Scisson, · 2012. 2. 24. · thus achieving a lower ton-ratio. Table 7 a and b Change in retorting...
Transcript of Scisson, · 2012. 2. 24. · thus achieving a lower ton-ratio. Table 7 a and b Change in retorting...
PRELIMINARY MINING ECONOMICS FOR MODIFIED IN SITUPROCESS*
Ronald B. Stone
Fenix Scisson, Inc.
5805 East 15th Street
Tulsa, Oklahoma 74115
Introduction
This paper presents some of the high
lights of the Phase II study effort conducted
under U.S. Bureau of Mines Contract No.
S0241073, and documented in the Final Report
entitled, "Technical and Economic Study of
the Modified In Situ Process for Oil Shale",
available through NTIS.
A thorough understanding of the economic
implications inherent in various factors in
the design of a complex facility, as
required for modified in situ production of
oil shale, will be needed if sound, econom
ical designs are to be achieved.
The Phase I effort, consisting of a
technical analysis of the process from a
mining standpoint, was reported briefly at
the 9th Oil Shale Symposium (April 29-30,
1976).
This paper highlights the effect of
variables in mining and processing of oil
shale that have an impact on mine design
and, ultimately, upon costs.
Background
The conclusions of the technical analysis
were that two mining system designs were
feasible for further study:
(1) Room and pillar- vertical drill and
blast concept,
(2) Tunnel boring- horizontal ring
drill and blast concept.
The room and pillar- vertical drill and
blast system (fig. 1) was considered tech
nically feasible in the current state of the
art, because it employed only the techniques
and equipment that are commonly used today.
This system approximates the one used by
Occidental Petroleum Corporation.
The tunnel boring- horizontal ring
drill and blast system (fig. 2) was consid
ered to be a second generation system in
which as much excavation as possible was
done by boring, and restabilization of
burned-out retorts was used to increase
?Results of work conducted under Phase II of Figure 1
U.S. Bureau of Mines - Contract #S0241073
Room and pillar -
vertical
drill and blast concept.
extraction ratio and resource recovery.
Resource recovery, using the tunnel boring
system, is increased by approximately 42
percent over recovery by conventional room
and pillar mine.
Figure 2. - Tunnel boring- horizontal ring
drill and blast concept.
Results
Technical analysis produced an apprecia
tion for the complex nature of a modified
in situ design. Because of the complexity
of the calculations to meet contract require
ments for cost benefit and cost trade-off
studies, and the inherently large number of
variables that must be considered in these
calculations, we decided to develop a com
puter program to provide the answers. Using
such a program would increase both efficiency
and accuracy of the computations needed to
improve the quality of the analysis. These
goals were achieved. In the process, we
developed a valuable tool for evaluating any
combination of the many design factors with
minimal effort; at the same time, a much
better understanding was afforded of the
complex and involved relationships inherent
in the design.
The basic computer program is a mathe
matical model of the various elements of the
design, including rock mechanics, retorting,
blasting, ventilation, quantities, and costs.
Sub-routines are interrelated so that a
change in one is properlyreflected in the
others .
All costs are based on January 1975 fig
ures."Operating"
costs are reported as
"cost ofsales"
which includes the direct,
indirect and fixed costs normally reported
to an operations manager."Capital"
costs
are reported as "initial capital costs",
including pre-construction, plant and equip
ment and initial development costs. Tract
bid payments were not included in the cal
culations because the study was made on a
generic basis, not for a specific site.
Reinvestment and expansion investment costs
were not calculated for each case, but were
calculated for a separate discounted cash
flow return on investment (DCFROI) portion
of the study of the two systems. Results
of cost comparisons were reported both in
terms of dollars-per-barrel anddollars-
per-cubic meter of daily production.
The first comparison was between the
two mining systems (table 1) . Major design
variables were held constant for both cases.
Results show that the room and pillar method
is more capital intensive but has a lower
cost of sales than the tunnel boring method.
The basic reason for the higher cost of
sales for the tunnel boring method is the
cost of stabilizing burned out retorts to
obtain increased resource recovery.
