1 I-74 Bridge Over Mississippi River Construction Travis Konda, PhD, PE, SE 2018 Midwest Geotechnical Conference, 27SEP18

Transcript of I-74 Bridge Over Mississippi River Construction...1 I-74 Bridge Over Mississippi River Construction...

Page 1: I-74 Bridge Over Mississippi River Construction...1 I-74 Bridge Over Mississippi River Construction Travis Konda, PhD, PE, SE. 2018 Midwest Geotechnical Conference, 27SEP18

1

I-74 Bridge Over Mississippi River Construction

Travis Konda, PhD, PE, SE2018 Midwest Geotechnical Conference, 27SEP18

Page 2: I-74 Bridge Over Mississippi River Construction...1 I-74 Bridge Over Mississippi River Construction Travis Konda, PhD, PE, SE. 2018 Midwest Geotechnical Conference, 27SEP18

2

Project Location and Scope

Page 3: I-74 Bridge Over Mississippi River Construction...1 I-74 Bridge Over Mississippi River Construction Travis Konda, PhD, PE, SE. 2018 Midwest Geotechnical Conference, 27SEP18

State-of-the-art Mississippi River Bridge

Page 4: I-74 Bridge Over Mississippi River Construction...1 I-74 Bridge Over Mississippi River Construction Travis Konda, PhD, PE, SE. 2018 Midwest Geotechnical Conference, 27SEP18

4

Project Leads

Page 5: I-74 Bridge Over Mississippi River Construction...1 I-74 Bridge Over Mississippi River Construction Travis Konda, PhD, PE, SE. 2018 Midwest Geotechnical Conference, 27SEP18

5

Project Team – 198M Contract (River Bridge)

• Designer – Benesch – EOR – Hanson – Geotech– Modjeski and Masters – Arch Spans

• General Contractor - Lunda Construction ($322 M)• Drilled Shaft Sub – Michels Foundation

• CEI – HNTB • GEC – AMEC

Page 6: I-74 Bridge Over Mississippi River Construction...1 I-74 Bridge Over Mississippi River Construction Travis Konda, PhD, PE, SE. 2018 Midwest Geotechnical Conference, 27SEP18

Project Scope – 198M Contract (River Bridge)

6

Page 7: I-74 Bridge Over Mississippi River Construction...1 I-74 Bridge Over Mississippi River Construction Travis Konda, PhD, PE, SE. 2018 Midwest Geotechnical Conference, 27SEP18

Shaft Installation – 198M Contract (River Bridge)

• 239 Production Drilled Shafts

• Water Shafts– 196 – 7 ft diameter (Approach Piers 2-11, 13-15)– 37 – 10 ft diameter (Arch Foundation Piers 12 and 13)

• Land Shafts– 6 – 10 ft diameter (Pier 16)

7

Page 8: I-74 Bridge Over Mississippi River Construction...1 I-74 Bridge Over Mississippi River Construction Travis Konda, PhD, PE, SE. 2018 Midwest Geotechnical Conference, 27SEP18

Shaft Installation – 198M Contract (River Bridge)

• Iowa DOT Specifications 2433 Concrete Drilled Shaft

• Contract payment– Drilled shaft, length installed (included concrete)– Rebar – lbs in cage, contract rebar

• Acceptance by CSL – Iowa DOT

8

Page 9: I-74 Bridge Over Mississippi River Construction...1 I-74 Bridge Over Mississippi River Construction Travis Konda, PhD, PE, SE. 2018 Midwest Geotechnical Conference, 27SEP18

Soil and Rock Profile

9

Page 10: I-74 Bridge Over Mississippi River Construction...1 I-74 Bridge Over Mississippi River Construction Travis Konda, PhD, PE, SE. 2018 Midwest Geotechnical Conference, 27SEP18

Drilled shaft Installation - CEI Tasks

• Continuous inspection, they are out there, we are out there• Top of rock determination• Drilling progress – document what is coming up • Determine shaft depth, hole preparation• Concrete placement• Drilled shaft report

