Project Slide Number
Arbor Heights Elementary School 2
Cascadia Elementary School & Robert Eagle Staff Middle School 13
Genesee Hill Elementary School 23
Hazel Wolf K-8 at Pinehurst 34
Olympic Hills Elementary School 45
Seattle New World School at TT Minor 50
New Thornton Creek Building 59
October 23, 2015
Seattle Public Schools Building Excellence IV Projects Under Construction
Arbor Heights Elementary School Elementary School
• Site: SW 104th Street is getting prepped for curb/gutter and sidewalk. The natural gas main line in SW 104th Street was relocated to allow storm water utility installation to complete.
• South Building: Roof joists are being placed and welded to structural frame. Light-gauge metal framing continues at the exterior and interior at floor 2. Hollow metal door frame installation is ongoing on floor 2. Mechanical, electrical, and plumbing rough-in are ongoing at floors 1 and 2.
• North Building: Structural steel erection ongoing. Roof joists are getting set and welded.
Arbor Heights Elementary School Site Plan
July 1, 2015 July 10, 2015
Arbor Heights Elementary School Aerial View from the South
September 30, 2015
Arbor Heights Elementary School SW 104TH Street Gas Line Relocation
October 14, 2015
Arbor Heights Elementary School SW 104th Street Curb/Gutter and Sidewalk Prep.
October 14, 2015
Arbor Heights Elementary School South Building Roof Joists
October 13, 2015
Arbor Heights Elementary School South Building 2nd Floor Exterior Wall Framing On-Going
October 14, 2015
Arbor Heights Elementary School South Building 2nd Floor Plumbing Rough-In On-Going
October 19, 2015
Arbor Heights Elementary School South Building 3rd Floor Structural Steel Welding
October 19, 2015
Arbor Heights Elementary School South Building 3rd Floor Looking West
October 19, 2015
Arbor Heights Elementary School North Building 2nd Floor Looking South East
October 19, 2015
Cascadia Elementary School & Robert Eagle Staff Middle School Site Plan
Cascadia Elementary School & Robert Eagle Staff Middle School Aerial Photo
Cascadia Elementary School & Robert Eagle Staff Middle School Elementary School Footings Concrete Pour, Looking SW
October 16, 2015
Cascadia Elementary School & Robert Eagle Staff Middle School Elementary School Footings and Walls, Looking North
October 16, 2015
Cascadia Elementary School & Robert Eagle Staff Middle School Elementary School Underground Communications/Electrical, Looking East
October 16, 2015
Cascadia Elementary School & Robert Eagle Staff Middle School Elementary School Parking Lot Prep, Looking South East
October 16, 2015
Cascadia Elementary School & Robert Eagle Staff Middle School Middle School Footings Formwork, Looking North West
October 16, 2015
Cascadia Elementary School & Robert Eagle Staff Middle School Middle School Formwork, Looking North East
October 16, 2015
Cascadia Elementary School & Robert Eagle Staff Middle School Middle School Footings Formwork, Looking West
October 16, 2015
Cascadia Elementary School & Robert Eagle Staff Middle School Roadway Restoration at Woodlawn for SPU
October 16, 2015
Genesee Hill Elementary School • Site: Continued excavation/installation of the storm water conveyance
system; completed trimming tree branches and clearing scotch broom at
the environmental critical area (ECA) near lower parking lot.
• Area 1: Installation of windows is ongoing; CMU veneer installation is
ongoing; in-wall backing ongoing; installation of spray foam insulation
ongoing; installation of GWB ongoing; MEP is ongoing.
• Area 2: Interior and exterior framing is ongoing at level 2; installation of
exterior sheathing ongoing; HVAC ductwork install at level 1 is ongoing.
• Area 3: Interior wall framing ongoing; CMU veneer ongoing; MEP ongoing.
• Area 4: MEP is ongoing; exterior framing and sheathing ongoing.
Genesee Hill Elementary School
Site Plan 4
Genesee Hill Elementary School Aerial View
October 15, 2015
Genesee Hill Elementary School Area 1 Installing Ridged Insulation and Z-Metal
Genesee Hill Elementary School Area 1 Installation of Rigid Insulation and CMU Veneer
Genesee Hill Elementary School Area 1 Level 2 Installation of Windows
Genesee Hill Elementary School Area 1 Level 2 Installation of GWB
Genesee Hill Elementary School Area 2 Level 1 Installation of Interior Framing
Genesee Hill Elementary School Area 2 Mechanical Power Termination to AHU’s
Genesee Hill Elementary School Area 3 Installation of CMU Veneer
Genesee Hill Elementary School Area 4 Sheathing Installation
Hazel Wolf K-8 at Pinehurst
• Site: Side sewer installs continued, backfill around foundations, general clean up.