To gain a better understanding of the
effect of each of the many variables on
cost, the following factors were selected
as having a direct bearing on costs:
Production rate (P)Grade (G)Retorting efficiency (RE)Entry size (ES)Burn rate (BR)Depth (D)Swell factor (SF)Retort height (RH)Equipment selection
Permissible regulations
Table 1 a and b - Comparison of base case
computer runs for two mining methods
Table 2 a and b - Change in production
Method
Cost of
Sales ($/BPD)
Initial Capital
Cost (000$/BPD)
S/BPD 5 7 9 11 13 S/BPD 3 5 7 9 11
Room & Pillar
Tunnel Boring
8.77
11.79
6,946
6,626
Design Constants
P - 50,000 BPD BR - 0.5 in/hr
G - 20 GPT SF - 25 percent
D - 1,000 ft RE - 60 percent
RH - 230 ft
Method
Cost of
Sales ($/CuM/Day)
Initial Capital
Cost (S/CuM/Day)
$/CuMPD 35 45 55 65 75 $/CuMPD 20 30 40 50 60
Room & Pillar 55.16 43,689
Tunnel Boring 74.16 A1.676
Design Constants
P - 7949 Cubic Meters/Day BR - 1.27 Centimeters/Hour
G - 68.68 Liters/Tonne SF - 25 Percent
D - 304.8 Meters RE - 60 Percent
RH - 70.10 Meters
The basic technique for comparisons is
to use a base case and change one variable
at a time to establish relative change.
Hereafter, cost comparisons apply to the
room and pillar method only, but the results
would be similar for the tunnel boring
method.
Comparison of Variables
Change- in-Product ion Rate - This change
does not appear to have a large effect on
cost. We did not have the opportunity to
select the appropriate equipment size for
the various production rates. Given proper
data, there would probably be a larger
change than shown in table 2. Optimum pro
duction for a single facility appears to be
below 50,000 BPD (7949 CuMPD) . It appears
that the economics of scale of the operation
have been exceeded at 50,000 BPD (7949 CuMPD),
Costs reported for a 25,000 BPD (3975 CuMPD)
Production
Rate
Barrels
per day
Cost of
Sales ($/BPD)
Initial Capital
Cost (000S/BPD)
$/BPD 5 7 9 11 13 $/BPD 3 5 7 9 11
25,000
* 50,000
75,000
9.16
8.77
8.94
7,768
6,946
6,965
* Base Case
Production
Rate
Cubic Meters
per day
Cost of
Sales (S/CuM/Day)
Initial Capital
Cost ($/CuM/Day)
S/CuMPD 35 45 55 65 75 S/CuMPD 20 30 40 SO 60
3975
* 7949
11924
57.61
55.16
56.23
48,859
43,689
43,809
production rate should not be considered
entirely valid; they can be bettered by
properly sizing the mining equipment.
Change of Grade - This change (table 3)
has a dramatic effect on cost. The 25
gallons-per-ton (124.02 liters-per-tonne)
line is not reported because it has too low
a resource recovery for the base conditions.
In this instance, a much more sophisticated
rock mechanics design technique would prob
ably yield a stable configuration. This
technique would require a stability analysis
of the pillar on an incremental basis (from
top to bottom) with each major kerogen-rich
zone being analyzed separately, but as a
part of the whole, rather than the present
technique of analyzing and designing only on
the richest zone. Computer runs made for
the tunnel boring system tend to confirm
this trend.
