S3_110930 PPP Presn_Sidharath Kapur

download S3_110930 PPP Presn_Sidharath Kapur

of 27

Transcript of S3_110930 PPP Presn_Sidharath Kapur

  • 8/3/2019 S3_110930 PPP Presn_Sidharath Kapur

    1/27

    1

    Project Structuring, Development and Financing of

    Delhi International Airport

    Sidharath Kapur

    CFO Airports,

    GMR Group, India

    The views expressed in these presentations are the views of the author and do not necessarily reflect the views or policies of

    the Asian Development Bank (ADB), or its Board of Directors or the governments they represent. ADB does not guarantee the

    source, originality, accuracy, completeness or reliability of any statement, information, data, finding, interpretation, advice,opinion, or view presented, nor does it make any representation concerning the same.

  • 8/3/2019 S3_110930 PPP Presn_Sidharath Kapur

    2/27

    Models of Privatization

    22

    Design and

    Build (D&B)

    D & B +

    Finance (D, B

    &F)

    DB&F +

    Maintain

    (DBF&M)

    DBF&M +

    Operate

    (DBFO&M)

    D&B+Own

    and Operate

    (DBOO)

    DBOO +

    Transfer

    (DBOOT)

    Privatization

    Ownership Govt Govt Govt Govt Private Private Private

    Investment Govt Govt Govt Govt Private Private Private

    Management Govt Govt Private Private Private Private Private

    Private

    SectorInvolvement

    Subcontract

    D&B

    Subcontract

    D & B

    DBF & Asset

    Maintenance

    DBFM +

    Operations

    Own and

    Operate

    Own and

    Operate

    Own

    Common Concession

    Formats

    Govt may retain partial

    equity in SPV

    Public Float,

    Private Sale,

    Joint Venture

    Delhi International Airport a specimen of DBOOT Model

  • 8/3/2019 S3_110930 PPP Presn_Sidharath Kapur

    3/27

    3

    Privatization Objectives - Government

    Infrastructure

    Required Airport Infrastructure

    Milestones for Capacity Expansion

    Time lines for construction

    Operations

    Financial and

    Economic

    Performance Standards

    Smooth and Uninterrupted operations

    Safety

    Concession Fees/Equity Valuation

    Government Guarantees and SupportTermination Payments

    Strong Sponsors

    Change of Control Restrictions

    Financial Viability

    Project Stability

    Control and

    Oversight

    Regulation Framework

    Change in Law

    Public Interest

  • 8/3/2019 S3_110930 PPP Presn_Sidharath Kapur

    4/27

    4

    Privatization Objectives - Concessionaire

    Financial

    Fair compensation to Investors for RisksCommercial Case

    Reliable Business Case

    Competitive Debt Financing

    Transparent and Predictable Regulation that

    covers Risk Based Cost of Equity and Debt Servicing

    Stability

    Operations

    Concession Period

    Long term Commitment of Government

    Legal and Political Stability

    Competing Airports

    Government Support for Security, ATC, Services

    Media and Public Perception

    Cost of Operation

    Independent Regulator or Concession Based Regulation

    Transparent and Predictable

    Commercial Expectations to be honored

    Non-Utility Based Risk coverage of Cost of Equity

    Ability to Service Debt

    Regulation

  • 8/3/2019 S3_110930 PPP Presn_Sidharath Kapur

    5/27

    5

    Privatization Objectives - Lenders

    Bankable

    Propositions

    Clear Regulatory Framework

    Sound and Viable Concession

    Predictable Revenue Streams

    Debt Servicing Ability

    Compensation and Termination

    Sponsors

    Other Issues

    Experience and Ability

    Stable Shareholding structure

    Financial Strength

    State of Airline Industry

    Direct AgreementsAbility to manage capital cost and timelines

  • 8/3/2019 S3_110930 PPP Presn_Sidharath Kapur

    6/27

    Delhi Transaction Agreement

    66

    30-year concessions agreement with a further 30 year option

    A mandatory Capital Expenditure program (key projects) to be completed byMarch 2010

    Massive liquidated damages for non-compliance

    Objective and subjective service standards

    Aeronautical charges currently as per AAI rates. In future, an independentregulator (AERA) to decide

    Limiting the use of land for non-Aero purposes to 5%.

