. 2. Drawings for fabrication, bending, and placement of concrete reinforcement. Comply with

ACI 315, Chapters 1 thru 8. For walls, show elevations to a minimum scale of 3 inch to 1 foot. Show bar schedules, stirrup spacing, diagrams of bent bars, arrangements and assemblies, as required for the fabrication and placement of concrete reinforcement.

3. List of concrete materials and concrete mix designs proposed for use. Include the results of all tests performed to qualify the materials and to establish the mix designs in

MAHG-101089 / MAHG-101089 Building 4430 4431

033150 - 2 CONCRETE

accordance with ACI 301, 3.9. Submit written report to Engineer for each proposed concrete mix at least 15 days prior to start of Work. Do not begin concrete production until mixes have been reviewed and are acceptable to Engineer. Mix designs may be adjusted when material characteristics, job conditions, weather, test results or other circumstances warrant. Do not use revised concrete mixes until submitted to and accepted by Engineer.

C. Laboratory Test Reports: Submit copies of laboratory test reports for concrete cylinders, materials and mix design tests. Production of concrete to comply with specified requirements is the responsibility of the Contractor.

1.04 PRODUCT DELIVERY, STORAGE AND HANDLING A. Deliver concrete reinforcement materials to the site bundled, tagged and marked. Use tags

indicating bar size, lengths, and other information corresponding to markings shown on placement diagrams.

B. All materials used for concrete must be kept clean and free from all foreign matter during transportation and handling and kept separate until measured and placed in the mixer. Bins or platforms having hard clean surfaces shall be provided for storage. Suitable means shall be taken during hauling, piling and handling to insure that segregation of the coarse and fine aggregate particles does not occur and the grading is not affected.

PART 2 – PRODUCTS 2.01 CONCRETE MATERIALS

A. Portland Cement: ASTM C 150, Type I. B. Aggregates: ASTM C 33.

1. Fine Aggregate: Clean, sharp, natural sand free from loam, clay, lumps or other deleterious substances. Dune sand, bank run sand and manufactured sand are not acceptable. a. Coarse Aggregate: Clean, uncoated, processed aggregate containing no clay, mud,

loam, or foreign matter, as follows: b. Crushed stone, processed from natural rock or stone. c. Washed gravel, either natural or crushed. Use of slag and pit or bank run gravel is

not permitted. 2. Coarse Aggregate Size: Size to be ASTM C 33, Nos. 57 or 67, unless permitted otherwise

by Engineer. C. Water: Clean, potable. D. Air-Entraining Admixture: ASTM C 260. E. Water-Reducing Admixture: ASTM C 494. Only use admixtures which have been tested and

accepted in mix designs. F. Slump Limits: Proportion and design mixes to result in concrete slump at the point of placement

of not less than one inch and not more than four inches. 2.02 FORM MATERIALS

A. Provide form materials with sufficient stability to withstand pressure of placed concrete without bow or deflection.

B. Exposed Concrete Surfaces: Acceptable panel-type to provide continuous, straight, smooth, as-cast surfaces. Use largest practical sizes to minimize form joints.

C. Unexposed Concrete Surfaces: Suitable material to suit project conditions. D. Provide ¾ inch chamfer at all exposed corners.

2.03 REINFORCING MATERIALS A. Reinforcing Bars: ASTM A 615, Grade 60. B. Welded Wire Fabric: ASTM A 185. C. Steel Wire: ASTM A 82.

MAHG-101089 / MAHG-101089 Building 4430 4431

033150 - 3 CONCRETE

D. Supports for Reinforcement: Bolsters, chairs, spacers and other devices for spacing, supporting and fastening reinforcement in place. 1. Use wire bar type supports complying with CRSI recommendations, except as specified

below. Do not use wood, brick, or other unacceptable materials. 2. For slabs on grade, use supports with sand plates or horizontal runners where base

materials will not support chair legs. E. For all concrete surfaces, where legs of supports are in contact with forms, provide supports

complying with CRSI, Manual of Standard Practice as follows: Either hot-dip galvanized, plastic protected or stainless steel legs.

2.04 GROUT A. Non-metallic, 100 percent solids, high strength epoxy grout.

1. Use clean well graded sand with epoxy resins suitable for use on dry or damp surfaces. 2. Product and Manufacturer; Provide one of the following:

a. Euco High Strength Grout by the Euclid Chemical Company. b. Sikadur 42 Grout by Sika Chemical Company. c. Five Star Epoxy Grout by U.S. Grout Corporation. d. Or equal.

B. Nonshrink, Nonmetallic Grout: 1. Premixed nonstaining cementitious grout requiring only the addition of water at the job

site. 2. Product and Manufacturer: Provide one of the following:

a. Euco N-S by the Euclid Chemical Company. b. Masterflow 713 by Master Builders Company. c. Five Star by U.S. Grout Corporation. d. Or equal.

C. Ordinary Cement-Sand Grout: 1. Except where otherwise specified use 1 part cement to 3 parts sand complying with the

following: a. Cement: ASTM C 150, Type I. b. Sand: ASTM C 33.

2.05 EXPANSION JOINTS A. Expansion joint filler shall be preformed expansion joint filler complying with ASTM D1752,

Type II cork. B. Expansion joint sealer:

1. Exterior and Interior Joints in Horizontal Planes: Two-Component Polyurethane Sealant: a. Polyurethane-based, 2-part elastomeric sealant complying with the following:

1) FS TT-S-00227, Type 1 (self-leveling) Class A. 2) Water Immersion Bond, FS TT-S-00227; Elongation of 25 percent with no

adhesive failure. 3) Hardness (Standard Conditions), ASTM C 661: 30-40. 4) Stain and Color Change, FS TT-S-00227 and ASTM C 510: No discoloration or

stain. 5) Accelerated Aging, ASTM C 793: No change in sealant characteristics after 250

hours in weatherometer. b. Product and Manufacturer: Provide one of the following:

1) Sonolastic Paving Joint Sealant by Sonneborn Division of Contech Incorporated. 2) Vulkem 255 by Mameco International. 3) Or equal.

2.06 WATERSTOPS A. Reference Standard: CRD-C 572.

MAHG-101089 / MAHG-101089 Building 4430 4431

033150 - 4 CONCRETE

1. Construction Joints: A dumbbell shape polyvinyl chloride waterstop with the following minimum requirements: a. Thickness: 3/8 inch. b. Length: Six inches. c. Bulb diameter: 3/4 inch.

2. Expansion Joints: A dumbbell shape polyvinyl chloride waterstop with the following minimum requirements: a. Thickness: 3/8 inch. b. Length: Nine inches. c. Bulb diameter: 3/4 inch.

B. Product and Manufacturer: Provide waterstops as manufactured by one of the following: 1. Vulcan Products, Inc. 2. W. R. Meadows, Inc. 3. Or equal.

PART 3 – EXECUTION 3.01 INSPECTION

A. Contractor and his installer shall examine the substrate and the conditions under which Work is to be performed and notify ENGINEER of unsatisfactory conditions. Do not proceed with the Work until unsatisfactory conditions have been corrected in a manner acceptable to Engineer.

3.02 FORMWORK A. Formwork: Construction so that concrete members and structures are correct size, shape,

alignment, elevation and position, complying with ACI 347. B. Provide openings in formwork to accommodate Work of other trades. Accurately place and

securely support items built into forms. C. Clean and adjust forms prior to concrete placement. Apply form release agents or wet forms, as

required. Retighten forms during and after concrete placement if required to eliminate mortar leaks.