Change of Burn Rate - This change (table
4) has a relatively large effect in the
range of 0.5-2 in. per hour (1.27 cm- 5. 8 cm
per hour), but does not have a significant
impact between 2.0 and 4.0 in. per hour
(5.8 cm-10.16 cm per hour). The effect of
lower burn rates on cost can be attributed
to satisfying the air requirements per
retort but at levels not exceeding the
capacities of the individual drifts. Higher
Table 3 a and b - Change in grade Table 5 a and b - Change in depth
Grade
Gallons
per ton
Grade
Liters /Tonne
51.51
* 68.68
124.02
Cost of
Sales ($/BPD)
$/BPD
11.83
8.77
Initial Capital
Cost (000$/BPD)
$/BPD
9,718
6,946
3 5 7 9 11
Not Reported Due To Low Resource Recovery
500 foot depth only
Cost of
Sales ($/CuM/Day)
$ /CuMPD
74.41
55.16
35 45 55 65 75
Initial Capital
Cost ($/CuM/Day)
$/CuMPD
61,124
43,689
20 30 40 50 60
Not Reported Due To Low Resource Recovery
152.4 Meters depth only
5a
Depth
Feet
Cost of
Sales (S/BPD)
Initial Capital
Cost (000$/BPD)
$/BPD 5 7 9 11 13 S/BPD
6,982
6,946
urce Reco
3 5 7 9 11
500
* 1,000
1,500
9.18
8.77
Not Re veryported Due To Low Reso
* Base Case
Depth
Meters
Cost of
Sales (S/CuM/Day)
Initial Capital
Cost (S/CuM/Day)
S/CuMPD 35 45 55 65 75 S/CuMPD 20 30 40 50 60
152.4
304.8
457.2
57.74
55.16
Not Rep
43,915
43,689
rce Recovorted Due To Low Resou ery
* Base Case
Table 4 a and b - Change in burn rate
Burn Rate
Inches
per hour
Cost of
Sales (S/BPD)
Initial Capital
Cost (000S/BPD)
S/BPD 5 7 9 11 13 S/BPD 3 5 7 9 11
* 0.5 8.77 6,946
2.0 8.29 5,434
4.0 8.30 5,307
* Base Case
Burn Rate
Centimeters
Hour
Cost of
Sales (S/CuM/Day)
Initial Capital
Cost (S/CuM/Day)
$ /CuMPD 35 45 55 65 75 S /CuMPD 20 30 40 50 60
* 1.27
5.08
10.16
55.16
52.14
52.20
43,689
34,179
33, 380
* Base Case
burn rates, not having an effect on cost,
indicate the need to spread out the opera
tion and enlarge the drift to meet ventila
tion requirements and each retort more
rapidly. This, in turn, means that more
mining areas are active and more equipment
is required.
Change in Depth - This change (table 5)
does not have a major effect on capital cost;
only the cost of sales is affected to any
degree. The 1500-ft (457.2 m) depth is not
reported because of low resource recovery.
This depth could possibly be designed for
adequate resource recovery by using an in
cremental pillar design, rather than a
weakest point. The system design used,
which minimizes the number of shafts re
quired, is partially responsible for the
small effect of depth on cost. Cost of
constructing and operating shafts is quite
small when compared to total capital and
operating costs. Major items related to
depth are shafts, hoisting, pumping, pipe
lines, electric feeder lines and ventila
tion.
Change of Swell Factor - This change
(table 6) produces a definite improvement in
cost, directly related to reduction of the
swell factor. Overall costs of the process
will be improved by reducing swell factor
to the lowest practical value consistent
with the pressure losses in the retort.
This is an area in which field research will
pay high dividends by developing the optimum
drilling and blasting technique to produce
the proper size of rubble. The goal of
drilling and blasting should be to obtain
uniform fragmentation of the oil shale
while minimizing the fines generated in the
blasting process. Reduction in swell factor
tends to make the entire mining process more
efficient as there is less swell room exca
vation per ton of material to be rubblized
thus achieving a lower ton-ratio. Table 7 a and b Change in retorting
efficiency
Table 6 a and b - Change in swell factor
Swell Factor
Percent
Cost of
Sales (S/BPD)
Initial Capital
Cost (000S/BPD)
S/BPD 5 7 9 11 13 S/BPD 3 5 7 9 11
15
20
* 25
7.96
8.38
8.77
6,387
6,659
6,946
=
* Base Case
Swell Factor
Percent
Cost of
Sales (S/CuM/Day)
Initial Capital
Cost (S/CuM/Day)
S/CuMPD 35 45 55 65 75 S/CuMPD 20 30 40 50 60
15
20
* 25
50.07
52.71
55.16
40,173
41,884
43,689
* Base Case
Retorting
Efficiency
Percent
Cost of
Sales (S/BPD)
Initial Capital
Cost (000S/BPD)
S/BPD 5 7 9 11 13 S/BPD 3 5 7 9 11
* 60
65
70
8.77
8.22
7.78
6,946
6,549
6,239
* Base Case
Retorting
Efficiency
Percent
Cost of
Sales (S/CuM/Day)
Initial Capital
Cost (S/CuM/Day)
S/CuMPD 35 45 55 65 75 S/CuMPD 20 30 40 50 60
* 60
65
70
55.16
51.70
48.93
43,689
41,192
39,242
* Base Case
Table 8 a and b - Change in entry height
Change in Retorting Efficiency- This
change (table 7) has an inverse effect on
costs; as the efficiency rises, costs drop.