– Time line– Depth– Yield

• Posting for payment

10

Page 11: I-74 Bridge Over Mississippi River Construction...1 I-74 Bridge Over Mississippi River Construction Travis Konda, PhD, PE, SE. 2018 Midwest Geotechnical Conference, 27SEP18

Approach Piers/Foundations

11

7 ft Drilled Shafts

Page 12: I-74 Bridge Over Mississippi River Construction...1 I-74 Bridge Over Mississippi River Construction Travis Konda, PhD, PE, SE. 2018 Midwest Geotechnical Conference, 27SEP18

Arch Pier/Foundations

12

Page 13: I-74 Bridge Over Mississippi River Construction...1 I-74 Bridge Over Mississippi River Construction Travis Konda, PhD, PE, SE. 2018 Midwest Geotechnical Conference, 27SEP18

Arch Pier/Foundations

13

Page 14: I-74 Bridge Over Mississippi River Construction...1 I-74 Bridge Over Mississippi River Construction Travis Konda, PhD, PE, SE. 2018 Midwest Geotechnical Conference, 27SEP18

Arch Pier/Foundations

14

Page 15: I-74 Bridge Over Mississippi River Construction...1 I-74 Bridge Over Mississippi River Construction Travis Konda, PhD, PE, SE. 2018 Midwest Geotechnical Conference, 27SEP18

Rigs and Equipment

• Contractor had three rigs working simultaneously, 8 to 14 hour days, working off of barges

• 2 – Liebherr L36 machines• 1 - IMF AF300 machine

15

Page 16: I-74 Bridge Over Mississippi River Construction...1 I-74 Bridge Over Mississippi River Construction Travis Konda, PhD, PE, SE. 2018 Midwest Geotechnical Conference, 27SEP18

Supporting Operations

16

Page 17: I-74 Bridge Over Mississippi River Construction...1 I-74 Bridge Over Mississippi River Construction Travis Konda, PhD, PE, SE. 2018 Midwest Geotechnical Conference, 27SEP18

Casing

17

Page 18: I-74 Bridge Over Mississippi River Construction...1 I-74 Bridge Over Mississippi River Construction Travis Konda, PhD, PE, SE. 2018 Midwest Geotechnical Conference, 27SEP18

Casing

18

Page 19: I-74 Bridge Over Mississippi River Construction...1 I-74 Bridge Over Mississippi River Construction Travis Konda, PhD, PE, SE. 2018 Midwest Geotechnical Conference, 27SEP18

Drilling Tools – Core Barrels and Augers

19

Page 20: I-74 Bridge Over Mississippi River Construction...1 I-74 Bridge Over Mississippi River Construction Travis Konda, PhD, PE, SE. 2018 Midwest Geotechnical Conference, 27SEP18

Drilling Tools – Flat Augers and Cleaning Pans

20

Page 21: I-74 Bridge Over Mississippi River Construction...1 I-74 Bridge Over Mississippi River Construction Travis Konda, PhD, PE, SE. 2018 Midwest Geotechnical Conference, 27SEP18

21

Drilling Tools

Page 22: I-74 Bridge Over Mississippi River Construction...1 I-74 Bridge Over Mississippi River Construction Travis Konda, PhD, PE, SE. 2018 Midwest Geotechnical Conference, 27SEP18

Drilling Tools – Down Hole Hammers

22

Page 23: I-74 Bridge Over Mississippi River Construction...1 I-74 Bridge Over Mississippi River Construction Travis Konda, PhD, PE, SE. 2018 Midwest Geotechnical Conference, 27SEP18

Drilling Tools – Down Hole Hammers

23

Page 24: I-74 Bridge Over Mississippi River Construction...1 I-74 Bridge Over Mississippi River Construction Travis Konda, PhD, PE, SE. 2018 Midwest Geotechnical Conference, 27SEP18

Drilling Tools – Down Hole Hammers

24

Page 25: I-74 Bridge Over Mississippi River Construction...1 I-74 Bridge Over Mississippi River Construction Travis Konda, PhD, PE, SE. 2018 Midwest Geotechnical Conference, 27SEP18

