Protocol Approval on Hold, IRB Submission, FDA Submission, Preparation for Protocol Activation, Final CTEP Approval, and Status Update Indicating Activation Second CTEP Review NCI Receipt of LOI 14 days 14 days 7 days Phase 1/Phase 2 Timeline: Unsolicited LOIs 16 days Day 1 – 60: LOI Approval 60 days Day 60 – 120: Protocol Development Day 120 – 210: Protocol Approval Consensus Evaluation If LOI is on Hold, Conference Call Resubmission of LOI and Final Consensus Evaluation 30 days 14 days LOI Approva l NCI Protocol Receipt CTEP Review with Comments Conference Call to Review Major Issues Resubmission of Protocol * * * Deadline for Protocol Activation is 540 days including “timeouts” * * * 25 days “Timeout” for industry approval and/or drug commitment “Timeout” for IRB & FDA review If LOI is Approved at Day 30 PI Writes and Submits Protocol using CTEP protocol template and Library of Materials WEEK 1 (Day 1) WEEK 5 (Day 30) WEEK 7 (Day 44) WEEK 9 (Day 60) WEEK 18 (Day 120) WEEK 9 - 18 (Day 60 – 120) WEEK 9 (Day 60) WEEK 22 (Day 150) WEEK 24 (Day 164) WEEK 30 (Day 210) WEEK 26 (Day 178) WEEK 27 (Day 185) Version 1.0 13 April 2010

description

Phase 1/Phase 2 Timeline: Unsolicited LOIs. Day 1 – 60: LOI Approval. NCI Receipt of LOI. Consensus Evaluation. Resubmission of LOI and Final Consensus Evaluation. If LOI is on Hold, Conference Call. WEEK 1 (Day 1). WEEK 5 (Day 30). WEEK 7 (Day 44). WEEK 9 (Day 60). 30 days. - PowerPoint PPT Presentation

Transcript of Second CTEP Review

Page 1: Second CTEP Review

Protocol Approval on Hold, IRB Submission, FDA Submission, Preparation for Protocol Activation,

Final CTEP Approval, and Status Update Indicating Activation

Second CTEPReview

NCI Receipt of LOI

14 days 14 days 7 days

Phase 1/Phase 2 Timeline: Unsolicited LOIs

16 days

Day 1 – 60: LOI Approval

60 days

Day 60 – 120: Protocol Development

Day 120 – 210: Protocol Approval

Consensus Evaluation

If LOI is on Hold, Conference Call

Resubmission of LOI and Final Consensus Evaluation

30 days 14 days

LOIApproval

NCI ProtocolReceipt

CTEP Review with Comments

Conference Call toReview Major

Issues

Resubmission of Protocol

* * * Deadline for Protocol Activation is 540 days including “timeouts” * * *

25 days

“Timeout” for industry approval

and/or drug commitment

“Timeout” for IRB & FDA

review

If LOI is Approved at Day 30

PI Writes and Submits Protocol using CTEP

protocol template and Library of Materials

WEEK 1(Day 1)

WEEK 5(Day 30)

WEEK 7(Day 44)

WEEK 9(Day 60)

WEEK 18(Day 120)

WEEK 9 - 18(Day 60 – 120)

WEEK 9(Day 60)

WEEK 22(Day 150)

WEEK 24(Day 164)

WEEK 30(Day 210)

WEEK 26(Day 178)

WEEK 27(Day 185)