This is a logical result and is to be
expected. Research by chemical engineers
should be continued at a high level with its
objective being increased retorting
efficiency as the grade of shale
decreases. Greater retorting efficiency
will increase resource recovery and make more
of the reserves economically available for
production. A better understanding of the
retorting reaction is needed to make pre
dictions as to the additional amount of kero
gen obtainable from the walls and pillars of
the retort.
Change in Entry Height - This change
(table 8) produces a surprise: capital cost
increases with a smaller entry. The unex
pected effect was traced to an increase in
the number of air and exhaust shafts needed
because of the lower capacity of smaller
tunnels and drifts to carry air for ventila
tion. In our final report to the Bureau of
Mines, we investigated this variable further
and found it affected many of the input val
ues. In fact, of 90 values listed, 39
changed with reduction in drift height; of
these 39 values, 21 decreased and 18 in-
Entry Height
Feet
Cost of
Sales (S/BPD)
Initial Capital
Cost (O00S/BPD)
S/BPD 5 7 9 11 13 S/BPD 3 5 7 9 11
20
* 30
8.77
8.77
7,490
6,946
8b
* Base Case
Entry Height
Meters
Cost of
Sales (S/CuM/Day)
Initial Capital
Cost (S/CuM/Day)
S/CuMPD 35 50 55 65 75 S/CuMPD 20 30 40 50 60
6.096
* 9.144
55.16
55.16
47,111
43,689
* Base Case
creased. This change produced a compensat
ing reaction in cost of sales and increased
initial capital investment. This exercise
especially well demonstrates the value of
having a computer design model. Such a
model provides the designer with a valuable
tool to test alternative ideas and deter
mines economic feasibility before committing
large sums of money to mine development.
Change in Retort Height - Table 9 is
made up for 15 gallons-per-ton (51.5 liters/
tonne) only, rather than the incomplete base
case, because a full range of values is
available for this grade. As would be
Table 9 a and b - Change in retort height Table 10 a and b - Equipmentselection
Retort Height
Feet
Cost of
Sales (S/BPD)
Initial Capital
Cost (000S/BPD)
S/BPD 5 7 9 11 13 S/BPD 3 5 7 9 11
230
380
530
11.59
10.46
9.46
9,195
8,992
8,651
Retort Height
Meters
Cost of
Sales (S/CuM/Day)
Initial Capital
Cost (S/CuM/Day)
S /CuMPD 35 45 55 65 75 S/CuMPD 20 30 40 50 60
70.10
115.82
161.54
72.90
65.79
60.63
57,835
56,495
54,413
10a1
Equipment
Cost of
Sales (S/BPD)
Initial Capital
Cost (000S/BPD)
S/BPD 5 7 9 11 13 S/BPD 3 5 7 9 11
FEL-T-C **
LHD-FB ***
8.77
7.67
6,946
5,935
Equipment
Cost of
Sales ($/CuM/Day)
Initial Capital
Cost (S/CuM/Day)
S/CuMPD 35 45 55 65 76 $/CuMPD 20 30 40 50 60
FEL-T-C **
LHD-FB ***
55.16
48.24
43,689
37,330
* Base Case
** Front-end Loader-Truck-Crusher
*** Load-Haul-Dump Feeder Breaker
expected, table 9 shows that variation in
retort height has a major effect on the
costs. While costs decrease as the retort
height increases, resource recovery also
decreases as the retort height increases,
conversely decreasing the life of the prop
erty. The decrease in resource recovery is
traceable directly to the rock mechanics
requirements for slender, stable pillars.
These requirements are related to the L/R
ratio of the pillars which, in turn, affects
extraction ratio, a part of the resource
recovery calculation.
Equipment Selection - This item (table
10) also has a significant effect on cost.
The initial design base case visualized the
use of large, front-end loaders and haul
trucks for the load-and-haul cycle, with the
rock being crushed before delivery onto a
conveyor belt. However, a significant cost
reduction is achieved when load-haul-dumps
(LHD) are combined with feeder-breakers.