    Retention of all staff initially and then of a significant number even after 3-years.

    ATC would still be under the control of AAI/DGCA.

    First right of refusal, if within 10% of best bid for a second airport within 150 km.

  • 8/3/2019 S3_110930 PPP Presn_Sidharath Kapur

    7/27

    Government Support (SSA, SGSA)

    77

    Passenger Service Fees Entitlement of Facilitation Component (35% of Fees)

    Tariff Increase as per SSA Schedule 1 Hybrid Till

    Clearances Assistance to take early clearances. Single window clearance

    mechanism.

    GOI Services Customs, Immigration, Security, Meteorological etc.

    ROFR Right of first refusal in case of new airport within 150 km radius.

    State Government Support Land availability for development, surface access

    to Airport, supply of Utilities, Clearances

  • 8/3/2019 S3_110930 PPP Presn_Sidharath Kapur

    8/27

    Lifeline of Delhi Airport Project

    8

    Baseline AAI approvesmodernizationproposal

    June 2003

    Issue of RFPApril 2005

    Start of New Dom.

    Terminal Ops

    April 2009

    Terminal 3Commissioning

    July 2010

    Award of

    Contract

    Jan 2006

    3rd Runway

    Ops begin

    Nov 2008

    Court Case on the Bid

    Decision

    Feb 2006

    Takeover of

    Operations

    May 2006

    Delhi Overtakes Mumbai as thebusiest airport in India FY 2011

    Supreme Court

    Clearance

    Sep 2006

    Foundationstone &

    Financial

    closure for T3

    Feb 2007

    Intl. Terminalrenovation causing

    passenger

    inconvenience

    2008

    Upgrade of Intl. TerminalComplete

    Jun 2008

  • 8/3/2019 S3_110930 PPP Presn_Sidharath Kapur

    9/27

    Delhi Airport Project - Highlights

    9

    Phase 1A Completed in mid 2008 Phase 1B Completed in Mar 2010

    Phase I Phase V

    Completion date 2010 2035

    Pax capacity (mm) 60 100

    Cargo cap. (mm tons) 0.5 3.6

    Runways 3 4

    PTB area (mm sqft) 5.5 17.2

    Key contracts awarded

    Design engineers: Mott McDonald, UK

    Project management consultants:

    Parsons Brinckerhoff, USA

    3rd runway and Terminal 3: L&T

    Terminal 3

    Terminal 1D

    Third Runway (4,430m)

    Taxiways, fire stations, associated infrastructure

    Upgrading of international terminal

    New interim domestic terminal, T1D already commissioned

    Terminal building (built-up area ~5mm sq fleet)

    78 aerobridges

    High speed rail link

    Multi-level car parking (4,300 lots)

    General aviation facilities expansion/upgrade of utilities

    A

    B

    D

    E

    C

    Existing international terminal building

    New integrated terminal building (T3)

    New runway

    Existing domestic terminal

    Land bank (250 acres)

    A

    B

    C

    D

    E

    Development plan overview over five phases Master development plan

  • 8/3/2019 S3_110930 PPP Presn_Sidharath Kapur

    10/27

    Airport Capacity, mppa Floor Area, sq m

    Construction

    Period, months

    London Heathrow 28 353,000 72

    Madrid 42 757,000 70

    Bangkok 45 563,000 60

    Kuala Lumpur 25 479,000 54

    Beijing 43 900,000 52

    Delhi T3 34 502,000 37

    Source: Jacobs Benchmarking study, 2009

    Timeline Challenges

  • 8/3/2019 S3_110930 PPP Presn_Sidharath Kapur

    11/27

    Minimum Connect Time

    Domestic/International 60 Minutes International/International 45 Minutes

    90% of all Passengers served by fixed bridges

    95% of Passengers wait less than 10 minutes at each ofImmigrations, Security and Customs facility

    Maximum queuing time at check in less than 20 minutesand 5 minutes for Economy & Business Class respectively

    95% of passengers take less than 45 minutes for arrivals

    OMDA Standard Challenges

  • 8/3/2019 S3_110930 PPP Presn_Sidharath Kapur

    12/27

    Seating for 80% of Gate Lounge Population

    Domestic First Bag 10 minutes, Last bag 30 minutes,International First bag 15 minutes, Last bag 40 minutes

    Car Parking

    Average time taken to find parking space 95% of drivers takeless than 5 minutes

    Average time depart airport from parking space 95% of driverstake less than 5 minutes

    Taxis Maximum waiting time 95% of passengers wait less than 3

    minutes

    OMDA Standard Challenges

  • 8/3/2019 S3_110930 PPP Presn_Sidharath Kapur

    13/27

    The Initial estimate was based on certain scope which has undergone many

    changes thereafter because of growth in traffic and change in specifications.