3.03 REINFORCEMENT, JOINTS AND EMBEDDED ITEMS A. Comply with the applicable recommendations of specified codes and standards, and ACI

Manual No. SP-66, latest edition, for details and methods of reinforcement placement and supports.

B. Clean reinforcement to remove loose rust and mill scale, earth, ice, and other materials which reduce or destroy bond with concrete.

C. Position, support, and secure reinforcement against displacement during formwork construction or concrete placement. Locate and support reinforcing by metal chairs, runners, bolsters, spacers and hangers, as required. 1. Place reinforcement to obtain the minimum concrete converges as shown and as

specified in ACI 318. Arrange, space, and securely tie bars and bar supports together with 16 gauge wire to hold reinforcement accurately in position during concrete placement operations. Set with ties so that twisted ends are directed away from exposed concrete surfaces.

2. Reinforcing steel shall not be secured to forms with wire, nails or other ferrous metal. Metal supports subject to corrosion shall not touch formed or exposed concrete surfaces.

D. Provide sufficient numbers of supports of strength required to carry reinforcement. Do not place reinforcing bars more than 2 inches beyond the last leg of any continuous bar support. Do not use supports as bases for runways for concrete conveying equipment and similar construction loads.

E. Splices: Provide standard reinforcement splices by lapping ends, placing bars in contact, and tying tightly with wire. Comply with requirements for minimum lap of spliced bars.

F. Install welded wire fabric in as long lengths as practical, lapping at least one mesh.

MAHG-101089 / MAHG-101089 Building 4430 4431

033150 - 5 CONCRETE

G. Concrete shall not be placed until the reinforcing steel is inspected and permission for placing concrete is granted by Engineer. All concrete placed in violation of this provision will be rejected.

H. Joints: Provide construction, isolation, and control joints as indicated or required. Locate construction joints so as to not impair the strength and appearance of the structure. Place isolation and control joints in slabs on ground to stabilize differential settlement and random cracking.

I. Installation of Embedded Items: Set and build into the Work anchorage devices and embedded items required for other Work that is attached to, or supported by cast-in-place concrete. Use setting diagrams, templates and instructions provided under other Sections and other contracts for locating and setting. Refer also to Paragraph 1.01.B., Coordination, above.

J. Waterstops: 1. General:

a. Comply with ACI 301, Chapter 6, and as specified below. All joints shall be made in accordance with manufacturer's instructions.

b. Obtain Engineer's approval for waterstop locations not shown. c. Provide waterstops in all foundations, tanks and other substructures up to an

elevation at least 12 inches above grade or to an elevation at least 12 inches above liquid level in tanks, whichever is higher, except where otherwise shown or noted.

2. Polyvinyl Chloride Waterstop: a. Tie waterstop to reinforcement so that it is securely and rigidly supported in the

proper position during concrete placement. Contin-uously inspect waterstops during concrete placement to insure their proper positioning.

b. Waterstops shall be fused using equipment as supplied by or recom-mended by the manufacturer.

c. Where required, weld polyvinyl chloride waterstop to steel waterstop by gently heating while applying pressure to the two materials. Use a steel plate and two “C” clamps to apply the pressure and a propane torch to apply the heat. The polyvinyl chloride waterstop shall be clamped between the steel waterstop and the steel plate which is held in place by the two "C" clamps. As heat is applied to the steel waterstop tighten the "C" clamps. Heat for approximately 15 minutes at a temperature just enough to make the polyvinyl chloride "runny" and the weld complete. After cooling remove the "C" clamps and plate. Engineer must approve polyvinyl chloride before embedding in concrete.

3.04 CONCRETE AND PLACEMENT A. Proportioning and Design of Mix:

1. Minimum compressive strength at 28 days: 4000 psi. 2. Maximum water cement ratio by weight: 0.45. 3. Minimum cement content: 564 pounds per cubic yard. 4. Normal weight: 145 pounds per cubic foot. 5. Use air-entraining admixture in all concrete: Provide not less than 4 percent nor more than

8 percent entrained air for concrete exposed to freezing and thawing, and from 2 percent to 4 percent for other concrete.

6. Calcium Chloride: Do not use calcium chloride in concrete, unless otherwise authorized in writing by the Engineer. Do not use admixtures containing calcium chloride.

B. Job-Site Mixing: Use drum type batch machine mixer, mixing not less than 3 minutes for one cubic yard or smaller capacity. Increase mixing time at least 1 minute for each additional cubic yard or fraction thereof.

C. Ready-Mixed Concrete: ASTM C 94. D. Concrete Placement: Comply with ACI 304, placing concrete in a continuous operation within

planned joints or sections. Do not begin placement until work of other trades affecting concrete is completed.

MAHG-101089 / MAHG-101089 Building 4430 4431

033150 - 6 CONCRETE

E. Consolidate placed concrete using mechanical vibrating equipment with hand rodding and tamping, so that concrete is worked around reinforcement and other embedded items and into all parts of forms.

F. Protect concrete from physical damage or reduced strength due to weather extremes during mixing, placement, and curing. 1. In cold weather comply with ACI 306. 2. In hot weather comply with ACI 305.

3.05 QUALITY OF CONCRETE WORK A. Make all concrete solid, compact and smooth, and free of laitance, cracks and cold joints. B. Cut out and properly replace to the extent ordered by the Engineer, or repair to the satisfaction

of the Engineer, surfaces which contain cracks or voids, are unduly rough, or are in any way defective. Patches or plastering will not be acceptable.

C. Repair, removal, and replacement of defective concrete as ordered by the Engineer shall be at no additional cost to the Owner.

3.06 CURING A. Begin initial curing after placing and finishing concrete as soon as free water has disappeared

from exposed surfaces. Where possible, keep continuously moist for not less than 72 hours. Continue curing use of moisture-retaining cover or membrane-forming curing compound. Cure formed surfaces by moist curing until forms are removed. Provide protection as required to prevent damage to exposed concrete surfaces.

B. Forms on structural walls shall be left in place for a minimum of 72 hours unless a cylinder breaks indicating the strength of the concrete has reached 75 percent of design strength.

C. Forms on structural floors and ceiling shall be left in place until a cylinder break indicates the strength of the concrete has reached 85 percent of design strength.

3.07 FINISHES A. Finish:

1. After placing concrete slabs, do not work the surface further until ready for floating. Begin floating when the surface water has disappeared or when the concrete has stiffened sufficiently. Check and level the surface plane to a tolerance not exceeding 3 inch in 10 feet when tested with a 10 foot straightedge placed on the surface at not less than 2 different angles. Cut down high spots and fill all low spots. Uniformly slope surfaces to drains. Immediately after leveling, refloat the surface to a uniform, smooth, granular texture.

2. After floating, begin the first trowel finish operation using a trowel. Begin final troweling when the surface produces a ringing sound as the trowel is moved over the surface.

3. Consolidate the concrete surface by the final hand troweling operation. Finish shall be free of trowel marks, uniform in texture and appearance, and with a surface plane tolerance not exceeding c inch in 10 feet when tested with a 10 foot straight edge. Grind smooth surface defects.

4. Use trowel finish for the following: Interior exposed slabs unless otherwise shown or specified.

5. Apply non-slip broom finish to exterior concrete slab and elsewhere as shown on the Drawings.

3.08 GROUT PLACEMENT A. General:

1. Place grout as shown and in accordance with manufacturer's instructing. If manufacturer's instructions conflict with the Specifications do not proceed until the Engineer provides clarification.