The inherently more efficient operation of
the LHD and feeder-breaker units, with
resulting lower unit operating costs and
fewer units required, reduces costs. The
need to match equipment to specific portions
of the work is apparent. Several other
equipment categories, such as drilling and
raise and tunnel boring, merit the same
detailed study manner to effect further
cost reductions.
Permissibility- A proposal to open a
new mine in the deeper, central part of the
Piceance Creek basin (Colorado) ,where gas
is almost certain to be present, immediate
ly raises questions of permissibility and
the effect of"permissible"
regulations.
Table 11 represents the impact on cost of
these regulations if all underground equip
ment is included. Related costs, as shown,
reflect fire protection control, ventila
tion, equipment and explosives. Some of the
proposed equipment cannot be certified at
present because no large engine testing
facility is available. No permissible ex
plosives are currently in use in experi
mental oil shale mines and, if they are not
required, their impact on cost may not be
as great as shown.
Composite Runs - The effect of combining
various good or positive parameters into a
new set of operating conditions is partially
demonstrated in table 12. The result is a
domino effect: costs decrease more rapidly
than would be expected by arithmetic pro
gression. This process illustrates the com
plex interactions which occur in the design
of a modified in situ facility. It also
gives research and engineering some pre-
Table 11 a and b -
PermissibilityTable 12 a and b - Composite runs
Cost of
Sales (S/BPD)
Initial Capital
Cost (0OOS/BPD)
S/BPD 5 7 9 11 13 S/BPD 3 5 7 9 11
* Nonpermissible
Permissible
8.77
11.70
6,946
8,712
lib
* Base Case
Cost of
Sales (S/CuM/Day)
Initial Capital
Cost (S/CuM/Day)
S/CuMPD 35 45 55 65 75 S/CuMPD 20 30 40 50 60
* Nonperaissible
Permissible
55.16
73.59
43,689
54,797
* Base Case
liminary goals to achieve:
Optimize burn rate
Lower swell factor
Increase retorting efficiency
. Select proper equipment
Adjust mine opening size to be com
patible with equipment size.
Other Investigations-
During the course
of this study, otherinvestigations were
conducted as a part of the total effort:
(1) Scheduling- Critical paths were
constructed for both room and
pillar and tunnel boring systems,
(2)Multi- level development
- Improving
resource recovery by shortening
retort pillars and using multi
level mining. No significant
improvement was found without
restabilization.
(3) Combination in situ and surface
retorting- A brief study of the
combination system was conducted
and, on the basis of information
then available for surface retort
ing, the system showed signifi
cant improvement in both cost of
sales and initial capital cost.
(4) Energy balance - The systems postu
lated will produce a positive
energy ratioof from 5.25 to
13.95, depending upon the par
ticular combination of variables
and conditions.
P - 7949 CuM/Day
G - 68.68 Liters/Tonne
D - 304.8 Meters
RH - 70.10 Meters
BR
SF
RE
DH
Equip.
1.27 Cm/Hr
25 percent
60 percent
9.14 Meters
5.08 Cm/Hr 10.16 Cm/Hr
20 percent 15 percent
65 percent 70 percent
6.09 Meters 6.09 Meters
FEL-TR-CRUSH LHD-FB LHD-FB
* Base Case
The economic evaluation used consisted
of a discounted cash flow. Return on invest
ment calculation (fig. 3) shows rate of
return plotted against selling price per
barrel. The plot gives an indication of the
economic feasibility of the process. This
calculation does not include bonus bid pay
ments. These are a front-end cost, reduc
ing discounted cash flow return on invest
ment by some unspecified amount, depending
upon the tract bid price.
(Bonus Bid Payments Not Included)
(Bonus Bid Payments Not Included)
b
^Y"^/)^Room & Pillar Mining
Y\ Base Case 40
I I 20.0-
O E1 /
| Tunnel Boring Mining
Base Case 40
10.0-
O c
8 o
50"
1
1
1
1
1
I . . j
10.0 15.0 20.0 25.0 30.0
60 90 120 150 180
Selling Price of Shale Oil ($/bbl.) and ($/CuM)
Selling Price of Shale Oil ($/bbl) and ($/CuM)
Figure 3. - Return on investment vs selling
price.
Summary
1. We conceived and designed two mining
systems .
2. We developed a computer program to
model the systems.
3. We made studies of the effect of
significant variables on cost.
4. We made an economic evaluation of the
two mining systems.