    For Project cost to be finalized, first we need to have all drawings in place. These

    drawings would have needed anything from 9 months to a year to be finalized.

    Thereafter they would have gone for bidding which could have taken anywhere up to

    6 months to finalize the construction contract and the Project cost.

    Since there was no time available in view of ensuing commonwealth games a

    parallel build and design philosophy was adopted.

    As such all the numbers shown as project cost are costs visualized at that

    stage.

    The initial project cost was based on limited number of drawings and was

    preliminary in nature. In this scenario, unless major packages were awarded, DIAL

    was not in a position to realistically estimate the project cost revisions.

    Project Cost Variation

  • 8/3/2019 S3_110930 PPP Presn_Sidharath Kapur

    14/27

    DescriptionInitialEstimate

    FirmedUp Cost

    Variance

    T1, T2 & initial CWIP 762 754 (8)

    Runway/taxiway/apron/ lighting 1,765 2,634 869

    Terminal 3 and Associated Buildings 4,669 6836 2,167

    Airport Services Building & Airport ConnectionBuilding

    160 160

    Preliminary, Preoperative & IDC 1,279 1,320 41

    Metro 350 350 -

    Upfront payment to AAI 150 150 -

    Rehabilitation of Runway 10-28 110 110

    Delhi Jal Board infrastructure funding 54 54

    New ATC Tower with Equipment 350 350

    Security Capex 139 139

    Total 8,975 12,857 3,882

    Figures in Rs. Crores

    Project Cost Variation

  • 8/3/2019 S3_110930 PPP Presn_Sidharath Kapur

    15/27

    Sl.No

    Particulars Total Terminal 3Airside/Landside

    Others

    a) Area/ Volume/ Specification Variance 1,446 1015 431

    b) Material Price Variation 973 705 268

    c) Other Items 617 447 170

    d)Addl. buildings (Airport ServicesBuilding +Airport Connection)

    160 160

    e) New ATC Tower with Equipment 350 350

    f) Runway-10/28 Rehabilitation 110 110

    g) Delhi Jal Board 54 54

    h) Preliminary Preoperative & IDC 41 41

    i) T1, T2 & other CWIP (8) (8)j) Security Related 139 139

    Total 3,882 2,167 869 846

    Figures in Rs. Crores

    Project Cost Variation

  • 8/3/2019 S3_110930 PPP Presn_Sidharath Kapur

    16/27

    Overall Cost Parameters BKK KUL PEK LHR MAD DEL Median Result

    BangkokKuala

    LumpurBeijing London Madrid Delhi

    Terminal Size (MPPA)

    Actual Cost

    Total Actual Cost (in millionUS$ and documented)

    2,800.00 1,600.00 3,800.00 4,100.00 2,948.20 1,659.90 2,874.10 Second

    Actual cost per mppa (inmillion US$) 62.20 64.00 88.40 146.40 $70.20 $48.80 67.10 Lowest

    Actual Cost / m2 of GFA(in US$)

    4,973.40 3,337.5 4,222.20 11,614.1 3,894.60 3,306.50 4,058.40 Lowest

    Adjusted Cost

    Adjusted Total Costs (in2008 million US$)

    3,354.90 3,079.50 4,213.10 4,151.20 3,353.90 2,496.30 3,354.40 Lowest

    Total Cost / mppa (in2008 million US$)

    74.60 123.20 98.00 148.30 79.90 73.40 88.90 Lowest

    Total Cost / m2 of GFA (in2008 US$)

    5,959.00 6,423.60 4,681.30 11,759.0 4,430.60 4,972.60 5,465.80 Third

    Terminal 3 is the most capital efficient and economical amongstTerminal 3 is the most capital efficient and economical amongstTerminal 3 is the most capital efficient and economical amongstTerminal 3 is the most capital efficient and economical amongst comparable Terminalscomparable Terminalscomparable Terminalscomparable Terminals