2. Drypacking will not be permitted.

MAHG-101089 / MAHG-101089 Building 4430 4431

033150 - 7 CONCRETE

3. Manufacturer's of proprietary products shall make available upon 72 hours notification the services of a qualified, full-time employee to aid in assuring proper use of the product under job conditions.

4. Placing grout shall conform to the temperature and weather limitations described in Paragraph 3.04 above.

3.09 WATERTIGHTNESS A. Each water-retaining structure (those which are intended to hold a liquid) shall be filled and

tested for leaks by the Contractor with clean water prior to surface coating or painting. Leaks shall be repaired by the Contractor. The procedure and manner in which leaks are repaired shall meet the approval of the Engineer. All costs associated with the testing and repair of leaks shall be at the expense of the Contractor. Prior to beginning of the leakage test, the structure shall be filled to the highest working water level and allowed to stand for a period of 24 hours to allow for absorption.

B. Leakage limitations shall be as follows: C. All water visibly flowing through a concrete wall shall constitute a leak and shall be repaired by

pumping and sealing the crack with a NSF-approved for potable water contact material. D. Damp areas not exceeding one percent of the total wall wetted area and not having visible

seepage shall be conditionally acceptable subject to all said dampness being eliminated by application of the water side surface treatment as may be specified. In the absence of a specified water side surface treatment or where said treatment does not eliminate wall dampness, the water side of the wall shall be prepared in accordance with the manufacturer's instructions and a NSF approved for potable water contact epoxy concrete surface coating applied.

E. All leakage testing shall be performed prior to backfill. F. To check for leakage through the tank bottoms, the fall in surface water level during tank testing

shall be measured and shall not exceed 0.5 inch in a 24 hour period, providing allowance for evaporation at a rate approved by the Engineer. Visual leaks, either flowing or damp areas, observed during the filling, absorption, or test periods shall be marked and locations recorded and repaired.

END OF SECTION

MAHG-101089 / MAHG-101089Building 4430 4431

055000 - 1 METAL FABRICATIONS

SECTION 055000 - METAL FABRICATIONSPART 1 GENERAL1.01 SECTION INCLUDES

A. Shop fabricated steel items.B. Steel Lintels (galvanized)C. Steel Handrails (galvanized)

1.02 RELATED REQUIREMENTSA. Section 079005 - Joint SealersB. Section 099000 - Painting and Coating: Paint finish.

1.03 REFERENCE STANDARDSA. ASTM A36/A36M - Standard Specification for Carbon Structural Steel; 2012.B. ASTM A53/A53M - Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated,

Welded and Seamless; 2012.C. ASTM A123/A123M - Standard Specification for Zinc (Hot-Dip Galvanized) Coatings on Iron and

Steel Products; 2013.D. ASTM A283/A283M - Standard Specification for Low and Intermediate Tensile Strength Carbon

Steel Plates; 2013.E. ASTM A307 - Standard Specification for Carbon Steel Bolts, Studs, and Threaded Rod 60 000

PSI Tensile Strength; 2012.F. ASTM A325 - Standard Specification for Structural Bolts, Steel, Heat Treated, 120/105 ksi

Minimum Tensile Strength; 2010.G. ASTM A325M - Standard Specification for Structural Bolts, Steel, Heat Treated 830 MPa

Minimum Tensile Strength (Metric); 2013.H. ASTM A653/A653M - Standard Specification for Steel Sheet, Zinc-Coated (Galvanized) or

Zinc-Iron Alloy-Coated (Galvannealed) by the Hot-Dip Process; 2013.I. ASTM A1011/A1011M - Standard Specification for Steel, Sheet and Strip, Hot-Rolled, Carbon,

Structural, High-Strength Low-Alloy, High-Strength Low-Alloy with Improved Formability, andUltra-High Strength; 2014.

J. AWS A2.4 - Standard Symbols for Welding, Brazing, and Nondestructive Examination;American Welding Society; 2012.

K. AWS D1.1/D1.1M - Structural Welding Code - Steel; American Welding Society; 2010 w/Errata.L. SSPC-Paint 15 - Steel Joist Shop Primer; Society for Protective Coatings; 1999 (Ed. 2004).M. SSPC-Paint 20 - Zinc-Rich Primers (Type I, "Inorganic," and Type II, "Organic"); Society for

Protective Coatings; 2002 (Ed. 2004).N. SSPC-SP 2 - Hand Tool Cleaning; Society for Protective Coatings; 1982 (Ed. 2004).

1.04 SUBMITTALSA. See Section 013000 - Administrative Requirements, for submittal procedures.B. Shop Drawings: Indicate profiles, sizes, connection attachments, reinforcing, anchorage, size

and type of fasteners, and accessories. Include erection drawings, elevations, and detailswhere applicable.1. Indicate welded connections using standard AWS A2.4 welding symbols. Indicate net weld

lengths.C. Welders' Certificates: Submit certification for welders employed on the project, verifying AWS

qualification within the previous 12 months.

MAHG-101089 / MAHG-101089Building 4430 4431

055000 - 2 METAL FABRICATIONS

PART 2 PRODUCTS2.01 MATERIALS - STEEL

A. Steel Sections: ASTM A36/A36M.B. Plates: ASTM A283.C. Pipe: ASTM A53/A53M, Grade B Schedule 40, black and hot-dip galvanized finish, as

indicated.D. Bolts, Nuts, and Washers: ASTM A325 (ASTM A325M), Type 1, plain.E. Welding Materials: AWS D1.1/D1.1M; type required for materials being welded.F. Shop and Touch-Up Primer: SSPC-Paint 15, complying with VOC limitations of authorities

having jurisdiction.G. Touch-Up Primer for Galvanized Surfaces: SSPC-Paint 20, Type I - Inorganic, complying with

VOC limitations of authorities having jurisdiction.2.02 FABRICATION

A. Fit and shop assemble items in largest practical sections, for delivery to site.B. Fabricate items with joints tightly fitted and secured.C. Continuously seal joined members by continuous welds.D. Grind exposed joints flush and smooth with adjacent finish surface. Make exposed joints butt

tight, flush, and hairline. Ease exposed edges to small uniform radius.E. Supply components required for anchorage of fabrications. Fabricate anchors and related

components of same material and finish as fabrication, except where specifically notedotherwise.

2.03 FABRICATED ITEMSA. Lintels: As detailed; prime paint finish.B. Steel Handrails:

1. Form exposed work level with accurate angles and straight aligned surfaces. Easeexposed edges to a radius of approximately 1/32" unless indicaed otherwise. Form bentmetal corners to smallest radius possible without causing grain separation or impairingwork.

2. Weld corners and seams continuously, complying with AWS recommendations. Atexposed conditions, grind exposed welds smooth and flusth to match and blend withadjoining surfaces.

3. Form exposed connections with hairline joints, flush and smooth, using concealedfasteners. Use exposed fasteners where indicated or if concealed fasteners is notpossible. For exposed fasterners utilize Phillips flat-head (countersunk) screws or bolts.

4. Fabricate and space anchoring devices to provide adequate support for intended use.5. Fabricate joints to be exposed to weather in a manner to exclude water or provide weep

holes where water may accumulate.6. Provide a zinc coating for those items shown to be galvanized as follows:

a. ASTM A 123 for galvanizing rolled, pressed, and forged steel shapes, plates, barsand strip 1/8" thick and heavier.

b. ASTM A386 for galvanizing assembled steel products.2.04 FINISHES - STEEL

A. Prime paint all steel items.1. Exceptions: Do not prime surfaces in direct contact with concrete, where field welding is

required, and items to be covered with sprayed fireproofing.B. Prepare surfaces to be primed in accordance with SSPC-SP2.C. Clean surfaces of rust, scale, grease, and foreign matter prior to finishing.D. Prime Painting: One coat.