Establishing Top of Rock

25

Page 26: I-74 Bridge Over Mississippi River Construction...1 I-74 Bridge Over Mississippi River Construction Travis Konda, PhD, PE, SE. 2018 Midwest Geotechnical Conference, 27SEP18

Hole – Final Preparation

26

Page 27: I-74 Bridge Over Mississippi River Construction...1 I-74 Bridge Over Mississippi River Construction Travis Konda, PhD, PE, SE. 2018 Midwest Geotechnical Conference, 27SEP18

27

Environmental Requirements

Page 28: I-74 Bridge Over Mississippi River Construction...1 I-74 Bridge Over Mississippi River Construction Travis Konda, PhD, PE, SE. 2018 Midwest Geotechnical Conference, 27SEP18

28

Environmental Requirements

Page 29: I-74 Bridge Over Mississippi River Construction...1 I-74 Bridge Over Mississippi River Construction Travis Konda, PhD, PE, SE. 2018 Midwest Geotechnical Conference, 27SEP18

Environmental Requirements - Sandbagging

29

Page 30: I-74 Bridge Over Mississippi River Construction...1 I-74 Bridge Over Mississippi River Construction Travis Konda, PhD, PE, SE. 2018 Midwest Geotechnical Conference, 27SEP18

Drilled Shaft Reinforcement – 7 ft

30

Page 31: I-74 Bridge Over Mississippi River Construction...1 I-74 Bridge Over Mississippi River Construction Travis Konda, PhD, PE, SE. 2018 Midwest Geotechnical Conference, 27SEP18

Drilled Shaft Reinforcement – 10 ft

31

Page 32: I-74 Bridge Over Mississippi River Construction...1 I-74 Bridge Over Mississippi River Construction Travis Konda, PhD, PE, SE. 2018 Midwest Geotechnical Conference, 27SEP18

Drilled Shaft Reinforcement – 10 ft

32

Page 33: I-74 Bridge Over Mississippi River Construction...1 I-74 Bridge Over Mississippi River Construction Travis Konda, PhD, PE, SE. 2018 Midwest Geotechnical Conference, 27SEP18

Drilled Shaft Reinforcement – 10 ft

33

Page 34: I-74 Bridge Over Mississippi River Construction...1 I-74 Bridge Over Mississippi River Construction Travis Konda, PhD, PE, SE. 2018 Midwest Geotechnical Conference, 27SEP18

Concrete Placement

• Iowa DOT mix D-57-C15

34

Page 35: I-74 Bridge Over Mississippi River Construction...1 I-74 Bridge Over Mississippi River Construction Travis Konda, PhD, PE, SE. 2018 Midwest Geotechnical Conference, 27SEP18

Concrete Placement

35

Page 36: I-74 Bridge Over Mississippi River Construction...1 I-74 Bridge Over Mississippi River Construction Travis Konda, PhD, PE, SE. 2018 Midwest Geotechnical Conference, 27SEP18

Drilled Shaft Reports – DSR

36

Page 37: I-74 Bridge Over Mississippi River Construction...1 I-74 Bridge Over Mississippi River Construction Travis Konda, PhD, PE, SE. 2018 Midwest Geotechnical Conference, 27SEP18

Acceptance of Shaft - CSL Testing

37

Page 38: I-74 Bridge Over Mississippi River Construction...1 I-74 Bridge Over Mississippi River Construction Travis Konda, PhD, PE, SE. 2018 Midwest Geotechnical Conference, 27SEP18

Harsh Conditions

39

Page 39: I-74 Bridge Over Mississippi River Construction...1 I-74 Bridge Over Mississippi River Construction Travis Konda, PhD, PE, SE. 2018 Midwest Geotechnical Conference, 27SEP18

Summary

• Shaft 1 – September 18, 2017• Shaft 239 – July 20, 2018

• Thank you –– Iowa DOT– Illinois DOT– FHWA