    Benchmarking by Jacobs

  • 8/3/2019 S3_110930 PPP Presn_Sidharath Kapur

    17/27

    Particulars Financial Closure Final Amount

    Equity-Shares Allotted 1,200 1,200

    Equity-Share Application Money - 1,250

    Internal Accruals 50 50

    Lease Deposits / Trade Deposits 2,739 1,471

    Rupee Term loan 3,650 3,650

    External Commercial Borrowing (ECB) 1,336 1,616

    Development Fee (Incl additional) - 3,620

    Total 8,975 12,857

    Figures in Rs. Crores

    Means of Finance

  • 8/3/2019 S3_110930 PPP Presn_Sidharath Kapur

    18/27

    Delhi Airport: Maximizing Value Through Suitable Joint Ventures

    18

  • 8/3/2019 S3_110930 PPP Presn_Sidharath Kapur

    19/27

    Joint Venture & Demerger

    Partner with third party to off-load assets/asset creation obligation and

    consequential financing burden.

    JVC obligated to arrange and manage financing.

    Upfront security deposit from JV.

    Collected c.USD 115 mn of security deposits Vs c.USD 45 mn of investmentoutlay.

    Revenue Sharing as % of Gross Sales.

    USD 440 million of assets/asset creation obligation off books.

    Long term valuation creation through equity holding.

    19

    Joint Ventures

  • 8/3/2019 S3_110930 PPP Presn_Sidharath Kapur

    20/27

    Funding Long & Short terms

    Rupee Financing INR 36,500 million commitments

    Consortium of 10 Rupee banks. Limited exposure for each bank

    Moratorium of 5 years with door to door commitment of 17 years

    Ease of disbursement

    USD Financing USD 350 mn commitment

    7 international banks in consortium of 8 banks

    5 year moratorium with door to door commitment of 13 years

    No disbursement for 1.5 years due to global financial meltdown

    Decision to replace international banks with domestic banks for USD borrowings

    Cost of borrowing increased from Libor + 175 bps to 475 bps

    Short term bridge loans Gap funding to meet the ECB delay Lower financing cost @7% to 9.5%

    Bullet repayment in 6 months from date of disbursement

    20

    Funding Challenges Putting the debt together

  • 8/3/2019 S3_110930 PPP Presn_Sidharath Kapur

    21/27

    Comfort to Lenders

    2121

    Share Pledge Agreement 30% Pledge over shares

    Non Disposal of Shares and Safety

    Net Arrangement Agreement

    21% NDU over shares

    Deed of Hypothecation First charge on all the revenues / receivables

    Airport Operator Direct AgreementAssignment of Insurance Policies

    First charge/assignment of all the rights;titles, permits, etc. of the Project Document

    Substitution Agreement In the event of default lenders can

    substitute operator with some other entity.

    GOI Guarantee as per SSA GoI guarantying transfer payment shortfall

    in the event AAI doesnt pay.

  • 8/3/2019 S3_110930 PPP Presn_Sidharath Kapur

    22/27

    Delhi Airport 2008 Credit Crunch

    Early 2008

    T1 & T2 under operations

    Modernization and new integrated terminal T3

    Under construction

    World record time lines-37 months

    Contracts awarded at peak in 2007

    Design & Build process Cost plus

    Financing tied up Dec 07 Indian &

    Foreign Lenders

    46% Committed revenue share

    Traffic increasing at steady pace

    Int Pax @9% , ATM @5.62%

    No regulator in place

    Land Bank of 250 acres-partly to be used for

    financing modernization and expansion Airlines flourishing - New flights, destination

    added

    22

    2008 End

    Challenges on both top & bottom line Traffic declined

    Real estate market crashed leading to fund

    gap of $ 400 mn

    ECB draw down held up $350 mn

    Inflation causing project cost over runs Committed revenue share payment to AAI

    Maintenance of highest service standards

    irrespective of cost

    Delay in DF approval

    Funding Challenges 2008 Credit Crunch

  • 8/3/2019 S3_110930 PPP Presn_Sidharath Kapur

    23/27

    Land Monetization

    Pure land monetization instead of self-development

    Upfront deposit 3 times Avg. Annual Rentals vs 6 years AAI requirement

    Mid 08, bid open for 45 acres land monetization

    Un favorable response from market - deferred for 15 acres

    Realized better rates higher by ~30%

    23

    Asset Areas

    Area in

    acres

    Advance Lease Deposit

    USD Mn

    First Round 30 186

    Second Round 15 134

    Total 45 320

    Land Monetization

  • 8/3/2019 S3_110930 PPP Presn_Sidharath Kapur

    24/27

    DF approval by Government to fill funding gap from funding from Land monetization

    Separate revenue stream securitized to bridge financing gap without impacting long

    term debt/equity or DSCR.

