    Observational Method in

    Geotechnical Engineering

    Robert J. Werner, P.E.

  • 7/29/2019 S17_I-20 Mississippi River Bridge at Vicksburg Geotechnical Solutions_LTC2013

    2/42

  • 7/29/2019 S17_I-20 Mississippi River Bridge at Vicksburg Geotechnical Solutions_LTC2013

    3/42

    FAILURE PLANE

  • 7/29/2019 S17_I-20 Mississippi River Bridge at Vicksburg Geotechnical Solutions_LTC2013

    4/42

    Design Based on Most Probable Conditions

    Identify Worse-Case Eventualities

    Develop Reliable Monitoring Plan

    Predict Monitoring Outcomes

    Establish Action Plan (In Advance)

    Monitor & Report Promptly

    Modify Design / Implement Action Plan

    Peck 1969 Ninth Rankine Lecture Advantages and Limitations of theObservational Method in Applied Soil Mechanics

  • 7/29/2019 S17_I-20 Mississippi River Bridge at Vicksburg Geotechnical Solutions_LTC2013

    5/42

  • 7/29/2019 S17_I-20 Mississippi River Bridge at Vicksburg Geotechnical Solutions_LTC2013

    6/42

  • 7/29/2019 S17_I-20 Mississippi River Bridge at Vicksburg Geotechnical Solutions_LTC2013

    7/42

    LOUISIANA SITE

  • 7/29/2019 S17_I-20 Mississippi River Bridge at Vicksburg Geotechnical Solutions_LTC2013

    8/42

    Design Based on Lower-Bound Conditions

    Identify Worse-Case Eventualities

    Continue Monitoring Plan

    Predict Monitoring Outcomes

    Establish Improvement Plan

    Monitor & Report

    Implement Improvement Plan if Warranted

  • 7/29/2019 S17_I-20 Mississippi River Bridge at Vicksburg Geotechnical Solutions_LTC2013

    9/42

    Pleistocene

  • 7/29/2019 S17_I-20 Mississippi River Bridge at Vicksburg Geotechnical Solutions_LTC2013

    10/42

    Session 67

    Wednesday 10:00-11:45

    Room 2

    Robert J. Werner, P.E.

  • 7/29/2019 S17_I-20 Mississippi River Bridge at Vicksburg Geotechnical Solutions_LTC2013

    11/42

    I-20 & US-80 BRIDGES

  • 7/29/2019 S17_I-20 Mississippi River Bridge at Vicksburg Geotechnical Solutions_LTC2013

    12/42

    BRIEF HISTORY

  • 7/29/2019 S17_I-20 Mississippi River Bridge at Vicksburg Geotechnical Solutions_LTC2013

    13/42

    1929 RR BRIDGE SLOPE FAILURE

  • 7/29/2019 S17_I-20 Mississippi River Bridge at Vicksburg Geotechnical Solutions_LTC2013

    14/42

    U.S. 80BRIDGETOWER 1

    PEDESTALS

  • 7/29/2019 S17_I-20 Mississippi River Bridge at Vicksburg Geotechnical Solutions_LTC2013

    15/42

    FAILURE PLANE US-80 BRIDGE

    NB-10

  • 7/29/2019 S17_I-20 Mississippi River Bridge at Vicksburg Geotechnical Solutions_LTC2013

    16/42

    NEW INCLINOMETER BORING

    IPI-10R

    IPI-10R

  • 7/29/2019 S17_I-20 Mississippi River Bridge at Vicksburg Geotechnical Solutions_LTC2013

    17/42

  • 7/29/2019 S17_I-20 Mississippi River Bridge at Vicksburg Geotechnical Solutions_LTC2013

    18/42

    426 423 870 423 426

    W-3 W-2 W-1 E-1 E-2 E-3

    PP15 PP15E E EF F EFF F

    Suspended

    Span

    Anchor

    Span

    Simple

    Span

    Simple

    Span

    Anchor

    Span

    EastWest

    CantileverSpans

    I-20 BRIDGE MOVEMENT

  • 7/29/2019 S17_I-20 Mississippi River Bridge at Vicksburg Geotechnical Solutions_LTC2013

    19/42

    SUMMARY OF I-20 PIER MOVEMENTS

    (in) (arc-sec) (in) (arc-sec)

    1. 1999 and 2000 Prior to 5/2001 6.00 6.50

    2. 2003 Feb2/5/2003 to

    2/6/20030.50 50 0.50 0

    3. 2005 Aug 8/2/2005 0.75 0 0.50 50

    4. 2005 Nov 11/17/2005 0.25 0 0.25 0

    5. 2006 Aug - Sep8/13/2006 to

    9/21/20060.50 50 0.75 75

    6. 2007 Sep - Dec9/21/2009 to

    12/19/20070.50 50 0.50 25

    7. 2009 Sep - Dec0/28/2009 to

    12/22/2009

    0.20 25 0.00 20

    8. 2010 Nov11/7/2010 to

    11/22/20100.20 25 0.00 10

    9. 2011 Oct10/20/2011 to

    10/24/20110.25 0 0.25 25

    10. 2012 June - Sep6/29/2012 to

    9/21/20121.25 75 1.00 75

    10.50 300 10.25 300

    Top of Pier E-1Top of Pier E-2

    Estimated Time or Time Period

    Total Movement (+/-)