MAHG-101089 / MAHG-101089Building 4430 4431

055000 - 3 METAL FABRICATIONS

2.05 FABRICATION TOLERANCESA. Squareness: 1/8 inch maximum difference in diagonal measurements.B. Maximum Offset Between Faces: 1/16 inch.C. Maximum Misalignment of Adjacent Members: 1/16 inch.D. Maximum Bow: 1/8 inch in 48 inches.E. Maximum Deviation From Plane: 1/16 inch in 48 inches.

PART 3 EXECUTION3.01 EXAMINATION

A. Verify that field conditions are acceptable and are ready to receive work.3.02 PREPARATION

A. Clean and strip primed steel items to bare metal where site welding is required.3.03 INSTALLATION

A. Install items plumb and level, accurately fitted, free from distortion or defects.B. Provide for erection loads, and for sufficient temporary bracing to maintain true alignment until

completion of erection and installation of permanent attachments.C. Field weld components indicated .D. Perform field welding in accordance with AWS D1.1/D1.1M.E. Obtain approval prior to site cutting or making adjustments not scheduled.F. After erection, prime welds, abrasions, and surfaces not shop primed or galvanized, except

surfaces to be in contact with concrete.3.04 TOLERANCES

A. Maximum Variation From Plumb: 1/4 inch per story, non-cumulative.B. Maximum Offset From True Alignment: 1/8 inch.C. Maximum Out-of-Position: 1/8 inch.

END OF SECTION

SECTION 087101 HARDWARE SETS BUILDING 4430

Hardware set notes: Specific manufacturer products listed in each set are for reference purposes only, used to indicate style, function, finish, grade, type, size, etc. Equivalent products by other manufacturers are generally acceptable and are listed in 08710, Part 2, 2.01 Materials. Hardware Set #1 Single Opening #’s:101A, 102A, 103A, 104A, 104B, 106A, 106B, 107A, 108A, 108B 3 each Butt hinge - ball-bearing - 4 1/2" x 4 1/2" - Hager BB1191 US32D NRP 1 each Mortise keyed lockset - Office function - Sargent 8205 L Lever x LE Escutcheon US26D - SFIC less core 1 each Wall stop - Hager 236W - US32D Hardware Set #2 Single Opening #’s:104C 3 each Butt hinge - ball-bearing - 4 1/2" x 4 1/2" - Hager BB1191 US32D NRP 1 each Mortise keyed lockset - Storeroom function - Sargent 8204 L Lever x LE Escutcheon US32D - SFIC less core 1 each Wall stop - Hager 236W - US32D Hardware Set #3 Single Opening # 108C, 109B, 110C, 110E, 114A, 115C, 119A, 119C, 119D, 119E, 119G, 120A 3 each Butt hinge - ball-bearing - 4 1/2" x 4 1/2" - Hager BB1191 US32D NRP 1 each Exit device - rim type – Sargent 8816 ETL US32D 1 each Closer - Sargent 1431 689 1 each Kick-plate - Hager 194S US32D 10" x 34" 1 each Door bottom brush sweep - Hager 770SB DBA 36" 1 each Weather-stripping - Hager 726S 17' 1 each Threshold - Hager DBA 412S 36" Hardware Set #4 Single Opening #’s:105A, 108B, 109A, 110B, 115A, 120B, 121B, 122A, 123A 3 each Butt hinge - ball-bearing - 4 1/2" x 4 1/2" - Hager BB1191 US32D NRP 1 each Mortise keyed lockset - Classroom function - Sargent 8237 L Lever x LE Escutcheon US32D - SFIC less core 1 each Closer - Sargent 1431 689 CPS 1 each Kick-plate - Hager 194S US32D 10" x 34" 1 each Door bottom brush sweep - Hager 770SB DBA 36" 1 each Weather-stripping - Hager 726S 17' 1 each Threshold - Hager DBA 412S 36"

Hardware Set #5 Single Opening #’s:111A, 113A 3 each Butt hinge - ball-bearing - 4 1/2" x 4 1/2" - Hager BB1191 US32D 1 each Mortise keyed lockset - Classroom function - Sargent 8237 L Lever x LE Escutcheon US32D - SFIC less core 1 each Closer - Sargent 1431 689 CPS 1 each Door bottom brush sweep - Hager 770SB DBA 36" 1 each Kickplate 8" x 34" - Hager 193S US32D 1 each mop Plate 4" x 35" - Hager 193S US32D 1 each Weather-stripping - Hager 726S 17' 1 each Threshold - Hager DBA 412S 3 Hardware Set #6 Single Opening #:116A, 124A, 125A, 126A 3 each Butt hinge - ball-bearing - 4 1/2" x 4 1/2" - Hager BB1191 US32D NRP 1 each Mortise keyed lockset - Classroom function - Sargent 8237 L Lever x LE Escutcheon US32D - SFIC less core 1 each Wall stop - Hager 236W - US32D Hardware Set #7 Single Opening #’s:117A, 126B 3 each Butt hinge - ball-bearing - 4 1/2" x 4 1/2" - Hager BB1191 US32D NRP 1 each Mortise keyed lockset - Storeroom function - Sargent 8204 L Lever x LE Escutcheon US32D - SFIC less core 1 each Closer - Sargent 1431 689 CPS 1 each Kick-plate - Hager 194S US32D 10" x 34" 1 each Door bottom brush sweep - Hager 770SB DBA 36" 1 each Weather-stripping - Hager 726S 17' 1 each Threshold - Hager DBA 412S 36" Hardware Set #8 Pair Opening #118A 6 each Butt hinge - ball-bearing - 4 1/2" x 4 1/2" - Hager BB1191 US32D NRP 1 each Mortise keyed lockset - Storeroom function - Sargent 8204 L Lever x LE Escutcheon US26D - SFIC less core 1 each Flush bolt - set of 2 - Hager 282D US26D 1 each Closer - Sargent 1431 689 CPS 2 each Door bottom brush sweep - Hager 770SB DBA 36" 1 each Brush Astragal set of 2 - Hager 802S DBA 1 each Threshold - Hager DBA 552S 72"

Hardware Set #9 Pair Opening #121A 6 each Butt hinge - ball-bearing - 4 1/2" x 4 1/2" - Hager BB1191 US32D NRP 1 each Mortise keyed lockset - Classroom function - Sargent 8237 L Lever x LE Escutcheon US26D - SFIC less core 1 each Flush bolt - set of 2 - Hager 282D US26D 2 each Door bottom brush sweep - Hager 770SB DBA 36" 1 each Threshold - Hager DBA 552S 72"