    Consortium of 7 Indian banks

    Repayment of securitized loan from DF collections

    24

    Passenger type Tickets purchased in INR

    (including taxes & levies)

    Domestic Sectors INR 200 per departing pax

    International Sectors INR 1,300 per departing pax

    Period 36 months effective 01 Mar 09

    Aggregate Amount ~ USD 400 mn first tranche

    (NPV basis)*

    Delhi-Securitization of Development Fee (DF)

    *Second tranche of DF is pending regulator approval

  • 8/3/2019 S3_110930 PPP Presn_Sidharath Kapur

    25/27

    Delhi Airport: Creating world-class capacity forIndias busiest airport

    25

    Land side facilities

    168 check in counters

    Multilevel Car Park Facility for 4,300

    cars & Surface Parking 2300 cars

    Retail area of 30,000 sq. m

    Air side facilities

    75 Aerobridges

    48 contact stands

    9 remote parking stands

    Brief project overview Financing (USD bn)

    Key recent developments

    Concession period of 30 years + option for

    another 30 years at the option of DIAL

    45.99% revenue share with AAI

    5,100 acres of total land available for

    operations and development

    ROFR till 2036 for a second airport within 150

    kms of the existing airport

    ROFR with the existing consortium partners in

    case of exit by an existing partner

    54.0%26.0%

    10.0%

    10.0%

    T3 key project features

    Completion of Phase IA ahead of the planned schedule

    Construction of Terminal 1D, and up gradation of 1C, 1D & T2

    completed

    Longest runway in the country

    New runway (CAT 3B lighting for landing at 50m visibility, can

    accommodate A380s) and taxiways completed 6 months ahead of

    schedule

    Phase-IB: Development of New Integrated Terminal (T3) complete

    Installation of aerobridges, travelators, baggage handling and

    cooling systems completed

    Contracts for duty-free/retail awarded for T3; other major non-

    aero contracts awarded

    Consortium partners

    Airport Capacity Time

    Changi Airport Singapore

    (T3)

    22 Million 76 months

    Heathrow T5 L ondon, UK 25 Million 60 months

    Beijing Airport New terminal

    for Olympics T3, China

    45 Million 60 months

    IGI Airport T3, New Delhi,

    India

    34 Million 37 months

  • 8/3/2019 S3_110930 PPP Presn_Sidharath Kapur

    26/27

    Operational Challenges

    2626

    Challenges Mitigation

    Loss of Job for govt. employees Retention of all staff initially and then of a significant

    number even after 3-years

    To get in sync over 50 agencies MoCA, AAI, BCAS, DGCA, Airlines, Electricity, Water,Environment, Health, CISF, DDA, NHAI, HUDA, Cargo,

    Customs, Cargo, Agriculture, Oil Cos., Metrological etc.

    SLAs with govt. operated

    activities like ATC, Customs,

    Security

    Educating and accounting various organization.

    Winning the trust

    Negative perception of Joint

    Ventures

    Educating of OMDA rights

    Educating of global practices

  • 8/3/2019 S3_110930 PPP Presn_Sidharath Kapur

    27/27

    Operational Challenges:Constant endeavor to improve passengers experience

    27

    Commercialoperations from

    T1D begun in

    April, 2009

    Commercial operations

    from T3 Internationaloperations from Jul10 &

    domestic operations from

    Nov10

    DIAL received accolades from GoI & travelers for efficient airport operations

    during evacuation of Indian nationals, many without valid travel / citizenship

    documents, from Egypt & Libya

    ASQ Score

    Ranked 101st

    (out of 101) in 2007ranked 12th

    (out of 154) in 2010airports worldwide