    1. Prior to 5/2001

  • 7/29/2019 S17_I-20 Mississippi River Bridge at Vicksburg Geotechnical Solutions_LTC2013

    20/42

    GENERALIZED PROFILE

  • 7/29/2019 S17_I-20 Mississippi River Bridge at Vicksburg Geotechnical Solutions_LTC2013

    21/42

  • 7/29/2019 S17_I-20 Mississippi River Bridge at Vicksburg Geotechnical Solutions_LTC2013

    22/42

  • 7/29/2019 S17_I-20 Mississippi River Bridge at Vicksburg Geotechnical Solutions_LTC2013

    23/42

  • 7/29/2019 S17_I-20 Mississippi River Bridge at Vicksburg Geotechnical Solutions_LTC2013

    24/42

  • 7/29/2019 S17_I-20 Mississippi River Bridge at Vicksburg Geotechnical Solutions_LTC2013

    25/42

    Peak Shear Strength = 5.4

  • 7/29/2019 S17_I-20 Mississippi River Bridge at Vicksburg Geotechnical Solutions_LTC2013

    26/42

  • 7/29/2019 S17_I-20 Mississippi River Bridge at Vicksburg Geotechnical Solutions_LTC2013

    27/42

    MOVEMENTS at I-8 (PIER E-2)

  • 7/29/2019 S17_I-20 Mississippi River Bridge at Vicksburg Geotechnical Solutions_LTC2013

    28/42

    3/31/11 BATHYMETRY

  • 7/29/2019 S17_I-20 Mississippi River Bridge at Vicksburg Geotechnical Solutions_LTC2013

    29/42

    SAA at I-8 (PIER E-2)

  • 7/29/2019 S17_I-20 Mississippi River Bridge at Vicksburg Geotechnical Solutions_LTC2013

    30/42

  • 7/29/2019 S17_I-20 Mississippi River Bridge at Vicksburg Geotechnical Solutions_LTC2013

    31/42

  • 7/29/2019 S17_I-20 Mississippi River Bridge at Vicksburg Geotechnical Solutions_LTC2013

    32/42

    INCLINOMETER I-12 at PIER E-1 (2003)

  • 7/29/2019 S17_I-20 Mississippi River Bridge at Vicksburg Geotechnical Solutions_LTC2013

    33/42

    I-12 InclinometerReading on

    March 11, 2012

    El. -63

    0.25 Additional DisplacementSince Last Reading in Oct. 2007

    Inclinometer Displacement isAbout 1/3 of Measured Topof Pier E-1 Movement

  • 7/29/2019 S17_I-20 Mississippi River Bridge at Vicksburg Geotechnical Solutions_LTC2013

    34/42

  • 7/29/2019 S17_I-20 Mississippi River Bridge at Vicksburg Geotechnical Solutions_LTC2013

    35/42

  • 7/29/2019 S17_I-20 Mississippi River Bridge at Vicksburg Geotechnical Solutions_LTC2013

    36/42

    Calibrate Stability & Deformation ModelsBased on Measured / Observed Conditions(Over the Past 84 Years)

    Identify Worse-Case Eventualities

    Develop Improvements That Do Not AlterFundamental Site Behavior

    Predict Monitoring Outcomes

    Establish Action Plan (Warning System,Structural Modifications)

    Continue Monitoring (Real-Time)

    Implement Additional Improvements, ifWarranted

  • 7/29/2019 S17_I-20 Mississippi River Bridge at Vicksburg Geotechnical Solutions_LTC2013

    37/42

    COMPLETE SCOUR HOLE FILLING

  • 7/29/2019 S17_I-20 Mississippi River Bridge at Vicksburg Geotechnical Solutions_LTC2013

    38/42

  • 7/29/2019 S17_I-20 Mississippi River Bridge at Vicksburg Geotechnical Solutions_LTC2013

    39/42

  • 7/29/2019 S17_I-20 Mississippi River Bridge at Vicksburg Geotechnical Solutions_LTC2013

    40/42

    STABILIZATION DRAINS

    I-20 DRAIN(1972)

    US-80DRAIN(1940s)

  • 7/29/2019 S17_I-20 Mississippi River Bridge at Vicksburg Geotechnical Solutions_LTC2013

    41/42

    SURFACE WATER DRAINAGE

  • 7/29/2019 S17_I-20 Mississippi River Bridge at Vicksburg Geotechnical Solutions_LTC2013

    42/42