END OF SECTION

SECTION 087102 HARDWARE SETS BUILDING 4431

Hardware set notes: Specific manufacturer products listed in each set are for reference purposes only, used to indicate style, function, finish, grade, type, size, etc. Equivalent products by other manufacturers are generally acceptable and are listed in 08710, Part 2, 2.01 Materials. Hardware Set #1 Single Opening #’s:216A, 217A, 224A 3 each Butt hinge - ball-bearing - 4 1/2" x 4 1/2" - Hager BB1191 US32D 1 each Mortise lockset - Privacy function - Sargent 8266 L Lever x LE Escutcheon US32D 1 each Wall stop - Hager 236W - US32D Hardware Set #2 Single Opening #’s:201A, 202A, 202B, 205A, 206A, 206B, 207A, 208A, 210A, 211A, 218A, 219A, 221A, 222A, 223A 3 each Butt hinge - ball-bearing - 4 1/2" x 4 1/2" - Hager BB1191 US32D NRP 1 each Mortise keyed lockset - Office function - Sargent 8205 L Lever x LE Escutcheon US26D - SFIC less core 1 each Wall stop - Hager 236W - US32D Hardware Set #3 Single Opening #’s:204A, 215A 3 each Butt hinge - ball-bearing - 4 1/2" x 4 1/2" - Hager BB1191 US32D NRP 1 each Mortise keyed lockset - Storeroom function - Sargent 8204 L Lever x LE Escutcheon US32D - SFIC less core 1 each Wall stop - Hager 236W - US32D Hardware Set #4 Single Opening #:212A 3 each Butt hinge - ball-bearing - 4 1/2" x 4 1/2" - Hager BB1191 US32D NRP 1 each Mortise keyed lockset - Classroom function - Sargent 8237 L Lever x LE Escutcheon US32D - SFIC less core 1 each Wall stop - Hager 236W - US32D Hardware Set #5 Single Opening # 220A 3 each Butt hinge - ball-bearing - 4 1/2" x 4 1/2" - Hager BB1191 US32D NRP 1 each Exit device - rim type – Sargent 8816 ETL US32D 1 each Closer - Sargent 1431 689 1 each Kick-plate - Hager 194S US32D 10" x 34"

END OF SECTION

MAHG-101089 / MAHG-101089 Building 4430 4431

312200 - 1 GRADING

SECTION 312200 - GRADING PART 1 GENERAL 1.01 SECTION INCLUDES

A. Topsoil and finish grading. 1.02 QUALITY ASSURANCE

A. Perform Work in accordance with State of Mississippi, Highway Department standards. PART 2 PRODUCTS 2.01 MATERIALS

A. Topsoil: Topsoil shall consist of natural friable soil that is representative of soils in the vicinity which produce heavy growths of crops, grass, or other vegetation and is reasonably free from underlying subsoil, clay lumps, objectionable weeds, litter, brush, matted roots, toxic substances, or any material that might be harmful to plan growth or be hindrance to grading, planting, or maintenance operations.

B. Obtain approved topsoil material off-site when satisfactory topsoil materials are not available on-site.

PART 3 EXECUTION 3.01 EXAMINATION

A. Verify that survey bench mark and intended elevations for the Work are as indicated. B. Poor soils conditions and groundwater may be encountered and should be expected on the

site. 3.02 PREPARATION

A. Identify required lines, levels, contours, and datum. B. Stake and flag locations of known utilities. C. Locate, identify, and protect from damage above- and below-grade utilities to remain. D. Notify utility company to remove and relocate utilities. E. Protect site features to remain, including but not limited to bench marks, survey control points,

existing structures, fences, sidewalks, paving, and curbs, from damage by grading equipment and vehicular traffic.

F. Protect trees to remain by providing substantial fencing around entire tree at the outer tips of its branches; no grading is to be performed inside this line.

G. Protect plants, lawns, rock outcroppings, and other features to remain as a portion of final landscaping.

3.03 TOPSOIL STRIPPING A. See Section 312323 for subsoil excavation and filling procedures.

3.04 SOIL STOCKPILING A. Stockpile topsoil to be re-used on site; remove remainder from site. B. Locate stockpiles where they will not interfere with the construction phases and at least 15 feet

away from areas of concentrated flows or pavements. C. Protect stockpiles from erosion.

3.05 FINISH GRADING A. Before Finish Grading:

1. Verify building and trench backfilling have been inspected. 2. Verify subgrade has been contoured and compacted.

B. Remove debris, roots, branches, stones, in excess of 1/2 inch in size. Remove soil contaminated with petroleum products.

MAHG-101089 / MAHG-101089 Building 4430 4431

312200 - 2 GRADING

C. Where topsoil is to be placed, scarify surface to depth of 3 inches. D. In areas where vehicles or equipment have compacted soil, scarify surface to depth of 3

inches. E. Place topsoil in areas where sodding are indicated. F. Place topsoil where required to level finish grade. G. Place topsoil to nominal depth of 3 inches. H. Place topsoil during dry weather. I. Remove roots, weeds, rocks, and foreign material while spreading. J. Near plants spread topsoil manually to prevent damage. K. Fine grade topsoil to eliminate uneven areas and low spots. Maintain profiles and contour of

subgrade. L. Lightly compact placed topsoil.

3.06 TOLERANCES A. Top Surface of Subgrade: Plus or minus 0.10 foot (1-3/16 inches) from required elevation. B. Top Surface of Finish Grade: Plus or minus 0.04 foot (1/2 inch).

3.07 REPAIR AND RESTORATION A. Existing Facilities, Utilities, and Site Features to Remain: If damaged due to this work, repair or

replace to original condition. B. Trees to Remain: If damaged due to this work, trim broken branches and repair bark wounds; if

root damage has occurred, obtain instructions from Architect/Engineer as to remedy. C. Other Existing Vegetation to Remain: If damaged due to this work, replace with vegetation of

equivalent species and size. D. Protecting Graded Areas: Protect newly graded areas from traffic and erosion. E. Repair and reestablish grades to specified tolerances where completed or partially completed

surfaces become eroded, rutted, settled, or where they lose compaction due to subsequent construction operations or weather conditions.

3.08 CLEANING A. Leave site clean and raked, ready to receive landscaping.

END OF SECTION

MAHG-101089 / MAHG-101089 Building 4430 4431

312323 - 1 FILL

SECTION 312323 - FILL PART 1 GENERAL 1.01 SECTION INCLUDES

A. Filling, backfilling, and compacting for footings, slabs-on-grade, paving, and site structures. B. Filling holes, pits, and excavations generated as a result of removal (demolition) operations.

1.02 REFERENCE STANDARDS A. AASHTO T 180 - Standard Specification for Moisture-Density Relations of Soils Using a 4.54 kg

(10-lb) Rammer and a 457 mm (18 in.) Drop; American Association of State Highway and Transportation Officials; 2010

B. ASTM C136 - Standard Test Method for Sieve Analysis of Fine and Coarse Aggregates; 2006. C. ASTM D698 - Standard Test Methods for Laboratory Compaction Characteristics of Soil Using

Standard Effort (12,400 ft-lbf/ft3 (600 kN-m/m3)); 2012. D. ASTM D1556 - Standard Test Method for Density and Unit Weight of Soil in Place by the Sand-

Cone Method; 2007. E. ASTM D1557 - Standard Test Methods for Laboratory Compaction Characteristics of Soil Using

Modified Effort (56,000 ft-lbf/ft3 (2,700 kN m/m3)); 2012. F. ASTM D2167 - Standard Test Method for Density and Unit Weight of Soil in Place by the

Rubber Balloon Method; 2008. G. ASTM D2487 - Standard Practice for Classification of Soils for Engineering Purposes (Unified

Soil Classification System); 2011. H. ASTM D3017 - Standard Test Method for Water Content of Soil and Rock in Place by Nuclear

Methods (Shallow Depth); 2005. I. ASTM D4318 - Standard Test Methods for Liquid Limit, Plastic Limit, and Plasticity Index of

Soils; 2010. 1.03 SUBMITTALS

A. See Section 013000 - Administrative Requirements, for submittal procedures. B. Fill Composition Test Reports: Results of laboratory tests on proposed and actual materials

used. C. Compaction Density Test Reports.