• Building A: A1 slab preparation and capillary break material
ongoing. Area A2 Mechanical ducting, electrical equipment /conduit and plumbing install continues as well as metal stud framing on first floor and penthouse. A3 - Stem wall concrete pour completed, Water proofing started and under slab utilities ongoing.
• Building B: Structural steel for the outside play area completed. • Building C: Metal roof decking installation continues. Skylight
frames installed. Slab on deck for 2nd floor (child care) area preparing for concrete pour.
Hazel Wolf K-8 at Pinehurst Site Plan
Hazel Wolf K-8 at Pinehurst Aerial View looking North West
Hazel Wolf K-8 at Pinehurst Area A2 Parapet Framing
October 14, 2015
Hazel Wolf K-8 at Pinehurst Area A1 to A2 Transition Slab Prep for Concrete Pour
October 14, 2015
Hazel Wolf K-8 at Pinehurst Area A2 First Floor Concrete Grinding Mock-Up
October 14, 2015
Hazel Wolf K-8 at Pinehurst Area A2 Second Floor Mechanical/Electrical Rough-in
October 14, 2015
Hazel Wolf K-8 at Pinehurst Area A2 Third Floor Science Deck
October 14, 2015
Hazel Wolf K-8 at Pinehurst Area B Covered Play Structural Steel
October 14, 2015
Hazel Wolf K-8 at Pinehurst Area C Gym/Commons/Daycare
October 14, 2015
Hazel Wolf K-8 at Pinehurst View from Penthouse Looking East
October 14, 2015
Olympic Hills Elementary School Site Plan
Olympic Hills Elementary School Geothermal Well Drilling, Looking South West
October 16, 2015
Olympic Hills Elementary School Detention Vault Backfill, Looking South
October 16, 2015
Olympic Hills Elementary School Soil Stockpile for Excavation Backfill, Looking East
October 16, 2015
Olympic Hills Elementary School Sewer Tie-In on 20th Ave NE
October 16, 2015
Seattle World School at T.T. Minor
• Area A – Office, Student Services, Health Clinic and Library: Admin addition footing layout and form work ongoing. Health Clinic underground utilities ongoing, concrete grade beam complete, original kitchen demolition ongoing.
• Area B – Multipurpose & Kitchen: Stem wall concrete pour complete, slab preparation ongoing, Boiler room abatement complete demolition ongoing, concrete footing pour.
• Area C – Classrooms: CMU wall layout ongoing, CMU rebar installation ongoing, underground utility complete, CMU grade beams complete.
Seattle World School at T.T. Minor Site Plan
Seattle World School at T.T. Minor Area A New Administration Addition Footing Layout and Underground Utilities
October 20, 2015
Seattle World School at T.T. Minor Area A Original Building Seismic Retrofit Footing Preparation
October 20, 2015
Seattle World School at T.T. Minor Area A Original Kitchen Demolition Part of New Health Clinic
October 20, 2015
Seattle World School at T.T. Minor Area A Health Clinic Underground Utilities and Grade Beams
October 20, 2015
Seattle World School at T.T. Minor Area B New Kitchen and Commons Addition Slab Preparation
October 20, 2015
Seattle World School at T.T. Minor Area B Boiler Room Abatement Complete, Demolition Ongoing
October 20, 2015
Seattle World School at T.T. Minor Area C Science Rooms Underground Utilities Complete, CMU Block Wall Layout
October 20, 2015
New Thornton Creek Building • Site: Continue installing footing drainage piping and downspouts. Continued
remove excess soil pile.
• Building A: Continued with exterior backfill around footings. Completed setting forms and installing rebar for stem walls. Poured remaining concrete stem walls. Stripped forms from concrete stem walls.
• Building B: Continued erecting structural steel in both library and two story academic wing. Began placing steel joist and decking in both library and first story of two story wing.
• Building C: Continued interior framing on classrooms. Continued installing HVAC ductwork and above ceiling plumbing and electrical. Continued with plumbing and electrical rough-in in classroom walls. Began install interior hollow metal window frames in hallway for classrooms.
New Thornton Creek Building Key Plan
New Thornton Creek Building Aerial Photo
October 15, 2015
New Thornton Creek Building Building A Pouring Concrete Stem Wall
New Thornton Creek Building Building B Structural Steel Erection
New Thornton Creek Building Building B Structural Steel and Decking Install for Mechanical Mezzanine
New Thornton Creek Building Building B 2nd Floor Academic Wing Structural Steel Erection
New Thornton Creek Building Building C - Roof Anchor, Pipe Vent and Skylight Frame
New Thornton Creek Building Building C Hollow Metal Frame Installation
New Thornton Creek Building Building C Plumbing Rough-in
New Thornton Creek Building Building C Electrical Rough-in