1.04 DELIVERY, STORAGE, AND HANDLING A. When necessary, store materials on site in advance of need. B. When fill materials need to be stored on site, locate stockpiles where they will not interfere with

the construction phases and at least 15 feet away from areas of concentrated flows or pavements. 1. Separate differing materials with dividers or stockpile separately to prevent intermixing. 2. Prevent contamination. 3. Protect stockpiles from erosion and deterioration of materials.

PART 2 PRODUCTS 2.01 FILL MATERIALS

A. General: Provide borrow soil materials when sufficient satisfactory soil materials are not available from excavations free from debris, roots, wood, scrap materials, vegetable matter, refuse or frozen material. Obtain approved fill materials off-site when satisfactory soil materials are not available on site.

B. Suitable Soils: Suitable Soils shall be ASTM D 2487 Soil Classification Groups GW, GP, GM, SW, SP, and SM or a combination of these groups; free of rock or gravel larger than 3 inches in any dimension, debris, waste, frozen materials, vegetation, and other deleterious matter.

MAHG-101089 / MAHG-101089 Building 4430 4431

312323 - 2 FILL

C. Structural Fill: Approved material with less than two percent (2%) organic matter, free of debris, with rocks no greater than 6 inches and Liquid Limit less than 30 and a Plasticity Index less than 15.

D. Sand: Clean sand with less than ten percent (10%) passing the No. 200 sieve. 2.02 ACCESSORIES

A. Geotextile Fabric: non-woven, geotextile; N-Series manufactured by Mirafi or approved equal. B. Vapor Retarder: 10 mil thick, polyethylene.

2.03 SOURCE QUALITY CONTROL A. See Section 014000 - Quality Requirements, for general requirements for testing and analysis

of soil material. B. Where fill materials are specified by reference to a specific standard, test and analyze samples

for compliance before delivery to site. C. If tests indicate materials do not meet specified requirements, change material and retest. D. Provide materials of each type from same source throughout the Work.

PART 3 EXECUTION 3.01 EXAMINATION

A. Verify that survey bench marks and intended elevations for the Work are as indicated. B. Identify required lines, levels, contours, and datum locations. C. See Section 312200 for additional requirements.

3.02 PREPARATION A. Scarify subgrade surface to a depth of 6 inches to identify soft spots. B. Cut out soft areas of subgrade not capable of compaction in place. Backfill with general fill. C. Compact subgrade to density equal to or greater than requirements for subsequent fill material. D. Until ready to fill, maintain excavations and prevent loose soil from falling into excavation.

3.03 DRAINAGE A. Effective drainage, including ditching and/or positive grading, should be established during the

initial stages of site development and modified as necessary during construction. B. Groundwater may be encountered and should be expected during excavation work. When

required the Contractor shall provide a system for controlling groundwater below excavations. C. Surface water shall be prevented from flowing into excavations and from flooding the project

site and surrounding areas by methods approved by the Engineer. D. Contractor shall not allow water to accumulate in excavations. Remove water to prevent

softening of foundation soils, undercutting of footings, ans soil changes detrimental to the stability of sub-grades and foundations. Contractor shall not use trench excavation as temporary drainage ditches.

E. Maintain grades so that the surface is well drained. When required the Contractor shall provide dewatering system necessary to convey water away from excavations.

3.04 EXCAVATION A. After clearing, grubbing, and stripping excavation are completed, excavate existing soils to

depths necessary to accomidate site structures and install the required pavement sections. B. Suitable excavation materials shall be used as general fill in areas outside building or pavement

areas as approved by the Engineer. If the site conditions permit, additional suitable excavation material may be wasted on site as approved by the Engineer.

MAHG-101089 / MAHG-101089 Building 4430 4431

312323 - 3 FILL

3.05 UNAUTHORIZED EXCAVATION A. The Contractor will not be compensated for excavation beyond the dimensions and elevations

as shown on the plans or that has been directed and approved by the Engineer. B. Any unauthorized excavation that requires filling shall be corrected at the Contractor's expense. C. No payment will be made for the removal, disposal, or replacement of material determined to

be loosened or undercut through carelessness or negligence on the part of the Contractor. 3.06 SUB-GRADE INSPECTION AND PREPARATION

A. After clearing, grubbing, and stripping excavations are completed, proof-roll the entire site using a loaded dump truck, having an axle weight of at least 10 tons to aid in identifying any additional localized soft or unsuitable material that should be removed.

B. The existing sub-grade soils shall be thoroughly compacted until the soils at a depth of 12 inches achieve at least 95 percent of maximum dry density according to Standard Proctor Density (ASTM D 698).

C. If unsatisfactory sub-grades are encountered or if the required compaction of in place soils cannot be achieved, additional undercutting and placement of appropriate fill material will be required.

3.07 REMOVAL OF UNSUITABLE MATERIALS A. When excavations encounter unsuitable materials below the bottom of the stripping or

excavation to the depths required to accommodate the grading plan and other improvements, the Contractor will be required to remove the materials and backfill with appropriate fill material as approved by the Engineer.

B. The depth and width of unsuitable or muck excavation will be as directed or approved by the Engineer.

C. All muck and fill formations below the bottom of the stripping or excavation to the depths required to accommodate the grading plan and other improvements shall be measured as unit price pay items in the Unsuitable Soils Allowance.

3.08 GENERAL FILL PLACEMENT AND COMPACTION A. Fill materials shall be placed on prepared and inspected sub-grade to contours and elevations

indicated using appropriate materials. B. Employ a placement method that does not disturb or damage other work. C. Do not fill over porous, wet, frozen or spongy subgrade surfaces. D. Maintain optimum moisture content of fill materials to attain required compaction density. E. In areas where groundwater or saturated soil conditions are encountered during the required fill

excavations, the initial lift of fill material should consist of Clean Sand placed to at least 2 feet above the static water table or to a distance to adequately bridge over the saturated soils. during placement below the groundwater table, the Clean Sand may be thoroughly "tracked" with a bulldozer in lieu of measured compaction tests.

F. Fill material meeting the requirements of Suitable Soils shall be placed to obtain final grade outside of building and pavement areas. This material should be compacted in 8 inch loose lifts to not less than 95 percent of the maximum dry unit weight according to ASTM D 698 (Standard Proctor).

G. Correct areas that are over-excavated. H. Reshape and re-compact fills subjected to vehicular traffic.

3.09 FILL PLACEMENT AND COMPACTION FOR SITE STRUCTURES AND PAVEMENTS A. Fill material meeting the requirements of Structural Fill shall be placed to the required grades,

lines, cross sections, and thickness as shown on the plans. This material should be compacted in 8 inch loose lifts to not less than 95 percent of the maximum dry unit weight according to ASTM D 698 (Standard Proctor).

MAHG-101089 / MAHG-101089 Building 4430 4431

312323 - 4 FILL

3.10 TOLERANCES A. Top Surface of General Filling: Plus or minus 1 inch from required elevations.

3.11 FIELD QUALITY CONTROL A. See Section 014000 - Quality Requirements, for general requirements for field inspection and

testing. B. Perform compaction density testing on compacted fill in accordance with ASTM D1556, ASTM

D2167, ASTM D3017, or ASTM D6938. C. Evaluate results in relation to compaction curve determined by testing uncompacted material in

accordance with ASTM D698 ("standard Proctor"), ASTM D1557 ("modified Proctor"), or AASHTO T 180.

D. If tests indicate work does not meet specified requirements, remove work, replace and retest. E. Frequency of Tests at Buildings and Paved Areas: At sub-grade and at each compacted fill and

backfill layer, at least one test for every 2,000 square feet or less of buildings or paved area but in no case fewer than three test.

3.12 CLEANING AND PROTECTION A. Remove unused stockpiled materials, leave area in a clean and neat condition. Grade stockpile

area to prevent standing surface water. B. Leave borrow areas in a clean and neat condition. Grade to prevent standing surface water. C. Protect newly graded areas from traffic and erosion. D. Repair and reestablish grades to specified tolerances where completed or partially completed

surfaces become eroded, rutted, settled, or where they lose compaction due to subsequent construction operations or weather conditions.

END OF SECTION

MAHG-101089 / MAHG-101089 Building 4430 4431

321313 - 1 CONCRETE PAVING

SECTION 321313 - CONCRETE PAVING PART 1 GENERAL 1.01 SECTION INCLUDES

A. Concrete sidewalks. 1.02 REFERENCE STANDARDS

A. ACI 211.1 - Standard Practice for Selecting Proportions for Normal, Heavyweight, and Mass Concrete; American Concrete Institute International; 1991 (Reapproved 2002).

B. ACI 301 - Specifications for Structural Concrete; American Concrete Institute International; 2010 (Errata 2012).

C. ACI 304R - Guide for Measuring, Mixing, Transporting, and Placing Concrete; American Concrete Institute International; 2000.

D. ACI 305R - Hot Weather Concreting; American Concrete Institute International; 2010. E. ACI 306R - Cold Weather Concreting; American Concrete Institute International; 2010. F. ASTM C39/C39M - Standard Test Method for Compressive Strength of Cylindrical Concrete

Specimens; 2014. G. ASTM C94/C94M - Standard Specification for Ready-Mixed Concrete; 2014. H. ASTM C173/C173M - Standard Test Method for Air Content of Freshly Mixed Concrete by the

Volumetric Method; 2014. I. ASTM C309 - Standard Specification for Liquid Membrane-Forming Compounds for Curing

Concrete; 2011. J. ASTM C685/C685M - Standard Specification for Concrete Made by Volumetric Batching and

Continuous Mixing; 2011. 1.03 SUBMITTALS

A. See Section 013000 - Administrative Requirements, for submittal procedures. B. Product Data: Provide data on joint filler, admixtures, and curing compound.

PART 2 PRODUCTS 2.01 PAVING ASSEMBLIES

A. Comply with applicable requirements of ACI 301. 2.02 FORM MATERIALS

A. Form Materials: Conform to ACI 301. 2.03 REINFORCEMENT

A. Reinforcing Steel and Welded Wire Reinforcement: Types specified in Section 033150. 2.04 CONCRETE MATERIALS

A. Obtain cementitious materials from same source throughout. B. Concrete Materials: As specified in Section 033150.

2.05 ACCESSORIES A. Curing Compound: ASTM C309, Type 1, Class A. B. Surface Retarder:

2.06 CONCRETE MIX DESIGN A. Proportioning Normal Weight Concrete: Comply with ACI 211.1 recommendations. B. Concrete Strength: Establish required average strength for each type of concrete as shown on

the drawings, as specified in ACI 301. C. Admixtures: Add acceptable admixtures as recommended in ACI 211.1 and at rates

recommended by manufacturer.

MAHG-101089 / MAHG-101089 Building 4430 4431

321313 - 2 CONCRETE PAVING

D. Fiber Reinforcement: Add to mix at rate of 1.5 pounds per cubic yard, or as recommended by manufacturer for specific project conditions.

E. Concrete Properties: 1. Compressive strength, when tested in accordance with ASTM C39/C39M at 28 days; As

indicated on drawings. 2. Fly Ash Content: Maximum 15 percent of cementitious materials by weight. 3. Calcined Pozzolan Content: Maximum 10 percent of cementitious materials by weight. 4. Silica Fume Content: Maximum 5 percent of cementitious materials by weight. 5. Water-Cement Ratio: Maximum 40 percent by weight. 6. Total Air Content: 4 percent, determined in accordance with ASTM C173/C173M. 7. Maximum Slump: 3 inches.

2.07 MIXING A. On Project Site: Mix in drum type batch mixer, complying with ASTM C685/C685M. Mix each

batch not less than 1-1/2 minutes and not more than 5 minutes. B. Transit Mixers: Comply with ASTM C94/C94M.

PART 3 EXECUTION 3.01 EXAMINATION

A. Verify compacted subgrade is acceptable and ready to support paving and imposed loads. B. Verify gradients and elevations of base are correct.

3.02 SUBBASE A. See Section 321123 for construction of base course for work of this Section.

3.03 FORMING A. Place and secure forms to correct location, dimension, profile, and gradient. B. Assemble formwork to permit easy stripping and dismantling without damaging concrete. C. Place joint filler vertical in position, in straight lines. Secure to formwork during concrete

placement. 3.04 REINFORCEMENT

A. Place reinforcement as indicated. 3.05 COLD AND HOT WEATHER CONCRETING

A. Follow recommendations of ACI 305R when concreting during hot weather. B. Follow recommendations of ACI 306R when concreting during cold weather. C. Do not place concrete when base surface temperature is less than 40 degrees F, or surface is

wet or frozen. 3.06 PLACING CONCRETE

A. Place concrete in accordance with ACI 304R. B. Ensure reinforcement, inserts, embedded parts, and formed joints are not disturbed during

concrete placement. C. Place concrete continuously over the full width of the panel and between predetermined

construction joints. Do not break or interrupt successive pours such that cold joints occur. D. Apply surface retarder to all exposed surfaces in accordance with manufacturer's instructions.

3.07 JOINTS A. Align curb, gutter, and sidewalk joints. B. Place 3/8 inch wide expansion joints at 20 foot intervals and to separate paving from vertical

surfaces and other components and in pattern indicated. 1. Form joints with joint filler extending from bottom of pavement to within 1/2 inch of finished

surface.

MAHG-101089 / MAHG-101089 Building 4430 4431

321313 - 3 CONCRETE PAVING

2. Secure to resist movement by wet concrete. C. Provide scored joints.

1. At 6 feet maximum intervals. 2. Between sidewalks and curbs. 3. Between curbs and pavement.

D. Provide keyed joints as indicated. E. Saw cut contraction joints 3/16 inch wide at an optimum time after finishing. Cut 1/3 into depth

of slab. 3.08 FINISHING

A. Area Paving: Light broom, texture perpendicular to pavement direction. B. Sidewalk Paving: Light broom, texture perpendicular to direction of travel with troweled and

radiused edge 1/4 inch radius. C. Curbs and Gutters: Light broom, texture parallel to pavement direction. D. Place curing compound on exposed concrete surfaces immediately after finishing. Apply in

accordance with manufacturer's instructions. 3.09 TOLERANCES

A. Maximum Variation of Surface Flatness: 1/4 inch in 10 ft. 3.10 FIELD QUALITY CONTROL

A. An independent testing agency will perform field quality control tests, as specified in Section 014000. 1. Provide free access to concrete operations at project site and cooperate with appointed

firm. 2. Submit proposed mix design of each class of concrete to inspection and testing firm for

review prior to commencement of concrete operations. 3. Tests of concrete and concrete materials may be performed at any time to ensure

conformance with specified requirements. B. Compressive Strength Tests: ASTM C39/C39M; for each test, mold and cure three concrete

test cylinders. Obtain test samples for every 100 cu yd or less of each class of concrete placed. 1. Take one additional test cylinder during cold weather concreting, cured on job site under

same conditions as concrete it represents. 2. Perform one slump test for each set of test cylinders taken.

C. Maintain records of placed concrete items. Record date, location of pour, quantity, air temperature, and test samples taken.

3.11 PROTECTION A. Immediately after placement, protect pavement from premature drying, excessive hot or cold

temperatures, and mechanical injury. B. Do not permit pedestrian traffic over pavement for 7 days minimum after finishing.

END OF SECTION

MAHG-101089 / MAHG-101089 Building 4430 4431

329223 - 1 SODDING

SECTION 329223 - SODDING PART 1 GENERAL 1.01 SECTION INCLUDES

A. Fertilizing. B. Sod installation. C. Maintenance.

1.02 DEFINITIONS A. Weeds: Includes Dandelion, Jimsonweed, Quackgrass, Horsetail, Morning Glory, Rush Grass,

Mustard, Lambsquarter, Chickweed, Cress, Crabgrass, Canadian Thistle, Nutgrass, Poison Oak, Blackberry, Tansy Ragwort, Bermuda Grass, Johnson Grass, Poison Ivy, Nut Sedge, Nimble Will, Bindweed, Bent Grass, Wild Garlic, Perennial Sorrel, and Brome Grass.

1.03 REFERENCE STANDARDS A. TPI (SPEC) - Guideline Specifications to Turfgrass Sodding; Turfgrass Producers International;

2006. 1.04 SUBMITTALS

A. Certification: Submit certification of grass species and location of sod source. B. Maintenance Data: Include maintenance instructions, cutting method and maximum grass

height; types, application frequency, and recommended coverage of fertilizer. 1.05 QUALITY ASSURANCE

A. Sod Producer: Company specializing in sod production and harvesting with minimum five years experience, and certified by the State of Mississippi.

B. Installer Qualifications: Company approved by the sod producer. 1.06 REGULATORY REQUIREMENTS

A. Comply with regulatory agencies for fertilizer and herbicide composition. 1.07 DELIVERY, STORAGE, AND HANDLING

A. Deliver sod on pallets. Protect exposed roots from dehydration. B. Do not deliver more sod than can be laid within 24 hours.

PART 2 PRODUCTS 2.01 MATERIALS

A. Sod: TPI, Certified Turfgrass Sod quality; cultivated grass sod; type indicated below; with strong fibrous root system, free of stones, burned or bare spots; containing no more than 5 weeds per 1000 sq ft. Minimum age of 18 months, with root development that will support its own weight without tearing, when suspended vertically by holding the upper two corners. 1. Eremochloa ophiuroides (Centipede) Grass Type: 98 percent.

B. Topsoil: See Section 312200 C. Fertilizer: Organic, granular controlled release fertilizer; recommended for grass, with equal

percentages of nitrogen, phosphoric acid, and potassium. D. Water: Clean, fresh and free of substances or matter that could inhibit vigorous growth of grass.

2.02 SOURCE QUALITY CONTROL A. Provide analysis of topsoil fill under provisions of Section 014000. B. Analyze to ascertain percentage of nitrogen, phosphorus, potash, soluble salt content, organic

matter content, and pH value. C. Submit minimum 10 oz sample of topsoil proposed. Forward sample to approved testing

laboratory in sealed containers to prevent contamination.

MAHG-101089 / MAHG-101089 Building 4430 4431

329223 - 2 SODDING

D. Testing is not required if recent tests are available for imported topsoil. Submit these test results to the testing laboratory for approval. Indicate, by test results, information necessary to determine suitability.

PART 3 EXECUTION 3.01 EXAMINATION

A. Verify that prepared soil base is ready to receive the work of this section. 3.02 PREPARATION

A. Prepare subgrade in accordance with Section 312200. B. Place topsoil in accordance with Section 312200.

3.03 FERTILIZING A. Apply fertilizer in accordance with manufacturer's instructions. B. Apply after smooth raking of topsoil and prior to installation of sod. C. Apply fertilizer no more than 48 hours before laying sod. D. Mix thoroughly into upper 2 inches of topsoil. E. Lightly water to aid the dissipation of fertilizer.

3.04 LAYING SOD A. Moisten prepared surface immediately prior to laying sod. B. Lay sod immediately after delivery to site to prevent deterioration. C. Lay sod smooth and tight with no open joints visible, and no overlapping; stagger end joints 12

inches minimum. Do not stretch or overlap sod pieces. D. Where new sod adjoins existing grass areas, align top surfaces. E. Where sod is placed adjacent to hard surfaces, such as curbs, pavements, etc., place top

elevation of sod 1/2 inch below top of hard surface. F. Water sodded areas immediately after installation. Saturate sod to 4 inches of soil. G. After sod and soil have dried, roll sodded areas to ensure good bond between sod and soil and

to remove minor depressions and irregularities. Roll sodded areas with roller not exceeding 90 lbs. for each foot of roller width.

3.05 MAINTENANCE A. Provide maintenance at no extra cost to Owner; Owner will pay for water. B. Mow grass at regular intervals to maintain at a maximum height of 2-1/2 inches. Do not cut

more than 1/3 of grass blade at any one mowing. C. Neatly trim edges and hand clip where necessary. D. Immediately remove clippings after mowing and trimming. E. Water to prevent grass and soil from drying out. F. Roll surface to remove irregularities. G. Control growth of weeds. Apply herbicides in accordance with manufacturer's instructions.

Remedy damage resulting from improper use of herbicides. H. Immediately replace sod to areas that show deterioration or bare spots. I. Protect sodded areas with warning signs during maintenance period.

END OF SECTION

81st Logistics Readiness SquadronBuilding 4431 Renovation/Furniture Plan

COMMAND SECTION

Description WxDxH Modular Quantity CC Office LGL DO CEM CCF RECEPTION CONF RMItems 4 Storage

Cabinet, 2 Door (Tall) 36x16x54 No 1 1

Cabinet, File (Lgl) 18x29x29 No 3 3

Cabinet, File (ltr) 16x20x29 No 4 2 1 1

Cabinet, File 2 Drawer/Door 37.5x21x30 No 6 2 1 3

Cabinet, File 4 Drawer (Lgl) 18x29x51 No 4 4

Cabinet, Shelf/Drawer 30x12x72 No 1 1

Cabinet, storage 36x24x80 No 3 3

Cabinet, Wardrobe (Metal) 24x24x72 No 1 1

Cabinet, Wardrobe (Wood) 24x24x72 No 2 1 1

Chair, Desk 27x27x40 No 8 2 1 1 1 1 2

Chair, Guest/Upholstered 27x30x42 No 29 2 2 2 2 3 18 18

Desk 84x42x30 No 2 1 1

Desk, Credenza 67x21x31 No 1 1

Desk, Hutch 63x17x47 No 2 1 1

Desk, L Shaped 81x68x30 No 3 1 1 1

Desk, Stand Up 24x18.5x43 No 1 1

Desk, U Shaped 110x78x31 No 2 1 1

Refrigerator 31x31x67 No 1 1

Shelves, 3 Shelf 34.5x13.5x37 No 2 1 1

Shelves, 5 Shelf 38x14x72 No 2 1 1

Sofa 71x40x36 No 2 1 1 2

Table, Coffee 36x24x16 No 1 1

Table, Conference (lg) 145x48x31 Yes 1 1 1

Table, Conference (Sm) 42x42x32 No 1 1

Table, Side 24x24x21 No 2 2 2

Trophy Case 54x22x49 No 1 1 186 24